This federal solicitation seeks maintenance dredging services at the Naval Submarine Base Kings Bay in Camden County, Georgia. The work includes dredging areas to required depths between 44 to 47 feet under a base bid with options for additional dredging, weir riser boards, and expanded basin dredging. The total estimated value is between $10 million to $25 million, and the performance period is 400 calendar days. Bids are due by December 29, 2020 under NAICS code 237990 and a $30 million small business size standard. This is a total small business set-aside held by the Army Corps of Engineers Jacksonville District.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EP21B0003
Jacksonville District
Naval Submarine Base Kings Bay Maintenance Dredging 44, 45, and 47-Foot Project
Camden County, Georgia
Construction Solicitation and Specifications Volume 1 of 2
24 NOVEMBER 2020
Naval Submarine Base Kings Bay, Maintenance Dredging 1 44, 45, and 47-Foot Project, Camden County, Georgia
DESIGN AUTHENTICATION
This project was designed by the Jacksonville District, U.S. Army Corps of Engineers. The initials or signatures and registration designations of individuals appear on these project documents within the scope of their employment as required by ER 1110-1-8152.
WILLIAM L. REILLY, P.E.
CHIEF, WATERWAYS SECTION
DESIGN BRANCH, ENGINEERING DIVISION
DENNIS J. ZEVENEY, P.E.
CHIEF, GEOSYSTEMS BRANCH
ENGINEERING DIVISION
DAVID DUDLEY, P.E.
CHIEF, DESIGN BRANCH
ENGINEERING DIVISION
LAUREEN A. BOROCHANER, P.E.
CHIEF, ENGINEERING DIVISION
REILLY.WILLIAM.L
UKE.1527897994
Digitally signed by
REILLY.WILLIAM.LUKE.152789799
Date: 2020.10.06 14:52:00 -04'00'
ZEVENEY.DENNIS.J.1
249349085
Digitally signed by
ZEVENEY.DENNIS.J.1249349085
Date: 2020.10.07 07:12:52 -04'00'
DUDLEY.DAVID.F.
1399388569
Digitally signed by
DUDLEY.DAVID.F.1399388569
Date: 2020.10.07 09:10:55 -04'00'
WIGNER.WILLIAM.
KEITH.1230084617
Digitally signed by
WIGNER.WILLIAM.KEITH.1230084
Date: 2020.11.05 15:40:02 -05'00'
NAVAL SUBMARINE BASE KINGS BAY, MAINTENANCE DREDGING 44, 45, AND 47-FOOT PROJECT, CAMDEN COUNTY, GEORGIA
DESCRIPTION OF WORK: REFER TO SECTION 01 11 00 FOR COMPLETE PROJECT DESCRIPTION
DRAWINGS: SEE DFARS CLAUSE 252.236-7001, SECTION 00700.
MAGNITUDE OF CONSTRUCTION IS BETWEEN $10,000,000 and $25,000,0000.
THIS SOLICITATION IS RESTRICTED AND SET-ASIDE FOR TOTAL SMALL BUSINESS. THE NAICS CODE FOR THIS PROJECT IS 237990
AND THE SMALL BUSINES SIZE STANDARD IS $30.0 MILLION.
IN ACCORDANCE WITH (IAW) FAR CLAUSE 52.236-27, AN ORGANIZED SITE VIST HAS BEEN SCHEDULED. SEE FAR 52.236-27, ALT I IN
SECTION 00100 FOR DETAILS.
YOU MUST BE REGISTERED IN THE SYSTEM FOR AWARD MANAGEMENT (SAM) TO RECEIVE AN AWARD FROM THIS SOLICITATION.
THE SAM WEBSITE IS LOACTED AT www.sam.gov.
**SEE BLOCK 11 - SEE SECTION 00700, FAR CLAUSE 52.211-10 FOR PERIOD OF PERFORMANCE.
**SEE ELECTRONIC BIDS IN SECTION 00800
BID OPENING WILL BE HELD VIRTUALLY VIA WEBEX. UTILIZE THE LINK AND CALL-IN INFORMATION PROVIDED BELOW:
https://usace1.webex.com/meet/tedra.n.thompson Audio Teleconference: 844-800-2712 Access Code: 199 262 9798
X
ANELIS I NAZARIO CASTILLO 904-232-3285
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
24-Nov-2020
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______60 calendar days and complete it w ithin ________400 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________**SECTION 0700
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time 29 December 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP
PAGE OF PAGES
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912EP21B0003 1 OF 204
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
NAVAL SUBMARINE BASE KINGS BAY, MAINTENANCE DREDGING
44, 45, AND 47-FOOT PROJECT, CAMDEN COUNTY, GEORGIA
LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
BASE
0001 MOBILIZATION AND DEMOBILIZATION JOB $_______________
0002 EXCAVATION, UNCLASSIFIED;
STATION 43+300 TO STATION 48+175
AND UPPER TURNING BASIN
(ESTIMATED QUANTITY - SEE NOTE 2) 300,000 CUBIC YARD $___________ $_______________
0003 EXCAVATION, UNCLASSIFIED;
STATION 39+141 TO STATION 43+300
AND EXPLOSIVE HANDLING BASIN
(ESTIMATED QUANTITY - SEE NOTE 2) 600,000 CUBIC YARD $___________ $_______________
0004 EXCAVATION, UNCLASSIFIED;
STATION 31+800 TO STATION 39+141 AND
MAGNETIC SILENCING FACILITY (MSF) NORTH
(ESTIMATED QUANTITY - SEE NOTE 2) 230,000 CUBIC YARD $___________ $_______________
0005 EXCAVATION, UNCLASSIFIED; SITE SIX NORTH
STATION 36+850 TO STATION 38+800
(ESTIMATED QUANTITY - SEE NOTE 2) 90,000 CUBIC YARD $___________ $_______________
0006 EXCAVATION, UNCLASSIFIED; SITE SIX SOUTH
AND ARDM YOKE;
STATION 34+233.1 TO STATION 36+548;
(ESTIMATED QUANTITY - SEE NOTE 2) 40,000 CUBIC YARD $___________ $_______________
0007 EXCAVATION, UNCLASSIFIED;
EXPLOSIVE HANDLING WHARVES (EHW)
STATION 41+420 TO STATION 43+320
(ESTIMATED QUANTITY - SEE NOTE 2) 25,000 CUBIC YARD $___________ $_______________
0008 EXCAVATION, UNCLASSIFIED;
REFIT WHARVES
STATION 45+850.4 TO STATION 48+175
(ESTIMATED QUANTITY - SEE NOTE 2) 15,000 CUBIC YARD $___________ $_______________
0009 EXCAVATION, UNCLASSIFIED;
DRY DOCK CAISSON GATE SILL AND
DRY DOCK CAISSON GATE MOORING FACILITY JOB $___________ $_______________
0010 STANDBY TIME (SEE NOTE 4)
(ESTIMATED QUANTITY) 120 HOUR $___________ $_______________
0011 BIRD MONITORING (SEE NOTE 6) JOB $_______________
0012 PARTNERING REGROUP 1 EACH $___________ $_______________
TOTAL BASE (LINE ITEMS 0001 THROUGH 0012) $_______________
OPTION A
0013 FIELD-CUT WEIR RISER BOARDS
(ESTIMATED QUANTITY) 200 EACH $___________ $_______________
TOTAL OPTION A (LINE ITEM 0013) $_______________
TOTAL BASE PLUS OPTION A (LINE ITEMS 0001 THROUGH 0013) $_______________
W912EP21B0003 00010A-1
NAVAL SUBMARINE BASE KINGS BAY, MAINTENANCE DREDGING
44, 45, AND 47-FOOT PROJECT, CAMDEN COUNTY, GEORGIA
LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
OPTION B
SECONDARY MAINTENANCE DREDGING
0014 MOBILIZATION AND DEMOBILIZATION JOB $_______________
0015 EXCAVATION, UNCLASSIFIED;
SITE SIX SOUTH AND ARDM YOKE
(ESTIMATED QUANTITY - SEE NOTE 2) 25,000 CUBIC YARD $___________ $_______________
0016 EXCAVATION, UNCLASSIFIED;
EXPLOSIVE HANDLING WHARVES (EHW)
(ESTIMATED QUANTITY - SEE NOTE 2) 35,000 CUBIC YARD $___________ $_______________
0017 EXCAVATION, UNCLASSIFIED;
REFIT WHARVES
(ESTIMATED QUANTITY - SEE NOTE 2) 20,000 CUBIC YARD $___________ $_______________
0018 EXCAVATION, UNCLASSIFIED;
DRY DOCK CAISSON GATE SILL AND
DRY DOCK CAISSON GATE MOORING FACILITY JOB $___________ $_______________
0019 EXCAVATION, UNCLASSIFIED; SITE SIX NORTH
STATION 36+850 TO STATION 38+800
(ESTIMATED QUANTITY - SEE NOTE 2) 35,000 CUBIC YARD $___________ $_______________
0020 BIRD MONITORING (SEE NOTE 6) JOB $_______________
0021 STANDBY TIME (SEE NOTE 4) 24 HOUR $___________ $_______________
TOTAL OPTION B (LINE ITEMS 0014 THROUGH 0021) $_______________
TOTAL BASE PLUS OPTIONS A AND B (LINE ITEMS 0001 THROUGH 0021) $_______________
OPTION C
SITE SIX NORTH EXPANDED BASIN
0022 EXCAVATION, UNCLASSIFIED
SITE SIX NORTH EXPANDED BASIN
(ESTIMATED QUANTITY - SEE NOTE 2) 415,000 CUBIC YARD $___________ $_______________
0023 BIRD MONITORING (SEE NOTE 6) JOB $_______________
TOTAL OPTION C (LINE ITEMS 0022 AND 0023) $_______________
TOTAL BID (LINE ITEMS 0001 THROUGH 0023) $_______________
W912EP21B0003 00010A-2
NAVAL SUBMARINE BASE KINGS BAY, MAINTENANCE DREDGING
44, 45, AND 47-FOOT PROJECT, CAMDEN COUNTY, GEORGIA
NOTES: (1) OFFEROR MUST PRICE ALL LINE ITEMS.
(2) QUANTITY INCLUDES REQUIRED DEPTH, ALLOWABLE OVERDEPTH AND SHOALING ESTIMATED TO OCCUR
BETWEEN DATES OF SURVEYS SHOWN ON DRAWINGS AND ACTUAL DREDGING.
(3) THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE OPTIONAL ITEMS IN ACCORDANCE WITH FAR CLAUSES 52.211-10 AND 52.217-7 (SECTION 00700). THE CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER, IN WRITING, A MINIMUM OF 7 DAYS PRIOR TO THE ANTICIPATED DATE OF THE DEMOBILIZATION OF A DREDGE PLANT.
(4) STANDBY TIME IS DEFINED AS WHEN THE DREDGE PLANT IS NOT IN OPERATION AT THE DIRECTION OF THE CONTRACTING OFFICER. STANDBY TIME SHALL BE UTILIZED ONLY DUE TO ENDANGERED SPECIES CONCERNS, DIFFERING SITE CONDITIONS, SECURITY OPERATIONS OR OTHER CONDITIONS AS DETERMINED BY THE CONTRACTING OFFICER. REQUIREMENTS FOR WORK STOPPAGES, DELAYS, OR OTHER IMPACTS ASSOCIATED WITH COMPLIANCE WITH SECTION 01 57 20 ENVIRONMENTAL PROTECTION ARE NOT PAID FOR UNDER THIS LINE ITEM. STANDBY TIME IS NOT AFFORDED FOR DELAYS CAUSED BY ADVERSE WEATHER CONDITIONS. PAYMENT WILL ONLY BE MADE FOR ACTUAL STANDBY TIME REQUIRED BY THE CONTRACTING OFFICER. SEE SECTION 01 22 00 MEASUREMENT AND PAYMENT. STANDBY TIME IN THE BASE IS AN
ESTIMATED QUANTITY. STANDBY TIME IN OPTION B IS NOT AN ESTIMATED QUANTITY.
(5) FOR THE SECURITY REQUIREMENTS, SEE PARAGRAPH "NAVAL SUBMARINE BASE KINGS BAY STATION ACCESS/
REGULATIONS" AND APPENDICES OF SECTION 01 11 00 SUMMARY OF WORK.
(6) PAYMENT WILL BE MADE FOR BIRD MONITORING IN ACCORDANCE WITH SECTION 01 57 20.
(7) FOR BIDDING PURPOSES, PROSPECTIVE BIDDERS SHOULD ASSUME A FULL MOBILIZATION AND DEMOBILIZATION.
UNDER THE BASE AND OPTION B.
W912EP21B0003 00010A-3
SECTION 00010A, Attachment A
INSTRUCTIONS FOR TECHNICAL INQUIRIES AND QUESTIONS
Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) December 18, 2020, Close of Business. To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.
All timely questions and approved answers will be made available through ProjNet.
The Solicitation Number is: W912EP21B0003
The Bidder Inquiry Key is: VIP5H9-7FKE34
Specific Instructions for ProjNet Bid Inquiry Access from ProjNet home page:
1. Identify the Agency. This should be marked as USACE.
2. Email. Enter the email address you would like to use for communication.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
5. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret
Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
6. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access from ProjNet home page:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. Identify the Agency. This should be marked as USACE.
3. Email. Enter the email address you used to register previously in ProjNet.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
6. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
W912EP21B0003 00100-i
Section 00100 - INSTRUCTIONS TO OFFERORS/EVALUATION FACTORS FOR AWARD
52.204-7 System for Award Management OCT 2018 52.211-2 Availability of Specifications, Standards, and Data Item
Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST)
APR 2014
52.214-3 Amendments to Invitations for Bids DEC 2016 52.214-4 False Statements in Bids APR 1984 52.214-5 Submission of Bids DEC 2016 52.214-6 Explanation to Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-34 Submission of Offers in The English Language APR 1991 52.214-35 Submission of Offers in U.S. Currency APR 1991 52.216-1 Type of Contract APR 1984 52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work
MAY 2014
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction
FEB 1999
52.222-38 Compliance with Veterans' Employment Reporting Requirements
FEB 2016
52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements
MAY 2014
52.225-23 Required Use of American Iron, Steel, and Manufactured Goods--Buy American Statute--Construction Materials Under Trade Agreements
OCT 2019
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
JUN 2020
52.233-2 Service of Protest SEP 2006 52.236-27 (Alt I) Site Visit (Construction) (Alternate I) FEB 1995 52.252-5 Authorized Deviations in Provisions APR 1984 252.204-7008 Compliance with Safeguarding Covered Defense Information
Controls
OCT 2016
252.225-7031 Secondary Arab Boycott of Israel JUN 2005
W912EP21B0003 00100-1
Section 00100 - INSTRUCTIONS TO OFFERORS/EVALUATION FACTORS FOR AWARD
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
(a) Definitions. As used in this provision--
Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.
Registered in the System for Award Management (SAM) means that--
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14) into SAM;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in SAM;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record ``Active''.
Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ``Unique Entity Identifier'' followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in SAM.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company physical street address, city, state, and Zip Code.
(4) Company mailing address, city, state and Zip Code (if separate from physical).
(5) Company telephone number.
(6) Date the company was started.
W912EP21B0003 00100-2
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company headquarters name and address (reporting relationship within your entity).
(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://www.sam.gov for information on registration.
(End of Clause)
52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM DESCRIPTIONS
LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION INFORMATION SYSTEM
(ASSIST) (APR 2014)
(a) Most unclassified Defense specifications and standards may be downloaded from the following ASSIST websites:
(1) ASSIST (https://assist.dla.mil/online/start/);
(2) Quick Search (http://quicksearch.dla.mil/);
(3) ASSISTdocs.com (http://assistdocs.com).
(b) Documents not available from ASSIST may be ordered from the Department of Defense Single Stock Point (DoDSSP) by--
(1) Using the ASSIST Shopping Wizard (https://assist.dla.mil/wizard/index.cfm);
(2) Phoning the DoDSSP Customer Service Desk (215) 697-2179, Mon-Fri, 0730 to 1600 EST; or
(3) Ordering from DoDSSP, Building 4, Section D, 700 Robbins Avenue, Philadelphia, PA 19111-5094, Telephone
(215) 697-2667/2179, Facsimile (215) 697-1462.
(End of Clause)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
W912EP21B0003 00100-3
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
(End of Clause)
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
(End of Clause)
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
(End of Clause)
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
(End of Clause)
W912EP21B0003 00100-4
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
(End of Clause)
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
W912EP21B0003 00100-5
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
(End of Clause)
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
(End of Clause)
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
Offers submitted in response to this solicitation shall be in the English language. Offers received in other than English shall be rejected.
(End of Clause)
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)
Offers submitted in response to this solicitation shall be in terms of U.S. dollars. Offers received in other than U.S.
dollars shall be rejected.
(End of Clause)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.
W912EP21B0003 00100-6
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Clause)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
Camden County 22.2% 6.9 %
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
W912EP21B0003 00100-7
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Camden County, Georgia.
(End of Clause)
52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS (FEB 2016)
By submission of its offer, the offeror represents that, if it is subject to the reporting requirements of 38 U.S.C.
4212(d) (i.e., if it has any contract containing Federal Acquisition Regulation clause 52.222-37, Employment Reports on Veterans), it has filed the most recent VETS-4212 Report required by that clause.
(End of Clause)
52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER
TRADE AGREEMENTS (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “designated country construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American -- Construction Materials Under Trade Agreements” (Federal Acquisition Regulation (FAR) clause 52.225-11).
(b) Requests for determination of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of FAR clause 52.225-11 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction materials, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(4)(i) of FAR clause 52.225-11.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
W912EP21B0003 00100-8
(d) Alternate offers. (1) When an offer includes foreign construction material, other than designated country construction material, that is not listed by the Government in this solicitation in paragraph (b)(3) of FAR clause 52.225-11, the offeror also may submit an alternate offer based on use of equivalent domestic or designated country construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of FAR clause 52.225-11 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of FAR clause 52.225-11 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic or designated country construction material, and the offeror shall be required to furnish such domestic or designated country construction material. An offer based on use of the foreign construction material for which an exception was requested-- (i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Clause)
52.225-23 REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS—BUY
AMERICAN STATUTE—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2019)
(a) Definitions. As used in this clause—
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
W912EP21B0003 00100-9
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St.
Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
Designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means the following:
(1) An unmanufactured construction material mined or produced in the United States. (The Buy American statute applies.)
(2) A manufactured construction material that is manufactured in the United States and, if the construction material consists wholly or predominantly of iron or steel, the iron or steel was produced in the United States. (Section 1605 of the Recovery Act applies.)
Foreign construction material means a construction material other than a domestic construction material.
Free trade agreement (FTA) country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of an FTA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in an FTA country into a new and different construction material distinct from the materials from which it was transformed.
Least developed country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
Manufactured construction material means any construction material that is not unmanufactured construction material.
Nondesignated country means a country other than the United States or a designated country.
Recovery Act designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement country (FTA)(Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore); or
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, W912EP21B0003 00100-10
Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia).
Recovery Act designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, or a least developed country construction material.
Steel means an alloy that includes at least 50 percent iron, between .02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
Unmanufactured construction material means raw material brought to the construction site for incorporation into the building or work that has not been—
(1) Processed into a specific form and shape; or
(2) Combined with other raw material to create a material that has different properties than the properties of the individual raw materials.
WTO GPA country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) The restrictions of section 1605 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-
5) (Recovery Act) do not apply to Recovery Act designated country manufactured construction material. The restrictions of the Buy American statute do not apply to designated country unmanufactured construction material. Consistent with U.S. obligations under international agreements, this clause implements—
(i) Section 1605 of the Recovery Act by requiring, unless an exception applies, that all manufactured construction material in the project is manufactured in the United States and, if the construction material consists wholly or predominantly of iron or steel, the iron or steel was produced in the United States (produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, except metallurgical processes involving refinement of steel additives); and
(ii) The Buy American statute by providing a preference for unmanufactured construction material mined or produced in the United States over unmanufactured construction material mined or produced in a nondesignated country.
(2) The Contractor shall use only domestic construction material, Recovery Act designated country manufactured construction material, or designated country unmanufactured construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to the construction materials or components listed by the Government as follows:
[Contracting Officer to list applicable excepted materials or indicate ``none''.]
(4) The Contracting Officer may add other construction material to the list in paragraph (b)(3) of this clause if the Government determines that—
W912EP21B0003 00100-11
(i) The cost of domestic construction material would be unreasonable;
(A) The cost of domestic manufactured construction material is unreasonable when the cumulative cost of such material, when compared to the cost of comparable foreign manufactured construction material, other than Recovery Act designated country construction material, will increase the overall cost of the contract by more than 25 percent;
(B) The cost of domestic unmanufactured construction material is unreasonable when the cost of such material exceeds the cost of comparable foreign unmanufactured construction material, other than designated country construction material, by more than 6 percent;
(ii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality; or
(iii) The application of the restriction of section 1605 of the Recovery Act to a particular manufactured construction material would be inconsistent with the public interest or the application of the Buy American statute to a particular unmanufactured construction material would be impracticable or inconsistent with the public interest.
(c) Request for determination of inapplicability of section 1605 of the Recovery Act or the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Cost;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(4) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed cost comparison table in the format in paragraph (d) of this clause.
(iii) The cost of construction material shall include all delivery costs to the construction site and any applicable duty.
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to section 1605 of the Recovery Act or the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable cost of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(4)(i) of this clause.
W912EP21B0003 00100-12
(3) Unless the Government determines that an exception to section 1605 of the Recovery Act or the Buy American statute applies, use of foreign construction material other than manufactured construction material from a Recovery Act designated country or unmanufactured construction material from a designated country is noncompliant with the applicable statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign (Nondesignated Country) and Domestic Construction Materials Cost Comparison
Construction Material Unit of Quantity Cost (Dollars)* Description Measure
Item 1:
Foreign construction material _______ _______ _______ Domestic construction material_______ _______ _______
Item 2:
Foreign construction material _______ _______ _______ Domestic construction material_______ _______ _______ (List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.)
(Include other applicable supporting information.)
[* Include all delivery costs to the construction site.]
(End of Clause)
52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN CERTAIN ACTIVITIES OR
TRANSACTIONS RELATING TO IRAN--REPRESENTATION AND CERTIFICATIONS. (JUN 2020)