B.08.03 - Solicitation Amend 03 2026.10.14 - W912HP27RA002 - FLETC Trade & Cargo.pdf
PDF 4 MB Posted
- Attached to
- Trade and Cargo Academy
- Solicitation number
- W912HP27RA002-0003
About this file
This is Amendment 0003 to Solicitation W912HP27RA002, issued by the US Army Engineer District Charleston on October 14, 2026, for construction projects at Charleston, South Carolina.
The amendment extends the Volume IV proposal deadline to November 6, 2026, at 12:00 PM local time and keeps ProjNet Bidder Inquiries open until October 16, 2026, at 12:00 PM local time. The proposal acceptance period has been reduced from 120 calendar days to 60 calendar days. Key technical revisions address environmental protection, earthwork, and deep pile foundation requirements for two facilities: the Combat Support Structure Prototype Facility (CSSPTF) and the Technical Classroom Addition (TCA). Environmental test results for any imported, relocated, or excavated fill material must be submitted 60 days prior to work performance. The Cooper Marl formation, identified as a primary hydrogeological confining unit beginning at approximately 45 feet depth, requires protection; pre-augering activities are limited to a maximum depth of 45 feet below ground surface. Amendments include revisions to CSSPTF and TCA specifications and drawings, updated HVAC ductwork pressure and seal class documentation, revised demolition plans for Building 286 accounting for prefabricated stairs replacement, and a new Channel Liner Installation detail for site utility plans. The contracting officer is Lauren Minzenberger, reachable at Lauren.O.Minzenberger@usace.army.mil or 843-329-8020.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The purpose of this amendment is as Block 14 (Description of Amendment/Modification):
follows:
-Incorporate revisions to Attachments 1-4 (see summary of changes for additional information).
-ProjNet Bidder Inquiries remain open until October 16, 2026 at 12:00pm local time.
-Volume IV proposals are extended to November 6, 2026 at 12:00pm local time.
-Adjust proposal acceptance period from 120 calendar days to 60 calendar days.
Summary of Key Amendments and Additions
CSSPTF Specifications The amendments introduce requirements related to environmental protection, earthwork, and deep pile foundations.
(Section 31 00 00) Environmental Testing: Environmental test results for any imported or relocated fill material, as well as for any area to be excavated, must be submitted to the Government 60 days prior to the work being performed.
(Section 31 62 13.20):
Protection of Cooper Marl Layer: The Cooper Marl formation, which begins at a depth of roughly 45 feet, is identified as a primary hydrogeological confining unit. To protect it from being punctured, any pre-augering activities are strictly limited to a maximum depth of 45 feet below the ground surface.
APPENDIX B - Furniture, Fixtures, & Equipment (FF&E) Design Specification APPENDIX C- SID Finish Package
CSSPTF
Updated drawings: S-102, M-101, M-701 (Ductwork Pressure/Seal Class)
TCA Specifications The amendments introduce requirements related to environmental protection, earthwork, and deep pile foundations.
(Section 31 00 00) Environmental Testing: Environmental test results for any imported or relocated fill material, as well as for any area to be excavated, must be submitted to the Government 60 days prior to the work being performed.
(Section 31 62 13.20):
Protection of Cooper Marl Layer: The Cooper Marl formation, which begins at a depth of roughly 45 feet, is identified as a primary hydrogeological confining unit. To protect it from being punctured, any pre-augering activities are strictly limited to a maximum depth of 45 feet below the ground surface.
TCA Drawings:
W912HP27RA0020003
Demolition plans for Building 286 updated accounting for adjacent stairs being replaced by prefabricated stairs.
A new Channel Liner Installation detail has also been added to the site utility plans.
Updates to HVAC with Ductwork Pressure/ Seal Class also addressed.
Section 00 00 00 - Procurement and Contracting Requirements
The following changes have been made:
INFORMATION FROM TO
Accept Within Days
120 60
Section 00 01 15 - List of Drawing Sheets
The following contract documents were added:
261013 - CSSPTF Drawings - Amendment 261013 - CSSPTF Specifications - Amendment 261013 - TCA Drawings Amendment 261013 - TCA Specification Amendment
W912HP27RA0020003
| IDCode: J |
| Page: 1 |
| Pages: 3 |
| AmendNo: 0003 |
| EffDate: 14 OCT 2026 |
| ReqNo: |
| ProjNo: 574629 |
| IssCode: W912HP |
| AdmCode: |
| IssuedBy: US ARMY ENGINEER DISTRICT CHARLESTO |
KO CONTRACTING DIVISION, 69A HAGOOD AVENUE
CHARLESTON, SC 29403-5107
UNITED STATES
LAUREN MINZENBERGER, EMAIL: LAUREN.O.MINZENBERGER@USACE.ARMY.MIL TELEPHONE: 843-329-8020 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W912HP27RA002 |
| SolDate: 15 SEP 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: ADDISON LAYFIELD |
| ContDate: |
| CODate: 14 OCT 2026 |
File details come from the government source that posted it. Updated .