The document is a Price List Attachment for a Blanket Purchase Agreement (BPA) for Roto-Jet Pump Maintenance at Grand Canyon National Park. The five-year BPA covers comprehensive maintenance services for three Roto-Jet 2200 model RG 3x2 pumps located at the North Rim's Roaring Springs Pumphouse, with services including annual inspections, preventative maintenance, emergency support, and potential pump replacements. The pricing schedule outlines ten line items covering tasks such as annual inspections, pump replacements, on-call technical support, emergency and non-emergency services, travel rates, and potential technician downtime.

The solicitation (140P1525Q0033) is issued by the Department of the Interior's National Park Service Intermountain Region, with an anticipated performance period from 5/10/2025 to 5/11/2030. Quotes must be submitted electronically to lindsay_mclaughling@nps.gov, with questions accepted until April 17, 2025 at 10:00am MT. The BPA will be firm-fixed price, and replacement parts will be evaluated separately on a case-by-case basis for fair and reasonable pricing at the individual call level. The government anticipates awarding a single BPA for these pump maintenance and service requirements.

View the file

Other files

File Type Posted
Sol_140P1525Q0033_Amd_0001.pdf PDF
Sol_140P1525Q0033.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price List

Attachment 4: 140P1525Q0033 GRCA Roto-Jet Pumps BPA
Grand Canyon National Park (GRCA) BPA Maintenance and Repairs on Roaring Springs Roto Jet Pumps
Contractor:(fill in orange blocks only)
UEI:
Date:
Point of Contact:
Email:
Item #Description of WorkUnit PriceUnit of MeasureExpected Frequency* (per year)Total Cost
1Annual inspection, service, and preventative maintenance required on Roto Jet 2200 model RG 3x2 pumps. Pump service to include but not limited to: observation of the general physical condition, pressures, flow, seal leakage, vibration, and oil level. Service to include: change bearing oil (approved oil: Mobil Delvac 1 ESP 5w-40 synthetic oil, oil incompatibility may cause bearing failure), dissassembley to clean and inspect pump, replace parts as necessary, replace seals (as required, allowable leakage is : 1 pint per hour), and clean strainer. Preventative maintenance to include: check alignment of electric motor/transmission/roto jet pump train, shim as necessary, ensure all equipment to skid bolts are secure. Grease all bearing races as required.$ - 0Each1$ - 0Enter lump sum amount for service (including techinican hourly rate and travel)
2There are (2) roto jet pumps installed on (2) pump pads. The Park owns (3) roto jet pumps (one as a spare). In a situation when an installed pump has failed, remove installed pump and install spare pump. Perform alignment, balancing, and start-up.$ - 0Each1$ - 0Enter lump sum amount for service (including techinican hourly rate and travel)
3On-call technical support with any minor maintenance and emergency issues associated with the (2) Roto Jet Pumps.$ - 0Hour3$ - 0Enter hourly rate for on-call technical support
4Non-Emergency Services$ - 0Hour3$ - 0Enter hourly rate for onsite labor
5Non-Emergency Services (Travel)$ - 0Round Trip3$ - 0Enter roundtrip travel rate for non-emergency services, 2 people
6Emergency Services$ - 0Hour3$ - 0Enter hourly rate for onsite labor
7Emergency Services (Travel)$ - 0Round Trip3$ - 0Enter roundtrip travel rate for emergency services, 2 people
8Annual replacement parts that result from inspections, emergency repairs, and equipment failureXXXX**See note below, Replacement parts will need to be determinated Fair and Reasonable at the individual BPA Call level.
9In the event of technician down time due weather, search and rescues (SAR's) or Medivac, when the Park's helicopter is unavailable to transport techinicians to or from the pumphouse or south Rim, in a timely manner, contractor employees will be required to wait for transport$ - 0Hour2$ - 0Enter hourly rate for down time
10Shop rate for pump rebuild and bench testing$ - 0Hour1$ - 0Enter Shoptime hourly rate
TOTAL$ - 0

*NOTE: This agreement is anticipated to have a five (5) year ordering period. Expected frequeny for some services are unknown. Therefore, these quantities are being used for evaluation purposes only based on unit prices. The price list may be updated annually as outlined in the BPA Terms and Conditions.

**NOTE: Annual replacements parts that result from inspection, emergency repairs and equipment failure will be included in the BPA. However, due unknown circumstance at this time, replacement parts will not be included in the Total Evaluated Price. Replacement parts will need to be determinated Fair and Reasonable at the individual BPA Call level and written notification must be given by the Contracting Officer prior to purchasing or installing replacement parts.