B.08 Att 9 Price and Payment Procedures.docx

DOCX document 33 KB Posted

Attached to
SOLICITATION AMENDMENT ANNOUNCEMENT W912GB25R0034_Jarva-Jaani School Renovation, Estonia
Solicitation number
W912GB25R0034
Issued by

About this file

This is a Price and Payment Procedures document that outlines the payment structure for a school renovation project in Jarva-Jaani, Estonia. The document breaks down payments into three base items and two option items. Base items include: (1) Reconfiguring floor plan with demolition and creation of new spaces in the basement, (2) Electrical room upgrades including new main electrical equipment and feeder breakers, and (3) Life and safety upgrades comprising new exterior exit stairs, fire doors, and light wells. Optional items include replacing combustible ceilings with LED lighting (Option 1) and updating the heat transfer station (Option 2).

The payment terms specify that all work not specifically associated with base or option items must be included in Base Item 0001. Each item will be paid as a lump sum job payment that includes all costs for labor, materials, equipment, quality control, environmental protection, and safety requirements. The Government reserves the right to award any option or combination of options in any order, and the exercise of any option does not commit them to award other options.

View the file

Other files

File Type Posted
B.08 W912GB25R00340002 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 SF30 W912GB25R00340002 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 W912GB25R00340001 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 SF30 W912GB25R00340001 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 Att 16 Site Visit Attendee Worksheet.xlsx XLSX spreadsheet
B.08 Att 10 Bank Letter of Assurance (BLA).docx DOCX document
B.08 Att 11 Bank Letter of Guarantee (BLG).docx DOCX document
B.08 Solicitation W912GB25R0034 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 Att 1 SOW_Location Map.pdf PDF
B.08 Att 3 SOW_Conceptual Basement Floor Plan.pdf PDF
B.08 Att 2a SOW_Existing Site Survey from 2019.pdf PDF
B.08 Att 14 Past Performance Questionnaire PPQ.docx DOCX document
B.08 Att 15 Price Schedule Jarva-Jaani.docx DOCX document
B.08 Att 4 SOW_Structural Calculations Guideline.pdf PDF
B.08 Att 12 Past Performance Information Sheet_Rev 13 Feb 2023.docx DOCX document
B.08 Att 5 SOW_Dedication Plaque.pdf PDF
B.08 Att 17 Commitment Letters.docx DOCX document
B.08 Att 6 SOW_Scope For Independent Structural Proofing.pdf PDF
B.08 Att 7 Full Spec Binder Jaarvi_Janni School Reno.pdf PDF
B.08 Att 13 Past Performance Overview Sheet_Rev 19 Jan 2023.xlsx XLSX spreadsheet
B.08 Att 8 Period of Performance Clause Jarva-Jaani.docx DOCX document
B.08 Att 2b SOW_Conceptual Site Plan.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

05/24

PART 1 GENERAL

PAYMENT TYPES

The costs for performance of any work required by the contract which is not associated with a specific base or option item description shall be included in the first base item (Base Item 0001).

Single Job Payment Items

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the PRICE SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved.

The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

SCHEDULE OF ITEMS: BASE ITEMS

Base Item 0001: Reconfigure Floor Plan

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of reconfiguring portions of the school. This includes demolishing interior walls in the basement to create open space for the locker rooms, provide new rooms in the basement as shown in the floor plan, replace all room surfaces in the basement area, relocate heat transfer station and associated piping, and replacing windows in the basement as indicated in the SECTION 01 10 10 and shown on the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

Base Item 0002: Electrical Room upgrades

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of new main electrical equipment in the basement servicing the school, including feeder breakers and switches as indicated in the SECTION 01 10 10 and shown on the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

Base Item 0003: Life and Safety Upgrades

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of new exterior exit stairs on the southern side of the basement, fire doors, and deficiencies in basement locker/changing room areas, and providing new light wells and windows to the southern side of the base as indicated in the SECTION 01 10 10 and shown on the conceptual layout, with the exceptions of the bid options listed below. This work shall include all applicable demolition and removals work to support the work elements contained in this item.

SCHEDULE OF ITEMS: OPTION ITEMS

Awarding of Options

The Government reserves the right to award any option or combination of options in any order and the exercise of any option will not commit the Government to award any other option(s).

Option 1: Item 0004: Replace Combustible Ceilings

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of replacing existing combustible ceilings in classrooms, corridors and stairs and installing LED lighting as indicated in in Att7 – Existing Ceilings Overview and SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.

Option 2: Item 0005: Update Heat Transfer Station

Unit of Measure: Job.

Payment will be made for costs associated with the design and construction of replacing the existing heat transfer station as indicated in SECTION 01 10 10 and the conceptual layout, with the exceptions of the bid options listed below.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section - V7 Aug 2020 SECTION 01 22 00 Page 3