This is a federal construction solicitation for the Trade and Cargo Academy project at the Federal Law Enforcement Training Center (FLETC) in Charleston, South Carolina, issued under Solicitation No. W912HP27RA002 by the U.S. Army Corps of Engineers.
The project encompasses comprehensive earthwork, foundation, and finishing work for a new training facility. Key requirements include: design and installation of precast prestressed concrete piles (maximum 55-ton capacity, driven to approximately 72 feet depth into the Cooper Marl formation); earthwork and site preparation including excavation, grading, and compaction to specified densities; and interior finishes including paint, flooring (tile, carpet, luxury vinyl), wall treatments, fixtures, and specialized spaces such as classrooms, offices, restrooms, and breakrooms. Critical environmental and structural controls mandate that pre-auger activities be limited to 45 feet below ground surface to protect the Cooper Marl confining layer and prevent contaminant migration. The contractor must provide a professional geotechnical engineer for site inspection, a qualified technician for field testing, and an independent geotechnical consultant for pile driving analysis and dynamic testing. Payment is on a lump-sum basis for all piles installed to minimum tip elevation while meeting acceptance criteria; no additional payment is provided for damaged, rejected, or misplaced piles. Extensive submittals are required including installation procedures, wave equation analysis, quality control procedures, concrete mix designs, test reports, and preconstruction condition surveys. The specification references numerous ASTM standards, ACI guidelines, and PCI manuals governing pile design, concrete testing, material specifications, and construction quality control.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Trade and Cargo Academy Solicitation No. W912HP27RA002 FLETC, Charleston, SC
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 22 13.00 20 02/14 SUPPLEMENTARY INSTRUCTIONS TO OFFERORS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24, CHG 1: 05/25 SUMMARY OF WORK
01 14 00 11/22, CHG 5: 05/25 WORK RESTRICTIONS
01 30 00 11/20, CHG 5: 02/25 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 08/23, CHG 1: 08/24 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21, CHG 1: 08/25 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 05/24, CHG 1: 05/25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 3: 08/25 QUALITY CONTROL
01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22, CHG 2: 08/25 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23, CHG 2: 11/25 OPERATION AND MAINTENANCE DATA
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 81 00 08/25 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 00 08/25 ASBESTOS REMEDIATION
02 83 00 08/25 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 10: 08/25 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 05/25 UNIT MASONRY
DIVISION 05 - METALS
05 05 23.16 08/18 STRUCTURAL WELDING
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 08/24, CHG 1: 08/25 MISCELLANEOUS METAL FABRICATIONS
05 51 00 08/23 METAL STAIRS
05 52 00 08/23 METAL RAILINGS
PROJECT TABLE OF CONTENTS Page 1
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 3: 05/25 ROUGH CARPENTRY
06 20 00 08/24 FINISH CARPENTRY
06 41 16.00 10 08/25 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 08/23, CHG 1: 08/25 BOARD AND BLOCK INSULATION
07 21 16 08/23, CHG 1: 08/25 MINERAL FIBER BLANKET INSULATION
07 22 00 08/23 ROOF AND DECK INSULATION
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 27 19.01 08/23, CHG 1: 08/24 SELF-ADHERING AIR BARRIERS
07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 47 09/19 ULTRA HIGH PERFORMANCE CONCRETE (UHPC)
PANELS
07 42 63 08/25 FABRICATED WALL PANEL ASSEMBLIES
07 52 00 08/25 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 08/23, CHG 1: 05/25 FLASHING AND SHEET METAL
07 81 00 02/11 SPRAY-APPLIED FIREPROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20, CHG 1: 08/25 STEEL DOORS AND FRAMES
08 11 16 05/17 ALUMINUM DOORS AND FRAMES
08 14 00 08/16 WOOD DOORS
08 31 00 05/17 ACCESS DOORS AND PANELS
08 33 23 08/20, CHG 2: 02/26 OVERHEAD COILING DOORS
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 87 00 09/19 ARCHITECTURAL WINDOW FILMS
08 91 00 08/20 METAL LOUVERS
DIVISION 09 - FINISHES
09 22 00 08/24 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/24, CHG 1: 05/25 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 11/24 RESILIENT FLOORING
09 68 00 11/24 CARPETING
09 72 00 08/17, CHG 1: 08/18 WALLCOVERINGS
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 22 39 08/20 FOLDING PANEL PARTITIONS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 08/24 LOCKERS
PROJECT TABLE OF CONTENTS Page 2
DIVISION 12 - FURNISHINGS
12 24 13 08/20 ROLLER WINDOW SHADES
12 48 13 08/23 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 14 - CONVEYING EQUIPMENT
14 24 23 08/25 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 05/24, CHG 1: 11/24 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00 11/25 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 02/25 SEISMIC BRACING FOR MECHANICAL SYSTEMS
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL AND
PLUMBING SYSTEMS
23 09 00 08/24, CHG 1: 08/25 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.01 08/24 LONWORKS DIRECT DIGITAL CONTROL FOR
HVAC AND OTHER BUILDING CONTROL SYSTEMS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 74 33.00 40 11/23 HVAC UNITS
23 81 29 02/20 VARIABLE REFRIGERANT FLOW HVAC SYSTEMS
23 82 46.00 40 05/17 ELECTRIC UNIT HEATERS
DIVISION 26 - ELECTRICAL
26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 08 13 08/26 COMMISSIONING OF ELECTRICAL SYSTEMS
26 20 00 05/25, CHG 2: 02/26 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 05/25 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
PROJECT TABLE OF CONTENTS Page 3
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 08 10 08/23 ELECTRONIC SECURITY SYSTEM ACCEPTANCE
TESTING
28 10 05 05/24 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 31 16.13 08/22, CHG 1: 11/23 CHEMICAL TERMITE CONTROL
31 62 13.20 11/20, CHG 2: 02/24 PRECAST/PRESTRESSED CONCRETE PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 20 05/22 BASE COURSE FOR RIGID AND SUBBASE FOR
FLEXIBLE PAVING
32 12 13 05/24 BITUMINOUS TACK COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23.16 11/24 ROAD AND PARKING LOT PAVEMENT MARKINGS
32 92 19 08/17, CHG 1: 08/21 SEEDING
DIVISION 33 - UTILITIES
33 11 00 08/24 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 71 02 02/26 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 02/26 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
APPENDICES
APPENDIX A - FLETC B286 Trade and Cargo Academy Hazmat Report APPENDIX B - Geotechnical Report APPENDIX C - Construction Work Plan FLETC Trade And Cargo Academy APPENDIX D - SID Finish Package
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
BarretR2 Highlight
31 00 00 08/23 EARTHWORK
BarretR2 Highlight
31 62 13.20 11/20, CHG 2: 02/24 PRECAST/PRESTRESSED CONCRETE PILES
BarretR2 Rectangle
BarretR2 Snapshot
BarretR2 Rectangle
SECTION 31 00 00
EARTHWORK
08/23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO T 180 (2025) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2023) Installation of Ductile-Iron Mains and Their Appurtenances
ASTM INTERNATIONAL (ASTM)
ASTM C33/C33M (2024a) Standard Specification for Concrete Aggregates
ASTM C117 (2023) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing
ASTM C136/C136M (2025) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM C150/C150M (2024) Standard Specification for Portland Cement
ASTM C260/C260M (2024) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C618 (2025a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C989/C989M (2025) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM D698 (2012; R 2021) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft. (600 kN-m/cu. m.))
ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer
SECTION 31 00 00 Page 1 than 75-µm (No. 200) Sieve in Soils by Washing
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D2216 (2019) Standard Test Methods for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
ASTM D2487 (2017; R 2025) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D4253 (2016; E 2019) Standard Test Methods for Maximum Index Density and Unit Weight of Soils Using a Vibratory Table
ASTM D4254 (2016) Standard Test Methods for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density
ASTM D4318 (2017; E 2018) Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM D4829 (2021) Standard Test Method for Expansion Index of Soils
ASTM D4832 (2016; E 2018) Standard Test Method for Preparation and Testing of Controlled Low Strength Material (CLSM) Test Cylinders
ASTM D6023 (2016) Standard Test Method for Density (Unit Weight), Yield, Cement Content, and Air Content (Gravimetric) of Controlled Low-Strength Material (CLSM)
ASTM D6103/D6103M (2017; E 2021) Standard Test Method for Flow Consistency of Controlled Low Strength Material (CLSM)
ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
SECTION 31 00 00 Page 2
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test Methods for Evaluating Solid Waste:
Physical/Chemical Methods
1.2 DEFINITIONS
1.2.1 Structural Fill
Soil material placed to support buildings, walls, pads, and other similar facilities.
1.2.2 Porous Fill
Free-draining material placed for subsurface drainage, as a capillary break, or another specific purpose.
1.2.3 Topsoil
Surface layer of primarily organic soil capable of supporting vegetation growth.
1.2.4 Utility Bedding Material
Fill placed to directly support pipes, conduits, cables, and appurtenant structures. Bedding may also be used to provide a cushion between utilities and bedrock, obstacles, obstructions and other unyielding materials.
1.2.5 Flowable Fill
Fill placed in a plastic or liquid form that flows to near its final placement location with limited assistance and subsequently cures or solidifies to provide a stable or impermeable barrier.
1.2.6 Satisfactory Materials
Satisfactory materials for fill, backfill, and/or any in-situ soils to remain in place comprise any materials classified by ASTM D2487 as GW, GP, GM, GC, SW, SP, SM, SC, ML. Maximum particle size to be no greater than one-half of the allowable lift thickness in any dimension.
1.2.7 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; roots and other organic matter or frozen material. Notify the Contracting Officer when encountering any contaminated materials.
1.2.8 Cohesionless Materials
Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C117, ASTM C136/C136M and ASTM D1140.
SECTION 31 00 00 Page 3
1.2.9 Cohesive Materials
Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesive only when the fines are plastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C117 , ASTM C136/C136M and
ASTM D1140.
1.2.10 Unstable Material
Unstable materials are too weak to adequately support the utility pipe, conduit, equipment, or appurtenant structure. Satisfactory material may become unstable due to ineffective drainage, dewatering, becoming frozen, excessive loading.
1.2.11 Expansive Soils
Expansive soils are defined as soils that have an expansion index greater than 20 when tested in accordance with ASTM D4829.
1.2.12 Degree of Compaction (Proctor)
Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum dry density obtained by the test procedure presented in ASTM D1557 ASTM D698 abbreviated as a percent of laboratory maximum dry density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum dry density in accordance with AASHTO T 180 -21 paragraph 1.5, Note 1.
1.2.13 Degree of Compaction (Relative Density)
Degree of compaction required for soils with less than 5 percent passing the No. 200 sieve, is expressed as a relative percentage of the maximum index density/dry unit weight and minimum index density/dry unit weight, obtained by the test procedures in accordance with ASTM D4253 and ASTM D4254, respectively, abbreviated as a percent of laboratory relative density.
1.2.14 Borrow
Soil brought to the project site from an external location for the purposes of project construction.
1.2.15 Subgrade
Earth materials directly below foundations and directly below granular base materials in building slab and pavement areas including shoulders.
1.3 SUBSURFACE DATA
Subsurface soil boring logs are shown in project plans. These data represent available subsurface information; however, variations may exist between boring locations.
SECTION 31 00 00 Page 4
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals with a "G, AE" designation are for Architect/Engineer of Record approval; submittals not having a "G" or "G, AE" designation are for information only. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Excavation and Trenching Plan ; G, AE
Borrow Plan ; G, AE
Dewatering Work Plan ; G, AE
SD-03 Product Data
Flowable Fill Mix Design ; G
Geotextiles
SD-06 Test Reports
Material Test Report ; G, AE
Borrow Site Testing ; G, AE
Pipe Inspection Report ; G, AE
Geotechnical Evaluation Report ; G
1.5 QUALITY CONTROL
1.5.1 Geotechnical Engineer
Provide a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The Geotechnical Engineer is responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions.
The Geotechnical Engineer is responsible for preparing and updating the Excavation and Trenching Plan and Dewatering Work Plan as construction progresses to reflect changing conditions and submit an updated plan if necessary. Submit a monthly Geotechnical Evaluation report , informing the Contractor and Contracting Officer of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any present or potential problems. The Contractor is responsible for arranging meetings with the Geotechnical Engineer and Contracting Officer throughout the contract duration.
1.5.2 Qualified Technician
Provide a Qualified Technician to inspect, monitor, sample, and performing field testing. The technician qualifications need to be one of the following: a current National Institute for Certification in Engineering Technologies (NICET) Level II minimum certification in Construction Materials Testing Soils; a Geologist-in-Training with minimum one-year experience; an Engineer-in-Training with minimum one-year experience; a Registered Geologist; or a Professional Engineer.
SECTION 31 00 00 Page 5
PART 2 PRODUCTS
2.1 SOIL MATERIALS
2.1.1 Structural Fill
Materials classified as GW, GP, GM, GC, GW-GM, GP-GM, SW, SP, SM, SW-SM, SC, SW-SC, SP-SM, CL, or CH in accordance with ASTM D2487. Select material type appropriate for the intended purpose.
2.1.2 Porous Fill
Materials containing less than 5 percent passing the No. 200 sieve.
Provide the gradation as appropriate for the intended purpose.
2.1.3 Topsoil
Material suitable for topsoil obtained from offsite areas excavations is defined as: Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7.
2.1.4 Utility Bedding Material
Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600. Install bedding for plastic piping to spring line of pipe. Utility bedding material may include the following:
2.1.4.1 Class I
Angular, 0.25 to 1.5 inch, graded stone, including a number of fill materials that have regional significance such as coral, slag, cinders, crushed stone, and crushed shells.
2.1.4.2 Class II
Coarse sands and gravels with maximum particle size of 1.5 inch, including various graded sands and gravels containing small percentages of fines, generally granular and noncohesive, either wet or dry. Soil Types GW, GP, SW, and SP are included in this class as specified in ASTM D2487.
2.1.4.3 Sand
Clean, coarse-grained sand classified as SW or SP by ASTM D2487 for bedding as indicated.
2.1.4.4 Gravel and Crushed Stone
Clean, coarsely graded natural gravel, crushed stone or a combination thereof identified as ASTM D2487 for bedding. Do not exceed maximum particle size of 1.5 inches.
2.2 FLOWABLE FILL
Design and submit flowable fill mix design to consist of Portland cement, SECTION 31 00 00 Page 6 fly ash, and/or slag cement and fine aggregate. Include the dry weights of cementitious material(s); quality and gradation of aggregates in the saturated surface-dry weights along with gradation tests; quantities, types, and names of admixtures; and quantity of water per cubic yard. The maximum unconfined compressive strength to be 200 psi at 28 days in accordance with ASTM D4832. The aggregates in accordance with ASTM C33/C33M Fine Aggregates. Air-entrain fill in accordance with ASTM C260/C260M. The air content to be between 8 and 15 percent in accordance with ASTM D6023. The flow to be between 8 and 12 inches in accordance with ASTM D6103/D6103M . Portland cement to be Type I or II in accordance with ASTM C150/C150M. Fly ash to be Class C in accordance with ASTM C618. Provide slag cement in Grade 100 or 120 in accordance with
ASTM C989/C989M.
2.3 BURIED WARNING AND IDENTIFICATION MARKERS
Provide polyethylene plastic and metallic core or metallic-faced, acid-and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines.
Provide tape on rolls, 3 inches minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Provide permanent color and printing, unaffected by moisture or soil.
Warning Tape Color Codes
Red Electric
Orange Telephone and Other Communications
Blue Water Systems
Green Sewer Systems
2.3.1 Warning Tape for Metallic Piping
Provide acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.003 inch and a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
2.3.2 Detectable Warning Tape for Non-Metallic Piping
Provide polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.004 inch, and a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Manufacture tape with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket
SECTION 31 00 00 Page 7 or provide with other means of corrosion protection.
2.3.3 Detection Wire for Non-Metallic Piping
Insulate a single strand, solid copper detection wire with a minimum of 12
AWG.
2.4 MATERIAL FOR RIP-RAP
Provide filter fabric and rock conforming to requirements noted on the plans for construction indicated.
2.5 BORROW
Provide borrow materials from sources located outside of Government property meeting the requirements of paragraph STRUCTURAL FILL.
2.6 GEOTEXTILE
Provide a pervious sheet of polyester, nylon, glass or polypropylene ultraviolet resistant filaments woven, spun bonded, fused, or otherwise manufactured into a non-raveling fabric with uniform thickness and strength. Submit a sample and material product data for all Geotextiles utilized.
PART 3 EXECUTION
3.1 PROTECTION
Perform all work specified in accordance with applicable requirements of the Corps of Engineers publication EM 385-1-1 Safety and Health Requirements Manual.
Use equipment of type and size appropriate for the site conditions (soil character and moisture content). Maintenance of exposed subgrades and fills is the responsibility of the Contractor. The Contractor is required to prevent damage by ineffective drainage, dewatering, and heavy loads and equipment by implementing precautionary measures. Repair or replace any defects or damage.
3.1.1 Underground Utilities
Location of the existing utilities indicated is approximate. Physically verify the location and elevation of the existing utilities indicated prior to starting construction. The Contractor is responsible for protecting utilities from damage during construction.
3.1.2 Drainage and Dewatering
Provide for the collection and disposal of surface and subsurface water encountered during construction.
3.1.2.1 Drainage
Provide for the collection and disposal of surface and subsurface water encountered during construction. Construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity and/or provide temporary
SECTION 31 00 00 Page 8 ditches, swales, and other drainage features and equipment as required to keep soils from becoming unstable, prevent erosion, or undermining of foundations. Remove unstable material from working platforms for equipment operation and soil support for subsequent construction features and provide new material as specified herein. It is the responsibility of the Contractor to assess the site conditions to employ necessary measures to permit construction to proceed.
3.1.2.2 Dewatering
Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. French drains, sumps, ditches or trenches are not allowed within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Perform control measures by the time the excavation reaches the water level in order to maintain the integrity of the in-situ material. While the excavation is open, maintain the water level continuously, at least 2 feet below the working level. Submit a Dewatering Work Plan outlining procedures for accomplishing dewatering work. Operate dewatering system continuously until construction work below existing water levels is complete. Measure and record performance of dewatering system at same time each day by use of observation wells or piezometers installed in conjunction with the dewatering system.
3.1.3 Shoring and Sheeting
Submit an Excavation and Trenching Plan to stabilize features, prevent undermining or unintended horizontal and vertical movement of adjacent structures, and prevent slippage or movement in banks or slopes adjacent to the excavation. Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of excavations. Drawings to include material sizes and types, arrangement of members, and the sequence and method of installation and removal. Calculations are to include data and references used.
3.1.4 Protection of Graded Surfaces
Protect newly backfilled, graded, and topsoiled areas from traffic, erosion, and settlements that may occur. Repair or reestablish damaged grades, elevations, or slopes.
3.2 BORROW
Select borrow material to meet the requirements and conditions of the fill for which it is to be used. Obtain borrow material from from approved private sources. Submit a Borrow Plan that includes materials to be excavated, stockpile locations, proposed slopes, drainage, and closure.
Unless otherwise provided in the contract, the Contractor is responsible for obtaining the right to procure material, pay royalties and other charges involved, and bear the expense of developing the sources, including rights-of-way for hauling from the owners. Unless specifically provided, do not obtain borrow within the limits of the project site without prior written approval. Environmental Test results shall be submitted to the Government 60 days before any imported or relocated fill material is placed on site. See Appendix B for Construction Work Plan for Navy Dig Permit.
SECTION 31 00 00 Page 9
Joan Comtois Highlight
3.2.1 Government Furnished Borrow Area(s)
3.2.1.1 Stripping and Stockpiling Operations in Borrow Area
Strip in accordance with paragraph STRIPPING. Strip at least 5 feet beyond the limits of the borrow excavation and any stockpiles of fill materials.
Stockpile materials within the borrow area work limits such that the stockpiles does not interfere with borrow operations. Stockpile borrow material awaiting transport in approved segregated piles. Maintain a minimum of 30 feet between all stockpile toes and the top of the borrow cut.
3.2.1.2 Drainage of Borrow Excavations
Provide adequate drainage of borrow area. Ensure that borrow operations result in minimum detrimental effects on natural environmental conditions.
3.2.2 Contractor Furnished Borrow Area(s)
Obtain approved borrow materials from approved offsite sources. If a borrow source is selected that is not a commercial entity from which soil material is directly purchased, submit a Borrow Plan that includes the borrow source location, geotechnical test results showing the fill material meets the Contract requirements, environmental test results in accordance with paragraph ENVIRONMENTAL REQUIREMENTS FOR OFF-SITE SOIL, and any Federal, State, and local permits required for excavation and reclamation of the borrow area.
3.2.3 Environmental Requirements for Off-Site Soil
Test offsite soils brought in for use as backfill for Total Petroleum Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and full Toxicity Characteristic Leaching Procedure (TCLP) including ignitability, corrosivity and reactivity. Backfill may not contain concentrations above the most current South Carolina Department of Environmental Services (SCDES) risk-based screening criteria, EPA Regional Screening Levels (RSLs), and EPA Toxicity Characteristics Leaching Procedure (TCLP) regulatory limits and Resource Conservation and Recovery Act (RCRA) hazardous waste characteristics 200 parts per million (ppm) of total petroleum hydrocarbons (TPH) and 20 ppm of the sum of Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and pass the TCLP test.
Determine TPH concentrations by using EPA Method 8015. Determine BTEX concentrations by using EPA SW-846.3-3 Method 5030/8020/8260B. Perform TCLP in accordance with EPA SW-846.3-3 Method 1311. Perform hazardous waste characteristic tests for ignitability, corrosivity, and reactivity in accordance with accepted standard methods. Perform PCB testing in accordance with accepted standard methods for sampling and analysis of bulk solid samples. Provide borrow site testing for petroleum hydrocarbons and BTEX from a grab sample of material from the area most likely to be contaminated at the borrow site (as indicated by visual or olfactory evidence), with at least one test from each borrow site.
Provide borrow site testing for hazardous waste characteristics (TPH, BTEX and TCLP) from a composite sample of material, collected in accordance with standard soil sampling techniques. Do not bring borrow material to project site until Borrow Plan containing environmental test results has been received and approved by the Contracting Officer.
SECTION 31 00 00 Page 10
3.3 SURFACE PREPARATION
3.3.1 Clearing and Grubbing
Clear and grub as specified in Section 31 11 00 CLEARING AND GRUBBING.
Remove trees, stumps, logs, shrubs, brush and vegetation and other items that would interfere with construction operations. Remove stumps entirely. Grub out matted roots and roots over 3 inches in diameter to at least 18 inches below existing surface.
3.3.2 Stripping
Strip suitable soil from the site where excavation or grading is indicated and stockpile separately from other excavated material. Material unsuitable for use as topsoil shall be wasted. Locate topsoil so that the material can be used readily for the finished grading. Where sufficient existing topsoil conforming to the material requirements is not available on site, provide borrow materials suitable for use as topsoil. Protect topsoil and keep in segregated piles until needed.
3.3.3 Proof Rolling
Perform proof rolling on exposed subgrade that is unfrozen and free of surface water (wet conditions resulting from rainfall). Notify the Contracting Officer a minimum of three days prior to proof rolling.
Perform proof rolling in the presence of the Contracting Officer.
After stripping, excavating, and rough grading to the planned elevation, proof roll the existing subgrade of all building, pavement locations with six passes of a loaded tandem axle dump truck. Operate the truck in a systematic manner to ensure the number of passes over all areas, and at speeds between 2.5 to 3.5 miles per hour. Subgrade materials that exhibit excessive deflection and/or rutting during proof rolling need to be scarified, aerated, and re-compacted to specified density at plus or minus 2 percent of optimum moisture content prior to being considered for remedial action by the Contracting Officer. When proof rolling under buildings, the building subgrade is considered to extend 5 feet beyond the building lines, and make one-half of the passes with the roller in a direction perpendicular to the other passes.
3.3.4 Stockpiling Operations
Place and grade stockpiles of satisfactory and unsatisfactory and wasted materials as specified. Keep stockpiles in a neat and well drained condition, giving due consideration to drainage at all times. Clear, grub, and seal by rubber-tired equipment, the ground surface at stockpile locations; separately stockpile excavated satisfactory and unsatisfactory materials. Protect stockpiles of satisfactory materials from contamination which may destroy the quality and fitness of the stockpiled material. Do not create stockpiles that could obstruct the flow of any stream, endanger a partly finished structure, impair the efficiency or appearance of any structure, or be detrimental to the completed work in any way. If the Contractor fails to protect the stockpiles, and any material becomes unsatisfactory, remove and replace such material with satisfactory material from approved sources.
SECTION 31 00 00 Page 11
3.4 EXCAVATION
Excavate to contours, elevation, and dimensions indicated. Excavate soil disturbed or weakened by Contractor's operations, and soils softened or made unstable for subsequent construction due to exposure to weather. Use material removed from excavations meeting the specified requirements in the construction of fills, subgrades, shoulders, bedding (as backfill), and for similar purposes to minimize surplus material and to minimize additional material to brought on site. Do not excavate below indicated depths except to remove unstable material as determined by the Geotechnical Engineer and confirmed by the Contracting Officer. Remove and replace excavations below the grades shown with appropriate materials as directed by the Contracting Officer. Environmental Test results shall be submitted to the Government 60 days before any excavation work is performed on site. See Appendix B for the Construction Work Plan for Navy Dig Permit.
If at any time during excavation, including excavation from borrow areas, the Contractor encounters material that may be classified as rock or as hard/unyielding material, uncover such material, and notify the Contracting Officer. Do not proceed with the excavation of this material until the Contracting Officer has classified the materials as common excavation or rock excavation. Failure on the part of the Contractor to uncover such material, notify the Contracting Officer, and allow sufficient time for classification and delineation of the undisturbed surface of such material will cause the forfeiture of the Contractor's right of claim to any classification or volume of material to be paid for other than that allowed by the Contracting Officer for the areas of work in which such deposits occur.
3.4.1 Ditches, Gutters, and Channel Changes
Finish excavation of ditches, gutters, and channel changes by cutting accurately to the cross sections, grades, and elevations shown. Do not excavate below grades shown. Backfill excessive excavation as directed by the Contracting Officer, with satisfactory, compacted, material or with suitable stone or cobble to grades shown. Dispose excavated material as shown or as directed. Do not allow material to be deposited within 4 feet from edge of a ditch. Maintain excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the work.
3.4.2 Trench Excavation Requirements
Excavate the trench as recommended by the manufacturer of the pipe to be installed. Slope trench walls below the top of the pipe, or make vertical, and of such width as recommended by the manufacturer. Provide vertical trench walls where no manufacturer installation instructions are available. Do not exceed the trench width of 24 inches below the top pipe plus pipe outside diameter (O.D.) for pipes of less than 24 inches inside diameter, and do not exceed 36 inches plus pipe outside diameter for pipe sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, provide redesign, stronger pipe, or special installation procedures. The Contractor is responsible for the cost of redesign, stronger pipe, or special installation procedures without any additional cost to the Government.
SECTION 31 00 00 Page 12
3.4.2.1 Bottom Preparation
Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Excavate bell holes to the necessary size at each joint or coupling to eliminate point bearing. Remove stones of 2 inch or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, to avoid point bearing.
3.4.2.2 Removal of Unyielding Material
Where overdepth is not indicated and unyielding material is encountered in the bottom of the trench, notify the Contracting Officer. Following approval, remove such material 4 inch below the required grade and replaced with suitable materials as provided in paragraph FILLING AND
COMPACTION.
3.4.2.3 Removal of Unstable Material
Where unstable material is encountered in the bottom of the trench, remove such material to the depth directed and replace it to the proper grade with suitable material as provided in paragraph FILLING AND COMPACTION.
When removal of unstable material is required due to the Contractor's fault or neglect in performing the work, the Contractor is responsible for excavating the resulting material and replacing it without additional cost to the Government.
3.4.2.4 Excavation for Appurtenances
Provide excavation for manholes, catch-basins, inlets, or similar structures of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown.
3.4.3 Underground Utilities
Perform work adjacent to utilities as indicated.For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
3.4.4 Structural Excavation
Following general excavation and rough grading activities, excavate the entire building footprint area and at least 5 feet beyond, to the deeper of 4 feet below existing grade or 2 feet below bottom of footings. Scarify the exposed surface to a depth of 6 to 8 inches, moisture-condition, and compact to at least 95 percent of laboratory maximum dry density. Do not excavate to final grade until just before concrete is to be placed.
Roughen level surfaces. Cut sloped surfaces as indicated into rough steps or benches to provide a satisfactory bond for compacting materials. For new pavement areas including exterior concrete pads, over-excavate to a minimum of 12 inches below bottom of new pavement/pad base course, scarify, moisture-condition, and compact to at least 95 percent.
SECTION 31 00 00 Page 13
Make excavations to the lines, grades, and elevations shown, or as directed. Provide trenches and foundation pits of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown. Clean rock or other hard foundation material of loose debris and cut to a firm, level, stepped, or serrated surface. Remove loose disintegrated rock and thin strata.
Concrete placement is not allowed until footing subgrades have been inspected and approved by the Contracting Officer.
3.4.5 Pile Cap Excavation
Stop the excavation at an elevation 6 to 12 inches above the bottom of the footing before driving piles. After pile driving has been completed, complete the remainder of the excavation to the elevations shown. Excavate to bottom of pile cap prior to placing or driving piles, unless authorized otherwise by the Contracting Officer. After the pile driving has been completed, remove loose and displaced material and complete excavation, leaving a smooth, solid, undisturbed surface to receive the concrete or masonry. Backfill and compact over-excavations and changes in grade due to pile driving operations to 95 percent of ASTM D698 maximum dry density.
3.4.6 Rock Excavation
Excavate rock encountered in the cut section to a depth of 6 inches below finished grade and replace with satisfactory material.
3.5 SUBGRADE PREPARATION
3.5.1 General Requirements
Shape subgrade to line, grade, and cross section as indicated. Remove unsatisfactory and unstable material in surfaces to receive fill or in excavated areas, as determined by proof rolling, and replaced with satisfactory materials. Do not place material on surfaces that are muddy, frozen, contain frost, or otherwise containing unstable material. Scarify the surface to a depth of 6 inches prior to placing fill. Step or bench sloped surfaces steeper than 1 vertical to 4 horizontal prior to scarifying. Place 6 inches of loose fill and blend with scarified material. When subgrade is part fill and part excavation or natural ground, scarify to a depth of 8 inches.
3.5.2 Subgrade for Structures, Spread Footings, and Concrete Slabs
Do not excavate below depth shown for structures, spread footings, and concrete slabs. If over excavation occurs, compact disturbed material to 95 percent of ASTM D698. After final rolling, the surface of the subgrade for buildings and pavements must not show deviations greater than 0.05 foot when tested with a 12-foot straightedge applied both parallel and at right angles to the centerline of the area.
3.5.3 Subgrade for Pavements
Compact top 12 inches of subgrade for pavements to at least 95 percent of ASTM D698. After final rolling, the surface of the subgrade for buildings and pavements must not show deviations greater than 0.05 foot when tested with a 12-foot straightedge applied both parallel and at right angles to the centerline of the area.
SECTION 31 00 00 Page 14
3.5.4 Subgrade Filter Fabric
Place filter fabric as indicated directly on prepared subgrade free of vegetation, stumps, rocks larger than 2 inch diameter and other debris which may puncture or otherwise damage the fabric. Repair damaged fabric by placing an additional layer of fabric to cover the damaged area a minimum of 3 feet overlap in all directions. Overlap fabric at joints a minimum of 3 feet. Obtain approval of filter fabric installation before placing fill or backfill. Place fill or backfill on fabric in the direction of overlaps and compact as specified herein. Follow manufacturer's recommended installation procedures.
3.6 FILLING AND COMPACTION
Prepare ground surface on which backfill is to be placed and provide compaction requirements for backfill materials in conformance with the applicable portions of paragraphs for SUBGRADE PREPARATION. Do not place material on surfaces that are muddy, frozen, or contain frost. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Moisten material as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used. Fill and backfill to contours, elevations, and dimensions indicated. Compact and test each lift before placing overlaying lift.
3.6.1 Trench Backfill
Backfill trenches to the grade shown. Backfill the trench to 2 feet above the top of pipe prior to performing the required pressure tests. Leave the joints and couplings uncovered during the pressure test. Do not backfill the trench until all specified tests are performed.
3.6.1.1 Replacement of Unyielding Material
Replace unyielding material removed from the bottom of the trench with satisfactory material or initial backfill material.
3.6.1.2 Replacement of Unstable Material
Replace unstable material removed from the bottom of the trench or excavation with satisfactory material placed in layers not exceeding 6 inches loose thickness.
3.6.1.3 Bedding and Initial Backfill
Provide bedding of the type and thickness shown. Place initial backfill material and compact it with approved tampers to a height of at least one foot above the utility pipe or conduit. Bring up the backfill evenly on both sides of the pipe for the full length of the pipe. Take care to ensure thorough compaction of the fill under the haunches of the pipe.
Except where shown or when specified otherwise in the individual piping section, provide bedding for buried piping in accordance with PART 2 paragraph UTILITY BEDDING MATERIAL. Compact backfill to top of pipe to 95 percent of ASTM D698 maximum dry density. Provide plastic piping with bedding to spring line of pipe.
3.6.1.4 Final Backfill
Do not begin backfill until construction below finish grade has been
SECTION 31 00 00 Page 15 approved, underground utilities systems have been inspected, tested and approved, forms removed, and the excavation cleaned of trash and debris.
Bring backfill to indicated finish grade. Where pipe is coated or wrapped for protection against corrosion, the backfill material up to an elevation 2 feet above sewer lines and one foot above other utility lines need to be free from stones larger than one inch in any dimension. Heavy equipment for spreading and compacting backfill are not to be operated closer to foundation or retaining walls than a distance equal to the height of backfill above the top of footing; compact remaining area in layers not more than 4 inches in compacted thickness with power-driven hand tampers suitable for the material being compacted. Place backfill carefully around pipes or tanks to avoid damage to coatings, wrappings, or tanks.
Do not place backfill against foundation walls prior to 7 days after completion of the walls. As far as practicable, bring backfill up evenly on each side of the wall and sloped to drain away from the wall.
Fill the remainder of the trench, except for special materials for buildings and pavements with satisfactory material. Place backfill material and compact as follows:
3.6.1.4.1 Buildings and Pavements
Place backfill up to the required elevation as specified. Do not permit water flooding or jetting methods of compaction. Compact as specified for Structural Fill.
3.6.1.4.2 Turfed or Seeded Areas and Miscellaneous Areas
Deposit backfill in layers of a maximum of 12 inches loose thickness, and compact it to 85 percent maximum dry density for cohesive soils and 90 percent maximum dry density for cohesionless soils. Apply this requirement to all other areas not specifically designated above.
3.6.1.5 Electrical Distribution System
Provide a minimum cover of 24 inches from the finished grade to direct burial cable and conduit or duct line, unless otherwise indicated.
3.6.1.6 Displacement of Features
After other required tests have been performed and the trench backfill compacted to the finished grade surface, inspect the pipe to determine whether unexpected or damaging displacement has occurred. Conduct walk-through inspection of pipe sizes larger than 48 inches. Inspect pipes smaller than 48 inches using remote methods using closed circuit television, sonar, or hybrid that can provide a 360-degree inspection of the pipe. Prepare and submit a pipe inspection report consisting of digital video or photos. If, in the judgment of the Contracting Officer, the interior of the pipe shows poor alignment or any other defects that would cause improper functioning of the system, replace or repair the defects as directed at no additional cost to the Government.
3.6.1.7 Buried Tape And Detection Wire
3.6.1.7.1 Buried Warning and Identification Tape
Provide buried utility lines with utility identification tape. Bury tape 12 inches below finished grade; under pavements and slabs, bury tape 6 inches below top of subgrade.
SECTION 31 00 00 Page 16
3.6.1.7.2 Buried Detection Wire
Bury detection wire directly above non-metallic piping at a distance not to exceed 12 inches above the top of pipe. Extend the wire continuously and unbroken, from manhole to manhole. Terminate the ends of the wire inside the manholes at each end of the pipe, with a minimum of 3 feet of wire, coiled, remaining accessible in each manhole. Furnish insulated wire over its entire length. Install wires at manholes between the top of the corbel and the frame, and extend up through the chimney seal between the frame and the chimney seal. For force mains, terminate the wire in the valve pit at the pump station end of the pipe.
3.6.2 Structural Fill Placement
Place fill and backfill beneath and adjacent to structures in successive horizontal layers of loose material not more than 8 inches in depth, or in loose layers not more than 4 inches in depth when using hand-operated compaction equipment. Do not place over wet or frozen materials. Compact to at least 90 percent of laboratory maximum dry density for cohesive materials or 95 percent of laboratory maximum dry density for cohesionless materials, except as otherwise specified. Perform compaction in such a manner as to prevent wedging action or eccentric loading upon or other damage to the structure. Moisture condition fill and backfill material to a moisture content that will readily facilitate obtaining the specified compaction.
3.6.3 Backfill for Appurtenances
After the manhole, catchbasin, inlet, or similar structure has been constructed, place backfill in such a manner that the structure is not be damaged by the shock of falling earth. Deposit the backfill material, compact it as specified for final backfill, and bring up the backfill evenly on all sides of the structure to prevent eccentric loading and excessive stress.
3.6.4 Porous Fill Placement
Provide under floor and area-way slabs on a compacted subgrade. Place in a single lift and compact with a minimum of two passes of a hand-operated plate-type vibratory compactor.
3.6.5 Flowable Fill
Place fill in a manner to completely fill voids in the location indicated. Do not place when atmospheric temperatures are expected to be below 33 degrees F at any time during the 3 day period following placement.
3.6.6 Compaction
3.6.6.1 General Site
Compact underneath areas designated for vegetation and areas outside the 5 foot line of the paved area or structure to 90 percent of ASTM D698.
3.6.6.2 Adjacent Areas
Compact areas within 5 feet of structures to 95 percent of ASTM D698.
SECTION 31 00 00 Page 17
3.7 RIP-RAP CONSTRUCTION
Construct rip-rap on filter fabric in accordance with SCDHEC State Standard,…