B08_140P2021R0018_Att04-VAReport_191008.pdf

PDF 12 MB Posted

Attached to
BOST-163343, Preserve Historic Shipyard Cranes 62
Solicitation number
140P2021R0018
Issued by

View the file

Other files

File Type Posted
140P2021R0018-0010_Att01_RevSpec099713_210512_0010.pdf PDF
Sol_140P2021R0018_Amd_0010.pdf PDF
Sol_140P2021R0018_Amd_0009.pdf PDF
140P2021R0018-0009_Att01_QuestionsAndResponses-Final_01-20_210601_0009.pdf PDF
Sol_140P2021R0018_Amd_0008.pdf PDF
Sol_140P2021R0018_Amd_0007.pdf PDF
140P2021R0018-0006_Att01_WD_MA08_Suffolk-Heavy_210430_0006.pdf PDF
Sol_140P2021R0018_Amd_0006.pdf PDF
Sol_140P2021R0018_Amd_0005.pdf PDF
Sol_140P2021R0018_Amd_0004.pdf PDF
Sol_140P2021R0018_Amd_0003.pdf PDF
140P2021R0018-0003_Att01_WD_MA08_Suffolk-Heavy_210319_0003.pdf PDF
140P2021R0018-0002_QuestionsAndResponses_01-18_210317_0002.pdf PDF
Sol_140P2021R0018_Amd_0002.pdf PDF
140P2021R0018-0001_Att01_ Preproposal Mtg Information_210302_0001.zip ZIP file
140P2021R0018-0001_Att02_WD_MA08_Suffolk-Heavy_210212_0001.pdf PDF
Sol_140P2021R0018_Amd_0001.pdf PDF
Sol_140P2021R0018.pdf PDF
B08_140P2021R0018_Att03-WD_MA08_Suffolk-Heavy_210101.pdf PDF
B08_140P2021R0018_Att01a-Specifications-Pg001-038_200625.pdf PDF
B08_140P2021R0018_Att01b-Specifications-Pg039-100_200625.pdf PDF
B08_140P2021R0018_Att01c-Specifications-Pg101-166_200625.pdf PDF
B08_140P2021R0018_Att05-PSP-sample_210215.pdf PDF
B08_140P2021R0018_Att01d-Specifications-Pg167-353_200625.pdf PDF
B08_140P2021R0018_Att05-PSP-forms_210215.zip ZIP file
B08_140P2021R0018_Att02-Drawings_200625.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Park Service Preserve Historic Ship Yard Cranes 62 & 65 Charleston Navy Yard,MA

Davis Brody Bond

Value Analysis Report Memo 08 October 2019

Charleston Navy Yard,MA

Davis Brody Bond

Value Analysis Report Memo 08 October 2019

1. Executive Summary

2. WJE Notes

3. Cost Summaries

4. Appendix A VA Presentation B WJE Memo

1. Executive Summary

On October 8, 2019 representatives from the National Park Service and the Architectural / Engineering team met at the Park to review project scope, objectives and preliminary cost estimates. A mini Value Assessment review was conducted which focused on multiple Schematic Design alternates. Issues of near term stabilization and long term conservation were discussed.

Four Schematic Design alternates were presented for each Crane, each with itemized scope tasks identified individually, each with varying alternate corrective measures and associated cost.

The Alternates were documented and presented as follows:

BASE: Minimum scope required to address ongoing continued deterioration ALT 1: Removal and minimum repairs using modern nonhistorical materials and methods.

ALT 2: Repairs using modern nonhistorical materials and methods.

ALT 3: Replacement inkind with historically appropriate materials and methods.

For the discussion and the VA assessment the individual scope items were identified as items 1 through 20. Dollar values were assigned to each, with variations per each alternate. These values were determined by the team cost estimator from Hanscomb Consulting.

In all cases near term stabilization has been recommended to address issues which could risk public safety. Beyond these items of public safety the team evaluated the individual items based on long tern conservation, ongoing and future maintenance, historic importance and cost. The result of the discussion introduced the Preferred Schematic Design Alternate. This Preferred Alternate and its associated estimated cost has been documented on the following pages.

In attendance at the park or via phone for the discussion included:

Steve Carlson, Preservation Specialist, National Parks of Boston Rani Guram, Project Manager, Denver Service Center, National Park Service (participation by phone) Mike Soliday, National Park Service (participation by phone) Mark Wagner, Davis Brody Bond Architects David Schnerch, Wiss Janney Elstner Associates, Engineers Nikki Bly, Wiss Janney Elstner Associates, Engineers

2. WJE NOTES

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

617.946.3400 tel www.wje.com

MEETING MINUTES NO. 1 October 8, 2019

NPS Cranes

VA Meeting - WJE Notes

REPORT DATE October 25, 2019

REPORTED BY Nikki Byl/David Schnerch

OWNER National Parks Services

ATTENDEES Steve Carlson

Rani Guram

Mike Soliday

Mark Wagner

David Schnerch

Nikki Byl

WJE PROJECT NO. 2017.6551.1

WJE PROJECT MGR. David Schnerch

ARCHITECT David, Brody, Bond

DISTRIBUTION Mark Wagner, mwagner@davisbrody.com

Astry Duarte, aduarte@davisbrody.com

The VA meeting took place at the NPS office at the Navy Yard with the Denver Service Center attendees calling in. After briefly discussing the project history the sequence of the topics discussed followed the memorandum prepared by WJE dated September 26, 2019 for Near/Long Term Conservation

Recommendations for Cranes 62 and 65. The discussion also included review of the Class C estimate.

Discussion Items:

Items 1-4 include the near-term stabilization of the cranes. Steve confirm the budget for these repairs is separate from the overall project and will be based on a sole-source contract.

Item 1, Backstay Stabilization – NPS agreed that backstay repairs could be performed by adding an additional steel plate or angle. NPS agreed that it is not desired to replace large members of the boom in kind.

Item 2, Backstay Weeps – No options are possible.

Item 3, Stabilization of Broken Glass – NPS requested that plywood coverings would be the base with

Lexan as an alternate.

Item 4, Stabilization of Loose Conduit, Signage, and Electrical Boxes – NPS was not concerned about the removal and disposal of conduit or electrical boxes. Replacement and reattachment of the signs should be incorporated into the longer-term project

Item 5, NPS discussed the possibility of moving Crane 62 before installing track clamps. Crane 62 may also be relocated to make the repairs more feasible. NPS will confirm the location.

Item 7, NPS discussed that they were looking for documentation and photos to determine the appropriate color for the new coating (period of significance). All elements that are safety yellow should remain so.

Item 8, DBB/WJE reiterated that hazardous materials testing (2017 ATC Report) was performed as part of the previous phase.

Item 9, Repair section loss at House (Cab) Walls – Repair with similar materials is the preferred option

NPS Cranes

VA Meeting - WJE Notes

MEETING MINUTES NO. 1 | WJE No. 2017.6551.1 | October 8, 2019 Page 2

Item 10, Repair section loss at House (Cab) Roofs – Sealing and waterproofing the roof is considered by NPS to be important as long as it does not affect the appearance.

Item 11, Repair of House (Cab) Floors – No option.

Item 12, Repair of Windows – Preferred option by closing.

Item 13, Repair of Doors – Provide a door where missing. Inoperable doors should be made operable.

Item 14, Cab Controls – Stabilization of the controls was selected.

Item 15, Steel Repairs – Replace fractured welds with new welds. Rivets replaced with bolts and nuts.

Caps should be used to retain the rivet appearance.

Item 16, Steel Coating Surface Preparation – NPS would like mechanical paint removal and removal by grit blasting to be retained as options. NPS requested that WJE provide recommendations regarding life-cycle costs.

Item 17, Steel Coating – Coatings used will depend on the level of surface preparation (Item 16).

Maintain options consistent with the recommendations for Item 16. Replication of the crane numbers should be included in the repairs.

Item 18, Cable Maintenance – The first cycle of cable maintenance will be performed as part of the repair documents. NPS will perform annual lubrication of the cables and hardware thereafter. Cables to provide a redundant means of supporting the boom and to allow installation of the hook should be included in the long term repairs.

Item 19, Inspection – The first inspection will be performed as part of the current repair project. NPS will coordinate annual inspections of the cranes or inspections after lightning strike or other significant events.

Item 20, Installation of Salvaged Elements – Crane capacity chart will be replicated and installed. The original will be retained by NPS. Installation of ladders with a lockable cage will be included in the scope for Crane 65. For Crane 62, locking of the existing ladders will be included in the current repair scope.

NPS requested the estimate be updated with the selected scope.

NPS suggested a separate meeting to discuss how best to approach the bidding, contractor selection, and contracting for the long term repair work. That meeting should include the contracting officer.

Division 1 specifications will be obtained by NPS from another project for use in the stabilization repairs.

Drawings for the long term repairs should be formatted using the NPS title block and layout.

3. COST SUMMARIES

NATIONAL PARK SERVICE

PRESERVE HISTORIC SHIP YARD CRANES 62 & 65

Charlston Navey Yard, MA DBB Job # 21713.AA

VALUE ASSESSMENT COST ESTIMATE SUMMARY

No. Description Base Scope Base Estimate Alternate Estimate

ALT 1

NON-HISTORIC

Alternate Estimate

ALT 2

NON-HISTORIC

Alternate Estimate

ALT 3

IN KIND HISTORIC

REPAIR

Addition of new steel plate or angle

$ 6,180 $ 9,270 $ 6,180 Addition of new steel plate or angle

Remove glass and install plywood

$ 11,400 $ 31,800

$ 22,800 $ 22,800 Remove glass and install Lexan

Remove all $ 5,100 $ 5,100

$ 8,200

$ 12,300

Repair $ 5,850 $ 9,000 $ 9,000

$ 6,750

Repair $ 3,250 $ 4,250 $ 4,250

$ 5,000

Repair $ 2,600 $ 3,400 $ 3,400 $ 2,600

Address existing windows to maintain

$ 4,160 $ 9,200 $ 9,200 $ 4,160 weather tight exterior

$ 3,640 $ 8,050

$ 10,500 $ 10,500 Make all doors operable. Replace doors in kind where missing

Stabilize controls in operator cab

$ 5,000 $ 6,250 $ 6,250 Stabilize controls by repairing bases

$ 8,500

$ 2,600

Install additional steel plates angles at areas of section loss

$ 16,000 R e p

Repair/replace damaged elements in kind $ 22,500

October 8, 2019

PREFERRED ALTERNATE

Replace deteriorated framing and cladding in kind

Replace deteriorated framing and roofing in kind

Repair areas of section loss at the house and operators cab floor. Structural framing for these elements may need to be assessed after panel removal

Address existing windows to maintain weather tight exterior.

per Value Assessment

08 October 2019

Stabilize potential fall hazards: Loose conduit, signage, electrical boxe.

Remove all

1A Backstay Stabilization Repair backstay at areas of section loss

3A Fall Hazards Stabilize potential fall hazards: Broken Glass

4A Fall Hazards

Stabilize potential fall hazards: Loose conduit, signage, electrical boxes

13A House/Cab Doors

14A

11A

Alternates

Replace backstay elements in kind

Remove glass and install new glass in Kind

Remove glass and install Lexan

Item

10A House/Cab Roofs

Repair areas of section loss at the house roofs.

Structural framing for these elements will need to be assessed after panel removal

9A House Walls

Repair areas of section loss at the house walls.

Structural framing for these elements will need to be assessed after panel removal

Cab Controls

Stabilize controls in operators cab.

Stabilize controls by removing and reinstalling with new bases

Remove controls

Stabilize/reattach

Remove and repair/replace in kind

Repair areas of section loss at the house and operators cab floor. Structural framing for these elements may need to be assessed after panel removal

Install waterproofing coating and additional flashing at seams,valleys and penetrations in order to improve water tightness and durability

Replace deteriorated framing and roofing in kind

Repair with alternate material

Replace deteriorated framing and cladding in kind

House/Cab Floors

Replace deteriorated framing and flooring in kind

Address existing doors to maintain weather tight exterior.

Restore doors to the original configuration and appearance

Stabilize controls by repairing bases

NPS CRANE 62- SD ALTERNATES / PREFERRED ALTERNATE

Replace doors in kind

12A House/Cab Windows Address existing windows to maintain weather tight exterior.

Restore windows to the original configuration and appearance (repair or replace frames, recoat frames, install glass)

Steel components should be assessed for section loss at the time of repair, after the removal of corrosion product. Careful attention should be given to crevice

R e p

Replace bolts/rivets in kind $ 17,500 $ 17,500 Replace bolts/rivets in kind

R e m o

Remove damaged elements and repair fracture welds

$ 20,000

Mechanical removal (SSPC SP-

3/SP-11),

$ 18,580 A b r

Abrasive blasting (SSPC SP-6/SP-10) $ 45,000 $ 45,000 $ 45,000 $ 45,000 Abrasive blasting (SSPC SP-6/SP-10)

Pack rust, ground out of joints

Penetrating sealer installed at joints

Spot prime/high quality coating system

$ 17,450 $ 20,600 $ 20,600

Seal open joints

$ 22,850 $ 22,850 Acrylic coating system

**Manufacturer research required

N/A $ - $ 5,000 $ 5,000 $ 5,000 $ 5,000 Replace missing or damaged truck elements

$ 850 $ 850 $ 850 $ 850 Replace or restore crane capacity chart

BASE ALT 1 ALT 2 ALT 3 PREFERRED

STABILIZATION TOTAL COST (without mark-up) = 22,680$ 22,680$ 31,000$ 53,370$ 34,080$

STABILIZATION TOTAL COST (WITH mark-up) = 78,700$ 78,700$ 107,570$ 185,194$ 118,258$

BASE TOTAL COST (without mark-up) = 76,530$ 109,390$ 127,600$ 141,050$ 127,960$

BASE TOTAL COST (WITH mark-up) = 293,875$ 420,058$ 489,984$ 541,632$ 491,366$

TOTAL COST (WITH 3.65 mark-up) = 372,575$ 498,757$ 597,554$ 726,826$ 609,624$

17A Steel Coating

Steel surfaces should be primed and coated with a high-performance coating system designed to protect structures in marine environments Acrylic coating system

Zinc primer/epoxy coating system everywhere

16A Prepare Steel (Coating)

Preparation: accessible corrosion product, the existing coatings, and all contaminants should be removed from the surface of the steel, in preparation for the application of a high-performance coating

15A Steel Repairs product. Careful attention should be given to crevice corrosion, where visible

Replace or restore crane capacity chart

Replace missing or damaged truck elements

20A Installation of salvaged elements

Install salvaged crane elements from the previously discassembled Crane 63

Charlston Navey Yard, MA DBB Job # 21713.AA

VALUE ASSESSMENT COST ESTIMATE SUMMARY

No. Description Base Scope Base Estimate Alternate Estimate

Added Cost including

Mark ups

Alternate Estimate

ALT 1

NON-HISTORIC

Alternate Estimate

ALT 2

NON-HISTORIC

Alternate Estimate

ALT 3

IN KIND HISTORIC

REPAIR

Addition of new steel plate or angle

$ 6,180 $ 9,270 $ 9,270 $ 6,180

Remove glass and install plywood

$ 11,400 $ 31,800 $ 42,840 $ 31,800

$ 22,800 $ 23,940 $ 22,800 $ 22,800 Remove glass and install Lexan

Remove all $ 5,100 $ 5,100

$ 8,200 $ 6,510 $ 8,200

$ 12,300 $ 15,120 $ 12,300

Repair $ 5,850 $ 9,000 $ 6,615 $ 9,000 $ 9,000 Replace deteriorated framing and cladding in kind

$ 6,750 $ 1,890 $ 6,750

Repair $ 3,250 $ 4,250 $ 2,100 $ 4,250 $ 4,250 Replace deteriorated framing and roofing in kind

$ 5,000 $ 3,675 $ 5,000

Repair $ 2,600 $ 3,400 $ 1,680 $ 3,400 $ 3,400 $ 2,600

Address existing windows to maintain

$ 4,160 $ 9,200 $ 10,584 $ 9,200 $ 9,200 $ 4,160 Address existing windows to maintain weather tight exterior.

weather tight exterior

$ 3,640 $ 8,050 $ 9,261 $ 8,050

$ 10,500 $ 14,406 $ 10,500 $ 10,500 Make all doors operable. Replace doors in kind where missing

$ 1,750 $ (3,969) $ 1,750

Stabilize controls in operator cab

$ 5,000 $ 6,250 $ 2,625 $ 6,250 $ 6,250 Stabilize controls by repairing bases

$ 8,500 $ 7,350 $ 8,500

$ 2,600 $ (5,040) $ 2,600

Install additional steel plates angles at areas of section loss

$ 16,000 Repair/replace damaged elements in kind $ 22,500 $ 13,650 $ 22,500

Replace bolts/rivets in kind $ 17,500 $ 3,150 $ 17,500 $ 17,500 Replace bolts/rivets in kind

Remove damaged elements and repair fracture welds

$ 20,000 $ 8,400 $ 20,000

October 8, 2019

Repair areas of section loss at the house and operators cab floor. Structural framing for these elements may need to be assessed after panel removal

PREFERRED ALTERNATE

per Value Assessment

08 October 2019

Stabilize potential fall hazards: Loose conduit, signage, electrical boxe.

Remove all

Replace backstay elements in kind

Alternates

Replace deteriorated framing and roofing in kind

Repair with alternate material

Replace deteriorated framing and cladding in kind

Replace backstay elements in kind

Remove glass and install new glass in Kind

Remove glass and install Lexan

Stabilize/reattach

Remove and repair/replace in kind

NPS CRANE 65- SD ALTERNATES / PREFERRED ALTERNATE

Replace doors in kind

12A House/Cab Windows Address existing windows to maintain weather tight exterior.

Restore windows to the original configuration and appearance (repair or replace frames, recoat frames, install glass)

15A Steel Repairs

Steel components should be assessed for section loss at the time of repair, after the removal of corrosion product. Careful attention should be given to crevice corrosion, where visible

Address existing doors to maintain weather tight exterior.

Restore doors to the original configuration and appearance

Address operability of doors

Stabilize controls by repairing bases

Stabilize controls by removing and reinstalling with new bases

Remove controls

Install waterproofing coating and additional flashing at seams,valleys and penetrations in order to improve water tightness and durability

9A House Walls

Repair areas of section loss at the house walls.

Structural framing for these elements will need to be assessed after panel removal

Cab Controls

Stabilize controls in operators cab.

Repair areas of section loss at the house and operators cab floor. Structural framing for these elements may need to be assessed after panel removal 11A House/Cab Floors

Replace deteriorated framing and flooring in kind

10A House/Cab Roofs

Repair areas of section loss at the house roofs.

Structural framing for these elements will need to be assessed after panel removal

Item

1A Backstay Stabilization Repair backstay at areas of section loss

3A Fall Hazards Stabilize potential fall hazards: Broken Glass

4A Fall Hazards

Stabilize potential fall hazards: Loose conduit, signage, electrical boxes

13A House/Cab Doors

14A

Mechanical removal (SSPC SP-

3/SP-11),

$ 18,580 Abrasive blasting (SSPC SP-6/SP-10) $ 45,000 $ 55,482 $ 45,000 $ 45,000 $ 45,000 $ 45,000 Abrasive blasting (SSPC SP-6/SP-10)

Pack rust, ground out of joints

Penetrating sealer installed at joints

Spot prime/high quality coating system

$ 17,450 $ 20,600 $ 6,615 $ 20,600 $ 20,600

Seal open joints

$ 22,850 $ 11,340 $ 22,850 $ 22,850 Acrylic coating system

**Manufacturer research required

BASE ALT 1 ALT 2 ALT 3 PREFERRED

STABILIZATION TOTAL COST (without mark-up) = 22,680$ 22,680$ 31,000$ 53,370$ 34,080$

STABILIZATION TOTAL COST (WITH mark-up) = 78,700$ 78,700$ 107,570$ 185,194$ 118,258$

BASE TOTAL COST (without mark-up) = 76,530$ 99,050$ 121,750$ 135,200$ 122,110$

BASE TOTAL COST (WITH mark-up) = 293,875$ 380,352$ 467,520$ 519,168$ 468,902$

TOTAL COST (WITH 3.65 mark-up) = 372,575$ 459,052$ 575,090$ 704,362$ 587,160$

16A Prepare Steel (Coating)

Preparation: accessible corrosion product, the existing coatings, and all contaminants should be removed from the surface of the steel, in preparation for the application of a high-performance coating

Acrylic coating system

Zinc primer/epoxy coating system everywhere

17A Steel Coating

Steel surfaces should be primed and coated with a high-performance coating system designed to protect structures in marine environments

Charlston Navey Yard, MA DBB Job # 21713.AA

VALUE ASSESSMENT COST ESTIMATE SUMMARY

TOTAL PROJECT COSTS - SD ALTERNATES / PREFERRED ALTERNATE

CRANE 62

BASE ALT 1 ALT 2 ALT 3 PREFERRED ALT

IMMEDIATE STABILIZATION $80,135

items 1-4 $78,700 $107,570 $185,194 $118,258 items 5-20 $320,011 $487,066 $499,392 $532,224 $491,366

LONG TERM PRESERVATION $320,011 $565,766 $606,962 $717,418 $609,624

CRANE 65

BASE ALT 1 ALT 2 ALT 3 PREFERRED ALT

IMMEDIATE STABILIZATION $83,135

items 1-4 $78,700 $107,570 $185,194 $118,258 items 5-20 $354,807 $451,699 $476,928 $509,760 $468,902

LONG TERM PRESERVATION $354,807 $530,399 $584,498 $694,954 $587,160

BASE = Provides non-historical repairs necessary to stabilize and prevent further deterioration

ALT 1 = Provides minimum upgraded Non-historical repairs

ALT 2 = Provides upgraded Non-historical repairs meeting a higher aesthetic standard using modern materials

ALT 3 = Provides historical repairs, replacing materials specific to the required period of significance

PREFERRED ALT = scope requirements per Value Assessment discussion on 08 October 2019

CRANES 62 & 65 TOTAL

BASE ALT 1 ALT 2 ALT 3 PREFERRED ALT

TOTAL IMMEDIATE STABILIZATION = $163,270 $157,400 $215,140 $370,388 $236,516

TOTAL LONG TERM PRESERVATION = $674,818 $938,765 $976,320 $1,041,984 $960,268

TOTAL COST = $838,088 $1,096,165 $1,191,460 $1,412,372 $1,196,784

October 8, 2019

4. Appendix

A VA Presentation

Charleston Navy Yard,MA

Value Analysis Presentation 08 October 2019

Agenda:

1. Introduction

2. Design History & Approach

3. Value Assessment

a. Stabilization / Preservation Alternates

b. Value / Cost Evaluation

Davis Brody Bond

Value Analysis Presentation 08 October 2019

INDEX OF DRAWINGS:

S000 COVER SHEET

S001 GENERAL NOTES

S002 STEEL REPAIR NOTES

S201 CRANE 62 ELEVATIONS

S202 CRANE 65 ELEVATIONS

S501 REPAIR DETAILS

LOCATION MAP

N.T.S.

CRANE 65

CRANE 62

MAP DATA ©2019 GOOGLE

N

CRANE 65

CRANE 62

INDEX OF DRAWINGS:

S000 COVER SHEET

S001 GENERAL NOTES

S002 STEEL REPAIR NOTES

S201 CRANE 62 ELEVATIONS

S202 CRANE 65 ELEVATIONS

S501 REPAIR DETAILS

LOCATION MAP

N.T.S.

CRANE 65

CRANE 62

MAP DATA ©2019 GOOGLE

N

CRANE 65

CRANE 65

Figure 15. Backstay arrows show areas of section loss of the steel web

Figure 16. Close-up of section loss at the web of the backstay

Figure 7. Side of house with projecting operator’s cab (highlighted)

Figure 8. Roof with A-frame/backstay assembly

Figure 34. Typical example of failed coating with surface corrosion

Figure 8. Roof with A-frame/backstay assembly

Figure 15. Water inside the steel U-shaped built-up section

Figure 20. pack rust at the lower backstay connection

Figure 19. Corrosion at rivets

Figure 53. Peeling flaking coating at the interior of the house

Figure 47. Machine house interior

Figure 48. Loss of glazing at operator’s cab

Figure 51. Sliding door adjacent to operator’s cab

(red) and removed electrical room door (yellow)

WJE

Observation #1, (north side)

WJE Observation #2, (south side)

WJE

Observation #4

WJE

Observation #3, (north side)

WJE

Observation #5 (south side)

WJE

Observation #7 (both sides)

WJE

Observation #9 (south side)

WJE

Observation #7 (both sides)

WJE Observation #15 (north side)

WJE

Observation #19

WJE

Observation #20 (all sides)

WJE

Observation #20

WJE Observation #22 (roof)

WJE

Observation #26 (south side)

WJE

Observation #33

WJE

Observation #34

WJE

Observation #21

WJE

Observation #14 ne e wn

WJE

Observation #11

WJE

Observation #6 (one of multiple locations)

WJE

Observation #11

WJE

Observation #32 (south side)

WJE

Observation #31 (north side)

Observation #1, (north side)

WJE

Observation #3 (both sides)

WJE

Observation #2

WJE

Observation #23

WJE

Observation #25 (all sides)

WJE Observation #27 (roof)

WJE

Observation #40

WJE

Observation #26

Observation #13 rane the s ple hown

WJE

Observation #4

WJE

Observation #5 (both sides)

WJE

Observation #8

WJE Observation #11 (Location A)

WJE Observation #11 (Location B)

WJE Observation #15

WJE Observation #16

WJE

Observation #24

WJE

Observation #33

WJE

Observation #39

WJE

Observation #7

WJE

Observation #7

WJE

Observation #9

WJE

Observation #21

WJE

Observation #22

WJE

Observation #31

WJE

Observation #32

WJE

Observation #37

Observation #38

Plotted: 10/3/2019 1:37 PM by Byl, Nikki File Name: \\wjebos1\projects\2017\2017.3xxx\2017.3665.1 - nps historic crane development (das)\Drawings\Sheets\2017-3665-1-S000.dwg

Seal

Architect

Client

DescriptionDateMark

Date

Project No.

Scale

Checked

Sheet Title

Sheet No.

Drawn

Project

A

B

1 2 3 4

C

D

C op yr ig ht

A ll rig ht s r es er ve d.

N o pa rt of th is d oc um en t m ay b e re pr od uc ed in a ny fo rm o r b y an y m ea ns w ith ou t pe rm is si on fr om

W is s, Ja nn ey

, E ls tn er

A ss oc ia te s, In c.

(W

JE

W

JE

d is cl ai m s a ny re sp on si bi lit y fo r i ts u na ut ho riz ed u se

THIS SHEET PLOTS FULL SIZE

AT 11x17 (INCHES)

0 1/2" 1"

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

617.946.3400 tel | 617.946.0740 fax www.wje.com

ENGINEERS

ARCHITECTS

MATERIALS SCIENTISTS

I

S

S

U

E

D

F

O

B

I

D

NPS Crane Stabilization

114 16th St

Charlestown, MA 02129

National Park Service, DSC

12795 W. Alameda Pkwy

Denver CO, 80225

2017.3665.1

October 3, 2019

NB/CH

DAS

As Noted

COVERSHEET

S000

INDEX OF DRAWINGS:

S000 COVER SHEET

S001 GENERAL NOTES

S002 STEEL REPAIR NOTES

S201 CRANE 62 ELEVATIONS

S202 CRANE 65 ELEVATIONS

S501 REPAIR DETAILS

Client:

LOCATION MAP

N.T.S.

NPS CRANE STABILIZATION

WJE Project No. 2017.3665.1

IDIQ Contract No. P15PC00035, Task Order 140P2019F0148, PMIS No. BOST - 163343

Client:Client: Architect:

National Park Service

Denver Service Center

12795 W. Alameda Pkwy

Denver CO, 80225

Client:

CRANE 65

CRANE 62

MAP DATA ©2019 GOOGLE

N

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

Engineer:

Davis Brody Bond, LLP

One New York Plaza, Ste. 4200

New York, NY 10004

GENERAL NOTES

1. CONTRACTOR SHALL VERIFY ALL DIMENSIONS AND

CONDITIONS IN FIELD. DO NOT SCALE DRAWINGS.

DIMENSIONS SHOWN ON THE DRAWINGS ARE TAKEN FROM

THE ORIGINAL CONSTRUCTION DOCUMENTS AND ARE

PROVIDED FOR INFORMATION ONLY.

2. CONTRACTOR SHALL VERIFY ALL QUANTITIES. QUANTITIES

SHOWN ARE FOR ESTIMATING PURPOSES ONLY.

3. THE CONTRACTOR SHALL COORDINATE REQUIREMENTS AND

PROVIDE PROOF OF INSURANCE PRIOR TO THE START OF

WORK.

4. THERE SHALL BE COMPLETE AND TIMELY COOPERATION

BETWEEN THE GENERAL CONTRACTOR AND

SUB-CONTRACTORS TO ENSURE SATISFACTORY PROGRESS

AND PERFORMANCE OF THE WORK.

5. THE CONTRACTOR SHALL SECURE AND PAY FOR ALL

PERMITS, LICENSES AND GOVERNMENT FEES AS REQUIRED.

THE CONTRACTOR SHALL COMPLY WITH CODES,

ORDINANCES, RULES, REGULATIONS, ORDERS AND OTHER

LEGAL REQUIREMENTS OF PUBLIC AUTHORITY, WHICH BEAR

ON THE PERFORMANCE OF THE WORK.

6. CONTRACTOR SHALL PROMPTLY SUBMIT VERBAL AND

WRITTEN NOTICE TO THE ARCHITECT/ENGINEER OF

OBSERVED VARIANCE OF THE CONTRACT DOCUMENTS FROM

ACTUAL ON-SITE CONDITIONS.

7. CONTRACTOR SHALL SUPPLY THE OWNER WITH MATERIAL

SAFETY DATA SHEETS (MSDS) FOR EACH MATERIAL THAT

WILL BE BROUGHT ONTO THE JOB SITE AND SHALL COMPLY

WITH THE REQUIREMENTS OF THE OSHA HAZARD

COMMUNICATION STANDARD

8. THE CONTRACTOR MUST SUBMIT DEMOLITION AND

CONSTRUCTION SCHEDULES TO THE OWNER AND

ARCHITECT/ENGINEER FOR APPROVAL PRIOR TO BEGINNING

DEMOLITION

9. THE PRODUCTS SPECIFIED ARE BELIEVED TO HAVE

PROPERTIES ADEQUATE FOR SUCCESSFUL COMPLETION OF

THE WORK. IF THE CONTRACTOR HAS FOUND THESE

PRODUCTS TO BE UNACCEPTABLE OR HAS HAD DIFFICULTY

USING THESE MATERIALS, THE CONTRACTOR SHALL

IMMEDIATELY INFORM THE ARCHITECT/ENGINEER

10. CONTRACTOR IS RESPONSIBLE FOR MEANS AND METHODS

OF THE REPAIR WORK

11. WISS, JANNEY, ELSTNER ASSOCIATES, INC. (WJE) SHALL NOT

HAVE CONTROL OVER OR CHARGE OF AND SHALL NOT BE

RESPONSIBLE FOR CONSTRUCTION MEANS, METHODS,

TECHNIQUES, SEQUENCES OR PROCEDURES, OR FOR

SAFETY PRECAUTIONS AND SAFETY PROGRAMS IN

CONNECTION WITH THE PROJECT. SINCE THESE ARE THE

RESPONSIBILITY OF OTHERS, WJE SHALL NOT BE

RESPONSIBLE FOR THE CONTRACTOR'S SCHEDULES OR

FAILURE TO CARRY OUT THE PROJECT IN ACCORDANCE

WITH CONTRACT DOCUMENTS. WJE SHALL NOT HAVE

CONTROL OVER OR CHARGE OF ACTS OR OMISSIONS OF THE

CONTRACTOR, SUBCONTRACTORS, OR THEIR AGENTS OR

EMPLOYEES, OR OF ANY OTHER NON-WJE PERSONS

PERFORMING PORTIONS OF THE PROJECT

12. CONTRACTOR IS SOLELY RESPONSIBLE FOR ALL JOB

SAFETY DURING THE REPAIR WORK, INCLUDING, BUT NOT

LIMITED TO THEIR SUBCONTRACTORS.

13. WORK REQUIRED SHALL PROCEED ONLY AT THE DIRECTION

OF THE OWNER ACCORDING TO SCHEDULES AS MUTUALLY

AGREED UPON. THE CONTRACTOR SHALL PROVIDE ALL

TEMPORARY CONTROLS AS NECESSARY TO ALLOW FOR SITE

OPERATIONS.

14. THE CONTRACTOR WILL LIMIT ON-SITE STORAGE OF

MATERIALS TO THOSE AREAS IDENTIFIED BY THE OWNER.

THE CONTRACTOR SHALL NOT UNREASONABLY ENCUMBER

SITE WITH MATERIALS OR EQUIPMENT. THE MATERIALS AND

EQUIPMENT SHALL BE CONFINED TO THE AREAS INDICATED

IN THE CONTRACT DOCUMENTS OR BY THE DIRECTION OF

THE OWNER OR ARCHITECT/ENGINEER. DO NOT LOAD

STRUCTURE WITH WEIGHT THAT WILL ENDANGER

STRUCTURE. CONTRACTOR SHALL ASSUME FULL

RESPONSIBILITY FOR THE PROTECTION AND SAFEKEEPING

OF PRODUCTS STORED ON PREMISES. CONTRACTOR SHALL

MOVE ANY STORED MATERIAL OR PRODUCTS WHICH

INTERFERE WITH OPERATIONS OF THE OWNER.

CONTRACTOR SHALL STORE MATERIAL ONLY IN AREAS

PROVIDED BY THE OWNER.

15. WATER AND ELECTRICITY MAY BE TAKEN FROM SITE FOR

CONSTRUCTION PURPOSES ONLY AT AREAS IDENTIFIED

ACCEPTABLE BY THE OWNER.

16. CONTRACTOR SHALL PROVIDE AND MAINTAIN REQUIRED

DUST BARRIERS, CANOPIES, BARRICADES, PROTECTION AND

WARNING LIGHTS IN GOOD CONDITION UNTIL THE

COMPLETION OF THE WORK REQUIRING SUCH PROTECTION

AND THEN REMOVE THE SAME. ALL CANOPIES AND

BARRICADES SHALL COMPLY WITH FEDERAL, STATE AND

LOCAL LAWS AND REGULATIONS.

17. THE CONTRACTOR SHALL MAINTAIN PREMISES FREE FROM

ACCUMULATIONS OF WASTE MATERIAL AND RUBBISH.

18. THE CONTRACTOR IS TO RETURN DAMAGED AREAS TO

ORIGINAL CONDITION.

19. THE CONTRACTOR SHALL PROTECT GROUNDS WHEN

PERFORMING WORK. THE CONTRACTOR WILL BE

RESPONSIBLE FOR DAMAGE TO GROUNDS AND BE REQUIRED

TO REPAIR OR REPLACE AS NECESSARY.

20. CONTRACTOR SHALL COMPLY WITH ALL NPS SECURITY

PROCEDURES.

21. COSTS CAUSED BY ILL-TIMED WORK, DEFECTIVE WORK OR

WORK NOT CONFORMING TO THE CONTRACT DOCUMENTS,

ARE THE RESPONSIBILITY OF THE CONTRACTOR.

22. THE CONTRACTOR SHALL PROVIDE SHORING, BRACING AND

SUPPORT AS REQUIRED TO MAINTAIN THE STRUCTURAL

INTEGRITY OF THE NEW OR EXISTING CONSTRUCTION

DURING THE WORK. CONSTRUCTION DEBRIS SHALL BE

REMOVED IN A MANNER THAT AVOIDS OVERLOADING

ADJACENT STRUCTURAL MEMBERS.

23. THE CONTRACTOR AND HIS RESPECTIVE SUBCONTRACTORS

SHALL EACH HAVE FIVE OR MORE YEARS EXPERIENCE

PERFORMING REPAIR WORK SIMILAR IN SIZE, TYPE, AND

COMPLEXITY TO WHAT IS SHOWN IN THE CONTRACT

DOCUMENTS.

24. ENFORCE STRICT DISCIPLINE AND GOOD ORDER AMONG

EMPLOYEES. DO NOT EMPLOY UNFIT PERSONS OR PERSONS

NOT SKILLED IN THE ASSIGNED TASK.

25. WHERE A DETAIL IS SHOWN FOR ONE CONDITION, IT SHALL

APPLY FOR ALL LIKE OR SIMILAR CONDITIONS, EVEN THOUGH

NOT SPECIFICALLY MARKED ON THE DRAWINGS.

26. ALL CONSTRUCTION SHALL BE SUBJECT TO REVIEW BY THE

ARCHITECT/ENGINEER BEFORE IT IS CONCEALED FROM

VIEW. COORDINATE EXPECTED REVIEW ITEMS WITH THE

ARCHITECT/ENGINEER PRIOR TO THE START OF

CONSTRUCTION AND PROVIDE REASONABLE NOTIFICATION

TO THE ARCHITECT/ENGINEER TO ALLOW FOR SUCH REVIEW

AS THE WORK PROCEEDS.

27. REMOVE AND DISPOSE OF IN A PROPER MANNER (OFF-SITE)

ALL EXISTING MATERIAL REMOVED FROM THE CRANE

DURING THE COURSE OF THE WORK ON A DAILY BASIS.

REMOVAL AND DISPOSAL SHALL BE SATISFACTORY TO THE

ARCHITECT/ENGINEER AND OWNER

28. CONTRACTOR SHALL COORDINATE USE OF PREMISES

UNDER THE DIRECTION OF THE OWNER. TEMPORARY

DISRUPTIONS TO THE USE OF THE SITE BY EMPLOYEES AND

PUBLIC, INCLUDING NOISE, DUST, AND DISRUPTION OF

UTILITIES, SHALL BE COORDINATED A MINIMUM OF 48 HOURS

IN ADVANCE AND APPROVED BY THE OWNER. CONTRACTOR

WORK NOT COORDINATED IN ADVANCE WHICH CAUSES

DISRUPTIONS TO THE USE OF THE SITE BY EMPLOYEES AND

PUBLIC MAY BE STOPPED BY THE OWNER AND SHALL NOT BE

COMMENCED AGAIN UNTIL PROPER COORDINATION IS

ACHIEVED. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL

COSTS RESULTING FROM WORK STOPPAGES OR DELAYS

CAUSED BY CONTRACTORS LACK OF COORDINATION WITH

THE OWNER.

29. THESE DRAWINGS APPLY TO THE PROJECT IDENTIFIED IN

THE TITLEBLOCK ONLY AND SHALL NOT BE USED FOR ANY

OTHER PURPOSE WITHOUT THE EXPRESSED WRITTEN

CONSENT OF WJE.

30. REFER TO PROVIDED HAZARDOUS MATERIALS TEST REPORT

PREPARED BY ATC GROUP SERVICES, LLC, DATED

NOVEMBER 1, 2017. ALL WORK-SITE PREPARATIONS AND

PRACTICES TO BE CONDUCTED IN ACCORDANCE WITH ALL

FEDERAL, MASSACHUSETTS, AND APPROPRIATE CITY AND

OTHER LOCAL REGULATIONS, STANDARDS AND CODES

PERTAINING TO WORKER HEALTH PROTECTION,

PROTECTION OF THE PUBLIC HEALTH AND THE

ENVIRONMENT.

APPLICABLE CODES AND STANDARDS

AMERICAN INSTITUTE OF STEEL CONSTRUCTION

AMERICAN WELDING SOCIETY

ASTM INTERNATIONAL

MASSACHUSETTS STATE BUILDING CODE, NINTH EDITION

OCCUPATIONAL SAFETY AND HEALTH ACT

ABBREVIATIONS

MIN. MINIMUM

N.T.S NOT TO SCALE

TYP. TYPICAL

V.I.F. VERIFY IN FIELD

SCOPE OF WORK

THIS PROJECT INCLUDES:

1. REMOVAL AND STABILIZATION OF LOOSE AND DISPLACED

ELEMENTS AS SHOWN ON DRAWINGS.

2. CREATE HOLES AT BACK BRACE ELEMENT AT LOCATIONS

SHOWN ON DRAWINGS.

3. PREPARATION AND WELDING OF NEW STEEL PLATES TO

MAST BACK BRACES (FLANGES AND WEBS) AS SHOWN ON

DRAWINGS.

Plotted: 10/3/2019 1:38 PM by Byl, Nikki File Name: \\wjebos1\projects\2017\2017.3xxx\2017.3665.1 - nps historic crane development (das)\Drawings\Sheets\2017-3665-1-S001.dwg

Seal

Architect

Client

DescriptionDateMark

Date

Project No.

Scale

Checked

Sheet Title

Sheet No.

Drawn

Project

A

B

1 2 3 4

C

D

C op yr ig ht

A ll rig ht s r es er ve d.

N o pa rt of th is d oc um en t m ay b e re pr od uc ed in a ny fo rm o r b y an y m ea ns w ith ou t pe rm is si on fr om

W is s, Ja nn ey

, E ls tn er

A ss oc ia te s, In c.

(W

JE

W

JE

d is cl ai m s a ny re sp on si bi lit y fo r i ts u na ut ho riz ed u se

THIS SHEET PLOTS FULL SIZE

AT 11x17 (INCHES)

0 1/2" 1"

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

617.946.3400 tel | 617.946.0740 fax www.wje.com

ENGINEERS

ARCHITECTS

MATERIALS SCIENTISTS

I

S

S

U

D

NPS Crane Stabilization

114 16th St

Charlestown, MA 02129

National Park Service, DSC

NB/CH

DAS

As Noted

GENERAL NOTES

S001

REPAIR NOTES

PART 1 - GENERAL

1.1 SUMMARY

A. SECTION INCLUDES: FABRICATION AND INSTALLATION OF

STEEL ELEMENTS.

1.2 REFERENCES

A. DEFINITIONS

1. WPS: WELD PROCEDURE SPECIFICATION

B. REFERENCE STANDARDS

1. AISC 360: SPECIFICATION FOR STRUCTURAL STEEL BUILDINGS

2. ASTM INTERNATIONAL

3. AWS D1.1: STRUCTURAL WELDING CODE - STEEL

1.3 REQUIRED SUBMITTALS

A. MILL CERTIFICATION REPORTS FOR ALL PLATES

B. WELDING CONSUMABLES MANUFACTURER'S CERTIFICATES

C. WELDER PERFORMANCE QUALIFICATION RECORD

D. WELDING QUALIFICATION DATA INCLUDING: WPS FOR EACH

WELD TYPE, PROCESS, AND POSITION

E. WELDER QUALIFICATION. MUST BE KEPT ON FILE ON SITE

F. FABRICATOR QUALIFICATIONS

G. INSTALLER QUALIFICATIONS

PART 2 - PRODUCTS

2.1 STEEL ELEMENTS

A. ALL NEW STEEL SHAPES: ASTM A36/36M

B. APPLY ZINC COATING BY HOT-DIP PROCESS IN ACCORDANCE

WITH ASTM A123.

2.2 AUXILIARY MATERIALS

A. WELDING ELECTRODES: COMPLY WITH AWS D1.1 TABLE 3.1

REQUIREMENTS FOR GROUP II OR HIGHER STEEL

SPECIFICATIONS, AND ELECTRODES LISTED IN APPROVED

WPSs.

2.3 FABRICATION

A. FABRICATE IN SHOP TO THE GREATEST EXTENT POSSIBLE.

COMPLY WITH REQUIREMENTS OF AISC 303, INCLUDING

TOLERANCES.

1. FLAME CUTTING OF NEW OR EXISTING STEEL IS NOT

PERMITTED.

2. GRIND CUT EDGES TO BE WELDED TO COMPLY WITH AWS D1.1

PART 3 - EXECUTION

3.1 EXAMINATION

A. EXAMINE SUBSTRATES AND CONDITIONS FOR COMPLIANCE

WITH REQUIREMENTS AND OTHER CONDITIONS AFFECTING

INSTALLATION OR PERFORMANCE.

3.2 PROTECTION

A. TAKE PRECAUTIONS TO ENSURE THE SAFETY OF PEOPLE AND

PROTECTION OF PROPERTY.

B. ERECT TEMPORARY BARRIERS, WALKWAYS, CANOPIES,

WALLS, ETC AS NECESSARY.

C. ASSUME RESPONSIBILITY FOR INJURY TO PERSONS OR

PROPERTY DUE TO WORK AND REMEDY AT NO COST TO THE

OWNER.

D. LIMIT ACCESS TO WORK AREA.

E. PROTECT FROM DAMAGE, ALL ELEMENTS OF COMPLETED

WORK, ORIGINAL CONSTRUCTION, AND PREVIOUS

FABRICATIONS WHICH ARE TO REMAIN.

3.3 INSTALLATION, GENERAL

A. INSTALL MISCELLANEOUS STEEL ELEMENTS IN ACCORDANCE

WITH REQUIREMENTS OF AISC 303.

B. POSITION STEEL ELEMENTS ACCURATELY IN LOCATION,

ALIGNMENT, AND ELEVATION INDICATED; WITH EDGES AND

SURFACES LEVEL, PLUMB, TRUE, AND FREE OF RACK.

C. MAINTAIN ERECTION TOLERANCES SPECIFIED BY AISC 303.

D. PERFORM CUTTING, DRILLING, AND FITTING REQUIRED TO

INSTALL STEEL ELEMENTS. FLAME CUTTING IS PROHIBITED.

E. BEFORE ASSEMBLY, REMOVE COATING, CLEAN SURFACES

THAT WILL BE IN PERMANENT CONTACT WITH ADJACENT

ELEMENTS.

F. PERFORM NECESSARY ADJUSTMENTS TO COMPENSATE FOR

DISCREPANCIES IN ELEVATIONS AND ALIGNMENT.

G. DO NOT USE THERMAL CUTTING DURING INSTALLATION.

H. GALVANIZED SURFACES: CLEAN AREAS WHERE GALVANIZING

IS DAMAGED OR MISSING AND REPAIR GALVANIZING USING

PAINTS CONTAINING ZINC DUST, TO COMPLY WITH ASTM

A780/A780M.

3.4 WELDED CONNECTIONS

A. COMPLY WITH AWS D1.1 FOR PREHEATING, REQUIRED

PROFILES, TOLERANCES, WELD APPEARANCE, WELD QUALITY,

AND FOR METHODS USED IN CORRECTING WELDING WORK.

B. PERFORM WELDING IN ACCORDANCE WITH WPSs BY

PROPERLY CERTIFIED WELDERS.

C. REMOVE DIRT, GREASE, OIL, AND FOREIGN MATTER PRIOR TO

WELDING.

D. PREHEAT BASE METAL AND MAINTAIN INTERPASS

TEMPERATURES IN ACCORDANCE WITH AWS D1.1.

E. REMOVE SLAG FROM COMPLETED WELDS AND CLEAN

ADJACENT WELD METAL BY BRUSHING OR OTHER SUITABLE

MEANS.

3.5 FIELD QUALITY CONTROL

A. CONTRACTOR TO PROVIDE ACCESS FOR NPS, NPS

REPRESENTATIVES, AND STRUCTURAL ENGINEER TO

PERFORM INSPECTIONS.

B. WELDED CONNECTIONS: WELDS WILL BE VISUALLY INSPECTED

IN ACCORDANCE TO AWS D1.1 AND THE REQUIREMENTS OF

THE APPLICABLE BUILDING CODE. ACCEPTANCE CRITERIA

WILL BE IN ACCORDANCE WITH AWS D1.1.

C. CONTRACTOR TO CORRECT DEFICIENCIES IN WORK THAT

INSPECTION AND/OR TESTING INDICATE DO NOT COMPLY WITH

CONTRACT DOCUMENTS IN A TIMELY MANNER.

3.6 REPAIRS AND PROTECTION

A. GALVANIZED SURFACES: CLEAN AREAS WHERE GALVANIZING

IS DAMAGED OR MISSING AND REPAIR GALVANIZING USING

PAINTS CONTAINING ZINC DUST, TO COMPLY WITH ASTM

A780/A780M.

3.7 CLEANING

A. CLEAN THE SITE AND WORK AREAS AT THE END OF EACH DAY.

B. AFTER COMPLETING WORK REPAIR AT NO COST TO OWNER

ALL ITEMS DAMAGED DURING WORK AND REMOVE AND

LEGALLY DISPOSE OF ALL DEBRIS AND SURPLUS MATERIALS.

Plotted: 10/3/2019 1:38 PM by Byl, Nikki File Name: \\wjebos1\projects\2017\2017.3xxx\2017.3665.1 - nps historic crane development (das)\Drawings\Sheets\2017-3665-1-S002.dwg

Seal

Architect

Client

DescriptionDateMark

Date

Project No.

Scale

Checked

Sheet Title

Sheet No.

Drawn

Project

A

B

1 2 3 4

C

D

C op yr ig ht

A ll rig ht s r es er ve d.

N o pa rt of th is d oc um en t m ay b e re pr od uc ed in a ny fo rm o r b y an y m ea ns w ith ou t pe rm is si on fr om

W is s, Ja nn ey

, E ls tn er

A ss oc ia te s, In c.

(W

JE

W

JE

d is cl ai m s a ny re sp on si bi lit y fo r i ts u na ut ho riz ed u se

THIS SHEET PLOTS FULL SIZE

AT 11x17 (INCHES)

0 1/2" 1"

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

617.946.3400 tel | 617.946.0740 fax www.wje.com

ENGINEERS

ARCHITECTS

MATERIALS SCIENTISTS

I

S

S

U

D

NPS Crane Stabilization

114 16th St

Charlestown, MA 02129

National Park Service, DSC

NB/CH

DAS

As Noted

STEEL REPAIR NOTES

S002

SIDE VIEW FRONT VIEW

REMOVE AND DISPOSE

OF DISPLACED/LOOSE

CONDUIT AND

ATTACHMENTS ALONG

BOOM LENGTH

REMOVE AND

DISPOSE OF ALL

BROKEN GLASS AT

THE CAB. CLEAN

FRAMES OF ALL

GLASS SHARDS AND

SPLINTERS. INSTALL

PLYWOOD AT DOOR

AND WINDOW

OPENINGS.

REMOVE CORRODED

ELECT. BOX AND

ATTACHMENTS AND

DISPOSE

REMOVE DISPLACED TOE

PLATE AND ATTACHMENTS

AND PROVIDE TO NPS FOR

STORAGE

REMOVE BROKEN SIGN

AND PROVIDE TO NPS

FOR STORAGE

REPAIR CORRODED

MAST BACK BRACE.

SEE SHEET S501.

Plotted: 10/3/2019 1:38 PM by Byl, Nikki File Name: \\wjebos1\projects\2017\2017.3xxx\2017.3665.1 - nps historic crane development (das)\Drawings\Sheets\2017-3665-1-S201.dwg

Seal

Architect

Client

DescriptionDateMark

Date

Project No.

Scale

Checked

Sheet Title

Sheet No.

Drawn

Project

A

B

1 2 3 4

C

D

C op yr ig ht

A ll rig ht s r es er ve d.

N o pa rt of th is d oc um en t m ay b e re pr od uc ed in a ny fo rm o r b y an y m ea ns w ith ou t pe rm is si on fr om

W is s, Ja nn ey

, E ls tn er

A ss oc ia te s, In c.

(W

JE

W

JE

d is cl ai m s a ny re sp on si bi lit y fo r i ts u na ut ho riz ed u se

THIS SHEET PLOTS FULL SIZE

AT 11x17 (INCHES)

0 1/2" 1"

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

617.946.3400 tel | 617.946.0740 fax www.wje.com

ENGINEERS

ARCHITECTS

MATERIALS SCIENTISTS

I

S

S

U

D

NPS Crane Stabilization

114 16th St

Charlestown, MA 02129

National Park Service, DSC

NB/CH

DAS

As Noted

CRANE 62 ELEVATIONS

S201

SCALE: 1/16" = 1'-0"

CRANE 62 ELEVATIONS

SIDE VIEW FRONT VIEW

REMOVE AND DISPOSE

OF LOOSE CONDUIT

AND CHAIN AND

ATTACHMENTS AND

BRACKETS AT BOOM

REMOVE AND DISPOSE

OF DISPLACED CONDUIT

AND ATTACHMENTS

REPAIR CORRODED

MAST BACK BRACE.

SEE SHEET S501.

REMOVE AND DISPOSE

OF CORRODED ELECT.

BOXES AND

ATTACHMENTS (FOUR

LOCATIONS).

REMOVE DISPLACED TOE

PLATE AND ATTACHMENTS

ANDPROVIDE TO NPS FOR

STORAGE

REMOVE BROKEN SIGN

AND PROVIDE TO NPS

FOR STORAGE

REMOVE AND

DISPOSE OF ALL

BROKEN GLASS AT

THE CAB. CLEAN

FRAMES OF ALL

GLASS SHARDS AND

SPLINTERS. INSTALL

PLYWOOD AT DOOR

AND WINDOW

OPENINGS.

Plotted: 10/3/2019 1:38 PM by Byl, Nikki File Name: \\wjebos1\projects\2017\2017.3xxx\2017.3665.1 - nps historic crane development (das)\Drawings\Sheets\2017-3665-1-S202.dwg

Seal

Architect

Client

DescriptionDateMark

Date

Project No.

Scale

Checked

Sheet Title

Sheet No.

Drawn

Project

A

B

1 2 3 4

C

D

C op yr ig ht

A ll rig ht s r es er ve d.

N o pa rt of th is d oc um en t m ay b e re pr od uc ed in a ny fo rm o r b y an y m ea ns w ith ou t pe rm is si on fr om

W is s, Ja nn ey

, E ls tn er

A ss oc ia te s, In c.

(W

JE

W

JE

d is cl ai m s a ny re sp on si bi lit y fo r i ts u na ut ho riz ed u se

THIS SHEET PLOTS FULL SIZE

AT 11x17 (INCHES)

0 1/2" 1"

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

617.946.3400 tel | 617.946.0740 fax www.wje.com

ENGINEERS

ARCHITECTS

MATERIALS SCIENTISTS

I

S

S

U

D

NPS Crane Stabilization

114 16th St

Charlestown, MA 02129

National Park Service, DSC

NB/CH

DAS

As Noted

CRANE 65 ELEVATIONS

S202

SCALE: 1/16" = 1'-0"

CRANE 65 ELEVATIONS

INSTALL NEW STEEL

PLATES AT WEBS.

TWO LOCATIONS.

SEE DETAIL 4/A501.

RESTORE

INCH DIAMETER DRAIN

HOLES BY DRILLING. TWO LOCATIONS

INSTALL NEW STEEL

PLATES AT FLANGE. FOUR

LOCATIONS (TWO SHOWN,

INCLUDE OPPOSITE SIDE

NOT SHOWN). SEE DETAIL

3/A501.

4" (V.I.F.)

PREPARE (E) SURFACES AND WELD

"x3

"x

" STEEL PLATE TO FLANGE AND

CROSS-BRACE. FOUR FLANGE LOCATIONS.

3/8

(E) CROSS-BRACE

(E) FLANGE (TYP.)

V

I F

PREPARE (E) SURFACES AND

WELD 5"x8"x

" STEEL PLATE TO

WEB AND BOTTOM PLATE.

CENTER ON WEB. TWO WEB

LOCATIONS.

3/8

(E) BOTTOM PLATE

(E) WEB (TYP.)

Plotted: 10/3/2019 1:42 PM by Byl, Nikki File Name: \\wjebos1\projects\2017\2017.3xxx\2017.3665.1 - nps historic crane development (das)\Drawings\Sheets\2017-3665-1-S501.dwg

Seal

Architect

Client

DescriptionDateMark

Date

Project No.

Scale

Checked

Sheet Title

Sheet No.

Drawn

Project

A

B

1 2 3 4

C

D

C op yr ig ht

A ll rig ht s r es er ve d.

N o pa rt of th is d oc um en t m ay b e re pr od uc ed in a ny fo rm o r b y an y m ea ns w ith ou t pe rm is si on fr om

W is s, Ja nn ey

, E ls tn er

A ss oc ia te s, In c.

(W

JE

W

JE

d is cl ai m s a ny re sp on si bi lit y fo r i ts u na ut ho riz ed u se

THIS SHEET PLOTS FULL SIZE

AT 11x17 (INCHES)

0 1/2" 1"

Wiss, Janney, Elstner Associates, Inc.

311 Summer Street, Suite 300

Boston, Massachusetts 02210

617.946.3400 tel | 617.946.0740 fax www.wje.com

ENGINEERS

ARCHITECTS

MATERIALS SCIENTISTS

I

S

S

U

D

NPS Crane Stabilization

114 16th St

Charlestown, MA 02129

National Park Service, DSC

NB/CH

DAS

As Noted

MAST BACK BRACE REPAIRS

S501

SCALE: NTS

BACK BRACE WEB

SCALE: NTS

BACK BRACE OVERALL

SCALE: NTS

FLANGE REPAIR DETAIL

SCALE: NTS

WEB REPAIR DETAIL

No. Description Base Scope Base Estimate Alternate Estimate

ALT 1

NON-HISTORIC

Alternate Estimate

ALT 2

NON-HISTORIC

Alternate Estimate

ALT 3

IN KIND HISTORIC

REPAIR

Addition of new steel plate or angle

$ 6,180 $ 9,270

Remove glass and install plywood

$ 11,400 $ 31,800

$ 22,800

Remove all $ 5,100

$ 8,200

$ 12,300

Repair $ 5,850 $ 9,000

$ 6,750

Repair $ 3,250 $ 4,250

$ 5,000

Repair $ 2,600 $ 3,400 $ 3,400

Address existing windows to maintain

$ 4,160 $ 9,200 $ 9,200 weather tight exterior

$ 3,640 $ 8,050

$ 10,500

Stabilize controls in operator cab

$ 5,000 $ 6,250

NPS CRANE 62- SD ALTERNATES

Replace doors in kind

12A House/Cab Windows Address existing windows to maintain weather tight exterior.

Restore windows to the original configuration and appearance (repair or replace frames, recoat frames, install glass)

Address existing doors to maintain weather tight exterior.

Restore doors to the original configuration and appearance

Stabilize controls by repairing basesStabilize controls in operators cab.

Stabilize/reattach

Remove and repair/replace in kind

Repair areas of section loss at the house and operators cab floor. Structural framing for these elements may need to be assessed after panel removal

Install waterproofing coating and additional flashing at seams,valleys and penetrations in order to improve water tightness and durability

Replace deteriorated framing and roofing in kind

Repair with alternate material

Replace deteriorated framing and cladding in kind

House/Cab Floors

Replace deteriorated framing and flooring in kind

Item

10A House/Cab Roofs

Repair areas of section loss at the house roofs.

Structural framing for these elements will need to be assessed after panel removal

9A House Walls

Repair areas of section loss at the house walls.

Structural framing for these elements will need to be assessed after panel removal

Alternates

Replace backstay elements in kind

Remove glass and install new glass in Kind

Remove glass and install Lexan

1A Backstay Stabilization Repair backstay at areas of section loss

3A Fall Hazards Stabilize potential fall hazards: Broken Glass

4A Fall Hazards

Stabilize potential fall hazards: Loose conduit, signage, electrical boxes

13A House/Cab Doors

11A

$ 8,500

$ 2,600

Install additional steel plates angles at areas of section loss

$ 16,000 R e p

Repair/replace damaged elements in kind $ 22,500

R e p

Replace bolts/rivets in kind $ 17,500

R e m o

Remove damaged elements and repair fracture welds

$ 20,000

Mechanical removal (SSPC SP-

3/SP-11),

$ 18,580 A b r

Abrasive blasting (SSPC SP-6/SP-10) $ 45,000 $ 45,000 $ 45,000

Pack rust, ground out of joints

Penetrating sealer installed at joints

Spot prime/high quality coating system

$ 17,450 $ 20,600 $ 20,600

Seal open joints

$ 22,850

N/A $ - $ 5,000 $ 5,000 $ 5,000

$ 850 $ 850 $ 850

BASE ALT 1 ALT 2 ALT 3

STABILIZATION TOTAL COST (without mark-up) = 22,680$ 22,680$ 31,000$ 53,370$

STABILIZATION TOTAL COST (WITH mark-up) = 78,700$ 78,700$ 107,570$ 185,194$

BASE TOTAL COST (without mark-up) = 76,530$ 126,840$ 130,050$ 138,600$

BASE TOTAL COST (WITH mark-up) = 293,875$ 487,066$ 499,392$ 532,224$

TOTAL COST (WITH 3.65 mark-up) = 372,575$ 565,765$ 606,962$ 717,418$

Replace or restore crane capacity chart

Replace missing or damaged truck elements

20A Installation of salvaged elements

Install salvaged crane elements from the previously discassembled Crane 63

16A Prepare Steel (Coating)

Preparation: accessible corrosion product, the existing coatings, and all contaminants should be removed from the surface of the steel, in preparation for the application of a high-performance coating

15A Steel Repairs

Steel components should be assessed for section loss at the time of repair, after the removal of corrosion product. Careful attention should be given to crevice corrosion, where visible

Acrylic coating system

Zinc primer/epoxy coating system everywhere

Cab Controls

Stabilize controls by removing and reinstalling with new bases

Remove controls

17A Steel Coating

Steel surfaces should be primed and coated with a high-performance coating system designed to protect structures in marine environments

14A

No. Description Base Scope Base Estimate Alternate Estimate

Added Cost including

Mark ups

Alternate Estimate

ALT 1

NON-HISTORIC

Alternate Estimate

ALT 2

NON-HISTORIC

Alternate Estimate

ALT 3

IN KIND HISTORIC

REPAIR

Addition of new steel plate or angle

$ 6,180 $ 9,270 $ 9,270

Remove glass and install plywood

$ 11,400 $ 31,800 $ 42,840 $ 31,800

$ 22,800 $ 23,940 $ 22,800

Remove all $ 5,100

$ 8,200 $ 6,510 $ 8,200

$ 12,300 $ 15,120 $ 12,300

Repair $ 5,850 $ 9,000 $ 6,615 $ 9,000

$ 6,750 $ 1,890 $ 6,750

Repair $ 3,250 $ 4,250 $ 2,100 $ 4,250

$ 5,000 $ 3,675 $ 5,000

Repair $ 2,600 $ 3,400 $ 1,680 $ 3,400 $ 3,400

Address existing windows to maintain

$ 4,160 $ 9,200 $ 10,584 $ 9,200 $ 9,200 weather tight exterior

$ 3,640 $ 8,050 $ 9,261 $ 8,050

$ 10,500 $ 14,406 $ 10,500

$ 1,750 $ (3,969) $ 1,750

Stabilize controls in operator cab

$ 5,000 $ 6,250 $ 2,625 $ 6,250

$ 8,500 $ 7,350 $ 8,500

$ 2,600 $ (5,040) $ 2,600

Install additional steel plates angles at areas of section loss

$ 16,000 Repair/replace damaged elements in kind $ 22,500 $ 13,650 $ 22,500

Item

1A Backstay Stabilization Repair backstay at areas of section loss

3A Fall Hazards Stabilize potential fall hazards: Broken Glass

4A Fall Hazards

Stabilize potential fall hazards: Loose conduit, signage, electrical boxes

13A House/Cab Doors

14A

Install waterproofing coating and additional flashing at seams,valleys and penetrations in order to improve water tightness and durability

9A House Walls

Repair areas of section loss at the house walls.

Structural framing for these elements will need to be assessed after panel removal

Cab Controls

Stabilize controls in operators cab.

Repair areas of section loss at the house and operators cab floor. Structural framing for these elements may need to be assessed after panel removal 11A House/Cab Floors

Replace deteriorated framing and flooring in kind

10A House/Cab Roofs

Repair areas of section loss at the house roofs.

Structural framing for these elements will need to be assessed after panel removal

Address existing doors to maintain weather tight exterior.

Restore doors to the original configuration and appearance

Address operability of doors

Stabilize controls by repairing bases

Stabilize controls by removing and reinstalling with new bases

Remove controls

NPS CRANE 65- SD ALTERNATES

Replace doors in kind

12A House/Cab Windows Address existing windows to maintain weather tight exterior.

Restore windows to the original configuration and appearance (repair or replace frames, recoat frames, install glass)

Steel components should be assessed for section loss at the time of repair, after the removal of corrosion product. Careful attention should be given to crevice

Alternates

Replace deteriorated framing and roofing in kind

Repair with alternate material

Replace deteriorated framing and cladding in kind

Replace backstay elements in kind

Remove glass and install new glass in Kind

Remove glass and install Lexan

Stabilize/reattach

Remove and repair/replace in kind

Replace bolts/rivets in kind $ 17,500 $ 3,150 $ 17,500

Remove damaged elements and repair fracture welds

$ 20,000 $ 8,400 $ 20,000

Mechanical removal (SSPC SP-

3/SP-11),

$ 18,580 Abrasive blasting (SSPC SP-6/SP-10) $ 45,000 $ 55,482 $ 45,000 $ 45,000 $ 45,000

Pack rust, ground out of joints

Penetrating sealer installed at joints

Spot prime/high quality coating system

$ 17,450 $ 20,600 $ 6,615 $ 20,600 $ 20,600

Seal open joints

$ 22,850 $ 11,340 $ 22,850

BASE ALT 1 ALT 2 ALT 3

STABILIZATION TOTAL COST (without mark-up) = 22,680$ 22,680$ 31,000$ 53,370$

STABILIZATION TOTAL COST (WITH mark-up) = 78,700$ 78,700$ 107,570$ 185,194$

BASE TOTAL COST (without mark-up) = 76,530$ 117,630$ 124,200$ 132,750$

BASE TOTAL COST (WITH mark-up) = 293,875$ 451,699$ 476,928$ 509,760$

TOTAL COST (WITH 3.65 mark-up) = 372,575$ 530,399$ 584,498$ 694,954$

17A Steel Coating

Steel surfaces should be primed and coated with a high-performance coating system designed to protect structures in marine environments Acrylic coating system

Zinc primer/epoxy coating system everywhere

16A Prepare Steel (Coating)

Preparation: accessible corrosion product, the existing coatings, and all contaminants should be removed from the surface of the steel, in preparation for the application of a high-performance coating

15A Steel Repairs product. Careful attention should be given to crevice corrosion, where visible

COST SUMMARY

BASE ALT 1 ALT 2 ALT 3

IMMEDIATE STABILIZATION $80,135

LONG TERM PRESERVATION $320,011 $565,766 $606,962 $717,418

CRANE 65

BASE ALT 1 ALT 2 ALT 3

IMMEDIATE STABILIZATION $83,135

LONG TERM PRESERVATION $354,807 $530,399 $584,498 $694,954

BASE = Provides non-historical repairs necessary to stabilize and prevent further deterioration

ALT 1 = Provides minimum upgraded Non-historical repairs

ALT 2 = Provides upgraded Non-historical repairs meeting a higher aesthetic standard using modern materials

ALT 3 = Provides historical repairs, replacing materials specific to the required period of significance

TOTAL IMMEDIATE STABILIZATION = $163,270

TOTAL LONG TERM PRESERVATION = $674,818 $1,096,165 $1,191,460 $1,412,372

TOTAL COST = $838,088

COST SUMMARY

4. Appendix

B…