This document is Amendment 0002 to Solicitation 140P8124B0004 for the Fog Seal and Restripe of Park Roads at Joshua Tree National Park.
The key details are:
- The purpose of the amendment is to incorporate an attachment for seal image locations, publish site visit attendance sheets, and answer a contractor question about the required qualifications.
- The bid due date remains August 6, 2024 at 2:00 PM PDT.
- The scope includes fog sealing and restriping various roads and pullouts within the park, with details provided on the length, location coordinates, and striping requirements for each.
- Designated material staging and equipment staging areas are identified.
- All other terms and conditions of the solicitation remain unchanged.
View the file
Other files for this federal contract opportunity
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P8124B0004 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPL
Boulder City NV 89005-2426 601 Nevada Way
NPS, PWR - LAKE MABO
07/15/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/02/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See Continuation Page
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Caroline Bachelier
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
140P8124B0004 Amendment 0002
The purpose of this amendment is to:
A. Incorporate Attachment 5 – JOTR For Seal Images with Locations.
B. Publish the site visit attendance sheets.
C. Answer contractor’s questions:
Question 1: Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
Answer 1: They do not need to be 3 separate individuals.
D. The bid due date remains the same, Aug 6, 2024, at 1400 PDT.
E. All other terms and conditions remain the same.
Fog Seal Keys View Road.
Keys View Road is 5.43 miles
This Road Will Need Double Yellow With Black Contrast Striping
Start Location 33°59'30.13"N 116° 9'48.21"W
End Location 33°55'37.18"N 116°11'9.85"W
Fog Seal Barker Dam Road
Barker Dam Road is 1.54 Miles
This Road Will Need Double Yellow With Black Contrast Striping
Start Location 34° 0'49.88"N 116° 9'45.39"W
End Location 34° 1'28.73"N 116° 8'32.86"W
Fog Seal Pinto Wye Road
Pinto Wye Road is .52 miles
Start Location 34° 1'12.34"N 116° 1'7.90"W
End Location 34° 1'17.31"N 116° 0'36.99"W
Fog Seal Hidden Valley Camp Ground Entrance
Hidden Valley Camp Ground Entrance is .12 Miles
This Road Will Need Double Yellow With Black Contrast Striping
Start Location 34° 0'49.89"N 116° 9'45.40"W
End Location 34° 0'58.42"N 116° 9'40.51"W
Fog Seal Indian Cove Road
Indian Cove Road is 1.95 Miles
This Road Will Need Double Yellow With Black Contrast Striping
Start Location 34° 7'13.88"N 116° 9'18.76"W End Location 34° 5'37.47"N 116° 9'23.96"W
Fog Seal 49 Palms Road
49 Palms Road is .85 miles
No striping required on this road.
Start Location 34° 7'11.00"N 116° 6'45.20"W
End Location 34° 7'23.57"N 116° 7'28.37"W
Sheeps Pass Campground Road is .29 miles
No striping required on this road
Start Location 34° 0'7.35"N 116° 7'28.39"W
End Location 33°59'59.24"N 116° 7'14.37"W
Fog Seal Cottonwood Springs Road.
Cottonwood Springs Road is 1.14 miles.
This Road Will Need Double Yellow With black contrast striping and edge line striping.
Start Location 33°44'53.29"N 115°49'28.79"W
End Location 33°44'14.45"N 115°48'39.70"W
Cottonwood Residential Road
Cottonwood Residential Road is .15 miles
No striping required
Start Location 33°44'47.09"N 115°49'13.96"W
End Location 33°44'51.11"N 115°49'6.11"W
Typical Pullout along roadway.
All pullouts will be fog sealed.
Fog Seal starts at West Boundary and proceeds to mile marker 13.
This section of road is 12.5 miles in length.
Entire entrance booth area will be fog sealed.
Start Location 34° 5'37.53"N, 116°15'56.68"W
East West Highway Main Road Start and End Points
Intersection of East West Highway and Keys View Road
This is the only area that contains turn lanes.
Park staff will repaint the arrows, stop bars, and stop stencils. Contractor will restripe all double yellow and white lines covered by asphalt emulsion except white edge line along curbed sections of roadway. Curbed sections of roadway will not have edge line repainted.
Intersection of East West Highway (RT12) and Keys View Road 33°59'30.05"N, 116° 9'47.87"W
Typical Pullout along roadway.
All pullouts will be fog sealed. There are 40 Pullouts.
Typical view of roadway with no curbing.
Typical view of roadway with curbing.
Pinto Wye Pit
Available to use during project. Location is about 4 miles into project site.
Pinto Wye Pit 11s 591117.50 m E 3764810.11 m N
Queen Valley Admin Site
Available for use during project. Location is approx. MM
11.5 on East West Highway.
Queen Valley Admin Site 34° 0'27.27"N, 116° 7'5.37"W