FOG SEAL PARK ROADS
Solicitation number
140P8124B0004
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to plan, schedule, and execute a fog seal and restripe of 23.35 miles of roadway within Joshua Tree National Park. The key objectives include surface preparation, application of a diluted CSS-1H type asphalt emulsion at a rate of 0.10 to 0.15 gallons per square yard, and repainting of centerline, edge line, and other roadway markings. The contractor will have limited use of the site and must coordinate closely with the government to minimize disruption to public access and use of the roads and parking areas during construction. The contractor must also comply with various environmental, safety, and quality control requirements, including an Accident Prevention Plan, Waste Recycling Plan, and Pedestrian/Vehicular Traffic Control Plan. The work is being procured by the Department of the Interior National Park Service Pacific West Region.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JOSHUA TREE

NATIONAL PARK

Fog Seal and Restripe Roads in Joshua Tree National Park.

PROJECT SPECIFICATIONS

PREPARED BY BRANDON MCEACHERN

NATIONAL PARK SERVICE

TWENTYNINE PALMS, CA

Table of Contents Table of Contents (TOC) 01 11 00 Summary of Work 03 01 27 00 Definition of Contract Line Items 05 01 31 00 Project Management and Coordination 07 01 32 16 Construction Schedule 10 01 33 23 Submittal Procedures 13 01 35 13 Archeological Protection 18 01 35 23 Safety Requirements 21 01 40 00 Quality Requirements 25 01 50 00 Temporary Facilities and Controls 29 01 57 23 Temporary Storm Water Pollution Prevention (SWPP) 34 01 73 40 Execution 40 01 74 19 Construction Waste Management and Disposal 43 01 77 00 Closeout Procedures 44 Supporting Documents FHWA DOT Standards FP-14

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Contractor Use of Site

3. Public Use of Site

4. Conduct of Operations

5. Work Restrictions

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: The Contractor shall plan, schedule, and execute a fog seal and restripe of

23.35 miles of roadway within Joshua Tree National Park.

Joshua Tree National Park 74485 National Park Dr, Twentynine Palms, CA, 92277

B. The Work consists of the following:

1. The objective of this contract is to plan, schedule, and execute a fog seal of 23.35 miles of roadway within Joshua Tree National Park.

2. Surface preparation; clean existing surface of loose material, dirt, and other deleterious material before placing the fog seal. All roads will be swept immediately before applying asphalt emulsion. Protect concrete work adjacent to the work.

3. Asphalt emulsion will be diluted to one part water to one-part emulsified asphalt.

and will be a CSS-1H type.

4. No sand will be used.

5. Asphalt will be applied at a rate of 0.10 to 0.15 gallons per square yard.

6. Edge of spray will be no more than 2 inches away from the curb-line in those areas with curbing.

7. After fog seal is complete the contractor will paint centerline and edge line markings to mirror the original markings before the fog seal was applied. All striping will be 4 inches in width. Black contrast striping will be 3 inches in width. Curbed areas of roadway do not need edge line. All line striping will consist of 2 coats with reflective beads added on the second coat. All striping will be 4 inches wide except the black contrast stripe which will be 3 inches. Park Roads employees will repaint all pavement stencils to include stop bars, stop ahead stencils, and turn arrows.

8. Paint will be a federal spec waterborne latex paint applied at a thickness of 14 mils.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to work areas and do not disturb portions of project site beyond these areas. Limit site disturbance, including earthwork and clearing of vegetation, to 10 feet beyond surface walkways, patios, surface parking, and utilities.

B. Storage of Materials: Confine storage of materials to designated areas as indicated by CO (Pinto Wye Pit, Queen Valley Pit).

C. Parking: Confine parking to designated areas as indicated by CO (Paved Pullouts).

D. Stockpiling: Confine stockpiling to designated areas as indicated by CO.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Do not fasten ropes, cables, or guys to existing trees.

3. Carefully supervise construction operations near trees to prevent damage.

F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

G. Construction Camp: Establishment of a camp within park will not be permitted.

H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

I. Pedestrian and/or Vehicular Traffic Control: Provide a traffic control plan for CO review, comment and acceptance if the project impedes, alters or affects the existing pedestrian and/or vehicular traffic. Products and procedures to be in accordance with Specification 01 50 00, 3.3, C Traffic Controls.

1.4 PUBLIC USE OF SITE

A. The roads and parking areas will be open to the public during construction. Contractor shall provide a pedestrian and/or vehicular traffic control plan for CO review and acceptance if the project impedes, alters or affects the existing pedestrian and/or vehicular traffic.

Contractor may utilize a proposed building/site plan to indicate traffic control measures.

B. Contractor shall conduct his operations to ensure the least inconvenience to public. Road and parking area closures may be permitted, when required, upon specific approval of Contracting Officer for a maximum of 24 hours.

1.5 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer.

Submit requests 3 business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 6:30 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: May be requested 48 hours in advance, subject to CO approval.

2. Early Morning Hours: May be requested due to higher summer temps.

B. Existing Utilities

1. Contractor is responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 50 feet of entrances, operable windows, or outdoor air intakes. Tobacco use and vaping is restricted to the inside of contractor vehicles.

D. Extreme Fire Danger: If a Red Flag Warning or other extreme fire danger warning is issued that includes the project site, the Contractor shall coordinate with the Contracting Officer for any additional work restrictions that may be required.

1.7 SPECIAL CONSTRUCTION REQUIREMENTS

A. Exotic Vegetation and Noxious Weeds

1. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Contractor shall ensure all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds and similar debris when a visual inspection does not disclose such material.

Inspection will be done by NPS Resources and/or Facilities staff upon arrival at JOTR.

Disassembly of equipment components or specialized inspection tools is not required.

B. Contractor shall notify the Contracting Officer at least two (2) days prior to moving any equipment onto the Project Area. Notification will include identifying the location of the equipment’s most recent operations. The Contractor shall arrange for the Contracting Officer to inspect each piece of equipment prior to it being placed in service.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends, and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 3 – EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line-Item Number 001: Fog Seal and Re-Stripe Roads.

1. This item includes centerline striping, fog lines, parking stall lines, crosswalks, stop sign lines, handicap symbols, painted islands, and turn areas. These include:

• Pinto Wye Road (closed to public) (.52 miles). Pinto Wye Road will need fog sealing with no striping. Length of road is 2,733 feet long.

• Hidden Valley Campground Entrance (open to public cannot be closed at all) (.12 miles). Hidden Valley campground entrance has 2 curbed pullouts.

Striping is double yellow with black contrast. No edge line required. Length of road is 624 feet. Total striping is 1,872 linear feet.

• Indian Cove Road (open to public, cannot be closed at all) (1.95 miles) Intersection at Indian Cove Rd and Indian Cove Ranger Station parking lot will need to be fog sealed 50 feet into each intersection. Striping will be double yellow with black contrast. No edge line required. Length of road is 10,275 feet. Total striping is 30,825 linear feet.

• 49 Palms Road (open to public, can be closed) (.85 miles). 49 palms Rd will need fog sealing. No striping required. Total length 4,468 feet.

• Sheep Pass Campground Road (open to public, cannot be closed) (.29 miles).

Sheep Pass Campground Rd will need fog sealing.

• Cottonwood Springs Road (open to public, can be closed in sections) (1.14 miles). Intersection of Cottonwood Springs Rd and Cottonwood visitors center parking will need to be fog sealed 50 feet into parking area. Intersection of Cottonwood Springs Rd and the dump station will need to be fog sealed 50 feet into dump station entrance and exit. Intersection at Cottonwood Springs Rd and Cottonwood Campground will need to be fog sealed 50 feet into campground. Striping will be double yellow with black contrast and white edge line. Length of road is 6,023 feet. Total striping is 30,115 linear feet.

Cottonwood Residential Road (closed to public) (.15 miles)

• Cottonwood Residential Rd has 4 driveways that will not receive fog seal.

Striping on this road is not required. Length of road is 797 feet.

• Keys View Road (open to public can be totally closed) (5.43 miles). Keys View Road has 9 curbed pull outs. Intersection at Keys View Rd and Cape Rock Parking lots will need to be fog sealed 50 feet into each of the intersections.

Intersection at Keys View Rd and Juniper Flats Parking lot will need to be fog sealed to the dirt. Intersection at Keys View and Lost Horse Mine Rd will need to be fog sealed to the dirt. Striping will be Double yellow with black contrast.

No edge line required. Length of road is 28,663 feet long. Total striping is

85,989 linear feet.

• Barker Dam Road (open to public can be closed in sections) (1.54 miles).

Barker Dam Rd has 9 curbed pullouts. Intersection at Barker Dam and Keys Ranch Rd will need to be fog sealed to the dirt. Intersection at Barker Dam Rd and Big Horn Pass Rd will need to be fog sealed to the dirt. Striping will be Double yellow with black contrast. No edge line required. Length of road is 8,124 feet long. Total striping is 24,372 linear feet.

• East West Highway (Park Blvd) (Open to public, cannot be closed at all) (12.5 miles). The start of the fog seal will be the West Entrance of Joshua Tree located in the town of Joshua Tree and will end at mile marker 13 located in between Ryan Mountain and Hall of Horrors. This road contains 8.36 Miles of road without curbing requiring edge lines. There are another 4.14 miles of areas with curbing that do not require edge line. Length of road requiring double yellow, black contrast, and edge lines: 8.36 Miles (220,700 linear feet) Length of road requiring double yellow, black contrast, and no edge lines. 4.14 Miles (65,565 linear feet).

This item includes payment for preparation of all existing surface conditions, containment methods to collect debris, protection methods of the air and soil, and the lawful disposal of generated waste materials.

END OF SECTION 01 27 00

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

A. Section includes administrative provisions for coordinating construction operations on

Project including, but not limited to, the following:

1. Construction Coordination

2. Submittals

3. Requests for Information (RFIs)

4. Project Meetings

1.2 CONSTRUCTION COORDINATION

A. Coordination:

1. Schedule construction operations in sequence required to obtain best results.

• Fog Seal then re-stripe

2. Properly plan construction operations. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work.

1.3 SUBMITTALS

A. The following items (as required for this project) shall be submitted a minimum of one week prior to the Preconstruction Conference. The Contracting Officer will notify Contractor of tentative date for Pre-Construction Conference.

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. SF1413 for Contactor and all Subcontractors Written statements from

Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Pedestrian/Vehicular Traffic Control Plan

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI with content of Paragraph 1.4.B below.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution: If Contractor's suggested resolution impacts

Contract Time or Contract Sum, Contractor shall state impact in RFI.

8. Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

• Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

2. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.

1.5 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange a meeting with Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

5. Coordination of Subcontractors

6. Labor law application payroll reports

7. Modifications

8. Payments to Contractor

9. Contract time

10. Contractor Performance Evaluation

11. Notice to proceed

12. Correspondence procedures

13. Acceptance/rejection of work

14. Progress meetings

15. Submittal procedures

16. Environmental requirements

17. Permit requirements

18. Saturday, Sunday, holiday and night work.

19. Reference materials

20. Schedule of Values

B. Progress Meetings: Contracting Officer may schedule weekly meetings with Contractor, as

1. Attendees: In addition to Government Representatives, the Contractor and any

Subcontractor, supplier, and other entity deemed necessary for attendance shall be represented.

2. Agenda: Review and correct or approve minutes of previous progress meeting.

Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings

b. Submittal status

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications

f. Work in progress and projected

g. Inspections of work in progress and projected (Special inspections etc.)

h. Construction Schedule update (provide updated Critical Path Method (CPM)).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

A. Section consists of Construction Schedule requirements including:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The Construction Schedule ensures adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. It shall assist the Contractor and Contracting Officer (CO) in monitoring the progress of the work, evaluating proposed changes, and processing Contractor's monthly progress payments. It shall include the dates in the contract, phases, milestones, occupancies, holidays, weather consideration, a critical path, and the requirements of this section.

1.2 SUBMITTALS

A. Electronic Copies: Schedules and reports submitted shall be in native electronic file formats and/or in PDF format. The intent of the Government is to limit the number of printed reports to those determined by the project team as essential.

B. Schedule of Values: After contract award and before Pre-Construction conference, submit schedule of dollar values based on Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit the baseline schedule in electronic format (native file and PDF) formatted to show the entire schedule for the entire construction period. Utilize Schedule of Values in preparation of Construction Baseline Schedule.

D. Critical Path Method (CPM) Reports: Concurrent with CPM schedule, submit in electronic format (PDF) the following computer-generated reports. For each activity, include activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for activities sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of activities sorted in ascending order of total float.

E. Construction Schedule Updates: Provide as requested by the Contracting Officer.

F. Construction Schedule Revisions and Time Impact Analysis: Provide as requested by the Contracting Officer. Incorporate a Fragmentary Network (Frag-Net) into currently accepted Construction Schedule that demonstrates how Contractor proposes to incorporate a modification, change, delay, or Contractor request.

1.3 QUALITY ASSURANCE

A. Contractor shall meet with Contracting Officer on day of the preconstruction conference to go over:

1. Discuss constraints, including phasing, work stages, area separations, interim milestones, and partial/substantial completions.

2. Review time required for review of submittals and re-submittals.

3. Review requirements for tests and inspections by independent testing and inspecting agencies.

4. Review time required for completion and startup procedures.

5. Review time required for obtaining and activating permits.

6. Review and finalize list of construction activities to establish the baseline schedule.

7. Discuss reporting requirements and protocol for naming and transmitting electronic submittals.

B. Contractor's Schedule Representative: Before the preconstruction conference, designate an authorized representative to be responsible for preparing and maintaining the Construction Schedule. Submit resume outlining qualifications of Scheduler to Contracting Officer for acceptance. Authorized representative will be responsible for preparing the Baseline Schedule, required updates, revisions, Time Impact Analyses, and reports.

1.4 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling.

B. Coordinate Construction Baseline Schedule with Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing Construction Baseline Schedule, ensure Subcontractor’s work at all tiers, and prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of work from parties involved.

3. Coordinate each construction activity in network with other activities and schedule in proper sequence.

PART 2 - PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.1 CONSTRUCTION SCHEDULE UPDATES

A. Progress Meeting Updates: Provide a three (3) week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize look-ahead schedule to facilitate and take notes on discussions held during progress meeting.

B. Monthly Schedule Updates:

1. General: Update the Construction Schedule on a monthly basis to reflect actual construction progress and activities throughout the entire contract period and until the project reaches the substantial completion milestone. The status date of each schedule update shall be the 7th day preceding the progress payment request date.

2. Procedure: Contractor shall meet with the Contracting Officer each month at either a Construction Schedule update meeting or during a weekly Progress Meeting to review progress made to date and discuss any changes to the baseline schedule.

a. Review actual progress made during update period; actual and potential delaying activities; impediments to progress; issues related to inclement weather; progress toward established milestones and project float.

Discussion shall include a review of work anticipated to be performed in the next month. Revisions to the schedule are be identified for evaluation and acceptance or rejection.

3. As Work progresses, indicate Actual Completion percentage for each activity.

4. Progress Payments: Monthly updating of the currently accepted Construction

Schedule shall be an integral part of the process upon which progress payments will be made. If Contractor fails to provide schedule updates or revisions, a portion of the monthly payment may be retained until corrections have been made.

C. Distribution: Distribute copies of accepted schedule to the Contracting Officer, Contracting Officers Representative, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility. Also post a copy in the Contractor’s field office.

1. When revisions are made, distribute updated schedules to same parties and post in same locations. Delete parties from distribution when they have completed their assigned portion of the Work.

D. Construction Schedule Revisions:

1. Required Revisions: If, as a result of the monthly schedule update, it appears the currently accepted Construction Schedule no longer represents actual prosecution and progress of the work, Contracting Officer will request, and Contractor shall submit, a revision to the Construction Schedule. Contractor may also request reasonable revisions to currently accepted Construction Schedule in event the Contractor's planning for the work is revised. If Contractor desires to make changes, Contractor shall notify Contracting Officer in writing, stating reason for proposed revision. Accepted revisions shall be incorporated into currently accepted Construction Schedule for next monthly schedule update.

2. Procedure: If revision to currently accepted Construction Schedule is contemplated, Contractor or Contracting Officer shall advise the other in writing at least seven calendar days prior to next monthly schedule update meeting, describing revision and reasons for the revision. Government-requested revisions will be presented in writing to the Contractor, who shall respond in writing within seven calendar days.

3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS AND CONTRACTOR

REQUESTS:

A. Requirements: When contract modifications or changes are initiated, delays experienced, or

Contractor desires to revise currently accepted Construction Schedule, Contractor shall submit to Contracting Officer a written time impact analysis illustrating the influence of modification, change, delay, or Contractor request on contract time.

B. Time Extensions: Activity delays, resulting in a late completion date projection, shall not automatically mean an extension of contract time is warranted or due to Contractor. It is possible a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in absorbing a part of available total float that may exist within an activity chain of the Schedule, not causing any effect on contract time. Time extensions will be granted in accordance with terms of contract.

C. Extension of contract time will be granted only to the extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.

D. Procedure: Each time impact analysis shall be submitted within time period stated in a request for proposal, or time period designated under the clauses entitled Changes or Default. In cases where Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, time impact analysis shall be incorporated into currently accepted Construction Schedule at next monthly schedule update.

E. Contract Modifications: Prepare time-impact analysis using fragnets to demonstrate effect of proposed change on overall Construction Schedule for each proposed contract modification concurrent with submission.

END OF SECTION 01 32 16

SECTION 01 33 23 - SUBMITTAL PROCEDURES

A. Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.2 GENERAL SUBMITTAL PROCEDURES

A. General: Prepare and submit submittals required by individual Specification Sections and in some cases as requested in drawings. Types of submittals are indicated in individual specific sections.

1. Contracting Officer (CO) reserves right to require submittals in addition to those called for in individual sections.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review for legibility, accuracy, completeness, and compliance with Contract Documents.

1. Coordinate submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of Work so processing will not be delayed because of need for concurrent review coordination.

a. Contracting Officer reserves right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Submittal List: Submittal list is attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements. The requirements of individual Specification Sections and terms and conditions of the Contract still apply regardless of what is shown on submittal list.

D. Processing Time: Allow time for submittal review, including time for re-submittals, as follows. Time for review shall commence when e-mail notification is received by Contracting Officer (or designee) indicating submittal has been posted on NPS management software website and is ready for review. When Contracting Officer has completed review, e-mail notification will be sent to Contractor indicating submittal has been processed. No extension of Contract Time will be authorized because of failure to transmit submittals in advance of Work to permit processing, including re-submittals.

1. Action Submittals

a. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

b. Re-submittal Review: Allow 15 days for review of each re-submittal.

2. Informational submittals

a. Review: Allow 10 days for review of each submittal.

E. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. Transmittal Form (CM-16): All submittals shall be transmitted using National Park

Service Transmittal Form (CM-16). No action will be taken on a submittal item unless accompanied by this Transmittal Form.

a. Complete the general information at the top of form.

b. Provide all required information based on submittal type

c. Attach all related documents.

d. Sign the Contractor section at bottom of the Transmittal Form (CM-16).

2. Physical samples: Complete Transmittal Form (CM-16) as described above. Deliver physical sample to the Contracting Officer (or designee) on site for processing. All comments and actions will be documented on the Transmittal Form (CM-16).

F. Identification: Submittal number or other unique identifier, including revision identifier.

1. Submittal number shall use a sequential number (e.g. .001). Re-submittals shall include alphabetic suffix after another decimal point (e.g. .001.A).

G. Re-submittals: Make re-submittals using same process used with initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in the title block on the Transmittal Form (CM-16) and clearly indicate extent of revision.

3. Re-submit submittals until they are marked "Approved" or "Approved with notations".

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and others as necessary for performance of construction activities.

I. Use for Construction: Use only final submittals with mark indicating "Approved" or "Approved with notations". Ensure notations have been incorporated and, at a minimum, keep one copy of final approved submittal on site for use during construction.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each submittal to show which products and options are applicable.

3. As applicable, include:

a. Manufacturer’s product specifications.

b. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.

c. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.

d. Printed performance curves.

e. Operational range diagrams.

f. Compliance with specified referenced standards.

g. Testing by recognized testing agency.

4. Submit product data in PDF (portable document format) file format before or concurrent with samples.

B. Shop Drawings: Not Used

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Complete and post the Transmittal Form (CM-16) for processing and documentation of action on submitted samples.

3. Identification: Attach label on unexposed side of Samples that includes:

a. Generic description of Sample

b. Product name and name of manufacturer

c. Sample source

d. Submittal Number and title of appropriate Specification Section

4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

5. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing full range of colors, textures, and patterns available.

a. Number of Samples: Submit two full sets of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. Contracting Officer will return with options selected.

6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include:

partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit four sets of Samples. Contracting Officer will retain three Sample sets; remainder will be returned.

D. Construction Materials: Contractor is encouraged to submit products made out of recycled or environmentally responsible material. Every effort will be made by National Park Service to approve these materials.

2.2 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by individual Specification

Sections.

1. Certificates and Certifications: Provide a notarized statement with signature of entity responsible for preparing certification. Certificates and certifications shall be signed by officer or other individual authorized to sign documents on behalf of that entity.

2. Informational submittals that do not comply with requirements specified in Contract Documents will be rejected.

B. Contractors Construction Schedule: Comply with requirements specified in Section 01 32 16

"Construction Schedule."

C. Accident Prevention Plan: Comply with requirements specified in Section 01 35 23 "Safety Requirements."

D. Schedule of Values: Comply with requirements specified in Section 01 32 16 "Construction Schedule."

E. Waste Recycling Plan: Comply with requirements specified in Section 01 74 19 "Construction Waste Management and Disposal."

F. Quality Control Plan: Comply with requirements specified in Section 01 40 00 "Quality Requirements."

G. Pedestrian/Vehicular Traffic Control Plan: Comply with requirements specified in Section 01 50

00, Part 3.3, C “Temporary Facilities and Controls, Support Facilities Installation, Traffic Controls.”

H. Qualification Data: Prepare written information demonstrating capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

I. Installer Certificates: Prepare written statements on manufacturer’s letterhead certifying Installer complies with Contract Documents and, where required, is authorized by manufacturer for this specific Project.

J. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying manufacturer complies with Contract Documents. Include evidence of manufacturing experience where required.

K. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying product complies with Contract Documents.

L. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying material complies with Contract Documents.

M. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with requirements in Contract Documents.

N. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

O. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

P. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in Contract Documents.

Q. Manufacturer’s Instructions: Prepare written or published information documenting manufacturer’s recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

R. Manufacturer’s Field Reports: Prepare written information documenting factory-authorized service representative’s tests and inspections. As applicable, include:

1. Statement on condition of substrates and their acceptability for installation of product.

2. Summary of installation procedures being followed, compliance with requirements and, if not, what corrective action was taken.

3. Results of operational and other tests and a statement of whether observed performance complies with the requirements.

PART 3 - EXECUTION

3.1 CONTRACTOR’S REVIEW

A. Review each submittal and check for coordination with other Work of Contract and for compliance with Contract Documents. Note corrections and field dimensions.

3.2 CONTRACTING OFFICER’S ACTION

A. General: Submittals will be disapproved without technical review if identification information is missing, not filled in, or if placed on back of submittal; an incorrect format of submittals is provided; transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.

1. Any work done or orders for materials or services placed before approval shall be at Contractor’s own risk.

B. Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate appropriate action on the Transmittal Form (CM-16). Submittal will be marked as defined below:

1. APPROVED: Acceptable with no corrections.

2. APPROVED WITH NOTATIONS: Minor corrections or clarifications required.

Comments are clear and no further review is required. Contractor shall address review comments when proceeding with the work.

3. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. Contracting Officer will identify reasons for disapproval. Contractor shall revise and resubmit with changes clearly identified.

C. Informational Submittals: CO will review each submittal and will either accept or reject it.

D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

END OF SECTION 01 33 23

SECTION 01 35 13 – ARCHEOLOGICAL PROTECTION

A. Section consists of protecting archeological resources contained in soil deposits.

1.2 DEFINITIONS

A. Archeological Resources Protection Act (ARPA) of 1979 (Public Law 96-95; 16 U.S.C. 470aa-mm), as amended was enacted to protect archaeological resources on public lands and Indian lands, and for other purposes. Defines archeological resources as any material remains of past human life or activities that are of archeological interest and at least 100 years old; Section 4 of the statute describes the requirements that must be met before Federal authorities can issue a permit to excavate or remove any archeological resource on Federal or Indian lands; the curatorial requirements of artifacts, and other materials excavated or removed.

B. ARPA: defines an “archeological resource” as any material remains of past human life or activities which are of archaeological interest and are at least 100 years of age. Such regulations containing such determination shall include pottery, basketry, bottles, weapons, weapon projectiles, tools, structures or portions of structures, pit houses, rock paintings, rock carvings, intaglios, graves, human skeletal materials, or any portion or piece of any of the foregoing items. Archeological resources are physical evidences of past human activity, including evidences of effects of that activity on the environment. Archeological resources represent both prehistoric and historic time periods, found above and below ground and under water.

C. National Historic Preservation Act (NHPA) of 1966 (54 U.S.C. Part 300308), as amended sets federal policy for historic preservation under 36 C.F.R. (Code of Federal Regulations) Part 800 “Protection of Historic Properties.”

D. NHPA: defines a “historic property” (or historic resource) as any prehistoric or historic district, site, building, structure, or object included in, or eligible for inclusion on, the National Register of Historic Places (NRHP), including artifacts, records, and material remains related to such a property or resource

E. NRHP (known also as the National Register [NR]) is a national program designed to identify, evaluate, and protect historic and archeological resources. The NR is the official Federal list of districts, sites, buildings, structures, and objects significant in American history, architecture, archeology, engineering, and culture that are at least 50 years of age.

F. Section 106 of the NHPA: requires federal agencies to take into consideration the effects on historic properties of projects they carry out, assist, fund, permit, license, or approve.

G. Native American Graves Protection and Repatriation Act (NAGPRA) of 1990: addresses the inventory, identification and treatment of Native American human remains and objects of cultural patrimony-funerary objects and sacred objects, particularly those in the collections of museums and federal agencies.

H. Culturally Sensitive Resource Area: an area determined to possess high potential for surficial and subsurface cultural deposits. If National Register eligible or listed archeological resources could not be avoided, an appropriate mitigation strategy would be developed in consultation with state historic preservation officer and, if necessary, associated American Indian tribes.

I. Non-Culturally Sensitive Areas: an area determined to have little, if any, potential to contain surficial and subsurface cultural deposits.

J. Archeological Monitor: a professional archeologist that meets the Secretary of the Interior’s

Professional Qualifications Standards for Archeology (36 C.F.R. Part 61; 36 C.F.R. Part 800.2) designated to oversee construction activities that have the potential to disturb surficial and subsurface cultural deposits. Representative of Government designated to oversee construction activities that could disturb archeological resources.

K. 36 C.F.R Part 800.13, Post-Review Discoveries: establishes a means for addressing inadvertent discoveries encountered during an undertaking.

A. Prior to commencement of construction, an NPS Section 106 Coordinator will submit an Archeological Monitoring and Inadvertent Discovery Plan.

1. Daily Work Schedule: Detail construction work in archeologically sensitive areas. Submit to Contracting Officer (CO) 30 days before start of ground disturbing site work. Key schedule to drawings and include the following information:

a. Construction site plan that identifies site-specific avoidance areas.

b. Start and ending dates of all ground-disturbing construction-related activities.

c. Types of construction activities, such as clearing and grubbing, topsoil stripping, structure or trench excavation, culvert and drainage pipe excavation and installation, landscaping, and post construction grading and clean-up.

d. Location of temporary facilities including field offices, staging areas, sanitary facilities, construction site barriers, access roads, haul routes, and borrow pits.

e. Methods and equipment used for each type of construction activity.

f. Identify work areas for relocating construction activities in the event of temporary location- specific work stoppages.

2. 30-days prior to start of ground-disturbing site work, Contractor to provide a site plan to the CO for NPS Section 106 Coordinator review and comment. 15-days prior to the work, Contractor to provide the revised site plan addressing any comments to the CO for final NPS Section 106 Coordinator review and acceptance.

3. 5-days prior to commencement of construction activities, submit final site plan to the equipment operator.

1.4 QUALITY ASSURANCE

A. At least one week before on-site work begins, Contractor shall meet with Contracting Officer and Archeological Monitor to discuss Daily Work Schedule, equipment, and special methods used in archeologically sensitive areas. Contractor shall ensure approved Daily Work Schedule is followed throughout construction.

2.1 DAILY WORK SCHEDULE

A. Daily Work Schedule is required for work occurring within archeologically sensitive areas.

Include all work that is to occur within the area and key the schedule to the drawings to include:

1. Starting and ending dates of ground-disturbing construction.

2. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, borrow pits, and haul and access roads.

3. Types of construction, such as clearing, topsoil stripping, structure or trench excavation, landscaping, and post construction clean-up.

4. Methods and equipment used for each type of construction.

5. Plan for relocating work in the event of temporary work stoppages at each archeologically sensitive area.

3.1 BARRICADES

A. Comply with requirements specified in Section 01 50 00 “Temporary Facilities and Controls.”

3.2 ARCHEOLOGICAL INVESTIGATION BY NON-NPS PERSONNEL – NOT USED

3.3 OBSERVATION

A. Archeological Monitor will observe ground-disturbing stie work, including construction of temporary facilities, at archeologically sensitive areas, from a safe location mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.

3.4 DISCOVERY OF RESOURCES

A. Pursuant to 36 C.F.R. § 800.13, in the event that previously unidentified cultural resources material remains are unintentionally exposed by some aspect of this project, procedures outlined in the Archeological Monitoring and Inadvertent Discovery Plan will be adhered to in accordance with the Guidance for National Park Service Compliance with Native American Graves Protection and Repatriation Act (NAGPRA) and NPS Cultural Resource Management Guideline, Appendix R. The Cultural Resources Manager is responsible for assessing the material remains and the area of discovery. Work will not resume at that location until the archeologist give approval.

B. In the event that human remains, funerary objects, sacred objects, or objects of cultural patrimony are unintentionally exposed by some aspect of this project, procedures outlined in the Archeological Monitoring and Inadvertent Discovery Plan will be adhered to in accordance with Guidance for National Park Service Compliance with the Native American Graves Protection and Repatriation Act (NAGPRA) and NPS Cultural Resource Management Guideline, Appendix R. The NAGPRA Coordinator is responsible for assessing. Work will not resume at the location of the discovery until the NAGPRA Coordinator gives approval.

C. If material remains are discovered,…