This is an Emergency Purchase Extension Approval form issued by the State of Illinois Chief Procurement Office for General Services, involving the Illinois Department of Transportation (IDOT) Business Services Division and vendor LCPTracker. The document approves an extension of emergency procurement for LCPTracker Payroll Solution software, which provides maintenance for prevailing wage laws and rates at state and federal levels. The original emergency contract (B-52275) ran from May 1, 2026 to July 29, 2026 for $77,822.10. The requested extension (B-54472) covers the period from October 30, 2026 to March 1, 2027 and is estimated at $106,000. This represents the second extension of the original emergency contract, following a previous extension (B-53289) from July 30, 2026 to October 29, 2026 for $79,474.54. The scope of work remains unchanged and focuses on maintaining the LCPTracker software to ensure compliance with prevailing wage requirements until a long-term Invitation for Bid (IFB) contract is executed.

The emergency extension was necessitated by delays in developing a long-term solicitation, combined with a failed initial bid (B-52823 received no bids) and ongoing protest issues with current solicitation B-53697, where the low bidding vendor has taken extension exceptions to terms and conditions. The competitive procurement process through IFB #27-494DOT-FINAD-B-53697 is currently under evaluation with a bid opening date of September 18, 2026. The justification for the extension centers on the critical nature of maintaining legal compliance with federal regulations including the Davis-Bacon Act, managing audit and dispute readiness through required three-year record retention, and performing over 70 automated validation checks on payroll submissions. The platform maintains FedRAMP Moderate and SOC security standards. No Business Enterprise Program (BEP) participation goal was established for this contract. The approval was signed by the Agency Procurement Officer on October 13, 2026, the Statewide Procurement Officer on October 15, 2026, and the Chief Procurement Officer on October 16, 2026.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EMERGENCY PURCHASE EXTENSION APPROVAL

State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v.26.1 Page 1 of 3

Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.

Zip: 92866State: CACity: OrangeAddress: 117 E. Chapman Ave.

Vendor: LCPTracker

Zip: 62764State: ILCity: SpringfieldAddress: 2300 South Dirksen Parkway

Requesting Agency: DOT - Transportation Division: Business Services

Extension Justification Original BidBuy Reference #: B- B-52275

Emergency Extension BidBuy Reference #: B- 54472

Amount of original contract: $ 77,822.1

Actual or Estimated: Estimated

Original Emergency Term Start Date:05/01/2026 Original Emergency Term End Date: 07/29/2026

Expected Extension Start Date: 10/30/2026 Expected Extension End Date: 03/01/2027

Amount of extension contract: $ 106,000 Actual or Estimated: Estimated

Is there BEP participation on this contract? If no, explain why

There is not an opportunity to establish a BEP goal at this time.

Has this emergency contract been extended before? Please detail in the space below:

BidBuy Reference # Amount Start Date End Date

B-53289 $79,474.54 Jul 30, 2026 Oct 29, 2026

$0.00

$0.00

1. Provide detail about the events that led the agency to conduct an emergency procurement:

The Agency entered into a Sole Source contract with LCPTracker that expired on 01/28/2026. Once the contract ended, the Agency completed a small purchase with emergency conditions until 04/30/2026. The initial development of a long-term solicitation took longer than expected, so the Agency had to declare an emergency while the solicitation was taking place. The first solicitation B-52823 had no bids. The current solicitation B-53697 is under protest and the low bidding vendor has taken extension exceptions to the terms and conditions.

2. What is the scope of work of the initial emergency contract? Please detail below:

Emergency Purchase Extension Approval v.26.1 Page 2 of 3

Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.

Zip: 92866State: CACity: OrangeAddress: 117 E. Chapman Ave.

Vendor: LCPTracker

Zip: 62764State: ILCity: SpringfieldAddress: 2300 South Dirksen Parkway

Requesting Agency: DOT - Transportation Division: Business Services

Maintain maintenance on the LCPTracker Payroll Solution software which provides maintenance for prevailing wage laws and rates at the State and Federal Level; until such time as the IFB contract has been executed.

3. Does this extension change the scope of work? Yes No If yes, please detail below:

Original BidBuy Reference #: B- B-52275

4. Provide justification for extending the original emergency contract:

LCPTracker needs to be maintained (and kept continuously updated) primarily to ensure strict legal compliance with prevailing wage laws such as the Davis-Bacon Act and to manage government contracts.

Legal Compliance: Federal, Sate, and local agencies are required to submit verified payroll records to ensure employees are paid correctly.

Audit and Dispute Readiness: Federal regulations (including the Davis-Bacon Act) mandate that employers and agencies retain all payroll documents for at least three years after project completion. Centralized maintenance protects businesses from sudden demands for historical records

Automated Error Checking: LCPTracker actively runs over 70 validation checks on submitted payrolls. Maintaining and inputing data properly prevents wage violations and identifies discrepancies before they result in financial penalties.

Data Security: The platform is continuously monitored and maintained to meet high-level government security standards, including FedRAMP Moderate and SOC requirements.

5. Does this emergency contract correct or eliminate the emergency condition?

Yes No Please detail:

The Agency has published an Invitation for Bid for a long-term software solution, and that IDOT is requesting an additional 120 day extension to complete the IFB procurement process.

6. Explain why the need cannot be met through a competitive procurement process.

The original contract was procured via the piggyback method of procurement from 2021 to 2024, before it was procured as a Sole Source from 2024 to 2025. Until the IFB is in place, the maintenance for the Agency’s payroll and prevailing software needs to remain in place

Emergency Purchase Extension Approval v.26.1 Page 3 of 3

Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.

Zip: 92866State: CACity: OrangeAddress: 117 E. Chapman Ave.

Vendor: LCPTracker

Zip: 62764State: ILCity: SpringfieldAddress: 2300 South Dirksen Parkway

Requesting Agency: DOT - Transportation Division: Business Services

7. Is a competitive procurement in process to replace this emergency contract?

Yes No Status: under evaluation

BidBuy Bid # 27-494DOT-FINAD-B-53697 has been published as an Invitation for Bid, with a Bid Opening Date of 09/18/2026. Currently the solicitation is under protest. Once a long -term contract is in place, the Agency will move to terminate the emergency contract.

8. What is the effect of a denial of this extension request?

The Agency will lose support of a vital part of its Payroll system, most particularly the prevailing wage component.

Original BidBuy Reference #: B- B-52275

Signatures below cannot be delegated.

APO Signature I am requesting an extension of the requested emergency contract. I believe all statements herein are true and correct to the best of my knowledge.

APO Signature: Date: Oct 13, 2026

SPO Signature

SPO Signature: Date: Oct 15, 2026

CPO Signature Based on my review, I approve the Agency to proceed in accordance with the emergency contract extension detailed in this document.

Based upon my review, I approve the Agency to proceed with the following changes:

CPO Signature: Date: Oct 16, 2026

Page of

Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.

State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v. 26.1

EMERGENCY PURCHASE EXTENSION APPROVAL

State of Illinois Chief Procurement Office for General Services Emergency Purchase Extension Approval v.26.1 Page of Section 20-30(a) of the Procurement Code provides that a contract for an emergency may be extended beyond 90 calendar days with the approval of the chief procurement officer (CPO). Prior to execution of the extension, the CPO shall receive this completed form justifying the extension. The duration of the extension shall be limited to the scope of the emergency.

Extension Justification Actual or Estimated:

Has this emergency contract been extended before? Please detail in the space below:

BidBuy Reference # Amount Start Date End Date

1. Provide detail about the events that led the agency to conduct an emergency procurement:

2. What is the scope of work of the initial emergency contract? Please detail below:

3. Does this extension change the scope of work?

If yes, please detail below:

4. Provide justification for extending the original emergency contract:

5. Does this emergency contract correct or eliminate the emergency condition?

Please detail:

6. Explain why the need cannot be met through a competitive procurement process.

7. Is a competitive procurement in process to replace this emergency contract?

8. What is the effect of a denial of this extension request?

Signatures below cannot be delegated.

APO Signature I am requesting an extension of the requested emergency contract. I believe all statements herein are true and correct to the best of my knowledge.

SPO Signature CPO Signature 11.0.0.20130303.1.892433.887364

DropDownList1: If no, explain why
DropDownList1: DOT - Transportation
DropDownList1: DOT - Transportation
DropDownList1: DOT - Transportation
CurrentPage:
PageCount:
VendorZip: 92866
VendorState: CA
VendorCity: Orange
VendorAddress: 117 E. Chapman Ave.
Vendor: LCPTracker
AgencyZip: 62764
AgencyState: IL
AgencyCity: Springfield
AgencyAddress: 2300 South Dirksen Parkway
AgencyDivision: Business Services
ReferenceNumber: B-52275
TextField15: 54472
AmountOfOriginal: 77822.10000000
ActualOrEstimated2: Estimated
Start: 05/01/2026
End: 07/29/2026
ExpectedExtensionStartDate: 10/30/2026
ExpectedExtensionEnd: 03/01/2027
AmtExtensionExpenditure: 106000.00000000
ActualOrEstimated3: Estimated
TextField5: There is not an opportunity to establish a BEP goal at this time.
TextField7: B-53289
NumericField4: 79474.54000000
DateField3: 2026-07-30
DateField4: 2026-10-29
TextField8:
NumericField2: 0
DateField5:
DateField6:
TextField9:
NumericField3: 0
DateField7:
DateField8:
TextField6: The Agency entered into a Sole Source contract with LCPTracker that expired on 01/28/2026. Once the contract ended, the Agency completed a small purchase with emergency conditions until 04/30/2026. The initial development of a long-term solicitation took longer than expected, so the Agency had to declare an emergency while the solicitation was taking place. The first solicitation B-52823 had no bids. The current solicitation B-53697 is under protest and the low bidding vendor has taken extension exceptions to the terms and conditions.
TextField13: Maintain maintenance on the LCPTracker Payroll Solution software which provides maintenance for prevailing wage laws and rates at the State and Federal Level; until such time as the IFB contract has been executed.
CheckBox7: 0
CheckBox8: 1
TextField1:
TextField2: LCPTracker needs to be maintained (and kept continuously updated) primarily to ensure strict legal compliance with prevailing wage laws such as the Davis-Bacon Act and to manage government contracts.

Legal Compliance: Federal, Sate, and local agencies are required to submit verified payroll records to ensure employees are paid correctly.

Audit and Dispute Readiness: Federal regulations (including the Davis-Bacon Act) mandate that employers and agencies retain all payroll documents for at least three years after project completion. Centralized maintenance protects businesses from sudden demands for historical records

Automated Error Checking: LCPTracker actively runs over 70 validation checks on submitted payrolls. Maintaining and inputing data properly prevents wage violations and identifies discrepancies before they result in financial penalties.

Data Security: The platform is continuously monitored and maintained to meet high-level government security standards, including FedRAMP Moderate and SOC requirements.

WhoAuthorizedWork:
CheckBox3: 0
CheckBox4: 1
TextField10: The Agency has published an Invitation for Bid for a long-term software solution, and that IDOT is requesting an additional 120 day extension to complete the IFB procurement process.
TextField12: The original contract was procured via the piggyback method of procurement from 2021 to 2024, before it was procured as a Sole Source from 2024 to 2025. Until the IFB is in place, the maintenance for the Agency’s payroll and prevailing software needs to remain in place
CheckBox6: 1
CheckBox5: 0
DropDownList2: under evaluation
TextField11: BidBuy Bid # 27-494DOT-FINAD-B-53697 has been published as an Invitation for Bid, with a Bid Opening Date of 09/18/2026. Currently the solicitation is under protest. Once a long -term contract is in place, the Agency will move to terminate the emergency contract.
TextField14: The Agency will lose support of a vital part of its Payroll system, most particularly the prevailing wage component.
TextField3: B-52275
AuthorizedSignature:
TitleField: 2026-10-13
SignatureField2:
DateField2: 2026-10-15
CheckBox1: 1
CheckBox2: 0
TextField4:
SignatureField1:
DateField1: 2026-10-16

File details come from the government source that posted it. Updated .