B.08.02 UD 2.4 ATCT - Cost Breakdown.pdf

PDF 179 KB Posted

Attached to
Construct Air Traffic Control Tower - Undisclosed location, Hashemite Kingdom of Jordan
Solicitation number
W912ER22R0006
Issued by

About this file

This file contains a cost breakdown and federal contract opportunity notice for the construction of an air traffic control tower in Jordan. The cost breakdown provides pricing for mobilization, site survey, tower construction including substructure, superstructure, closures, cab, interiors, services, backup generator and special inspections. It also includes pricing for supporting facilities such as demolition, site electrical and utility systems, access road, parking lot and improvements. The federal contract opportunity notice seeks bids for the design and construction of a new 12-story air traffic control tower with reinforced concrete pile foundation, steel superstructure, precast concrete facade and standing seam metal roof. The project scope includes an elevator, catwalk, fire and HVAC systems, emergency power, utilities and site work. The solicitation number is W912ER22R0006 and the contract value is between $10-25 million. The response deadline is not provided.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P2# 474512

PROPOSER:

RFP: W912ER22R0006

PROJECT: Air Traffic Control Tower, UD 2.4 LOCATION: Jordan DATE:

JOOH HOOH BOND

Mobilization and Demobilization in accordance with the contract documents

0002 Site Survey in accordance with the contract documents

Construct Air Traffic Control Tower in accordance with the contract documents

0003AA Construct Substructure

0003AB Construct Super Substructure

0003AC Construct Exterior Closures

0003AD Construct Air Traffic Control Cab

0003AE Construct Building Interiors

0003AF Construct Building Services

0003AG Provide & Install Backup Generator

0003AH Provide Special Inspections

0 0 0 0 0 0 0 0 0 0 0 0

Construct Air Traffic Control Tower Supporting Facilities in accordance with the contract documents

0004AA Demolition

0004AB Construct Site Electrical Distribution System

0004AC Construct Water Distribution Piping System

0004AD Construct Site Fire Water Piping System

0004AE Construct Site Sanitary Sewer Collection Piping System

0004AF Construct Site Communication Distribution System

0004AG Construct Site Storm Water Collection System

0004AH Construct Access Road

0004AJ Construct Aggregate Parking Lot

0004AK Construct Site Improvements

0 0 0 0 0 0 0 0 0 0 0 0

Option #1 Construct Asphalt Paving for Parking Lot in accordance with the contract documents

Option #2 Construct Security Fencing in accordance with the contract documents

TOTAL BASE + OPTION PRICE (ITEMS 0001 - 0006)

DIRECT

MATERIALS COST

SUB

CONTRACTOR

COST

TOTAL

DIRECT

COST

LABOR MAN-HOURS DIRECT LABOR

COST

DIRECT

EQUIPMENT COST

TOTAL BASE BID PRICE (ITEMS 0001 - 0004)

TOTAL OPTION PRICE (ITEM 0005 - 0006)

TOTAL (ITEMS 0004AA - 0004AK)

TOTAL (ITEMS 0003AA - 0003AG)

OVERHEAD/

INDIRECT COST PROFIT TOTAL PROPOSED

COST

COST BREAKDOWN

ITEM DESCRIPTION

EXHIBIT 1 Page 1 of 1