This Request for Quotes (RFQ) is issued by the City of Palo Alto's Public Works Department for automatic fire extinguishing system inspection, testing, and repair services across 33 municipal facilities totaling approximately 1.3 million square feet. The scope of work includes quarterly inspections (June, September, December, and March), annual inspections (June and December), and five-year maintenance service tests and certifications for wet pipe fire sprinkler systems and fire standpipe systems in community centers, libraries, parking garages, fire stations, and other city buildings. All work must comply with NFPA 25 2025 Edition standards and California Code of Regulations Title 19. Deliverables include completed inspection forms submitted to the City within five days, documentation uploaded to The Compliance Engine system at contractor expense, and repair proposals for work exceeding $500 submitted within three days of inspection. The question submission deadline is March 13, 2026 at 1:00 p.m., with bids due electronically through the City's OpenGov portal by March 23, 2026 at 3:00 p.m. No pre-bid conference is scheduled. The contract term is three years, commencing June 1, 2026 and concluding May 30, 2029, with inspections beginning June 1, 2026.
Required qualifications include a valid California State Contractor's License (C-16 classification for fire protection) and current Department of Industrial Relations registration. Within ten business days of award notification, the selected contractor must furnish 100 percent Performance and Payment Surety Bonds. Contractors must comply with California prevailing wage requirements under Labor Code Sections 1720 et seq., maintain certified payroll records, and satisfy apprenticeship employment requirements. The contract includes a dedicated budget allotment for repairs, with 275 hours of straight-time labor budgeted annually for repair work. The estimated project value is approximately $500,000 across the three-year contract period, with bid security of at least 10 percent of the bid amount required. Award will be made to the lowest responsive and responsible bidder based on the combined total of base bid prices for years one, two, and three. Contractors must maintain comprehensive insurance throughout the contract term, including Workers' Compensation, General Liability ($1,000,000 per occurrence and aggregate), Automobile Liability ($1,000,000 per occurrence and aggregate), and Professional Liability ($1,000,000), with the City named as additional insured on applicable policies. Liquidated damages are assessed at $500 per day for unexcused delays. The City reserves the right to award multiple contracts and reject all bids at its discretion.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUBLIC WORKS DEPARTMENT
REQUEST FOR QUOTES (BID )# RFQ197145
AUTOMATIC FIRE EXTINGUISHING SYSTEM INSPECTION, TESTING, AND REPAIR
BID DUE DATE: Monday, March 23, 2026 BEFORE 3:00 pm
TABLE OF CONTENTS
Section 1 Request for Quotes Summary
Section 2 Instruction to Bidders
Section 3 Specifications/Scope of Work
Section 4 Bidder's Questionnaire
Attachments:
A - General_Services_Agreement
B - Insurance Requirements
C - Payment Bond
D - Performance Bond
E - Final Bidder Bid Pages FY 27 28 29
F - Fire_Sprinkler_Description_of_Systems_03-09-2026 (2)
G - Fire Sprinkler Systems Inspection Scope of Work updated
Request for Quotes (RFQ) #RFQ197145 2 Automatic Fire Extinguishing System Inspection, Testing, and Repair
Request for Quotes (RFQ) #RFQ197145 3
1. REQUEST FOR QUOTES SUMMARY
1.1. Quote Submittal Information
Bids shall be submitted electronically through the City’s OpenGov portal at:
https://procurement.opengov.com/portal/palo-alto-ca
RFQ Date: March 10, 2026
Question Submission Deadline: March 13, 2026, 1:00pm
Quote Submission Deadline: March 23, 2026, 3:00pm
1.2. Addenda/Clarifications/Questions
Should discrepancies be found in this RFQ or should there be a need to clarify this RFQ, Questions/Clarifications must be received by no later than 1:00 pm on Friday, March 13, 2026.
Correspondence shall be communicated through the City’s OpenGov portal within the Q&A tab.
Responses from the City will be communicated through the City’s OpenGov portal to all recipients of this
RFQ via addendum. Inquiries received after the date and time stated may not be accepted. All addenda shall become part of this RFQ and acknowledged through the City’s OpenGov portal. The City shall not be responsible for nor be bound by any oral instructions, interpretations or explanations issued by the
City or its representatives.
“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section
10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”
Please note: If the City is unable to confirm that the bidder/contractor’s DIR registration is current, the
City may disqualify the bidder in accordance with applicable law including but not limited to Labor Code section 1725.5.
1.3. Verification of Contractor's License
The City will verify the status of the contractor’s license by checking the Contractor’ State License Board
(www.cslb.ca.gov). The contractor's license and business must match. This verification includes information on any outstanding Board disciplinary action pending against the contractor.
1.4. Pre-Bid Conference
A Pre-Bid Conference is not scheduled.
https://procurement.opengov.com/portal/palo-alto-ca https://www.cslb.ca.gov/
Request for Quotes (RFQ) #RFQ197145 4
1.5. Contractor's License Type
The prime contractor for this work shall possess a valid State of California Contractor’s License in the following category or categories:
A. Contractor will be a qualified State of California State Licensing Board Licensed Fire
Protection Contractor (C-16) as defined in subsection (b) of Section 7058 of the Business and Professions Code.
B. Contractor will have a current Department of Industrial Relations (DIR) number.
2. INSTRUCTION TO BIDDERS
The below Instructions to Bidders includes requirements for submitting a Bid for this request for quotes.
2.1. Submittal
Quotes shall be submitted through the City’s electronic procurement system. A Quote which is attempted to be delivered or which is received after the stated time shall be deemed non-responsive and rejected. The Bidder shall have the sole and exclusive responsibility for ensuring that a quote is received by the time stated herein. Any Quote that is incomplete, unclear, or that fails to fully comply with the applicable requirements set forth herein, including, but not limited to, use of the forms provided by the City, may be rejected as nonresponsive.
2.2. Responsibility of Bidder
A Quote shall be submitted at the sole cost and expense of the Bidder and, in submitting such quote to the City, the Bidder waives any claim or demand against the City which the Bidder may have for any direct or indirect cost or expense of preparing and submitting such Quote.
2.3. Bid Submittals
Bid Form and Bidder’s Documents: Bids must be submitted though the City’s OpenGov portal. Bidder must complete all required items in full and provide signed versions of any documents required in this
RFQ (collectively, the “Bidder’s Documents”). The Bidder will ensure that the information the Bidder inputs into the electronic procurement system matches the information on the Bidder’s Documents it uploads to the electronic procurement system. Any conflict or discrepancy will be resolved as provided in below in "Requirements and Order of Precedence", below, of this Section ("Bid Submittals").
Bidder’s Questionnaire: Each Bid must be accompanied by a completed Bidder’s Questionnaire as provided in this RFQ. Submission of a Bidder’s Questionnaire containing false or incomplete information may be grounds for rejection of the Bid as non-responsive and/or disqualification of the Bidder as not responsible.
Requirements and Order of Precedence: In the event of any conflict or discrepancy between any requirements provided in this RFQ (including but not limited to bid submittal requirements) and any requirements that may be stated in the City’s electronic procurement system, the requirements of this
Request for Quotes (RFQ) #RFQ197145 5
RFQ will control. In the event of any conflict or discrepancy between information included on (or omitted from) the Bid Form or Bidder’s Documents uploaded to the City’s electronic procurement system and any information inputted into the City’s electronic procurement system, the information included on (or omitted from) the uploaded information or Bidder’s Documents will control. For clarity, the Bidder’s Documents uploaded into the electronic procurement system constitute a Bidder’s Bid, whereas the information a Bidder inputs into the electronic procurement system is for administrative convenience and will not control over the uploaded Bidder’s Documents in event of a conflict or discrepancy.
2.4. Bid Authorization
Any person logging into the electronic procurement system to submit a Bid or any other electronic document required by the City must be authorized by the company or entity being represented, either in a personal or representative capacity, to access and submit such bid documents. If the person does business under his or her own name, that person shall login under his or her own login as authorized by the City’s OpenGov portal. If the person does business under a fictitious business name, that person shall login under his or her own login as authorized by the City's OpenGov portal. If the person logins for and on behalf of a partnership, the person shall do so with his or her authority to sign/login under his or her own login as authorized by the OpenGov.
2.5. Withdrawal of Bid
Prior to the date and time set for the opening of Bids, a Bidder who has submitted a bid and accepted the terms and conditions in the City’s electronic procurement system, may withdraw its bid by selecting
“Unsubmit Bid” at any time before the deadline for the receipt of Bids as specified in the RFQ Summary.
No Bidder may withdraw its Bid for a period of ninety (90) days after the date set for the opening of, subject to applicable California Law and Palo Alto Municipal Code Section 2.30.460(c), whichever occurs first.
2.6. Request(s) for Clarification
Any Bidder may submit a Question or Inquiry to the Question & Answer section of this RFQ for the clarification of any aspect of the Specifications or any other related information, or part thereof, which is a part of the RFQ. Such request shall be submitted electronically via the City’s electronic procurement system Q&A function. Such requests shall be submitted before 1:00 pm on Friday, March 13, 2026. All responses will be made available on the City's OpenGov portal at least three (3) Business Days prior to the opening of Quotes. The City reserves the right to issue an addendum or addenda per the "Addenda"
Section of the Instructions to Bidders of the RFQ.
2.7. Addenda
The City reserves the right to issue a written Addendum or Addenda to the electronic solicitation prior to the bid closing date and time. During the Bid process there may be changes to the Contract
Documents, which would require an issuance of an addendum or Addenda. City disclaims any and all liability for loss, or damage to any Bidder who does not receive any addendum issued by City in connection with this RFQ. Any Bidder by submitting a Bid waives any and all claims and demands Bidder may have against City on account of the failure of delivery of any such Addendum to Bidder. Any and all
Request for Quotes (RFQ) #RFQ197145 6
Addenda issued by City shall be deemed included in this RFQ, and the provisions and instructions therein contained shall be incorporated into any Bid submitted by Bidder.
2.8. Specifications
The specifications or scope of work included have been prepared to describe the standard quality, and other characteristics needed to meet City requirements. The City will accept alternate quotation of a designed material, product, thing, service, “or equal”, and will determine if such alternate quotation(s) are satisfactory in meeting a mandatory requirement or specification and if the proposed alternate meets the intent of the original mandatory requirement. The City reserves the right in its sole discretion to reject any alternate proposals that do not meet the specifications. This current section is a subsection of "Instructions to Bidders" and is not the "Specifications" section. See "Specifications/Scope of Work" section of this RFQ.
2.9. Prevailing Wages
This Project is subject to prevailing wages and related requirements as a “public works” under
California Labor Code Sections 1720 et seq. and related regulations. Contractor is required to pay general prevailing wages as defined in California Labor Code Section 1773.1 and Subchapter 3, Title 8 of the California Code of Regulations Section 16000 et seq., as amended from time to time. Pursuant to
Labor Code Section 1773, the City has obtained the general prevailing rate of per diem wages and the general rate for holiday and overtime work in this locality for each craft, classification, or type of worker needed to execute the contract for this Project from the State of California Department of Industrial
Relations (“DIR”). Copies of these rates may be obtained at the City’s Purchasing Department office. The general prevailing wage rates are also available at the DIR, Division of Labor Statistics and Research, website (see e.g. http://www.dir.ca.gov/DLSR/PWD/index.htm) as amended from time to time.
Contractor shall post a copy of the general prevailing wage rates at all Project job sites and shall pay the adopted prevailing wage rates as a minimum. Contractor shall comply with all applicable provisions of
Division 2, Part 7, Chapter 1 of the California Labor Code (Labor Code Section 1720 et seq.), including, but not limited to, Sections 1720, 1725.5, 1771, 1771.1, 1771.4, 1773.2, 1774, 1775, 1776, 1777.5, 1782, 1810, 1813 and 1815, and all applicable implementing regulations, including but not limited to
Subchapter 3, Title 8 of the California Code of Regulations Section 16000 et seq. (8 CCR Section 16000 et seq.), as amended from time to time.
2.10. DIR Registration and Other Requirements
General Notice to Contractor
City requires Contractor and its Subcontractors to comply with all applicable requirements of the
California Labor Code including but not limited to Labor Code Sections 1720 through 1861, and all applicable related regulations, including but not limited to Subchapter 3, Title 8 of the California Code of
Regulations Section 16000 et seq., as amended from time to time. Additional information regarding public works and prevailing wage requirements is available on the DIR website (see e.g.
http://www.dir.ca.gov) as amended from time to time.
Labor Code Section 1771.1(a) http://www.dir.ca.gov/DLSR/PWD/index.htm) http://www.dir.ca.gov/
Request for Quotes (RFQ) #RFQ197145 7
City provides notice to Contractor of the requirements of California Labor Code section 1771.1(a), which reads:
“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or Section 10164 or 20103.5 of the Public Contract Code, provided the contactor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.”
DIR Registration Required
City will not accept a bid proposal from or enter into this Construction Contract with Contractor without proof that Contractor and its Subcontractors are registered with the California Department of Industrial
Relations (“DIR”) to perform public work, subject to limited exceptions.
Posting of Job Site Notices; Compliance Monitoring
City gives notice to Contractor and its Subcontractors that Contractor is required to post all job site notices prescribed by law or regulation and Contractor is subject to compliance monitoring and enforcement by DIR.
2.11. Certified Payroll
Contractor shall furnish certified payroll records directly to the Labor Commissioner (DIR) in accordance with Subchapter 3, Title 8 of the California Code of Regulations Section 16461 (8 CCR Section 16461).
City requires Contractor and its Subcontractors to comply with the requirements of Labor Code section
1776, including but not limited to:
i. Keep accurate payroll records, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by, respectively, Contractor and its Subcontractors, in connection with the Project.
ii. The payroll records shall be verified as true and correct and shall be certified and made available for inspection at all reasonable hours at the principal office of
Contractor and its Subcontractors, respectively.
iii. City requests Contractor and its Subcontractors to submit the certified payroll records to the City’s Project Manager at the end of each week during the Project.
iv. If the certified payroll records are not provided as required, then Contractor and its
Subcontractors shall be subject to a penalty of one hundred dollars ($100.00) per calendar day, or portion thereof, for each worker, and City shall withhold the sum
Request for Quotes (RFQ) #RFQ197145 8 total of penalties from the progress payment(s) then due and payable to Contractor.
This provision supplements the provisions of Section 15 hereof.
v. Inform the City’s Project Manager of the location of Contractor’s and its
Subcontractors’ payroll records (street address, city and county) at the commencement of the Project, and also provide notice to the City’s Project
Manager within five (5) business days of any change of location of those payroll records.
2.12. Employment of Apprentices
Contractor shall comply with the statutory requirements regarding employment of apprentices including without limitation Labor Code Section 1777.5. The statutory provisions will be enforced for penalties for failure to pay prevailing wages and for failure to comply with wage and hour laws.
2.13. Opening of Bids
Electronic Opening
All Bidders and members of the public may view bid results in the electronic procurement system after bid closing. The City reserves the right to change the originally scheduled Bid date and time to a later date and time by issuing an electronic Addendum to that effect. Any and all Quotes received by the City on or before the deadline shall be accepted by the electronic procurement system on the date scheduled for the due date.
2.14. Contract Award
Subject to the conditions of this RFQ, the City will award the contract, if an award is made, to the lowest responsive and responsible Bidder. In determining whether the Bidder is responsible, the City will use the criteria set forth in Palo Alto Municipal Code Section 2.30.440, as set forth below:
1. To have demonstrated the attribute of trustworthiness, and to have the quality, fitness, capacity, experience, and skill to satisfactorily perform the work, or provide the goods and/or services called for in the request for quotes;
2. To have the ability to perform the contract within the time specified;
3. To have the equipment, facilities and resources of such capacity and location to enable the bidder to perform the contract;
4. To have the ability to provide, as required, future maintenance, repair, parts and service for the use of goods purchased;
5. To have a record of satisfactory or better performance under prior contracts with the city or others; and
6. To have complied with applicable laws, regulations, policies (including city policies), guidelines and orders governing prior or existing contracts performed by the bidder.
Request for Quotes (RFQ) #RFQ197145 9
2.15. Determination of Lowest Bid
The lowest bid shall be the lowest total of the bid prices quoted on the Bid Schedule. This total is being used for the purpose of determining the lowest bid.
The lowest Bid shall be the lowest total of the Base Bid prices for year 1 (Table A), year 2 (Table B) and year 3 (Table C). Year 2 and Year 3 specifically identify in this RFQ as being used for the purpose of determining the Bid price. For purposes of this section, the Bid for additional year two and three are used for determining the Bid price are Year 2 and Year 3, Bid Tables # Tables A and Tables B for year 1, year 2 and year 3.
2.16. Waiver of Minor Irregularities
The City may exercise its discretion to waive minor irregularities, defects or informalities in the
Bids/Quotes, so long as the waiver would not affect the amount of the Bid or give the Bidder an advantage over others.
2.17. Bid Discrepancies
In the case of a discrepancy between a written amount and the corresponding figures, the written amount shall govern. In the case of a discrepancy between an item price and the corresponding unit price multiplied by the corresponding estimated quantity, the unit price multiplied by the estimated quantity shall govern. In the case of discrepancy between the actual arithmetic total of all items and the total stated by the Bidder, the actual arithmetic total shall govern.
2.18. Award of Contract and Rejection of Bids
Decision to Award
A contract may be awarded to the lowest responsible bidder. The City reserves the right to award more than one Contract with respect to the RFQ.
Decision to Reject
The City reserves the unfettered right to reject all Quotations for any reason or for no reason, to re-advertise an RFQ, or to cancel an RFQ. The City reserves the right to reject as non-responsive any
Quotation which is incomplete, modified, unsigned, or illegible or which is not otherwise submitted in accordance with the requirements of this RFQ.
2.19. Certification of Nondiscrimination
By submitting a quotation, the Bidder certifies that: in the performance of the Contract, if awarded, it shall not discriminate in the employment of any person due to the race, skin color, gender, gender identity, age, religion, disability, national origin, ancestry, sexual orientation, pregnancy, genetic information or condition, housing status, marital status, familial status, weight or height of such person;
and further certifies that it is in compliance with all Federal, State and local laws, regulations, rules, directives and executive orders regarding nondiscrimination in employment.
2.20. Exceptions
To the specifications, scope of work, General Services Agreement or requirements issued must be itemized and justified in writing and included with proposals or quotations submitted.
Request for Quotes (RFQ) #RFQ197145 10
2.21. Performance, Payment Surety Bonds
Within ten (10) business days of issuance of the Notice of Award, the selected Bidder shall furnish City a
Performance Surety Bond, and Payment Surety Bond. Both bonds shall be in the amount of 100% of the
Contract Sum, and in accordance with requirements contained in the General Conditions of this RFQ.
2.22. Liquidated Damages
Pursuant to Public Contract Code Section 7203, if Contractor fails to achieve Final Completion of the entire Work within the Contract Time, including any approved extensions thereto, City may assess liquidated damages on a daily basis for each day of Unexcused Delay in achieving Final Completion, based on the amount of five hundred dollars ($500) per day, or as otherwise specified in the Special
Provisions. Liquidated damages may also be separately assessed for failure to meet milestones specified elsewhere in the Contract Documents, regardless of impact on the time for achieving Final Completion.
The assessment of liquidated damages is not a penalty but considered to be a reasonable estimate of the amount of damages City will suffer by delay in completion of the Work. The City is entitled to setoff the amount of liquidated damages assessed against any payments otherwise due to Contractor, including, but not limited to, setoff against release of retention. If the total amount of liquidated damages assessed exceeds the amount of unreleased retention, City is entitled to recover the balance from Contractor or its sureties. Occupancy or use of the Project in whole or in part prior to Final
Completion, shall not operate as a waiver of City’s right to assess liquidated damages.
2.23. Insurance Requirements
The Bidder awarded the Contract must, for the term of the Contract obtain and maintain insurance with the coverage specified the attachment regarding Insurance Requirements , provided by companies with
AM Best’s key rating of A-:VII, or higher, which are licensed or authorized to transact insurance business in the state of California.
3. SPECIFICATIONS/SCOPE OF WORK
3.1. Automatic Fire Extinguishing Systems Quarterly, Annual, & Five- Year Inspection, Testing, and Repair Services (See complete scope of work in attachments)
A. Sope of Work:
1. Provide quarterly inspections for all City buildings, which have Wet Pipe Fire Sprinkler
Systems and Fire Standpipe Systems.
2. Provide Annual inspections for all City buildings, which have Wet Pipe Fire Sprinkler
Systems and Fire Standpipe Systems.
3. Perform a Five-Year test and certification on the automatic fire suppression systems that are due during the three-year contract period.
2. Details of Work Performed:
1. All inspections, maintenance, and services will be done in accordance with the NFPA
25 2025 Edition of the California Code of Regulations, as amended by CCR Title 19.
Request for Quotes (RFQ) #RFQ197145 11
2. Contractor will use the inspection forms from the 2025 Edition of the California Code of Regulations. No other forms will be acceptable.
3. Email copies of all competed inspections forms within five days to project manager or designee.
4. All inspection forms will also be uploaded to The Compliance Engine. Contractor will pay all fees to provide this service.
5. For Annual and Five-Year inspections contractor will apply the proper inspection stickers as per the CCRs.
2. Scheduling:
1. All inspections will occur within the first two weeks of the month they are due.
2. Quarterly inspections will be done in the months of June, September, December and
March.
3. Perform annual inspections in June and December. June and December quarterly inspections will be included in the annual inspections.
4. The June and December Annual inspections are divided up as follows:
2. June o Rinconada Library o Lucie Stern Children’s Theater o Fire Station 3 o Golf Course o Ted Thompson Parking Garage o Baylands Interpretive Center o MSC – A o MSC – B o MSC – C o Utility Control Center o Fire Station 8 o Arastradero Preserve Buildings o Lot J Parking Garage o Lot R Parking Garage o Rinconada Pool o Jr. Museum o Public Safety Building
• December o Children’s Library o Lucie Stern Community Theater o Lucie Stern Community Center o Art Center o College Terrace Library
Request for Quotes (RFQ) #RFQ197145 12 o Civic Center o Cubberley Wings H & FH o Cubberley Auditorium o Cubberley Theater o Parking Lot S/L o Mitchell Park Community Center and Library o Sherman Ave. Parking Garage o Pets In Need Module Building o Bryant Street Community Center
5. Complete all Five-Year inspection and testing services as outlined in specifications.
6. Contractor will email inspection schedule to the Facilities Leads at least one week prior to month the inspections are due.
6. Notifications:
1. When required to do so by a Municipal Code, contractor will notify the local fire authority having jurisdiction in advance of the work start date.
2. Contractor will also notify the local Fire Communications Center and any applicable
Central Office Alarm company when conducting system testing and/or repairs.
3. Facilities Management is responsible for notification of all occupants of the property subject to inspection and testing.
2. Deficiencies and Corrections:
1. Contractor should note deficiencies found during the inspections on the inspection sheet.
2. Minor repairs of less than $500 (labor and materials per system) do not need prior approval of Facilities Management and should be done immediately.
3. Send a proposal for repairs exceeding $500 to Facilities Management within three days after inspection.
B.
4. BIDDER'S QUESTIONNAIRE
4.1. Company Type*
Please indicate that which most closely reflects the type for your company.
☐ California Corporation
☐ Corporation Organized under the laws of a State other than California (Provide the name of the State, location of head offices and locations of all offices in California)
☐ Limited Liability Company (Provide list of names of general partners and state which partner or partners are managing partner(s) in "Additional Information" section of Bidder's Questionnaire)
☐ Sole Proprietorship
☐ Partnership
Request for Quotes (RFQ) #RFQ197145 13
☐ Limited Liability Partnership (Provide list of names of general partners and state which partner or partners are managing partner(s) in "Additional Information" section of Bidder's Questionnaire)
☐ Other (Attach applicable information in "Additional Information" section of Bidder's Questionnaire)
*Response required
4.2. Head Office Location*
Please specify where your head office is located.
*Response required
4.3. California Offices*
Please specify, if there are any, where your California offices are located.
*Response required
4.4. Years of Experience Under Current Business Name*
How many years have you (or your company) done business under the name being used to submit?
*Response required
4.5. Years of Similar Experience*
How many years of experience similar to work or services covered in this RFQ?
*Response required
4.6. References*
Please provide relevant references of similar projects satisfactorily completed in the last three (3) years.
For each reference, please provide the following:
• Company Name
• Company Address
• Contact Individual Name
• Contact Phone Number
• Contact Email Address
• Date of Completion of Project or Service
• Contract Amount
*Response required
4.7. Previous Work for City of Palo Alto*
Have you (or your company) previously worked for the City of Palo Alto?
☐ Yes
Request for Quotes (RFQ) #RFQ197145 14
☐ No
*Response required
When equals "Yes"
4.7.1. Previous Work for City of Palo Alto (continued)*
You have indicated that you (or your company) have previously worked for the City of Palo Alto.
Please provide the Position Title you held, the Department in which you worked, Start and End Dates and indicate if you were Full Time or Part Time or worked as a Consultant or indicate some other type of business relationship that applied.
*Response required
4.8. Plants, Facilities, and Equipment*
Please provide a list of the plant(s), and/or facilities, and equipment owned by the Bidder which are available for use in connection with the proposed work as may be required herein.
For each item item on the list, please provide the following:
• Quantity
• Name, Type, Model, Capacity of Item, Facility or Equipment
• Condition
• Location
*Response required
4.9. Management Staff*
Please provide a list of the Bidder's management staff who will manage the proposed work or service.
For each staff member, please be sure to provide the following:
• Full Name
• Field of Expertise
• Capabilities
• Relevant Experience
*Response required
4.10. California Contractor's License*
Please enter the California Contractor's License Number for your company.
*Response required
4.11. DIR Registration*
Enter your California Department of Industrial Relations (DIR) Contractor Registration Number.
Request for Quotes (RFQ) #RFQ197145 15
Please Note:If the City is unable to confirm that the bidder/contractor’s DIR registration is current, the
City must disqualify the bidder, as required by Labor Code section 1725.5.”
*Response required
4.12. Quote Documents Upload*
Please upload your documents here. This includes warranty information and any other documentation you are uploading as a part of your quote.
*Response required
4.13. Separate Pricing Sheet*
Please download the below bid form document, complete, and upload.
• Final_Bidder_Bid_Pages_FY_2...
*Response required
4.14. Additional Information
This file upload is for any sections or questions or responses of yours that indicated to provide additional information. Please provide all information by uploading a file here with all required information or your bid may be deemed incomplete and as such non-responsive.
4.15. Bidder Acknowledgement*
In response to this Request for Quotation (RFQ), the undersigned, as Bidder, declares that the only persons or parties interested in this Bid as principals are those named herein; that this Bid is made without collusion with any other person, firm or corporation; that the Bidder has carefully examined the specifications herein referred to; and the Bidder proposes and agrees, if this Bid is accepted, that the
Bidder will contract with the City of Palo Alto (City), to provide all necessary materials, and furnish the specified requirements in this RFQ, in the manner herein prescribed and at the prices stated in the Bid.
☐ Please confirm
*Response required
4.16. Confirmation of Information*
The undersigned certifies under penalty of perjury under the laws of the State of California that all of the answers and responses to all questions and requested information within the Bidder's Questionnaire are true and correct.
*The individual confirming represents and warrants that he or she has the legal capacity and authority to bind the bidder/party submitting the Bid.
☐ Please confirm
*Response required https://government-project.s3.us-west-2.amazonaws.com/244987/47d2b5db-8958-4c67-9ddf-b58354f999e9_Final_Bidder_Bid_Pages_FY_27_28_29.docx
Request for Quotes (RFQ) #RFQ197145 16
Text133