This is a blank bid schedule pricing template for the Zuni Comprehensive Community Health Center Cooling Tower Repair by Replacement Project (Solicitation No. 75H70126R00023), issued by the Indian Health Service under the Department of Health and Human Services. The project is located in Zuni, New Mexico and is identified as Project No. AQ22ZS005.
The bid schedule requires contractors to provide lump sum (LS) pricing for eleven line items covering the complete scope of the cooling tower system replacement. These items include: General Requirements (Division 01), Demolition and Removal, Cooling Tower Equipment (HVAC), Basin and Structural Work, Mechanical Systems Installation, Electrical and Controls, Installation Labor, Testing/Commissioning and Start-Up, Water Treatment and Cleaning, Closeout and Warranty, and a Temporary Cooling System. Bidders must provide both a unit cost and total cost for each item, with a subtotal for items 1-11, followed by General Contractor Overhead and Profit, and New Mexico Gross Receipts Tax (NMGRT) calculated at 6.5 percent. The note specifies that all taxes and fees must be included within the bid items and that bidders must bid on all items of all schedules to be considered responsive for award.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
K29 Bid Schedule_Blank
| BID SCHEDULE |
| Zuni, New Mexico |
| Zuni Cooling Tower System Repalcement |
| Project No. AQ22ZS005 |
Item No. Schedule A - Cooling Tower System Replacement Estimated Quantity Unit Unit Cost Total Cost
| 1 | General Requirements - Div. 01 | 1 | LS | $ | $ |
| 2 | Demolition & Removal | 1 | LS | $ | $ |
| 3 | Cooling Tower Equipment - HVAC | 1 | LS | $ | $ |
| 4 | Basin & Structural Work | 1 | LS | $ | $ |
| 5 | Mechanical Systems Installation | 1 | LS | $ | $ |
| 6 | Electrical & Controls | 1 | LS | $ | $ |
| 7 | Installation Labor | 1 | LS | $ | $ |
| 8 | Testing, Commissioning & Start-Up | 1 | LS | $ | $ |
| 9 | Water Treatment & Cleaning | 1 | LS | $ | $ |
| 10 | Closeout & Warranty | 1 | LS | $ | $ |
| 11 | Temporary Cooling System | 1 | LS | $ | $ |
| Subtotal Items 1 - 11 | $ - 0 | ||||
| GC Overhead & Profit | |||||
| Subtotal | $ - 0 | ||||
| NMGRT 6.5000% | $ - 0 | ||||
| Total Cost | $ - 0 |
NOTE: Include all taxes and fees within the bid items. Bidder must bid on all items of all schedules to be considered responsive for award.