B08_2025_Bid_Schedule-SAHO_Containers_FY25-27.docx

DOCX document 26 KB Posted

Attached to
GATE-SAHO FY25 CONTAINERS & DISPOSAL Federal contract opportunity
Solicitation number
140P4525Q0032
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document is a Contract Bid Schedule for container and disposal services at the Sandy Hook Unit of Gateway National Recreation Area. The solicitation (140P4525Q0032) covers a base year (FY2025) and two optional subsequent years (FY2026 and FY2027), with specific line items for container services and disposal. The bid requires contractors to provide:

  1. Base Bid (FY2025): 18 x 30-cubic-yard containers for Maintenance Operations, disposal fees for 100 tons of mixed construction waste, and 3 x 6-yard single-stream recycling containers with twice-weekly collection. 2. Option Years (FY2026 and FY2027): Identical service requirements with the same quantities and collection specifications. The bid schedule allows contractors to price each line item, with a total grand total calculation for the entire three-year period. The opportunity is issued by the Department of the Interior National Park Service Northeast Region, located at Fort Hancock, New Jersey, with services to be performed from May 1 of each specified year through April 30 of the subsequent year.

View the file

Other files for this federal contract opportunity

Other files attached to GATE-SAHO FY25 CONTAINERS & DISPOSAL, newest first.
File Type Posted
B09_More_Questions_and_Answers_0004.docx DOCX document
Sol_140P4525Q0032_Amd_0004.pdf PDF
Sol_140P4525Q0032_Amd_0003.pdf PDF
Sol_140P4525Q0032_Amd_0002.pdf PDF
Sol_140P4525Q0032_Amd_0001.pdf PDF
Sol_140P4525Q0032.pdf PDF
B08_References_Worksheet.doc DOC document
B03_2015-4195.pdf PDF
B08_REV_Separately_Priced_In_Accordance_with_FAR_Clause_52.pdf PDF
A04_2025_SOW-SAHO_Containers_FY25-27.docx DOCX document
B08_Technical_Questionnaire.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT BID SCHEDULE

Containers and Disposal Request for FY2025 (Base Bid), Option Year 1, and Option Year 2 Gateway National Recreation Area - Sandy Hook Unit Submit bid for all items: Failure to do so may render the bid non-responsive. Refer to definition of bid items for the bid item descriptions.

BASE BID ITEM NO 10:

Provide eighteen (18) -30 CY containers for Maintenance Operations at Sandy Hook Unit from May 1, 2025 through April 30, 2026 at various locations at Sandy Hook. This cost will include the delivery, usage, and pick-up of the container.

BASE BID ITEM NO 10: UNIT SUM $ _ _/Container x 18 EA =$ _ _TOTAL

BASE BID ITEM NO 20:

Disposal fees Cost per ton for 100.0 tons to account for the tonnage of the containers of the Maintenance Operations of mixed construction waste from May 1, 2025 through April 30, 2026.

BASE BID ITEM NO 20: UNIT SUM $ _ _/Ton x 100.0 tons =$ _ _TOTAL

BASE BID ITEM NO 30:

Provide 3 - 6-yard Single Stream Recycling Containers with 2x per week collection, Contractor’s costs shall include all delivery, usage, and collections costs for all dumpsters:

BASE BID ITEM NO 30: UNIT SUM $_ _/Container/month x 3 units X 4 month = $ TOTAL

TOTAL BASE BID (FFP line Items 10 through 30) = $_______ __________

Provide 18 -30 CY containers for Maintenance Operations at Sandy Hook Unit from May 1, 2026 through April 30, 2027 at various locations at Sandy Hook. This cost will include the delivery, usage, and pick-up of the container.

BID ITEM NO 40: UNIT SUM $ __ __/Container x 18 EA =$ ___ _TOTAL

OPTION YEAR 1- BID ITEM NO 50:

Disposal fees Cost per ton for 100.0 tons to account for the tonnage of the containers of the Maintenance Operations of mixed construction waste from May 1, 2026 through April 30, 2027.

BID ITEM NO 50: UNIT SUM $ _ __/Ton x 100.0 tons =$ __ _TOTAL

OPTION YEAR 1- BID ITEM NO 60:

Provide 3 - 6-yard Single Stream Recycling Containers with 2x per week collection, Contractor’s costs shall include all delivery, usage, and collections costs for all dumpsters:

BID ITEM NO 60: UNIT SUM $____ _/ Container/month x 3 units X 4 month = $ TOTAL

TOTAL OPTION YEAR 1 (FFP line Items 40 through 60) = $_______

OPTION YEAR 2- BID ITEM NO 70:

Provide 18 -30 CY containers for Maintenance Operations at Sandy Hook Unit from May 1, 2027 through April 30, 2028 at various locations at Sandy Hook. This cost will include the delivery, usage, and pick-up of the container.

BID ITEM NO 70: UNIT SUM $ __ __/Container x 18 EA =$ ___ _TOTAL

OPTION YEAR 2- BID ITEM NO 80:

Disposal fees Cost per ton for 100.0 tons to account for the tonnage of the containers of the Maintenance Operations of mixed construction waste from May 1, 2027 through April 30, 2028

BID ITEM NO 80: UNIT SUM $ _ _/Ton x 100.0 tons =$ __ _TOTAL

OPTION YEAR 2- BID ITEM NO 90:

Provide 3 - 6-yard Single Stream Recycling Containers with 2x per week collection, Contractor’s costs shall include all delivery, usage, and collections costs for all dumpsters:

BID ITEM NO 90: UNIT SUM $_ _/ Container/month x 3 units X 4 month = $ TOTAL

TOTAL OPTION YEAR 2 (FFP line Items 70 through 90) = $_______

GRAND TOTAL: (LINE ITEMS 10 through 90) = $__________________

END OF SCHEDULE

File details come from the government source that posted it. Updated .