b. Statement of Work.pdf
PDF 1 MB Posted
- Solicitation number
- 1284LL25Q0057
- Issued by
-
Department of Agriculture Forest Service
About this file
This Statement of Work (SOW) details an electrical installation project for the USDA at the Coeur d'Alene Nursery involving Argus Titan control panel wiring and relay installation for seven new greenhouse bays. The project requires an Idaho-certified Journeyman electrician to install a low-voltage system connecting multiple equipment types (including 20 exhaust fans, 14 roof ventilation motor control boxes, 14 natural gas heaters, and 40 LED lights) to Argus Titan control panels, enabling centralized environmental monitoring and control.
The work is scheduled to begin September 29th and must be completed by January 2nd, with all installation occurring between 7:00 am and 3:30 pm Monday through Friday. The contractor will use shielded low-voltage cable to step down 120V equipment signals to 24V and connect them to the control panels, with metal conduit and weatherproof fittings. After installation, the contractor must provide operational instructions to nursery staff. The project supports a newly constructed greenhouse complex designed to grow over a million seedlings, replacing nine older greenhouses and implementing state-of-the-art technological control systems to reduce manual monitoring requirements.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
4.0 Government Furnished Property
5.0 Deliverables / Schedule
6.0 Contractor’s Key Personnel
7.0 Facility Location and Security Requirements
Project Argus Titan control panel wiring and relay installation
General Information
1.0 Scope of Work
Install the low voltage system and relays for all equipment (listed below) in the new greenhouses (see site map) at the Coeur d’Alene Nursery. System and relays shall tie in with the existing Argus Titan control system used by the nursery for the greenhouses. Metal conduit shall run from the equipment in each of the seven greenhouse bays to the Titan control panels. Shielded, low-voltage cable, weatherproof fittings, and appropriate cord grips shall be used when deemed appropriate by the Idaho-certified electrician.
The end result shall allow nursery staff to control the growing environment and set parameters from a central computer.
2.0 Background
In 2022, demolition of 9 greenhouses built in the 1960’s was completed and 7 new greenhouse bays were built with construction finishing in the fall of 2024. These new greenhouses employ state of the art technology to provide growing space for over a million seedlings. These houses are designed to be run by the greenhouse control system Argus Titan. All the other greenhouses on the property utilize this technology. This system requires a network of low voltage wires and relays to be run from each individual piece of equipment in each bay to the main control panels located in between the 7 bays. The control panels communicate with a central computer sending out live updates and allowing remote monitoring of systems. Currently, the equipment in these bays is being run manually or with external thermostats, requiring around-the-clock monitoring by nursery staff. Completing the installation of the Argus Titan system will greatly reduce the daily workload on nursery staff and increase the efficiency of the greenhouse-growing environment. The greenhouse bays are as follows:
Bay 1: 40’x60’, 2400 sqft.
Bay 2: 40’x100’, 4000 sqft.
Bay 3: 40’x100’, 4000 sqft.
Bay 4: 40’x100’, 4000 sqft.
Bay 5: 40’x100’, 4000 sqft.
Bay 6: 40’x100’, 4000 sqft.
Bay 7: 40’x100’, 4000 sqft.
Contractor Requirements
3.0 Technical Requirements / Tasks
The Argus Titan wiring will require shielded low voltage cable and weatherproof fittings. 120V wire from each piece of existing equipment shall be stepped down to a 24V signal wire connected to the Argus Titan control panels.
The Contractor should not rely on any measurements provided by the Government and should verify all measurements prior to submitting their quote and ordering materials.
The Contractor will be responsible for running low voltage wire and relays (where necessary) from the existing equipment listed below, to the Argus Titan control panel.
(20) exhaust fans
(14) roof ventilation motor control boxes
(14) natural gas heaters
(14) electric fan jets
(2) cooling wall pad pumps
(2) cooling wall motors
(40) overhead fans
(40) LED lights
(2) TN21/HM2 Soil moisture sensors
(2) TN21 - Back up temp sensors
(2) OMNI/RHT Aspirated Temp/RH
All construction debris shall be removed from the site by the contractor prior to final payment being requested.
5.0 Deliverables / Schedule
Key Deliverables Work will ideally begin September 29th and be completed no later than January 2nd barring supply issues. All work shall be completed between the hours of 7:00 am and 3:30 pm Monday through Friday (excluding Federal Holidays). Any work outside of those hours will require prior written acknowledgment and agreement between the Contractor and Contracting Officer or the Contracting Officer's Representative. After installation requirements have been completed, the Contractor shall provide either a written or verbal hand down of operating directions to the COR or other technical nursery staff for all the components installed.
6.0 Contractor’s Key Personnel
The Contractor’s Key personnel must be an Idaho state certified Journeyman electrician experienced with Argus Titan.
7.0 Facility Location and Security Requirements
Building locations are on the attached map of the facilities (red box indicates area of work). The nursery is open Monday through Friday from 7:30 am to 4:00 pm and closed on weekends and all Federal Holidays. The Contractor shall check in at the greenhouse office with Molly or other greenhouse staff when they are on site.
4.0 Government Furnished Property
(2) Argus Titan Control Panels (previously installed) Climate Sensors:
* (2) OMNI/RHT Aspirated Temp/RH
* (2) TN21 - Back-up Temp Sensors
* (2) TN21/HM2 Soil Moisture Sensors
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Background |
| Contractor Requirements |
| 3.0 Technical Requirements / Tasks |
| 4.0 Government Furnished |
| 5.0 Deliverables / Schedule |
| 6.0 Travel |
| 7.0 Contractor’s Key Personnel |
| 8.0 Security Requirements |
| 9.0 Data Rights |
| 10.0 Section 508 – Electronic and Information Technology Standards |
| Attachment- Site Map of Coeur d’Alene Nursery. Red box indicates area of work. |