GROUP1-18-R-J021
Jacksonville District
Jacksonville Harbor, Maintenance Dredging, 40-Foot Project Cut-55 and Lower Terminal Channel
Duval County, Florida
Construction Solicitation and Specifications Task Order
18 MARCH 2021
Jacksonville Harbor, Maintenance Dredging GROUP1-18-R-J021 40-Foot Project, Cut-55 and Lower Terminal Channel
DESIGN AUTHENTICATION
This project was designed by the Jacksonville District, U.S. Army Corps of Engineers. The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as required by ER 1110-1-8152.
WILLIAM L. REILLY, P.E.
CHIEF, WATERWAYS SECTION
DESIGN BRANCH, ENGINEERING DIVISION
DENNIS J. ZEVENEY, P.E.
CHIEF, GEOSYSTEMS BRANCH
ENGINEERING DIVISION
DAVID DUDLEY, P.E.
CHIEF, DESIGN BRANCH
ENGINEERING DIVISION
LAUREEN A. BOROCHANER, P.E.
CHIEF, ENGINEERING DIVISION
NEVES.MICHAE
L.P.1392765405
Digitally signed by
NEVES.MICHAEL.P.1392765405
Date: 2021.03.03 14:54:22 -05'00'
ZEVENEY.DENNIS.J.1249349085 Digitally signed by ZEVENEY.DENNIS.J.1249349085 Date: 2021.03.08 10:28:57 -05'00'
DUDLEY.DAVID.F.13
99388569
Digitally signed by
DUDLEY.DAVID.F.1399388569
Date: 2021.03.08 15:51:10 -05'00'
WIGNER.WILLIAM.
KEITH.1230084617
Digitally signed by
WIGNER.WILLIAM.KEITH.1230084
Date: 2021.03.10 08:03:36 -05'00'
GROUP1-18-R-J021 SF 1442-A1
ADDENDUM TO THE STANDARD FORM 1442
JACKSONVILLE HARBOR, MAINTENANCE DREDGING 40-FOOT PROJECT, CUT-
55 AND LOWER TERMINAL CHANNEL DUVAL COUNTY, FLORIDA
NOTICE OF INTENT TO ORDER: THIS OPPORTUNITY IS AVAILABLE ONLY TO
THE FOLLOWING CONTRACTORS AWARDED A CONTRACT UNDER
SOLICITATION NUMBER W912EP18R0029, GROUP 1 – UNRESTRICTED:
W912EP18R0029: Callan Marine, Ltd. (W912EP19D0023); Cashman Dredging & Marine Contracting Co., LLC (W912EP19D0024); Cavache Inc. (W912EPD0025);
Continental Heavy Civil Corp (CHC) (W912EP19D0026); Cottrell Contracting Corporation (W912EP19D0027); Great Lakes Dredge & Dock Company, LLC (W912EP19D0028); J.T. Cleary Inc. (W912EP19D0029); Manson Construction Co.
(W912EP19D0030); Marinex Construction, Inc. (W912EP19D0031); Norfolk Dredging Company (W912EP19D0032); Orion Marine Construction, Inc.
(W912EP19D0033); Southern Dredging Co., Inc. (W912EP19D0034); The Dutra Group (W912EP19D0035); Waterfront Property Services, LLC dba Gator Dredging (W912EP19D0036); Weeks Marine, Inc. (W912EP19D0037).
PROPOSALS WILL NOT BE CONSIDERED FROM ANY ENTITY OTHER THAN THE
PREVIOUSLY LISTED FIRMS INCLUDED IN THE GROUP 1 – UNRESTRICTED
DREDGING MATOC POOL.
EVALUATION: The award of the task order will be made on the basis of Lowest Price, Technical Acceptable (LPTA) evaluation method. To be considered technically acceptable, an offeror’s proposal must be rated “Acceptable under all non-price factors.
The factors for evaluation will be as follows:
FACTOR 1 - Availability of technically acceptable dredge(s).
FACTOR 2 - Past performance.
FACTOR 3 – Price.
SUBMISSION REQUIREMENTS: Contractors are required to submit the following:
FACTOR 1 - Availability of technically acceptable dredge(s).
The contractor shall provide a letter on company letterhead identifying the dredge(s) the contractor proposes to do the work and the current location of dredge(s).
Note: Any type of dredge can be utilized, however if a cutter suction is selected it must be a 16” or larger.
Evaluation Method:
The Government will evaluate all identified dredge(s) submitted to determine whether
GROUP1-18-R-J021 SF 1442-A2
the identified dredge(s) have been found technically acceptable by the Contracting Officer prior to the proposal due date. The Government will also determine whether the dredge(s) are available to meet the required period of performance as stated in the Notice of Intent.
To be determined Acceptable for Factor 1, the identified dredge(s) must have been found technically acceptable prior to the proposal due date and be available to meet the required period of performance.
FACTOR 2 - Past performance.
NO SUBMISSION REQUIREMENT. Past Performance information submitted in response to the Dredging MATOC (Solicitation No. W912EP18R0029) will be used to determine the offeror’s record of complying with contractual requirements and meeting acceptable levels of performance risk.
Evaluation Method:
Past Performance was recently evaluated for all contractors under the Dredging MATOC. An "Acceptable" rating was earned under Past Performance for all offerors that received an award in accordance with the solicitation evaluation criteria for the Dredging MATOC (Solicitation No. W912EP18R0029). Therefore, for this task order, all offerors will receive the Past Performance rating of "Acceptable".
Note: For future task orders, the Government reserves the right to use recent and relevant project data independently obtained from other Government or commercial sources or from any other sources available to include, but not limited to: (1) the Past Performance Information Retrieval System (PPIRS), (2) Federal Awardee Performance and Integrity Information System (FAPIIS) or Electronic Subcontract Reporting System (eSRS), or other data bases; (3) interviews with Program/Project Managers and Contracting Officers or rely upon personal business experience with the offeror; and (4) consider any information the offeror submits which explains any problems encountered on the identified contract and the offeror's corrective actions. The Government reserves the rights to obtain and evaluate past performance information from any source it deems appropriate. Information related to the contractor’s (or contractor’s team) performance in Quality, Schedule, Management, Regulatory Compliance and Safety/Security will be reviewed from the aforementioned additional sources to determine if the offeror is “Acceptable” or “Unacceptable.
FACTOR 3 – Price.
The Offeror’s submission for this factor shall be fully completed. Offeror completeness addresses the extent to which the elements of the price proposal are consistent with the requirements of the RFP.
Offerors are required to submit the following:
(1) Completed Bid Schedule (see Section 00010A).
GROUP1-18-R-J021 SF 1442-A3
(2) Bid Guarantee per Section 00700, Clause 52.228-1 and Section 00100A, Paragraph 2.4(c) of the MATOC
(3) Completed “Addendum to the Standard Form 1442” with the latest revision.
THE FOLLOWING INFORMATION IS APPLICABLE ONLY TO THIS TASK ORDER:
Block 7 -- Issued By:
USA Engineer District Jacksonville Contracting Division 701 San Marco Blvd.
Jacksonville, FL 32207-8175
Block 9 -- For additional information contact:
A. Jennifer Carter
Email Address: Jennifer.L.Carter@usace.army.mil
B. Telephone No.: (904) 232-1051
Block 10. The Government Requires Performance of the Work as Described in this solicitation.
Description of Work: Refer to Section 01 11 00 for complete description.
Magnitude of Construction is Between $1,000,000.00 and $5,000,000.00
NAICS Code: 237990 Small Busines Size Standard: $27.5M
You must be registered in the System for Award Management (SAM) in order to receive an award from this Notice of Intent. The SAM website is located at www.sam.gov.
Block 11. The performance period is mandatory. (Refer to FAR Clause 52.211-10 in Section 00700).
Block 12A. The Contractor must furnish any required performance and payment bonds: YES
Block 12B. The contractor must furnish any required performance and payment bonds within 10 calendar days after award of the task order.
Block 13. Additional Solicitation Requirement
A. Offers to perform the required work are due electronically at the following email addresses by 2:00PM, local time on 31 March 2021:
Jennifer.L.Carter@usace.army.mil and carbon copy (cc) tedra.n.thompson@usace.army.mil and griselle.gonzalez@usace.army.mil.
mailto:Jennifer.L.Carter@usace.army.mil http://www.sam.gov/ mailto:Jennifer.L.Carter@usace.army.mil mailto:tedra.n.thompson@usace.army.mil mailto:griselle.gonzalez@usace.army.mil
GROUP1-18-R-J021 SF 1442-A4
B. An offer guarantee is required. An electronic copy of the bid guarantee shall be submitted with the offer and the Original must be received within two calendar days of the submission date for proposals.
C. All offers are subject to the (1) work requirements and (2) other provisions and clauses incorporated in the Notice of Intent in full text or by reference.
D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NOTICE TO OFFERORS: Offerors are to complete Blocks 14, 15, 17, 19 and 20A - 20D below:
Block 14. Name and Address of Offeror (including Zip Code):
DUNS: ___________________ CAGE: _______________
Block 15. Telephone No. (Include area code): _____________________
Block 16. Remittance Address: (Include only if difference than Item 14)
Block 17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this Notice of Intent, if this offer is accepted by the Government in writing within 60 calendar days after the date offers are due.
Block 18. The offeror agrees to furnish any required performance and payment bonds.
Block 19. Acknowledgement of Revision (The offeror acknowledges receipt of revisions to the notice of intent -- give number and date of each).
REVISION
NO.
DATE
GROUP1-18-R-J021 SF 1442-A5
Block 20A. Name and Title of Person Authorized to Sign Offer (Type or print)
Block 20B.
Email Address
Block 20C. Signature Block 20D.
Offer Date
Block 26 -- This Task Order will be administered by:
North Florida Area Office 6735 Southpoint Drive South Suite 140 Jacksonville, FL 32216
Block 27 -- Payment will be made by:
USACE Finance Center 5722 Integrity Drive
ATTN: CEFC-AO-P
Millington, TN 38054-5005
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
JACKSONVILLE HARBOR, MAINTENANCE DREDGING
40-FOOT PROJECT, CUT-55 AND LOWER TERMINAL CHANNEL
DUVAL COUNTY, FLORIDA
LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
BASE
0001 MOBILIZATION AND DEMOBILIZATION JOB $_______________
0002 EXCAVATION, UNCLASSIFIED
LOWER TERMINAL CHANNEL
STATION 11+29.77 TO STATION 65+00
(ESTIMATED QUANTITY, SEE NOTE 1) 88,000 CUBIC YARD $____________ $_______________
0003 TURBIDITY MONITORING JOB $_______________
0004 ENDANGERED SPECIES OBSERVERS
(HOPPER DREDGES ONLY) JOB $_______________
0005 MOBILIZATION AND DEMOBILIZATION FOR
SEA TURTLE TRAWL SWEEPING
(HOPPER DREDGES ONLY, SEE NOTE 3) JOB $_______________
0006 SEA TURTLE TRAWL SWEEPING
(HOPPER DREDGES ONLY, SEE NOTE 3) 1 DAY $____________ $_______________
0007 DEDICATED MANATEE AND SEA TURTLE
OBSERVER (MECHANICAL DREDGING ONLY,
SEE NOTE 4) JOB $_______________
0008 BIRD MONITORING (SEE NOTE 5) JOB $_______________
0009 STANDBY TIME (SEE NOTE 6) 24 HOUR $____________ $_______________
0010 DISPOSAL AREA PUMPOUT (SEE NOTE 7) 1 DAY $____________ $_______________
0011 PARTNERING REGROUP 1 EACH $____________ $_______________
TOTAL BASE (LINE ITEMS 0001 THROUGH 0011) $_______________
OPTION A
0012 EXCAVATION, UNCLASSIFIED
CUT-55 STATION 37+00 TO LOWER
TERMINAL CHANNEL STATION 7+00
(ESTIMATED QUANTITY, SEE NOTE 1) 14,000 CUBIC YARD $____________ $_______________
0013 TURBIDITY MONITORING JOB $_______________
0014 ENDANGERED SPECIES OBSERVERS
(HOPPER DREDGES ONLY) JOB $_______________
0015 DEDICATED MANATEE AND SEA TURTLE
OBSERVER (MECHANICAL DREDGING ONLY,
SEE NOTE 4) JOB $_______________
0016 BIRD MONITORING (SEE NOTE 5) JOB $_______________
TOTAL OPTION A (LINE ITEMS 0012 THROUGH 0016) $_______________
TOTAL BID (LINE ITEMS 0001 THROUGH 0016) $_______________
SEE NEXT PAGE FOR NOTES.
GROUP1-18-R-J021 00010A-1
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
JACKSONVILLE HARBOR, MAINTENANCE DREDGING
40-FOOT PROJECT, CUT-55 AND LOWER TERMINAL CHANNEL
DUVAL COUNTY, FLORIDA
NOTES: (1) THE TOTAL QUANTITY SHOWN FOR EACH EXCAVATION CLIN INCLUDES REQUIRED DEPTH, ALLOWABLE OVERDEPTH, AND SHOALING ESTIMATED TO OCCUR BETWEEN THE DATES OF SURVEYS SHOWN ON THE DRAWINGS AND ACTUAL DREDGING. THE CONTRACTOR MUST NOT PERFORM WORK IN EXCESS OF THE
TOTAL ESTIMATED QUANTITY GIVEN FOR EACH CLIN.
(2) OFFER MUST PRICE ALL LINE ITEMS. SEE SECTION 00100 "INSTRUCTIONS TO OFFERORS".
(3) SEA TURTLE TRAWL SWEEPING IS REQUIRED WHEN DIRECTED BY THE CONTRACTING OFFICER. SEE
SECTION 01 57 20 ENVIRONMENTAL PROTECTION.
(4) MANATEE AND SEA TURTLE MONITORING IS REQUIRED FOR MECHANICAL DREDGING ONLY. SEE
SECTION 01 57 20 ENVIRONMENTAL PROTECTION.
(5) NESTING SEASON SURVEYS MUST BEGIN ON APRIL 1 OR 10 DAYS PRIOR TO COMMENCEMENT OF WORK (INCLUDING SURVEYING ACTIVITIES), WHICHEVER IS LATER, AND MUST BE CONDUCTED DAILY
THROUGHOUT THE CONSTRUCTION PERIOD OR THROUGH AUGUST, WHICHEVER IS EARLIER.
(6) STANDBY TIME IS DEFINED AS WHEN THE DREDGE PLANT IS NOT IN OPERATION AT THE DIRECTION OF THE CONTRACTING OFFICER. STANDBY TIME WILL BE UTILIZED ONLY DUE TO ENDANGERED SPECIES CONCERNS, DIFFERING SITE CONDITIONS, SECURITY OPERATIONS OR OTHER CONDITIONS AS DETERMINED BY THE CONTRACTING OFFICER. REQUIREMENTS FOR WORK STOPPAGES, DELAYS OR OTHER IMPACTS ASSOCIATED WITH COMPLIANCE WITH SECTION 01 57 20 ENVIRONMENTAL PROTECTION ARE NOT PAID FOR UNDER THIS LINE ITEM. STANDBY TIME IS NOT AFFORDED FOR DELAYS CAUSED BY ADVERSE WEATHER CONDITIONS OR IMPROPER OPERATIONAL PROCEDURES. PAYMENT WILL ONLY BE MADE FOR ACTUAL
STANDBY TIME REQUIRED BY THE CONTRACTING OFFICER.
(7) DISPOSAL AREA PUMPOUT TO PROTECT EXISTING BIRD NESTS IS REQUIRED WHEN DIRECTED BY THE
CONTRACTING OFFICER. SEE SECTION 01 57 20 ENVIRONMENTAL PROTECTION.
GROUP1-18-R-J021 00010A-2
SECTION 00010A, Attachment A
INSTRUCTIONS FOR TECHNICAL INQUIRIES AND QUESTIONS
Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) March 24, 2021, Close of Business. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.
All timely questions and approved answers will be made available through ProjNet.
The Solicitation Number is: GROUP1-18-R-J021
The Bidder Inquiry Key is: QFN4SY-4P8QPQ
Specific Instructions for ProjNet Bid Inquiry Access from ProjNet home page:
1. Identify the Agency. This should be marked as USACE.
2. Email. Enter the email address you would like to use for communication.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
5. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret
Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
6. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access from ProjNet home page:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. Identify the Agency. This should be marked as USACE.
3. Email. Enter the email address you used to register previously in ProjNet.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
6. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
GROUP1 -18-R-J021 00100-1
ORDERING GUIDE – APPENDIX E
THE FOLLOWING PAGES CONTAIN ADDENDUMS TO SPECIFIC CLAUSES
OF THE ORIGINAL SOLICITATION NUMBER(S): W912EP18R0029;
THIS ADDENDUM IS ONLY APPLICABLE TO THIS
SPECIFIC TASK ORDER
REQUEST FOR PROPOSAL NUMBER: GROUP1-18-R-R021
PROJECT TITLE:
JACKSONVILLE HARBOR, MAINTENANCE DREDGING 40-FOOT
PROJECT, CUT-55 AND LOWER TERMINAL CHANNEL DUVAL
COUNTY, FLORIDA
NOTICE TO OFFERORS: The information on the following pages is provided for the various clauses and/or paragraphs which require information to be filled in (when applicable) on each Request for Proposal for Task Orders issued under the awarded contracts. All applicable clauses, terms and conditions contained in the original solicitation and subsequently awarded contracts become part of each Task Order.
GROUP1 -18-R-J021 00100-2
ADDENDUM TO SECTION 00100, INSTRUCTIONS TO OFFERORS
THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00100
ARE HEREBY PROVIDED:
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO
ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB
1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
21.8% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed.
Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10
GROUP1 -18-R-J021 00100-3
working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Duval County, Florida.
(End of provision)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) (ALTERNATE I) (FEB
1995) (CESAJ ADAPTATION)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for – 25 March 2021, 0900 local time.
(c) Participants will meet at the warehouse, 3077 Talleyrand Ave. Jacksonville, FL 32206
(d) Participants should call Gavin Jackson at (904) 570-4121 on or before 1200pm EST, 24 March 2021 to make arrangements.
(e) Core borings are NOT available. (If available, follow the instructions in the Physical Data paragraph in Section 00 11 00 and 00 31 32 of individual request for proposals issued for task orders under this contract to make arrangements to inspect the borings. Failure to follow the instructions may result in a delay ranging in duration from one hour to 4 days.)
(f) After the site visit, a memorandum summarizing the visit may be posted to the appropriate website under the solicitation number. This posting will be strictly for informational purposes only. The memorandum will not become a part of the solicitation. If the solicitation needs to be changed as a result of information obtained during the site visit, a written amendment will be made available to all registered vendors. Questions regarding any information given in the memorandum must be directed to the person whose name appears in item 9 of
GROUP1 -18-R-J021 00100-4
the Addendum to the Standard Form 1442.
(End of provision)
GROUP1 -18-R-J021 00700-1
ADDENDUM TO SECTION 00700, CONTRACT CLAUSES
THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00700
ARE HEREBY PROVIDED:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 45 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 75 calendar days after the Contractor receives the notice to proceed.
The time stated for completion shall include final cleanup of the premises.
The total completion time of 75 calendar days includes the following:
Base Bid 70 calendar days (includes 45 calendar days mob/demob)
Option A 5 calendar days
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $718 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE
ITEM (MAR 1989)
The Government may require the delivery of the numbered line items, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the options (A) by written notice to the Contractor on or before July 8, 2021. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
GROUP1 -18-R-J021 00700-2
52.228-11 INDIVIDUAL SURETY—PLEDGE OF ASSETS (FEB 2021)
(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond—
(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1;
and
(2) Standard Form 28, Affidavit of Individual Surety.
(b) The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102- 1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.
(c) A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—
(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.
(2) Contracts subject to alternative payment protection (see FAR 28.102- 1(b)(1)). For the full contract performance period plus 1 year.
(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.
GROUP1 -18-R-J021 00700-3
(d) The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.
52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN
2020)
(a) Definitions. As used in this clause-
Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, GROUP1 -18-R-J021 00700-4 or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of the Treasury, Financial Management, Service Surety Bond Branch, 3700 East West Highway, Room 6 F01, Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
GROUP1 -18-R-J021 00700-5
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title File Drawing No.
Jacksonville Harbor, Plans G-01 Maintenance Dredging, 40-Foot Project Lower Terminal Channel, Duval County, Florida
GROUP1 -18-R-J021 00800-1
ADDENDUM TO SECTION 00800, SPECIAL REQUIREMENTS
THE REQUIRED FILL-INS FOR FOLLOWING CLAUSES OF SECTION 00800
ARE HEREBY PROVIDED:
LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR
SUBCONTRACTORS
The award decision for this contract was based, in part, on an evaluation of the personnel and/or subcontractors the Contractor included in its proposal for the positions and/or items of subcontracted work identified at the end of this paragraph. The Contractor agrees these personnel and/or subcontractors will be employed as described in its proposal and no substitutes will be employed without prior written approval of the Contracting Officer or Administrative Contracting Officer. The Contractor further agrees that any proposed substitutes shall meet or exceed the qualifications of the original personnel and/or subcontractors. If the Contractor’s proposal did not name a subcontractor for an identified item of work, the Contractor will not be allowed to subcontract that item of work without prior approval of the Contracting Officer or Administrative Contracting Officer. The limitations described herein shall apply to the following positions and/or items of subcontracted work: Named dredge(s).
(End of paragraph)
ADDENDUM TO SECTION 00800A, WAGE DETERMINATIONS & OTHER
ATTACHMENTS ARE HEREBY PROVIDED:
THIS PROJECT INCORPORATES BOTH THE FLORIDA STATEWIDE HEAVY
DREDGING AND HOPPER DREDGING WAGE DECISIONS
No. Title Date No. of Pages 1 Note --- 2 General Decision Number FL20210002 01/01/2021 6 3 General Decision Number FL20210003 01/01/2021 5
NOTE
EXECUTIVE ORDER (EO) 13658 ESTABLISHES AN HOURLY MINIMUM WAGE OF
$10.95 FOR 2021 THAT APPLIES TO ALL CONTRACTS SUBJECT TO THE
DAVIS-BACON ACT FOR ALL HOURS PERFORMED ON THE CONTRACT IN
CALENDAR YEAR 2021
IF YOU HAVE ANY QUESTIONS CONCERNING THE APPLICATION OF THE
WAGE DECISIONS FURNISHED FOR THIS PROJECT, PLEASE CONTACT:
FRAN RUSSELL, OFFICE OF COUNSEL, JACKSONVILLE DISTRICT, U.S. ARMY
CORPS OF ENGINEERS AT fran.g.russell@usace.army.mil
GROUP1-18-R-J021 00800A-1
mailto:fran.g.russell@usace.army.mil
"General Decision Number: FL20210002 01/01/2021
Superseded General Decision Number: FL20200002
State: Florida
Construction Type: Heavy Dredging
Counties: Florida Statewide.
Dredging Construction Projects FLORIDA (Excluding West of the Aucilla River and its tributary waterways)
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/01/2021
* ENGI0025-002 10/01/2020
Rates Fringes
Dredging : (Hydraulic Dredges Over 20"")
GROUP1-18-R-J021 00800A-2
CLASS A1....................$ 41.42 18.31+a CLASS A2....................$ 36.91 18.31+a CLASS B1....................$ 35.82 18.31+a CLASS B2....................$ 33.72 18.31+a CLASS C1....................$ 32.80 18.21+a CLASS C2....................$ 31.74 18.21+a CLASS D.....................$ 26.37 18.11+a
Hydraulic Dredges Under 20"" Cook........................$ 8.11 1.73+b Deckhand....................$ 7.77 1.73+b Engineer....................$ 9.59 1.73+b Launchman...................$ 8.19 1.73+b Leverman....................$ 10.03 1.73+b Mate........................$ 8.82 1.73+b Mess Cook...................$ 7.71 1.73+b Messman & Janitor...........$ 7.53 1.73+b Oiler & Fireman.............$ 8.11 1.73+b Shoreman....................$ 7.82 1.73+b Spider Barge Operator.......$ 8.68 1.73+b Spill Barge Operator........$ 8.68 1.73+b Welder......................$ 9.79 1.73+b
CLASSIFICATIONS:
CLASS A1: Deck Captain, Leverman, Mechanical Dredge Operator.
Licensed Tug Operator over 1000 HP CLASS A2: Crane Operator (360 swing) CLASS B1: Derrick Operator (180 swing), Spider/Spill Barge Operator, Timber Fork Operator, Dozer Operator, Engineer, Blaster/Driller, Fill Placer, Electrician, Licensed Boat Operator, Licensed Crew Boat Operator.
CLASS B2: Certified Welder.
CLASS C1: Mate, Drag Barge Operator, Welder, Assistant Fill
Placer, Steward.
CLASS C2: Boat Operator.
CLASS D: Shoreman, Deckhand, Rodman, Scowman, Cook, Messman, Oiler, Janitor, Drill Oiler
PREMIUMS: Additional 20% for hazardous material work
FOOTNOTE APPLICABLE TO ABOVE CRAFTS:
a. New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
Vacation Contribution of 8% of straight time rate multiplied by the total hours worked.
b. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day. Plus Vacation contribution of 8% of straight time pay for all hours worked.
GROUP1-18-R-J021 00800A-3
INCENTIVE PAY : (Add to Hourly Rate)
Operator (NCCCO License/Certification) $1.80; Licensed Tug Operator over 1000 HP (Assigned as Master) USCG licensed Master of Towing Vessels (MOTV) $1.80; Licensed Boat Operator (assigned as lead boat captain) USCG licensed boat operator $1.30; Engineer (QMED and Tankerman endorsement or licensed engineer (USCG) $1.80; Oiler QMED and Tankerman endorsement (USCG) $1.80; All classifications Tankerman endorsement only (USCG) $1.55; Deckhand or Mater AB w/Lifeboatman only (USCG) $1.80; Welder (ABS certification) $1.55
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage
GROUP1-18-R-J021 00800A-4
determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those
GROUP1-18-R-J021 00800A-5
classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
GROUP1-18-R-J021 00800A-6
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
GROUP1-18-R-J021 00800A-7
"General Decision Number: FL20210003 01/01/2021
Superseded General Decision Number: FL20200003
State: Florida
Construction Types: Heavy Dredging
Counties: Florida Statewide.
HOPPER DREDGE CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate, if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/01/2021
SUFL1993-010 05/24/1993
GROUP1-18-R-J021 00800A-8
Rates Fringes
Self-Propelled Hopper Dredge Drag Tenders................$ 8.21
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
GROUP1-18-R-J021 00800A-9
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
GROUP1-18-R-J021 00800A-10
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.