Project Manual for Haven House Roof Pitch, Water Diversion, & Infiltration Project

This is a comprehensive project manual prepared by SOLARC Architecture, Inc. for Clackamas County Housing & Community Development Division's Haven House renovation project located at 15170 SE River Road, Milwaukie, Oregon 97267. The project, identified as Project #22-035, involves replacement of roof wood framing to re-pitch the roof, replacement of rock retaining walls in the backyard, improvement of site stormwater drainage, and associated site work. The manual includes detailed specifications for rough carpentry with pressure-treated and graded lumber; roof and wall sheathing materials; shop-fabricated wood trusses with metal connector plates; exterior finish carpentry including trim and soffits; thermal insulation with glass-fiber and mineral-wool blankets; weather barriers and flexible flashing; asphalt shingle roofing with underlayment and metal flashing; fiber-cement siding; sheet metal flashing and trim for roof and wall penetrations; joint sealants; exterior painting; segmental retaining walls; and stormwater conveyance and subdrainage systems. Construction is to be performed by a single prime contractor under a fixed-price arrangement, with the contractor responsible for coordinating all work, maintaining a detailed construction schedule, managing submittals and requests for information, conducting quality control testing and inspections, and completing final closeout documentation including record drawings and warranties.

The manual establishes comprehensive administrative and procedural requirements governing contractor responsibilities for project management, scheduling, temporary facilities, quality assurance, safety, waste management, and final completion procedures. Contractors must submit a detailed construction schedule within 30 days of notice to proceed, including procurement activities, submittal review times, and startup and testing periods, with monthly updates reflecting actual progress. All submittals, including product data, shop drawings, samples, and certificates, require architect review and approval before installation, with initial review periods of 14 days and resubmittal reviews requiring an additional 14 days. The contractor shall engage qualified testing agencies to perform quality control services including field testing of materials, compaction verification for fill materials, inspection of segmental retaining wall installations, and pressure testing of drainage piping systems. Temporary facilities must include job site offices, heating and cooling equipment, sanitary facilities, adequate lighting, and fire protection systems compliant with NFPA 241. The contractor is responsible for final cleaning of all surfaces, removal of temporary facilities, correction of deficient work identified during substantial completion inspection, and submission of all closeout documentation including warranties, operation and maintenance manuals, and as-built drawings within seven days of requesting substantial completion inspection.

View the file

Other files

File Type Posted
119-23 Att E.pdf PDF
119-23 Att C Reference Check Form.pdf PDF
ITB for GPS Collars .pdf PDF
119-23 Att A Sample Contract.pdf PDF
119-23 Att F.pdf PDF
119-23 Att B.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLARC ARCHITECTURE, INC. TABLE OF CONTENTS

PROJECT #: 22-035

23 MAR 2023

CLACKAMAS COUNTY

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 1

TABLE OF CONTENTS

STAMP PAGE

DIVISION 01 GENERAL REQUIREMETNS

01 10 00 Summary 01 25 00 Substitution Procedures 01 31 00 Project Management & Coordination 01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 40 00 Quality Requirements 01 50 00 Temporary Facilities & Controls 01 60 00 Product Requirements 01 73 00 Execution 01 74 19 Construction Waste Management & Disposal 01 77 00 Close Out Procedures 01 78 39 Project Record Documents

DIVISION 02 EXISTING CONDITIONS

02 41 19 Selective Demolition

DIVISION 03 CONCRETE

NOT USED

DIVISION 04 MASONRY

NOT USED

DIVISION 05 METALS

NOT USED

DIVISION 06 WOOD, PLASTICS, & COMPOSITES

06 10 00 Rough Carpentry 06 16 00 Sheathing 06 17 53 Shop-Fabricated Wood Trusses 06 20 13 Exterior Finish Carpentry 06 64 00 Plastic Paneling

DIVISION 07 THERMAL & MOSITURE PROTECTION

07 21 00 Thermal Insulation 07 25 00 Weather Barrier 07 31 13 Asphalt Shingles 07 46 46 Fiber-Cement Siding 07 62 00 Sheet Metal Flashing & Trim 07 92 00 Joint Sealants

DIVISION 08 OPENINGS

NOT USED

SOLARC ARCHITECTURE, INC. TABLE OF CONTENTS

23 MAR 2023

CLACKAMAS COUNTY

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 2

DIVISION 09 FINISHES

09 91 13 Exterior Painting

DIVISION 10 SPECIALITIES

NOT USED

DIVISION 11 EQUIPMENT

NOT USED

DIVISION 12 FURNISHINGS

NOT USED

DIVISION 20 MECHANICAL PROVISIONS

NOT USED

DIVISION 22 PLUMBING

NOT USED

DIVISION 23 HEATING, VENTILATION, AND AIR CONDITIONING

NOT USED

DIVISION 26 ELECTRICAL

NOT USED

DIVISION 27 COMMUNICATIONS

NOT USED

DIVISION 28 ELECTRONIC SAFETY & SECURITY

NOT USED

DIVISION 31 EARTHWORK

NOT USED

DIVISION 32 EXTERIOR IMPROVEMENTS

32 32 23 Segmental Retaining Walls

DIVISION 33 UTILITIES

33 42 00 Stormwater Conveyance 33 46 00 Subdrainage

SOLARC ARCHITECTURE, INC. STAMP PAGE

23 MAR 2023

CLACKAMAS COUNTY

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 1

ARCHITECT MECHANICAL ENGINEER

Divisions: Divisions:

SOLARC Architecture Nate Carter

NOT APPLICABLE

CIVIL ENGINEER PLUMBING ENGINEER

Divisions: Divisions:

PACE Engineering Brian Lee

NOT APPLICABLE

STRUCTURAL ENGINEER ELECTRICAL ENGINEER

Divisions: Divisions:

NOT APPLICABLE NOT APPLICABLE

SOLARC ARCHITECTURE, INC. SECTION 01 10 00

PROJECT #: 22-035 SUMMARY

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 00 00 00 - 1

SECTION 01 10 00 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work under Owner's separate contracts.

5. Owner-furnished/Contractor-installed (OFCI) products.

6. Contractor's use of site and premises.

7. Coordination with occupants.

8. Work restrictions.

9. Specification and Drawing conventions.

B. Related Requirements:

1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.2 PROJECT INFORMATION

A. Project Identification: Haven House – Roof Pitch, Water Diversion, & Infiltration Project

1. Project Location: 15170 SE River Road, Milwaukie, Oregon 97267.

B. Owner: Clackamas County – Housing & Community Development Division

1. Owner's Representative: Steve Kelly; SteveKel@Clackamas.us; 971.284.9949

C. Architect: SOLARC Architecture, Inc.

1. Architect's Representative: Nate Carter; Nate@Solarc-A.com; 971.344.1919

D. Architect's Consultants: Architect has retained the following design professionals, who have prepared designated portions of the Contract Documents:

1. Civil Engineer: PACE Engineering

a. Civil Representative: Brian Lee; BrianL@PaceEngrs.com; 503.597.3222

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 00 00 00 - 2

1. Replacement of the roof wood framing to re-pitch the roof, replacement the rock retaining in the back yard, improvement site stormwater drainage, and other Work indicated in the Contract Documents.

B. Type of Contract:

1. Project will be constructed under a single prime contract.

1.4 CONTRACTOR'S USE OF SITE AND PREMISES

A. Unrestricted Use of Site: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.5 COORDINATION WITH OCCUPANTS

A. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1.6 WORK RESTRICTIONS

A. Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise indicated.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions. Email will constitute written permission for this requirement.

D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 00 00 00 - 3

1. Notify Owner not less than two days in advance of proposed disruptive operations.

2. Don’t produce Noise, Vibration, Duct, and Odors over allowable limits established by Clackamas County that will affect surrounding neighbors.

E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances within the existing site is not permitted.

F. Employee Identification: Provide identification of Contractor personnel working on Project site.

G. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Owner's representative.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.

3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.

4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 00 Contracting Requirements: General provisions of the Contract, including General and Supplementary Conditions, apply to all Sections of the Specifications.

C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 10 00

SOLARC ARCHITECTURE, INC. SECTION 01 50 00

PROJECT #: 22-035 SUBSTITUTION PROCEDURES

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 50 00 - 1

SECTION 01 25 00 - SUBSTITUTION PROCEDURES

1.1 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. Section 01 60 00 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.2 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required in order to meet other Project requirements but may offer advantage to Contractor or Owner.

1.3 ACTION SUBMITTALS

A. Substitution Requests: Submit digital copy of each request for consideration the Architect and Owner. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use form acceptable to Architect.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.

b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section.

Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 50 00 - 2

features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.

h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within 7 days of receipt of a request for substitution.

Architect will notify Contractor of acceptance or rejection of proposed substitution within 14 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 50 00 - 3

1.5 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

1.6 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 21 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within 30 days after commencement of the Work. Requests received after that time may be considered or rejected at discretion of Architect.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract Documents.

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 50 00 - 4

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 25 00

SOLARC ARCHITECTURE, INC. SECTION 01 31 00

PROJECT #: 22-035 PROJECT MANAGEMENT & COORDINATION

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 1

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Digital project management procedures.

5. Project meetings.

B. Related Requirements:

1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.2 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

1.3 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 2

B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

1.4 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

3. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

4. Review: Architect will review coordination drawings to confirm that, in general, the Work is being coordinated, but not for the details of the coordination, which are

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 3

Contractor's responsibility. If Architect determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, Architect will so inform Contractor, who shall make suitable modifications and resubmit.

1.5 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Owner name.

2. Owner's Project number.

3. Name of Architect.

4. Architect's Project number.

5. Date.

6. Name of Contractor.

7. RFI number, numbered sequentially.

8. RFI subject.

9. Specification Section number and title and related paragraphs, as appropriate.

10. Drawing number and detail references, as appropriate.

11. Field dimensions and conditions, as appropriate.

12. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

13. Contractor's signature.

14. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Architect.

D. Architect's Action: Architect will review each RFI, determine action required, and respond.

Allow 14 days for Architect's response for each RFI. RFIs received by Architect after 3:00 p.m.

will be considered as received the following working day.

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 4

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal.

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect and Owner in writing within 7 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly. Use of software log that is part of web-based Project management software is acceptable. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's response was received.

F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within 3 days if Contractor disagrees with response.

1.6 DIGITAL PROJECT MANAGEMENT PROCEDURES

A. Use of Architect's Digital Data Files: Digital data files of Architect's CAD drawings may be provided by Architect for Contractor's use during construction.

1. Digital data files may be used by Contractor in preparing coordination drawings, Shop Drawings, and Project record Drawings.

2. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 5

3. Digital Drawing Software Program: Contract Drawings are available in 2023 AutoCAD.

Earlier versions AutoCAD are available upon request but are limited to the 2000 version of AutoCAD or newer.

4. Contractor shall execute a data licensing agreement in the form of a Electric Drawing Release included in Project Manual, located immediately after this section.

a. Subcontractors, and other parties granted access by Contractor to Architect's digital data files shall execute a data licensing agreement for each request.

b. Access to Sub-Consultant digital data files may require an additional data licensing agreement.

5. The digital data files available are limited to those that are included in the Contract Drawing set.

B. PDF Document Preparation: Where PDFs are required to be submitted to Architect, prepare as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.

1.7 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than 14 days after execution of the Agreement.

1. Attendees: Authorized representatives of Owner, Property Tenant Representative, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference.

Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Responsibilities and personnel assignments.

b. Tentative construction schedule.

c. Critical work sequencing and long lead items.

d. Designation of key personnel and their duties.

e. Lines of communications.

f. Use of web-based Project software.

g. Procedures for processing field decisions and Change Orders.

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 6

h. Procedures for RFIs.

i. Procedures for testing and inspecting.

j. Procedures for processing Applications for Payment.

k. Distribution of the Contract Documents.

l. Submittal procedures.

m. Preparation of Record Documents.

n. Use of the premises and existing building.

o. Work restrictions.

p. Working hours.

q. Owner's occupancy requirements.

r. Responsibility for temporary facilities and controls.

s. Procedures for moisture and mold control.

t. Procedures for disruptions and shutdowns.

u. Construction waste management and recycling.

v. Parking availability.

w. Office, work, and storage areas.

x. Equipment deliveries and priorities.

y. First aid.

z. Security.

aa. Progress cleaning.

3. Minutes: Contractor is responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity when required by other sections and when required for coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect and Owner of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Possible conflicts.

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 7

i. Compatibility requirements.

j. Time schedules.

k. Weather limitations.

l. Manufacturer's written instructions.

m. Warranty requirements.

n. Compatibility of materials.

o. Acceptability of substrates.

p. Temporary facilities and controls.

q. Space and access limitations.

r. Regulations of authorities having jurisdiction.

s. Testing and inspecting requirements.

t. Installation procedures.

u. Coordination with other work.

v. Required performance results.

w. Protection of adjacent work.

x. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Conduct progress meetings at biweekly intervals.

1. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for the three weeks ahead of meeting date.

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 31 00 - 8

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site Security.

8) Site use.

9) Temporary facilities and controls.

10) Progress cleaning.

11) Quality and work standards.

12) Status of correction of deficient items.

13) Field observations.

14) Status of RFIs.

15) Status of Proposal Requests.

16) Pending changes.

17) Status of Change Orders.

18) Pending claims and disputes.

19) Documentation of information for payment requests.

3. Minutes: Contractor is responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 31 00

ELECTRONIC DRAWING RELEASE

ELECTRONIC DRAWING FILES TBAE STATEMENT, DISCLAIMER AND COPYRIGHT NOTICE

Copyright 2023 Solarc Architecture, Inc.

All Rights Reserved

STATEMENT:

This electronic drawing file is released under the authority of Architects name: Nathan Daniel Carter Registration number: 6463 Who maintains the original file. This electronic drawing file may be used as a background drawing. No person may make any modification to this electronic file without the Architect’s express written permission.

Project Name: Clackamas County: Haven House Roof Pitch, Water Diversion, and Infiltration Project Solarc Job Number: 22-035

DISCLAIMER:

This data is authorized “AS IS” without any warranty as to its performance, accuracy, freedom from error, or as to any results generated through its use, including without limitation, any implied warranties of merchantability or fitness for a particular purpose. You assume the entire risk as to the results and performance of this data.

COPYRIGHT NOTICE:

The designs represented by these drawings are copyrighted and are subject to copyright protection under 17 U.S.C.

$101, et seq., as amended. Unauthorized use of these drawings or the designs represented therein will subject the infringer to damages and/or judicial action as provided by federal law. The designs represented by these drawings may not be electronically, photographically, or otherwise copied without the written authorization of Solarc Architecture, Inc.

I have read and understand the above statement and agree per my signature below:

Name: __________________________________________

Date: __________________________________________

Reason for Request: _________________________________

SOLARC ARCHITECTURE, INC. SECTION 01 32 00

PROJECT #: 22-035 CONSTRUCTION PROGRESS DOCUMENTATION

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 32 00 - 1

SECTION 01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION

1.1 SUMMARY

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

2. Construction schedule updating reports.

3. Daily construction reports.

4. Site condition reports.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.

1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

D. Event: The starting or ending point of an activity.

E. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 32 00 - 2

1.3 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

1. PDF file.

2. Paper copies, of sufficient size to display entire period or schedule, as requested.

B. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.

C. Construction Schedule Updating Reports: Submit with Applications for Payment.

D. Daily Construction Reports: Submit at weekly intervals.

E. Site Condition Reports: Submit at time of discovery of differing conditions.

1.4 COORDINATION

A. Coordinate Contractor's Construction Schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from entities involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

1.5 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.

B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of final completion.

1. Contract completion date to not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

C. Activities: Treat each floor or separate area as a separate numbered activity for each main element of the Work. Comply with the following:

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Architect.

2. Procurement Activities: Include procurement process activities for the long lead items and major items, requiring a cycle of more than 30 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 32 00 - 3

3. Submittal Review Time: Include review and resubmittal times indicated in Section 01 33 00 "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with submittal schedule.

4. Startup and Testing Time: Include no fewer than 14 days for startup and testing.

5. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Architect's administrative procedures necessary for certification of Substantial Completion.

6. Punch List and Final Completion: Include not more than 14 days for completion of punch list items and final completion.

D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Phasing: Arrange list of activities on schedule by phase.

2. Owner-Furnished Products: Include a separate activity for each product. Include delivery date indicated in Section 01 10 00 "Summary." Delivery dates indicated stipulate the earliest possible delivery date.

3. Work Restrictions: Show the effect of the following items on the schedule:

a. Coordination with existing construction.

b. Uninterruptible services.

c. Use-of-premises restrictions.

d. Seasonal variations.

e. Environmental control.

E. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion.

F. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues:

1. Unresolved issues.

2. Unanswered Requests for Information.

3. Rejected or unreturned submittals.

4. Notations on returned submittals.

5. Pending modifications affecting the Work and the Contract Time.

G. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule two days before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 32 00 - 4

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate final completion percentage for each activity.

H. Distribution: Distribute copies of approved schedule to Architect, Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices.

2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

1.6 GANTT-CHART SCHEDULE REQUIREMENTS

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart-type, Contractor's Construction Schedule within 30 days of date established for the Notice of Award.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1.7 REPORTS

A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:

1. List of subcontractors at Project site.

2. Equipment at Project site.

3. Material deliveries.

4. High and low temperatures and general weather conditions, including presence of rain or snow.

5. Testing and inspection.

6. Accidents.

7. Meetings and significant decisions.

8. Stoppages, delays, shortages, and losses.

9. Meter readings and similar recordings.

10. Emergency procedures.

11. Orders and requests of authorities having jurisdiction.

12. Change Orders received and implemented.

13. Construction Change Directives received and implemented.

14. Services connected and disconnected.

15. Equipment or system tests and startups.

16. Partial completions and occupancies.

23 MAR 2023

ROOF PITCH, WATER DIVERSION, & INFILTRATION PROJECT 01 32 00 - 5

17. Substantial Completions authorized.

B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 32 00

SOLARC ARCHITECTURE, INC. SECTION 01 33 00

PROJECT #: 22-035 SUBMITTAL PROCEDURES

SUBMITTAL PROCEDURES 013300 - 1

SECTION 01 33 00 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

1.2 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Architect's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.3 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit, as an action submittal, a list of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Architect and additional time for handling and reviewing submittals required by those corrections.

1.4 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Architect.

4. Name of Contractor.

5. Names of subcontractor, manufacturer, and supplier.

6. Unique submittal number, including revision identifier. Include Specification Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.

7. Category and type of submittal.

8. Submittal purpose and description.

SUBMITTAL PROCEDURES 013300 - 2

9. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

10. Drawing number and detail references, as appropriate.

11. Indication of full or partial submittal.

12. Location(s) where product is to be installed, as appropriate.

13. Other necessary identification.

14. Remarks.

15. Signature of transmitter.

B. Options: Identify options requiring selection by Architect.

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations; include relevant additional information and revisions, other than those requested by Architect on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

D. Electronic Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

1.5 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package, and transmit to Architect by sending via email. Include PDF transmittal form. Include information in email subject line as requested by Architect.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.

Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

SUBMITTAL PROCEDURES 013300 - 3

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittal Review: Allow 14 days for review of each resubmittal.

D. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Architect's Submittal Review document.

1.6 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams that show factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.

5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B.…