This file is a Description of Systems spreadsheet for the City of Palo Alto, detailing fire sprinkler and standpipe systems across 29 municipal locations. The spreadsheet catalogs comprehensive system specifications for facilities including community centers, libraries, parking garages, fire stations, and other city buildings. The inventory encompasses 29 primary locations with multiple risers and systems at some sites, totaling over 70 individual fire sprinkler and standpipe systems across addresses ranging from Cubberley Community Center to the Public Safety Building. Each entry documents system type (wet, dry, pre-action, or combination systems), the number of risers, standpipes, hose valves, fire department connections (FDC), private service mains, hydrants, and detailed component descriptions including control valves, gauges, drains, flow switches, and alarm devices. The contract spans three years from June 1, 2026 through May 30, 2029, with quarterly, annual, and five-year inspection, testing, and repair services required in accordance with NFPA 25 2025 Edition and California Code of Regulations Title 19.

The file serves as the baseline system inventory for contractors bidding on the City of Palo Alto's automatic fire extinguishing system maintenance contract. All inspections, testing, and repairs must comply with applicable fire safety codes and standards. The contract includes a dedicated budget allotment for repair services, which contractors will bill against as repairs are required. The spreadsheet notation indicates that the Description of Systems may not include all components, with contractors responsible for inspecting entire systems during service activities. Inspections commence on June 1, 2026, with ongoing quarterly, annual, and five-year maintenance cycles throughout the three-year contract period.

View the file

Other files

File Type Posted
Automatic_Fire_Extinguishing_System_Inspection,_Testing,_and_Repair.pdf PDF
Automatic_Fire_Extinguishing_System_Inspection,_Testing,_and_Repair.pdf PDF
Final_Bidder_Bid_Pages_FY_27_28_29.docx DOCX document
Final_Bidder_Bid_Pages_FY_27_28_29.docx DOCX document
Fire_Sprinkler_Systems_Inspection_Scope_of_Work_updated.pdf PDF
Fire_Sprinkler_Systems_Inspection_Scope_of_Work_updated.pdf PDF
Fire_Sprinkler_Description_of_Systems_03-09-2026_(2).xlsx XLSX spreadsheet
Performance_Bond.pdf PDF
General_Services_Agreement.pdf PDF
Bid_List_for_Fire_Sprinkler_Systems_Inspection_FY27.docx DOCX document
Bid_List_for_Fire_Sprinkler_Systems_Inspection_FY27.docx DOCX document
Fire_Sprinkler_Systems_Inspection_Scope_of_Work_FY_27,_28,_29.docx DOCX document
Insurance_Requirements.pdf PDF
Payment_Bond.pdf PDF
Appendix_G_Solicitation_Plan_Checklist_-_Automatic_Fire_Extinguishing_Systems_Inspection,_Testing,_and_Repair_Services.pdf PDF
Bidder_Bid_Pages_FY_27,_28,_29.docx DOCX document
Fire_Sprinkler_Description_of_Systems_03-09-2026.xlsx XLSX spreadsheet
Fire_Sprinkler_Systems_Inspection_Scope_of_Work_FY_27,_28,_29.docx DOCX document
General_Services_Agreement.pdf PDF
Insurance_Requirements.pdf PDF
Payment_Bond.pdf PDF
Appendix_G_Solicitation_Plan_Checklist_-_Automatic_Fire_Extinguishing_Systems_Inspection,_Testing,_and_Repair_Services.pdf PDF
Bidder_Bid_Pages_FY_27,_28,_29.docx DOCX document
Fire_Sprinkler_Description_of_Systems_03-09-2026.xlsx XLSX spreadsheet
Performance_Bond.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Note: “Description of Systems” may not include all system components, but contractor is responsible for inspecting systems in their entirety.

ItemLocation AddressWet Sprinkler/#SystemsStandpipe Type/#Hose ValvesFDCPrivate Service Main/#HydrantFACP/ WMGDescription of Systems.
1Cubberley Community Center TheaterYNYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV, alarm CV One riser, Two gauges, One main drain, flow switch and inspector test valve.
4000 Middlefield Rd1
2Cubberley Community Center H & FH BuildingsYNYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV, alarm CV One riser, Two gauges, One main drain, flow switch and inspector test valve.
4000 Middlefield Rd.1
3Cubberley Community Center AuditoriumYCL 2 WET HVYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV, alarm CV One riser, Two gauges, One main drain, flow switch and inspector test valve.
4000 Middlefield Rd.12
4Lucie Stern Children’s TheaterYNYY/YOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, electric bell and inspector test valve.
1305 Middlefield Rd.11
5.Lucie Stern Community CenterYCL 2 WET HV/ Hoses RemovedYY/NOne riser, OSY MCV (SCV off Theater riser), Butterfly SCV in storage room, flow switch in ceiling hatch, shares FDC with Community Theater riser.
1305 Middlefield Rd.131
6a.Lucie Stern Community TheaterYCL 2 WET HV/ Hoses RemovedYY/NRiser 1 of 2. One 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, (Shared with Lucie Stern system) OS&Y SCV in attic, alarm CV One riser, Two gauges, One main drain, flow switch, electric bell and inspector test valve.
1305 Middlefield Rd.221
6b.Lucie Stern Community Theater Scene ShopRiser 2 of 2. One 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, (Shared with Lucie Stern system) Two gauges, One main drain, flow switch, and inspector test valve.
7Rinconada LibraryYNYYY/NOne 2 inlet FDC, Swing FDCCV in basement, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, and inspector test valve.
1213 Newell Rd.1
8Baylands Nature Interpretive CenterYNYNY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, Two gauges, One main drain, flow switch, water motor gong and inspector test valve.
2775 Embarcadero Rd.1
9Utility Control CenterYNYY /NOne 2 inlet FDC, Wafer FDCCV @ riser, PIV MCV, alarm CV One riser, One gauge, One main drain, flow switch, and inspector test valve. *(Building also has existing Halon System NIC)
3241 East Bayshore Rd.11
10aArt CenterYNYYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, electric bell and inspector test valve.
1313 Newell Rd.2
10bPre-action fire sprinkler system
Section off riser 2, Swing CV, OS&Y SV, Alarm CV, Three gauges, Two drains, One FS
11Municipal Service Center Building AYCL 2 WET HV/ Hoses RemovedYYY/NWet pipe fire sprinkler system with hose drops
3201 East Bayshore Rd.221One 2 inlet FDC shared with riser 2, Riser 1 of 2 x-connected, OS&Y SCV, alarm CV, One gauge, One main drain, flow switch, inspector test valve.
12Municipal Service Center Building BYCL 2 WET HV/ Hoses RemovedYYY/NWet pipe fire sprinkler system with hose drops
3201 East Bayshore Rd.141One 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, Butterfly SCV @ paint booth, alarm CV One riser, One gauge, One main drain, flow switch, inspector test valve.
13Municipal Service Center Building CYCL 2 WET HV/ Hoses RemovedY/NWet pipe fire sprinkler system with hose drops
3201 East Bayshore Rd.24One 2 inlet FDC shared with riser 2, Riser 2 of 2 x-connected, OS&Y SCV, alarm CV, One gauge, One main drain, flow switch, inspector test valve.
14Ted Thompson Parking GarageYClass 1 Wet/Hoses RemovedYNY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, water motor gong and inspector test valve.
275 Cambridge Avenue141
15aLot S/L Parking GarageYCL 1 DRYYNY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, and inspector test valve per system
445 Bryant St.7241SPR/2ST
15bBryant Street Community CenterYNShared w/SLNY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, electric bell and inspector test valve. FACP, OS&Y/FDC Shared with Lot S/L Riser in Trash Enclosure
429 Bryant1
16Lot R Parking GarageYCL 1 DRYYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, and inspector test valve per system
528 High Street4121SPR/1ST
17Children’s LibraryYNYYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, and inspector test valve. (3) Wharf Hydrants
1275 Harriet St113 Wharf
18Rinconada PoolYNNNN/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, electric bell and inspector test valve.
777 Embarcadero Road1
19College Terrace LibraryYNYNY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, electric bell and inspector test valve.
2300 Wellesley St.1
20Arastradero Preserve BuildingsYNYNN?NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, electric bell and inspector test valve. Hydrant is not fed from 4" OS&Y
1530 Arastradero Rd.21
21Golf Course Club HouseYNYYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, electric bell and inspector test valve.
1875 Embarcadero Road1+Basement1
22a.Civic CenterYCL 1 Wet Combination/CL2 Wet HV Hoses removedYNY/NRiser 1 of 3 x-connected, shared FDC ET AL, OS&Y SV, Alarm CV, Two gauges, One main drain, FS, ITV. 1 6" Main PRV 1 4" Main PRV
250 Hamilton Avenue3 Garage 10 Tower 1 Police 2 Pre-Act13CL1/14CL21, 4WAY
22b.Riser 2 of 3 x-connected, Shared FDC ET AL, OS&Y SV, Alarm CV, 10 BFLY SV’s, 12 gauges, 10 MD, 10 FS & ITV, 9 – 1 ½” & 12 – 2 ½” outlet valves, PRV
22c.Riser 3 of 3 x-connected, shared FDC ET AL, OS&Y SV, @ riser, One BFLY SV, Three gauges, Three drains, Two FS, ITV, 8 – 2 ½” outlet valves
22d.Pre-action fire sprinkler system
Section off riser 2, Swing CV, OS&Y SV, Alarm CV, Three gauges, Two drains, One FS
Located in garage Level A
22e.Pre-action fire sprinkler system
Section off riser 2, Swing CV, MCV, Two BFLY SV, Alarm CV, Five gauges, Three drains, One FS. Two tampers at 2nd Floor
Located in closet for computer room
22f.Diesel Engine Driven Fire Pump
One horizontal centrifugal, Diesel driven 750 GPM, Controller, Jockey pump, Supplied by water main, Churn and flow meter present, no test header.
22g.Fire Pump diesel engine annual maintenance service
23Mitchell Park LibraryYNYYY/NTwo 2 inlet FDC, Wafer FDCCV @ riser, PIV MCV, alarm CV One riser, One gauge, One main drain, flow switch, and inspector test valve. P.S.M HYD+ 1 Wharf Hydrant
3700 Middlefield Road212+1Wharf
23bMitchell Park Community Center – Building BYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, water motor gong and inspector test valve.
3700 Middlefield Road1
23cMitchell Park Community Center – Building CYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, water motor gong and inspector test valve.
3700 Middlefield Road1
24Fire Station 8YNNNY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, water motor gong and inspector test valve.
3300 Pagemill Road1
25Fire Station 3YNYYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, electric bell and inspector test valve.
799 Embarcadero Road1(2Floors11
26JR. MuseumYNYYY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, electric bell and inspector test valve.
1451 Middlefield Road11
27Sherman Parking GarageYCL 1 WETYNY/NTwo 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, One gauge, One main drain, flow switch, electric bell and inspector test valve Per floor control assembly. One electric fire pump.
350 Sherman Ave.7211
28Pets In Need Modular BuildingYNYNY/NOne 2 inlet FDC, Swing FDCCV, OS&Y MCV @ riser, alarm CV One riser, Two gauges, One main drain, flow switch, electric bell and inspector test valve.
3281 E. Bayshore Road11
29aPublic Safety BuildingYCL 1 WET CombinationYNY/NRisers w/ butterfly control valves, check valves, flow switches, drains, gauges and hose valves
250 Sherman Ave.6 + 2 DI Pre-Action4Risers/17 HVs2500 GPM horizontal split case electric pump, gravity fed from external water storage tank , 2 Double Interlock Preaction Systems.
29bDouble interlock pre action system w/ (2) butterfly control valve, check valve, flow switch, (2) drains, 3 gauges, air compressor and alarm panel.
29cDouble interlock pre action system w/ (2) butterfly control valve, check valve, flow switch, (2) drains, 3 gauges, air compressor and alarm panel.