This is a past performance information sheet template (Attachment 12) that contractors must complete to document their relevant experience for the Purvciems EMS Garage Renovation project in Latvia. The form requires details about completed projects including completion date, final cost in EUR, project delivery method (Design-Build or Design-Bid-Build), scope/purpose, square footage of new construction versus renovation work, percentage of self-performed work, and whether the project was for US DoD.

The form must indicate whether the contractor served as Prime (performed at least 15% and managed all work), Subcontractor, Joint Venture partner, or Key Subcontractor. For anything other than Prime, additional explanation is required about the contractor's role and how their experience benefits this procurement. Key Subcontractors must provide a signed letter of commitment to perform work for the duration of the contract in order for the Offeror to claim their past performance.

View the file

Other files

File Type Posted
B.08 W912GB25R00340002 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 SF30 W912GB25R00340002 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 W912GB25R00340001 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 SF30 W912GB25R00340001 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 Att 16 Site Visit Attendee Worksheet.xlsx XLSX spreadsheet
B.08 Att 10 Bank Letter of Assurance (BLA).docx DOCX document
B.08 Att 11 Bank Letter of Guarantee (BLG).docx DOCX document
B.08 Solicitation W912GB25R0034 _ IEU-25-0023 Jarva-Jaani School Renovation.pdf PDF
B.08 Att 1 SOW_Location Map.pdf PDF
B.08 Att 3 SOW_Conceptual Basement Floor Plan.pdf PDF
B.08 Att 2a SOW_Existing Site Survey from 2019.pdf PDF
B.08 Att 14 Past Performance Questionnaire PPQ.docx DOCX document
B.08 Att 15 Price Schedule Jarva-Jaani.docx DOCX document
B.08 Att 4 SOW_Structural Calculations Guideline.pdf PDF
B.08 Att 5 SOW_Dedication Plaque.pdf PDF
B.08 Att 17 Commitment Letters.docx DOCX document
B.08 Att 6 SOW_Scope For Independent Structural Proofing.pdf PDF
B.08 Att 9 Price and Payment Procedures.docx DOCX document
B.08 Att 7 Full Spec Binder Jaarvi_Janni School Reno.pdf PDF
B.08 Att 13 Past Performance Overview Sheet_Rev 19 Jan 2023.xlsx XLSX spreadsheet
B.08 Att 8 Period of Performance Clause Jarva-Jaani.docx DOCX document
B.08 Att 2b SOW_Conceptual Site Plan.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 12 (amended 13 FEB2023) W912GB24R0046; IEU-24-0010 Purvciems EMS Garage Renovation, Latvia

CONTRACTOR PAST EXPERIENCE INFORMATION SHEET

PROJECT NO. IEU-25-0023 Järva-Jaani School Renovation, Estonia, Page 1

Project Name, Contract number, and Location:

Past Performance:

1. The day, month, and year work was completed: _______________

2. Is this project more than 75% complete? ____ Yes ____ No If “No” explain current percentage of completion, if yes and between 75-99% complete please explain how the percentage was calculated and what work remains.

3. The final cost of this project €_________________________

4. Do not provide a listing of existing or previous contracts, but rather provide detailed information of work for this project:

o Design- Build or Design-Bid-Build o Scope of the project, to include purpose/use of facility.

o Size of the project, differentiate square footage of new construction versus renovation if project includes both.

o Type and percentage of work that was self-performed.

o Whether the project involved new construction, renovation, or both. Clearly delineate square meters for construction and renovation.

o Whether the project was completed for the United States DoD.

(Continue typing if required to provide more information)

ATTACHMENT 2 – CONTRACTOR PAST EXPERIENCE INFORMATION SHEET

PROJECT NO. IEU-24-0010 Purvciems EMS Garage Renovation, Latvia Page 2

Offeror: A contractor and/or company submitting a proposal for this solicitation.

Prime Contractor: A contractor that performed at least 15% of the work, and managed all other work for the project.

Sub Contractor: A contractor that performed part of the project work, but did not manage the entire project.

Joint Venture: More than one contractor with a legal binding agreement to work together.

Key Subcontractor: A contractor that has signed a letter of commitment to perform work for the duration of the contract for the Offeror, and the Offeror may take credit for the Key Subcontractor’s past performance if it was meaningful to this procurement. Ensure you the letter of commitment is signed by both the Offeror and the Key Subcontractor.

5. Mark one of these selections:

Work was completed as the ____ Prime ____ Subcontractor ___ Joint Venture __ Key Subcontractor

a. No additional information is required for work performed as the Prime other than what is on Page 1 of this form.

b. If work was as a Joint Venture, explain the relationship of the company, which company performed the work, and how the work performed and the relationship provides an added benefit for experience.

c. If work was performed as a Key Subcontractor, explain how the work performed as a Key Subcontractor provides an added benefit for experience:

d. If work was as a Subcontractor, explain how the work performed as a Subcontractor is a benefit for experience such as, responsible for the work performed and managed the portion of work performed including submittals: