B.08.02 FY21-26 Dive SATOC Pricing Schedule.xlsx

XLSX spreadsheet 22 KB Posted

Attached to
NWD - Dive Services Base + Four Option Years Federal contract opportunity
Solicitation number
W912EF21Q0049
Issued by
Department of the Army Corps of Engineers Engineering District Walla Walla

View the file

Other files for this federal contract opportunity

Other files attached to NWD - Dive Services Base + Four Option Years, newest first.
File Type Posted
Bidder Inquiry W912EF21Q0049.pdf PDF
B.08.02 Solicitation Past Performance.pdf PDF
B.08.02 Solicitation Key Personnel.pdf PDF
B.08.02 Sample Task Order for Quote.pdf PDF
B.08.02 Contractor Check List.xlsx XLSX spreadsheet
B.08.02 Solicitation (W912EF21Q0049).pdf PDF
B.08.02 Sample Task Order for Quote.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

NWD - FY21-26 UNDERWATER DIVE SERVICES
IDIQ UNIT PRICE SCHEDULE
Note: It is estimated that all jobs performed under this contract will require a minimum 5-person crew as described in item 0001.
Most jobs will require dive depths of less than 100 feet and will be 1 to 2 days in duration.
The intent of this contract is to provide diver-directed emergency/time critical underwater services as required for the Walla Walla and Portland District for the period of base year of this contract. There are four option years.
PRICE SCHEDULE FOR WALLA WALLA, WASHINGTON
Base YearOY1OY2OY3OY4
Line ItemDescriptionUnit of MeasureUnit PriceUnit PriceUnit PriceUnit PriceUnit Price
0001Basic Dive Day (8 hrs): Using surface supplied air (SSA), employing a 5 person dive team comprised of: (1) non-diving dive supervisor, (2) divers, (1) standby diver, (1) tender, . Include all associated dive equipment and tools, dual lock dive chamber, camera/monitoring with DVD recording capability. (Standard length of individual dive shift per calendar day is (4) four hours, maximum of three four-hour dive shifts per 12-hour work day allowed.)
0001AAStandard dive up to 50 feet deepPer Day
0001AB51 – 100 feet deepPer Foot
0001AC101 – 150 feet deepPer Foot
0001AD151 - 200 feet deepPer Foot
0002Additional Qualified Diver added to the 5 person dive team for a basic 8 hour work day.
0002AAStandard dive up to 50 feet deepPer Day
0002AB51 – 100 feet deepPer Foot
0002AC101 – 150 feet deepPer Foot
0002AD151 - 200 feet deepPer Foot
0003Mobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the dive site. Note: Time required to do this does not constitute part of the dive day.
0003AAMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the Dworshak dive site.*1 per each task order
0003ABMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the Lower Granite dive site.*1 per each task order
0003ACMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the Little Goose dive site.*1 per each task order
0003ADMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the Lower Monumental dive site.*1 per each task order
0003AEMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the Ice Harbor dive site.*1 per each task order
0003AFMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the McNary dive site.*1 per each task order
0003AGMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the Lucky Peak dive site.*1 per each task order
0004Mobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dams
0004AAMobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dam, Dworshak dive site.*1 per each task order
0004ABMobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dam, Lower Granite dive site.*1 per each task order
0004ACMobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dam, Little Goose dive site.*1 per each task order
0004ADMobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dam, Lower Monumental dive site.*1 per each task order
0004AEMobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dam, Ice Harbor dive site.*1 per each task order
0004AFMobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dam, McNary dive site.*1 per each task order
0004AGMobilization and demobilization of workboat (dive boat) to USACE Walla Walla District Dam, Lucky Peak dive site.*1 per each task order
0005Dive Boat capable of accommodating dive crew, 2 Corps of Engineers personnel and all necessary equipment. Boat must have sufficient freeboard and horsepower to navigate the Snake River.Per Day
0006Welding supplies and consumablesPer Hour
0007Overtime pay rate-Dive supervisor.Per Hour
0008Overtime pay rate-DiverPer Hour
0009Overtime pay rate-TenderPer Hour
0010Overtime pay rate for standby diverPer Hour
0011Overtime pay rate for ROV Pilot/OperatorPer Hour
0012Overtime pay rate for PilebuckPer Hour
0013Remote Operated Vehicle Crew: includes ROV pilot and operator, 8 hours per day, truck, fuel and per diems.Per Day
0014Remote Operated Vehicle: A Class II or III, HD ROV Package Refer to section 3 CONTRACTOR PROVIDED SPECIAL UNDERWATER EQUIPMENTPer Day
0015Additional Equipment Required based on an individual task order requirement: The Mark up percentage to be added%
0016Mobilization and Demobilization of Modular Floats & Skiff to dive site.
0016AAMobilization and Demobilization of Modular Floats & Skiff to Dowrshak dive site.*1 per each task order
0016ABMobilization and Demobilization of Modular Floats & Skiff to Lower Granite dive site.*1 per each task order
0016ACMobilization and Demobilization of Modular Floats & Skiff to Little Goose dive site.*1 per each task order
0016ADMobilization and Demobilization of Modular Floats & Skiff to Lower Monumental dive site.*1 per each task order
0016AEMobilization and Demobilization of Modular Floats & Skiff to Ice Harbor dive site.*1 per each task order
0016AFMobilization and Demobilization of Modular Floats & Skiff to McNary dive site.*1 per each task order
0016AGMobilization and Demobilization of Modular Floats & Skiff to Lucky Peak dive site.*1 per each task order
0017Pilebuck Crew: includes 8-hour Pilebuck (4-man) crew to set up and assemble the floats and to place equipment onto floats.Per Day
0018Modular Floats 13’ x 30’ : includes floats to accommodate dive spread and skiff with outboardPer Day
0019Modular Floats 32’ x 30’ : includes floats to accommodate dive spread and recompression chamber and skiff with outboard.Per Day
0020Basic Dive Day (8 hrs): Using surface supplied air (SSA-NITROX/Mixed Gas), employing a six-person dive team comprised of (1) non-diving dive supervisor, (3) diver, (1) standby diver, (1) tender, . Include all associated dive equipment and tools, dual lock dive chamber, camera/monitoring with DVD recording capability.
0020AAStandard dive up to 50 feet deepPer Day
0020AB51 – 100 feet deepPer Foot
0020AC101 – 125 feet deepPer Foot
0020AD126 - 200 feet deepPer Foot
0021Basic Dive Day (8 hrs): Using surface supplied air (SSA-NITROX/Mixed Gas), employing a eight- person dive team comprised of (1) non-diving dive supervisor, (4) diver, (1) standby diver, (2) tender. Include all associated dive equipment and tools, dual lock dive chamber, camera/monitoring with DVD recording capability.
0021AAStandard dive up to 50 feet deepPer Day
0021AB51 – 100 feet deepPer Foot
0021AC101 – 125 feet deepPer Foot
0021AD126 - 200 feet deepPer Foot
0022Penetration Dives (dives into confined spaces) 26 feet and beyondPer Foot

Total Walla Walla District - 0 - 0 - 0 - 0 - 0

PRICE SCHEDULE FOR PORTLAND, OREGON
0025Basic Dive Day (8 hrs): Using surface supplied air (SSA), employing a 5 person dive team comprised of: (1) non-diving dive supervisor, (2) diver, (1) standby diver, (1) tender. Include all associated dive equipment and tools, dual lock dive chamber, camera/monitoring with DVD recording capability. (Standard length of individual dive shift per calendar day is (4) four hours, maximum of three four-hour dive shifts per 12-hour work day allowed.)
0025AAStandard dive up to 50 feet deepPer Day
0025AB51 – 100 feet deepPer Foot
0025AC101 – 150 feet deepPer Foot
0025AD151 - 200 feet deepPer Foot
0026Additional qualified diver, added to 5 person dive team for basic 8-hour work day.
0026AAStandard dive up to 50 feet deepPer Day
0026AB51 – 100 feet deepPer Foot
0026AC101 – 150 feet deepPer Foot
0026AD151 - 200 feet deepPer Foot
0027Mobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the dive site.
0027AAMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to the Bonniville dive site.*1 per each task order
0027ABMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to The Dalles dive site.*1 per each task order
0027ACMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to John Day dive site.*1 per each task order
0027ADMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Astoria OR, Columbia River dive site*1 per each task order
0027AEMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Jess Dam, Rogue River, dive site.*1 per each task order
0027AFMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to John Day dive site.*1 per each task order
0027AGMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Big Cliff Dam, Willamette River Basin, dive site.*1 per each task order
0027ACMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Cougar Dam, Willamette River Basin, dive site.*1 per each task order
0027AHMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Detroit Dam, Willamette River Basin, dive site.*1 per each task order
0027AIMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Dexter Dam, Willamette River Basin, dive site.*1 per each task order
0027AJMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Foster Dam, Willamette River Basin, dive site.*1 per each task order
0027AKMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Green Peter Dam, Willamette River Basin, dive site.*1 per each task order
0027ALMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Hills Creek Dam, Willamette River Basin, dive site.*1 per each task order
0027AMMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Cougar Dam, Willamette River Basin, dive site.*1 per each task order
0027ANMobilization and demobilization for equipment, divers, dive chamber, and other necessary equipment to Lookout Point Dam, Willamette River Basin, dive site.*1 per each task order
Note: Time required to do this does not constitute part of the dive day. All Portland District public access facilities including John Day, The Dalles, Bonneville, Willamette and Rogue River Projects as well as work sites, facilities and vessels under the direction of Channel and Harbors Branches.
0028Mobilization and demobilization of workboat (dive boat) to USACE Portland District public access facilities and work sites, facilities and vessels under the direction of Channel and Harbors Branches
0028AAMobilization and demobilization of workboat (dive boat) to USACE Portland District public access facilities and work sites, facilities and vessels under the direction of Channel and Harbors Branches Portland Oregon, Columbia River*1 per each task order
0028ABMobilization and demobilization of workboat (dive boat) to USACE Portland District Dam, Bonneville dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Dam, The Dales dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Dam, John Day dive site.*1 per each task order
0028ADMobilization and demobilization of workboat (dive boat) to USACE Portland District Astoria, OR Columbia River dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Jess Dam, Rogue River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Big Cliff Dam, Willamette River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Cougar Dam, Willamette River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Detroit Dam, Willamette River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Dexter Dam, Willamette River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Foster Dam, Willamette River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Green Peter Dam, Willamette River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Hills Creek Dam, Willamette River Basin, dive site.*1 per each task order
0028ACMobilization and demobilization of workboat (dive boat) to USACE Portland District Lookout Point Dam, Willamette River Basin, dive site.*1 per each task order
0029Dive Boat capable of accommodating dive crew, 2 Corps of Engineers personnel and all necessary equipment. Boat must have sufficient freeboard and horsepower to navigate the Columbia RiverPer Day
0030Welding supplies and consumablesPer Hour
0031Overtime pay rate-Dive supervisor.Per Hour
0032Overtime pay rate-DiverPer Hour
0033Overtime pay rate-TenderPer Hour
0034Overtime pay rate for standby diverPer Hour
0035Overtime pay rate for ROV Pilot/OperatorPer Hour
0036Overtime pay rate for PilebuckPer Hour
0037Remote Operated Vehicle Crew: includes ROV pilot and operator, 8 hours per day, truck, fuel and per diems.Per Day
0038Remote Operated Vehicle: includes ROV (Deep Ocean Engineering Phantom XTL or equal) with maximum 500’ umbilical, generator, monitor and recorder.Per Day
0039Additional Equipment Required based on an individual task order requirement: The Mark up percentage to be added%
0040Mobilization and Demobilization of Modular Floats & Skiff*Each
0040AAMobilization and demobilization to USACE Portland District public access facilities and work sites, facilities and vessels under the direction of Channel and Harbors Branches Portland Oregon, Columbia River*1 per each task order
0040ABMobilization and demobilization of Modular Floats and Skiff to USACE Portland District Dam, Bonneville dive site.*1 per each task order
0040ACMobilization and demobilization of Modular Floats and Skiff to USACE Portland District Dam, John Day dive site.*1 per each task order
0040ADMobilization and demobilization of Modular Floats and Skiff to USACE Portland District Dam, The Dales dive site.*1 per each task order
0040AEMobilization and demobilization of Modular Floats and Skiff to USACE Portland District Columbia River, Astoria, OR*1 per each task order
0040AFMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Jess Dam, Rogue River Basin*1 per each task order
0040AGMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Big Cliff Dam, Willamette River Basin*1 per each task order
0040AHMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Cougar Dam, Willamette River Basin*1 per each task order
0040AIMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Detriot Dam, Willamette River Basin*1 per each task order
0040AJMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Dexter Dam, Willamette River Basin*1 per each task order
0040AKMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Foster Dam, Willamette River Basin*1 per each task order
0040ALMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Green Peter Dam, Willamette River Basin*1 per each task order
0040AMMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Hills Creek Dam, Willamette River Basin*1 per each task order
0040ANMobilization and demobilization of Modular Floats and Skiff to USACE Portland District, Lookout Point Dam, Willamette River Basin*1 per each task order
0041Pilebuck Crew: includes 8-hour Pilebuck (4-man) crew to set up and assemble the floats and to place equipment onto floats.Per Day
0042Modular Floats 13’ x 30’ : includes floats to accommodate dive spread and skiff with outboardPer Day
0043Modular Floats 32’ x 30’ : includes floats to accommodate dive spread and recompression chamber and skiff with outboard.Per Day
0045Basic Dive Day (8 hrs): Using surface supplied air (SSA-NITROX/Mixed Gas), employing a six-person dive team comprised of (1) non-diving dive supervisor, (3) diver, (1) standby diver, (1) tender. Include all associated dive equipment and tools, dual lock dive chamber, camera/monitoring with DVD recording capability.
0045AAStandard dive up to 50 feet deepPer Day
0045AB51 – 100 feet deepPer Foot
0045AC101 – 125 feet deepPer Foot
0044AD126 - 200 feet deepPer Foot
0045Basic Dive Day (8 hrs): Using surface supplied air (SSA-NITROX/Mixed Gas), employing a 8 person dive team comprised of (1) non-diving dive supervisor, (4) diver, (1) standby diver, (2) tender. Include all associated dive equipment and tools, dual lock dive chamber, camera/monitoring with DVD recording capability.
0045AAStandard dive up to 50 feet deepPer Day
0045AB51 – 100 feet deepPer Foot
0045AC101 – 125 feet deepPer Foot
0045AD126 - 200 feet deepPer Foot
0046Penetration Dives (dives into confined spaces) 26 feet and beyondPer Foot
Total Unit Portland District- 0- 0- 0- 0- 0
Total /Year- 0- 0- 0- 0- 0
*Each task order will have only one mob/demobilization charge whether it runs one or several days.
As prescribed at FAR 31.205-46, travel costs incurred for travel in the Continental United States, Alaska, Hawaii, The Commonwealth of Puerto Rico, and territories and possessions of the United States, shall not exceed on a daily basis the maximum per diem rates in effect at the time of travel as set forth in the Joint Travel Regulations, Volume 2, DoD Civilian Personnel, Appendix A, prescribed by the Department of Defense. Lodging and per diem apply to jobs that run more than one day. Each task order will allow for these costs based on number of days over the first day and be part of the task order pricing proposal.
Air Travel (Economy/Coach)Joint Travel Regulation
https://www.gsa.gov/travel/plan-book/transportation-airfare-rates-pov-rates-etc
Auto MileageJoint Travel Regulation
https://www.gsa.gov/travel/plan-book/transportation-airfare-rates-pov-rates-etc
Per DiemJoint Travel Regulation
https://www.gsa.gov/travel/plan-book/per-diem-rates
Regulations applied to this IDIQ are subject to change.

https://www.gsa.gov/travel/plan-book/transportation-airfare-rates-pov-rates-etchttps://www.gsa.gov/travel/plan-book/transportation-airfare-rates-pov-rates-etchttps://www.gsa.gov/travel/plan-book/per-diem-rates Sheet2

File details come from the government source that posted it. Updated .