B.08.02 li09_011010 SOW.pdf
PDF 268 KB Posted
- Solicitation number
- IEU-24-0008
- Issued by
-
Department of the Army European Command
About this file
This document is a Statement of Work for the renovation of the Svencionys Fire and Rescue Station in Svencionys, Lithuania. The US Army Corps of Engineers (USACE) Europe District plans to solicit proposals for a design-build project to renovate the existing two-story, solid masonry/concrete building.
The key renovation requirements include insulating the exterior walls and attic, replacing the asbestos roof and installing a new exterior insulation finish system (EIFS), replacing the roof gutters and downspouts, providing a perimeter drainage trench, replacing exterior doors and garage windows, extending the existing heating system to the garage, replacing lighting fixtures in the garage, providing an epoxy floor coating in the main garage, and replacing the flat roof membrane on the half basement structure. The project is located at Latitude 55°8'0.36"N, Longitude 26°9'45.80"E.
The USACE plans to issue a full and open solicitation for a single design-build, firm-fixed price construction contract with an estimated value between $500,000 and $1,000,000 USD. The anticipated contract duration is between one and two years after award. The solicitation is expected to be released in May 2024.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Europe District
APO AE 09049
li09
Statement of Work Project Number:
Proj. No.: 70089 Fiscal Year: 2024
Švenčionys Fire and Rescue Station Švenčionys, Lithuania
Prepared by:
Design Section
Engineering Branch
21MAR2024
01 10 10 Statement of Work Švenčionys Fire and Rescue Station
21-Mar-24 Page 2 of 43
SECTION 01 10 10
STATEMENT OF WORK
SECTION TABLE OF CONTENTS:
1 GENERAL
2 CIVIL AND GEOTECHNICAL
3 ARCHITECTURAL
4 STRUCTURAL
5 ELECTRICAL & COMMUNICATIONS
6 MECHANICAL & PLUMBING
7 FIRE PROTECTION (Covered in other sections)
ATTACHMENTS
Attachment # 1 Location Map Attachment # 2 Conceptual Site Plan Attachment # 3 Annotated Drawings Attachment # 4 Structural Calculations Guideline Attachment # 5 Dedication Plaque Attachment # 6 Existing Utilities Plan Attachment # 7 Scope for Independent Structural Proofing Attachment # 8 Existing Elevations
1.0 GENERAL
1.1 PROJECT DESCRIPTION
The Request for Proposal (RFP) provides parameters for a design-build project for renovation of a fire and rescue station in Švenčionys, Lithuania; Latitude 55° 8'0.36"N, Longitude 26° 9'45.80"E (Refer to the attached Location Map.)
The Švenčionys Fire and Rescue Station is located in the south-eastern region of Lithuania. The facility was constructed in the 19th Century as a horse carriage barn. The original building was renovated in 1940 and has had multiple additions and modifications since. The main vehicle garage was added in 1994 along with a small one-story multi-purpose space. An additional two-story office space was added in 1996. Since that time, there has not been significant modernization or rehabilitation of the facility or major building components. The facility is inadequate compared to modern day standards and the current condition hinders the response capabilities and resiliency of the Fire and Rescue Service.
Fire fighters work on a 24-hour shift followed by three days off. There are 14 building occupants during the day (8 fire fighters and 6 administrative staff) and 9 at night.
The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:
a. Insulate exterior walls and attic slab. Class B classification for energy consumption per EU regulation 2017/1369 of 4 July 2017 must be achieved.
Provide exterior insulation finish system (EIFS) for all exterior walls.
b. Provide exterior polymer composite board finish for the building main entry facades only (northeast and northwest building facades).
c. Replace asbestos roofs and attic insulation.
d. Replace roof gutters and downspouts.
e. Provide a perimeter drainage trench around the fire and rescue station.
f. Connect building downspouts to the municipal storm system.
g. Provide PCC apron around the fire and rescue station.
h. Replace four (4) exterior doors.
21-Mar-24 Page 3 of 43
i. Replace maintenance garage #105 windows.
j. Extension of existing heating system to service garage.
k. Replacement of the light fixtures in garage.
l. Provide epoxy mastic floor coating in the main garage.
m. Replace flat roof membrane for half basement structure.
n. Replace existing vehicle garage exhaust extraction system with new.
1.2 GENERAL REQUIREMENTS
The Contractor must deliver fully functional, turnkey type facilities (without mobile furniture) as described in this document. The work includes - but is not limited to
- design, demolition, fabrication, delivery, installation, construction, and site work.
The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the
SOW.
These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.
1.2.1 BASE ITEMS AND OPTIONAL ITEMS
This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to Specification Section 01 22 00 PRICE AND PAYMENT PROCEDURES. The Schedule of Items identifies the breakdown between the individual base items and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base or Optional Items.
Consider all items not specifically identified in the Optional Items as part of the Base Items.
1.3 FUNCTIONAL AREAS
Refer to the attached drawings for a depiction of the required functional areas and spatial adjacencies for the site and new facilities/structures.
1.4 SUBMITTALS
Designer of Record approval is required for submittals with a “DA” designation.
Government approval is required for submittals with a “G” or “GA” designation.
Submittals having an “FIO” designation are for Contractor Quality Control approval.
Submit the following to the Contracting Officer (KO) in accordance with Section 01
33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G
Sequencing Plan; G
SD-05 Design Data
65% Pre-Final Design; DA/GA
95% Final Design; DA/GA
100% Corrected Final Design; DA/GA
21-Mar-24 Page 4 of 43
SD-06 Test Reports
Test Results and Reports; FIO
1.4.1 DESIGN SUBMITTALS
Provide a complete design package at each milestone, as described in RFP Section 01 33 16-DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.
1.4.2 TEST REPORTS
Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with RFP Section 01 33 00-SUBMITTAL PROCEDURES. Submittals will be considered for information only (FIO) submittals unless specifically identified as a submittal requiring government approval. Coordinate with the KO after award for the specific items to be included in the submittal register.
1.5 MATERIALS AND EQUIPMENT
Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.
Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the KO.
1.5.1 LIFE-SPAN
The facility and the installed equipment must be permanent construction with an expected lifespan of more than 25 years.
1.5.2 MAINTAINABILITY
Provide low maintenance materials and systems appropriate for the project climate and location.
1.5.3 OPERABILITY
Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.
1.5.4 STANDARDIZATION
Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.
1.6 DESIGN DIMENSIONS
Develop the design using the metric system.
1.7 DESIGN CRITERIA
Project design, site facilities, utility systems and material standards must be in accordance with Host Nation building codes (current versions as of the date of RFP, unless otherwise indicated). In the absence of Host Nation building codes, use the International Building Code (IBC) and the codes, technical standards, and regulations referenced in this RFP.
While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited
21-Mar-24 Page 5 of 43 standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the KO. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.
Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
1.8.1 DEMOLITION
The Contractor is responsible for all required demolition as indicated in this scope.
1.8.1.1 ABATEMENT AND DISPOSAL
All demolished materials, including hazardous materials identified below, must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.
1.8.1.2 LOCATION OF HAZARDOUS MATERIAL
There is assumed asbestos in the roof sheeting.
The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the KO and provide the results of the relevant sampling and testing. Provide the hazardous material report no later than 30 days after Notice to Proceed (NTP) for information and approval.
1.8.2 PROTECTION OF WORK AREA
1.8.2.1 DUST AND DEBRIS CONTAINMNET
Seal the project area with construction barriers and dust partitions in order to contain construction dust and debris and maintain a clean environment outside of the work area. In addition to protections within the work area, provide temporary protection for all finishes from the entrance of the facility to each area of work.
Patch and repairing any damage caused during construction. Coordinate the locations of barriers with the Government prior to the start of work.
1.8.2.2 PROTECTION OF FURNITURE, FIXTURES, AND EQUIPMENT
Protect all existing furniture, fixtures, and equipment that remain within the work area. Coordinate with the Government for any special protection measures required for sensitive equipment. The Contractor is responsible for repairing or replacing any damage caused during construction. The Contractor must conduct a preconstruction survey of furniture, fixtures, and equipment with a Government representative present.
1.8.2.3 NOISE AND VIBRATION CONTROL
Employ demolition and construction methods that minimize the production of sound and vibration. Coordinate the schedule of especially loud or disruptive activities with the KO prior to the start of work.
1.8.2.4 PROTECTION OF EGRESS AND LIFE SAFETY
The Contractor must not take actions that hinder existing egress paths or disrupt operation of life safety systems without prior coordination with the KO and all applicable authorities having jurisdiction (AHJ). The Contractor is responsible for supplying signage or other protective measures as required by the KO or AHJ prior to impeding the egress path or life safety system.]
21-Mar-24 Page 6 of 43
1.8.2.5 MOISTURE CONTROL
Establish and implement a moisture control strategy for controlling moisture and condensation to prevent building damage, minimize mold contamination and reduce health risks related to moisture.
1.8.2.6 ENVIRONMENTAL TOBACCO SMOKE CONTROL
Smoking is prohibited with the building and a minimum of 15 meters of all building entrances, operable windows, and building ventilation intakes.
1.8.2.7 REDUCE ENVIRONMENTAL IMPACT OF MATERIALS
Use construction products that have a lesser or reduced effect on human health and the environment.
Provide products that meet or exceed EPA’s recycled content recommendations available at the link below or local equivalent.
https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program
Provide products composed of the highest percentage of biobased content consistent with the USDA BioPreferred Program, if products meet performance requirements and are available locally at a reasonable cost.
Do not use ozone depleting compounds and high global warming potential (GWP) chemicals.
1.8.2.7 ELECTRIFICATION
Do not provide fossil fuel burning equipment. In accordance with ECB 2023-08 and E.O. 14057, provide all electric technologies for space conditioning, water heating, cooking, and laundry.
1.8.3 SEQUENCING OF CONSTRUCTION WORK
The Contractor must sequence construction to allow the facility to remain operational during construction. Do not block access to occupied areas during construction.
Utility and communication services must remain functional in all occupied areas.
Provide a Sequencing Plan with the 95% Final Design Submittal. The Sequencing Plan must describe the proposed performance of construction operations to comply with the stated sequencing requirements. The Sequencing Plan must include a graphical depiction of the sequencing of each work area and mobilization/staging area. The Sequencing Plan is in addition to the requirements of RFP Section 01 32 01-PROJECT SCHEDULE or 01 32 16-SMALL PROJECT PROGRESS SCHEDULES (NOTE: Only one of these specifications applies to this contract, refer to other documents for the section applicable to this project).
END OF SECTION
21-Mar-24 Page 7 of 43
2.0 CIVIL AND GEOTECHNICAL
Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional, and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.
2.1 SCOPE SUMMARY
Civil works for this project include, but are not limited to, site survey, geotechnical investigation, site layout, demolition, earthwork, storm system, and pavement. Refer to the bid schedule for which of these are base bid or optional.
2.2 EXISTING CONDITIONS
2.2.1 TOPOGRAPHY
There is no known topographic survey for the project site. The existing site contains buildings, pavement, utilities, fences, and a tree. There is very little vegetation and no apparent slope to the site. The existing information shown on Att. #2 - Conceptual Site Plan was compiled from google earth and site photos.
2.2.2 UTILITIES
The building is connected to municipal electrical, potable water supply, telephone, and sanitary utilities. A local municipal storm sewer exists but the building is not connected to it. An existing utility map is available in Att. #6 – Existing Utility Information. Contractor must verify all utility locations (surface and subsurface) in the field prior to the first design submittal.
2.2.3 GEOTECHNICAL
There is no geotechnical information available for the project site.
The Contractor must perform a Geotechnical Investigation and submit a Geotechnical Report as part of the Design Analysis. Refer to other sections of this SOW for the requirements of the Geotechnical Investigations and Report.
2.2.4 ENVIRONMENTAL
There are no known environmental protection areas or archeological preservation areas on the project site. There is no prior knowledge of any hazardous or contaminated materials in the site’s soil or pavement. Apparent environmental hazards include high winds, heavy snow, and flooding due to heavy rains.
2.2.5 EXISTING CONDITIONS INVESTIGATION
Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:
a. Weather or similar physical conditions at the site.
b. Existing depth of groundwater and drainage characteristics of the existing soil.
c. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.
d. Determination of the existing laundry room drainage channel and/or piping source and discharge.
e. Mobilization and staging constraints.
2.3 DESIGN SUBMITTALS
Provide civil design submittals in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.
65% Design Submittal:
a. Pre-Final Design Analysis of civil features.
b. Final Site Survey (include in the Design Analysis).
21-Mar-24 Page 8 of 43
c. Final Geotechnical Report (include in the Design Analysis).
d. Final Existing Conditions Plan.
e. Pre-Final Demolition Plan.
f. Pre-Final Pavement Profiles, Cross Sections, and Details
g. Pre-Final Utility (Storm) Profiles, Cross Sections, and Details.
h. Preliminary Civil Specifications
95% Design Submittal:
Update all items from the 65% Design Submittal to 95% (Final) Design. Incorporate all 65% design comments.
100% Submittal:
The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal.
Address all previous government review comments before submitting.
As Built Drawing Submittal:
In addition to the as-built requirements discussed in RFP Section 01 78 00-CLOSEOUT SUBMITTALS, provide a topographical survey of the site per requirements of SOW Section 2.6-SITE SURVEY. Include existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original Site Survey.
2.3.1 DESIGN ANALYSIS
Submit a Design Analysis in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD.
Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval.
Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.
The Design Analysis includes but is not limited to:
a. Discussion of Storm system constraints and design decisions. Provide a hydrologic and hydraulic analysis of the storm system, including offsite areas that contribute to and influence the project’s storm system. Provide drainage basin map(s), rainfall data, and coefficients used. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Use the Rational Method or TR-55 for analysis and design. In the absence of Host Nation requirements, use a minimum 10-year storm frequency for analysis and design.
Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the storm system. Confirm that the existing receiving system has adequate capacity to receive the additional stormwater flow generated by the project.
b. Site Survey as an appendix.
c. Geotechnical Investigation and Report as an appendix.
2.3.2 DESIGN DRAWINGS
Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features. Provide comprehensible differentiation between features that are proposed, existing, future, 21-Mar-24 Page 9 of 43 or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. In the absence of the Host Nation’s drafting requirements, Reference USACE A/E/C Graphics Standard for graphic requirements.
2.3.3 SPECIFICATIONS
Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.
2.4 DESIGN CRITERIA
Provide civil design in accordance with Host Nation codes. In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:
a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering
b. UFC 3-220-01, Geotechnical Engineering
c. USACE A/E/C Graphics Standard (ERDC/ITL TR-19-6)
2.5 GEOTECHNICAL INVESTIGATION AND REPORT
Perform a geotechnical investigation and assessment of the project site to determine the subsurface conditions and geotechnical parameters for pavement and utility design. Perform the necessary amount of testing, and test pits at depths suitable for the project improvements. Include geotechnical investigation in areas where borrow material will be used. The Geotechnical work must be performed under the supervision of a professional geotechnical engineer registered with the jurisdiction having authority, and the report must be signed by the Geotechnical Engineer. In the absence of Host Nation codes, perform the geotechnical investigation and report per conforming to the applicable Eurocode standard and National Annexes.
Coordinate testing locations with the KO to avoid impact to existing utilities and facility operations. Utility locates, permits, pavement removal and vegetation clearing are the Contractor’s responsibility. Repair disturbed areas with a concrete patch in paved areas, and compacted soil in non-paved areas. The repaired area must be flush with the adjacent surface. Following restoration, stake and flag each of the hole locations with test pit identification numbers. In paved areas, use white paint on the paved surface to mark hole locations. Provide a map indicating the test pit locations.
2.5.1 REPORT
Include, as applicable, the following information:
a. Description of field work completed, and equipment used; names, signatures and stamps of licensed professionals involved; name of drilling company.
b. A description of site subsurface conditions, regional geology, and seismic conditions at the site.
c. Site map of test pit locations.
d. Bore hole logs with classification of all subsurface materials. The logs must distinguish fill materials from native materials, include all in-situ test results, and include groundwater depth information, if groundwater is encountered. Distinguish between bedrock and rock boulders.
e. Reports of all the field and laboratory testing.
f. Recommendations for preparation, placement, and compaction of onsite soils, soil replacement, soil amendment/treatment, structural fill, topsoil, and trench backfill. Include dewatering and temporary retaining structure needs.
g. Frost Depth.
h. Recommendations for the storm system involving infiltration.
i. Calculations to support conclusions and recommendations.
2.5.2 DESIGN DRAWINGS AND SPECIFICATIONS
21-Mar-24 Page 10 of 43
On the design drawings and/or specifications, include geotechnical information that affect the design of the project, including but is not limited to, test pit locations, test pit logs, groundwater and frost depths, and any details that convey requirements for site preparation.
2.6 SITE SURVEY
Conduct and provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Survey must be conducted prior to the first design submittal. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project.
Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis. Locate and show on the topographic survey the following information:
a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.
b. Survey monuments. Include description.
c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.
d. Buildings and other miscellaneous structures. Provide finish floor elevation.
e. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations
f. Surface Drainage Features.
g. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground; pipe sizes and materials.
h. Fences. Include height, material, direction of outrigger, gate locations and types.
i. Signs. Include sign text.
j. Trees. For tree removal, identify trees per Host Nation permitting requirements.
Where selective clearing will be proposed, locate trees over 150-millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.
k. Locate environmentally sensitive areas (determined and marked by others).
l. Geotechnical test pit locations.
m. North arrow and scale of drawing.
n. Legend depicting the symbols and abbreviations used on the drawing.
o. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.
Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.
Upon completion of construction, update the original survey with an As-built survey of the site as constructed, including underground utility locations and depths.
Submit the As-built survey to the KO for approval.
Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. In the absence of the Host Nation’s coordinate system, use the Universal Transverse Mercator (UTM) coordinate system. The vertical coordinate system must be based on sea level.
2.7 SITE LAYOUT
21-Mar-24 Page 11 of 43
Locate the proposed utilities indicated on Att. #2 – Conceptual Site Plan as indicated on the attached Conceptual Site Plan. Amend the site layout as determined by the site-specific constraints, code requirements, the owner’s preferences, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work. Locate proposed utility mains a minimum of 3 meters away from existing buildings.
The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.
2.8 DEMOLITION
Remove existing pavement and other features to construct the proposed improvements.
Provide straight, neat sawcuts at limits of pavement removal. All contaminated soils discovered require special testing and disposal per Host Nation requirements.
2.8.1 CONSTRUCTION LIMITS
Do not disturb any areas past the site’s property line, with the exception of utility trenches. The Contractor is responsible for coordination and permits associated with improvements outside the property boundary. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.
2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as required by the KO. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the KO prior to performing said work.
2.8.3 TREES
If it cannot be avoided, remove trees with driplines within the footprint of the proposed improvements. Protect trees which might be damaged during construction, with a 1.8-meter-high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. Trees are defined as larger than 150mm diameter at 1.3 meters above existing grade. Mitigate for tree removal per Host Nation requirements. Tree cutting interrelated processes need to be coordinated with responsible persons and local authorities. This includes, but is not limited to, compensation measures and endangered species studies. The Contractor is responsible for permitting, environmental studies, and coordination with local authorities related to tree and vegetation demolition.
2.8.4 UTILITIES
Any existing utilities encountered within the site boundary that are impacted by this project must be protected, or relocated if protection is not feasible. Relocate existing utility mains outside the structural zone of influence of proposed buildings and structures. Utilities impacted by this project that require decommissioning, or that are already out of service, must be removed up to the utility main and capped. Reroute existing utilities to remain in accordance with SOW Section 2.10-
UTILITIES.
2.8.5 DUST, DEBRIS, AND EROSION CONTROL
Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily. Remove and
21-Mar-24 Page 12 of 43 transport the debris in a manner that prevents spillage on streets or adjacent areas.
Apply local regulations regarding hauling and disposal.
2.8.7 ADDITIONAL REQUIREMENTS
Reference RFP Section 00 74 01-SPECIAL CONDITIONS, and 01 30 01-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.
2.9 EARTHWORK
Perform all earth work necessary for the installation of the proposed improvements.
2.9.1 PLANS AND SPECIFICATIONS
Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems. The earthwork requirements must not conflict with the recommendations in the Contractor-provided Geotechnical Report.
2.9.2 CONTAMINATED SOIL
Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the KO for further guidance.
2.9.3 SATISFACTORY MATERIAL
Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.
Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.
2.9.4 BACKFILL COMPACTION
In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e., a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the KO. All structure foundation excavations must be inspected and approved by the Contractor’s Geotechnical Engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer and approved by the KO.
2.9.5 ENGINEERED SOIL SUPPORT SYSTEMS
Provide engineered soil support systems (i.e., shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.
2.9.6 SITE GRADING
Provide site grading that directs storm water runoff away from buildings and structures either by drainage systems or by grading as follows:
a. Finished grades of earth/grass surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 5% for the first 2 meters.
21-Mar-24 Page 13 of 43
b. Finished grades of paved surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 2% for the first 2 meters.
c. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties. Provide storm improvements if ponding is unavoidable.
The Contractor must limit proposed landscape slopes to a maximum 4H:1V for grass areas requiring mowing and 2H:1V for non-grass areas, which require non-erodible surface (i.e., rock, shrubs with mulch).
2.10 UTILITIES
This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, gas, liquid fuel, and heat. See Sections 5.0-ELECTRICAL & COMMUNICATIONS, Section 6.0-MECHANICAL, and Section 7.0-FIRE PROTECTION for additional utility requirements.
In the absence of Host Nation requirements, design utilities per IBC and UFC 3-201- 01, Civil Engineering. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations. Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used; whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.
Coordinate all required installation, relocation, improvement, and protection of utilities held by third party (e.g., public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.
Provide utility materials per IBC requirements. Provide corrosion protection for utilities that provides the minimum life expectancy specified in Section 1.0-GENERAL.
Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.
2.10.1 STORM SYSTEM
Provide a gravity storm drainage system to direct runoff away from improvements, eliminate ponding, and prevent erosion. A pump system is not allowed. An infiltration system is not allowed. Proposed storm improvements include:
a. Perimeter drainage trench around the facility that consists of a minimum 30 cm wide trench with drainage material (gravel) from grade to the depth of the building footings. Provide perforated drainage pipe in the drainage trench that connects to the municipal storm system with a solid wall pipe. Provide filter fabric geotextile between drainage trench aggregate and native ground.
b. Connect building downspouts to the municipal storm system in a separate pipe than the perimeter trench drainage system.
c. Reroute drainage from the existing drainage channel and/or piping through the laundry room to the existing sanitary system. The new drainage system must not allow storm water or sewage backflow into the laundry room.
Allowable storm pipe materials include polyvinyl chloride (PVC), high density polyethylene (HDPE), ductile iron, or reinforced concrete pipe. Storm structures must be concrete, with traffic rated cast iron or ductile iron frames and covers.
Provide metal covers over all drainage collection trenches constructed through
21-Mar-24 Page 14 of 43 existing paved sidewalks, driveways, or parking areas. Trench covers shall be rated for loading from the fire station’s largest truck.
After installation, test storm lines and structures for leakage and deflection per Host Nation codes. Provide test results to the COR. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.
In the absence of Host Nation standards, design the storm drainage system per UFC 3-201-01, Civil Engineering Chapter 3-Storm Drainage Systems.
2.11 PAVEMENT
Proposed pavements for the project include:
a. Portland cement concrete (PCC) apron of minimum 1 meter wide around the fire and rescue station. Minimum thickness of concrete is 150mm. Minimum thickness of granular base is 100mm. Provide thicker base if required to protect weak subgrade soils or to reduce frost penetration into the subgrade. Install the top of the apron a minimum of 100mm above the adjacent ground. Provide a minimum of 50mm of bury on the concrete. Provide expansion joint between building and apron. Provide expansion joints within the building apron spaced at 1 meter maximum to prevent cracking. Provide expansion joint between building and apron.
Provide medium broom finish on PCC concrete.
b. Replace existing pavement sections where the trenching occurs for utility installation and where pavement is removed for below grade exterior wall waterproofing work. Sawcut a minimum 30 centimeters beyond edge of trench.
2.12 LANDSCAPING
Provide grass seed and 20 centimeters of topsoil on the site in areas that do not have pavement or a building within the limits of disturbance. Seeds must be locally sourced from a certified plant nursery, and native to the area. Provide seed coverage density per manufacturer/supplier’s recommendations. Provide watering, weeding, and any other necessary care to establish growth. Limit planting to times of the year per local codes and/or manufacturer/supplier’s recommendations. Replace topsoil and seeds, at Contractor’s expense, in areas which do not have new growth coverage of 75% before the warranty period ends.
Before using chemicals during landscaping work, including for use on plants and on site features, the Contractor must submit to the KO, in the form of brochures, certificates and other technical material, information about the chemicals proposed, including about their environmental compatibility. Their use is only permitted with approval of the KO.
21-Mar-24 Page 15 of 43
3.0 ARCHITECTURAL
3.1 PROJECT DESCRIPTION
Provide and perform architectural design and construction services to provide a complete, accessible, functional, and usable fire and rescue station.
Renovate existing two-story, solid masonry / concrete building complex that will serve as fire and rescue station.
Extensive coordination is required between the architectural work and the work of other disciplines described in this SOW.
3.1.1 DESIGN
Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the KO. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.
3.1.2 DESIGN SUBMITTALS
Provide all architectural submittals after contract award in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and 01 33 00-SUBMITTAL PROCEDURES. Prepare and submit the documents listed below at the submittals indicated.
3.1.2.1 65% DESIGN SUBMISSION
Include the following drawings and reports as applicable to the project:
a. Code Summary – Provide a tabular code compliance summary indicating Host Nation and/or IBC life safety requirements for all new facilities.
b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.
c. Demolition Plans – Provide existing floor plans, indicating all demolition required.
d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.
e. Building Elevations – Provide all building elevations indicating all exterior materials.
f. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
g. Building Section – Indicate heights of critical building elements.
h. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.
i. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.
j. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.
3.1.2.2 95% DESIGN SUBMISSION
The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include the following drawings and reports as applicable to the project:
21-Mar-24 Page 16 of 43
a. All documents from the 65% submittal updated to incorporate 65% review comments.
b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.
c. Building Elevations – Provide all building elevations indicating all exterior materials.
d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.
e. Building Section – Indicate heights.
f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.
g. Section and Plan Details – Provide details of critical building intersections.
h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.
i. Finish Schedule – Indicate all proposed finishes.
j. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.
k. Final Specifications – Provide line items and detailed descriptions of all work to be performed.
3.1.2.3 100% DESIGN SUBMISSION
The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the 95% Submittal updated to incorporate all previous review comments.
3.2 TECHNICAL CRITERIA AND STANDARDS
Design and construct the project in accordance with the requirements outlined in Section 1.7 DESIGN CRITERIA.
3.2.1 LIFE SAFETY REQUIREMENTS
The Design must meet all Host Nation and local Fire Suppression System codes and requirements. All new structures must have exits and means of egress that comply with current Host Nation codes and standards. In the absence of Host Nation codes and standards, for individual concerns of Life Safety the Contractor must follow the International Building Code (IBC).
3.2.2 HANDICAPPED ACCESSIBILITY REQUIREMENTS
Handicapped accessibility requirements do not apply to this facility.
3.3 GENERAL SCOPE OF WORK
Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain, snow and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the KO. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.
3.4 DETAILED SCOPE OF WORK
The Contractor is responsible for the following specific tasks required for the construction of this facility.
21-Mar-24 Page 17 of 43
3.4.1 DEMOLITION
Demolition work includes, but is not limited to, the following items:
a. Demolish and remove existing exterior façade finishes.
b. Demolish and remove existing roofing and attic insulation.
c. Demolish and remove existing roof gutters and downspouts.
d. Demolish and remove existing doors.
e. Demolish and remove existing garage windows.
f. Remove existing communication pole and footing.
3.4.2 BUILDING SYSTEM AND MATERIALS
The intent of this RFP is to allow the Contractor the maximum flexibility to design and construct this facility in an economical manner without sacrificing good engineering practices, quality materials and systems. The Government requires low or no maintenance finish materials to the greatest extent possible. Provide a design informed by the modular size of selected materials. Building materials as described herein are minimum requirements and may require revision based on code compliance and criteria.
3.4.2.1 FIRE PROTECTION RATINGS OF INTERIOR FINISHES
All interior finishes must conform to Host Nation fire protection standards/requirements.
3.4.2.2 ACOUSTICAL DESIGN
Doors, walls, floors, and ceilings must meet the minimum sound protection per Host Nation requirements.
3.4.2.3 THERMAL INSULATION
Provide thermal insulation in accordance with Host Nation, local requirements, and class B classification for energy consumption per EU regulation 2017/1369 of 4 July 2017.
3.4.2.4 CORROSION PREVENTION
All exterior materials and finishes must be appropriate for continuous exterior exposure. All materials susceptible to UV degradation must contain UV inhibitors.
Provide corrosion resistant coatings on all materials susceptible to corrosion.
Coatings must be applied in the factory prior to delivery to the maximum extent practicable. Physically separate dissimilar metals with non-conductive hardware. Do not install aluminum in direct contact with concrete. Treat all wood with preservatives where it is contact with concrete or exposed to the exterior. Cover all exterior wood with metal flashing or exterior grade paint. Do not install wood in contact with soil.
3.4.3 EXTERIOR CONSTRUCTION WORK
Provide the following exterior architectural systems.
3.4.3.1 EXTERIOR WALLS
Design and repair existing exterior walls in accordance with (IAW) the requirements of this SOW. Refer to Section 4.0 STRUCTURAL. Exterior walls must have smoke/fire resistance ratings as required by Host Nation, and local fire and life safety codes.
Provide exterior wall finishes appropriate for the wall structure as required below.
3.4.3.1.1 EXTERIOR WALL INSULATION FINISH SYSTEM (EIFS)
Install new exterior insulation finish system (EIFS) with new polystyrene thermal insulation, stucco and paint. Install exterior insulation system consisting of insulation boards, to include mineral lightweight plaster and fiberglass reinforcing net. Insulation boards must meet requirements for class B classification for energy consumption per EU regulation 2017/1369 of 4 July 2017. Install EIFS system on the
21-Mar-24 Page 18 of 43 building base. Dowel all boards. Provide all necessary expansion joints, base and corner rails, diagonal fiberglass-reinforcing fabric at the window and door corners, and end flashing at eaves. Use products from a single system, by a single manufacturer, which are certified by the manufacturer to be suitable for the purpose.
This also applies to the paint. Apply products in accordance with the manufacturer's instructions. Provide all necessary sealing e.g. at windowsills. Submit a sample of the insulation system along with the manufacturer's catalog data including installation instructions, typical details and product data for approval.
3.4.3.1.2 EXTERIOR FAÇADE WPC BOARD FINISH – WOOD POLYMER COMPOSITE BOARDS
Provide thermal insulation and exterior wood polymer composite board finish for the building main entry facades only (northeast and northwest building facades).