Attmt 2 Vendor Price Sheet TSFS FY24 Alarm and Monitoring Rev1.xls
XLS spreadsheet 57 KB Posted
- Solicitation number
- 6933A224Q000016
About this file
This document appears to be a vendor price sheet for an Alarm and Monitoring System installation project on the Training Ship Freedom Star for the U.S. Maritime Administration (MARAD). The solicitation number is 6933A224Q000016, and the project involves replacing the existing obsolete I.S.I.S 700C system with a new ABS/USCG approved system. The new system will include all existing alarms and monitoring points, along with an additional 10% capacity for digital and analog inputs and outputs.
The price sheet provides a breakdown of estimated labor and material costs for the alarm and monitoring system, as well as supplemental labor and materials. The total cost estimate for the base scope of work is $10,000. The document also includes detailed labor cost breakdowns by trade and labor category. No specific response dates, award dates, or set-asides are provided in this attachment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Availabilty Summary Estimate
| Freedom Star Vendor Price Sheet | 5-Aug-24 | |||||
| AVAILABILITY SUMMARY ESTIMATE SHEET | (See individual estimate sheets tab for detailed breakdown of estimate) | |||||
| Item No. | Title / Description | Material, Misc & Other Costs | ||||
| Total Labor Cost | Total Cost estimate | |||||
| SECTION 200: WORK ITEMS | ||||||
| 1 | Alarm and Monitoring System | $ - 0 | ||||
| 2 | Supplemental Labor | $ 10,000.00 | $ 10,000.00 | |||
| 3 | Supplemental Materials | $ - 0 | ||||
| Total w/o Optional Items | $ 10,000.00 |
Individual Item Estimates
| Job Title: | Item 1 | ||||
| Labor Costs | Summary of Costs | ||||
| Trade | Manhours | Labor Hours | Labor Rate/Hour | Total | |
| Blacksmith | Straight Time | $0.00 | |||
| Boiler maker | Premium Time (1-1/2) | $0.00 | |||
| Burner | Premium Time (2) | $0.00 | |||
| Carpenter | Travel Time | $0.00 | |||
| Chipper | Total Labor Costs | $0.00 | |||
| Electrician | Material | ||||
| Engineering Services | Tech Rep | ||||
| Fire watch | Equipment | ||||
| General Labor | Other (Specify) | ||||
| Joiner | Total Costs Other Than Labor | $0.00 | |||
| Lagger | Grand Total | $0.00 | |||
| Machinist Inside | Remarks: | ||||
| Machinist Outside | |||||
| NDT | |||||
| Painter | |||||
| Pipefitter | |||||
| QA | |||||
| Rigger | |||||
| Sheet Metal | |||||
| Shipfitter | |||||
| Welder | |||||
| Total | 0.0 | ||||
| Job Title: | Item 2 | ||||
| Labor Costs | Summary of Costs | ||||
| Trade | Manhours | Labor Hours | Labor Rate/Hour | Total | |
| Blacksmith | Straight Time | $0.00 | |||
| Boiler maker | Premium Time (1-1/2) | $0.00 | |||
| Burner | Premium Time (2) | $0.00 | |||
| Carpenter | Travel Time | $0.00 | |||
| Chipper | Total Labor Costs | $0.00 | |||
| Electrician | Material | ||||
| Engineering Services | Tech Rep | ||||
| Fire watch | Equipment | ||||
| General Labor | Other (Specify) | ||||
| Joiner | Total Costs Other Than Labor | $0.00 | |||
| Lagger | Grand Total | $0.00 | |||
| Machinist Inside | Remarks: | ||||
| Machinist Outside | |||||
| NDT | |||||
| Painter | |||||
| Pipefitter | |||||
| QA | |||||
| Rigger | |||||
| Sheet Metal | |||||
| Shipfitter | |||||
| Welder | |||||
| Total | 0.0 | ||||
| Job Title: | Item 3 | ||||
| Labor Costs | Summary of Costs | ||||
| Trade | Manhours | Labor Hours | Labor Rate/Hour | Total | |
| Blacksmith | Straight Time | 0.0 | $0.00 | ||
| Boiler maker | Premium Time (1-1/2) | $0.00 | |||
| Burner | Premium Time (2) | $0.00 | |||
| Carpenter | Travel Time | $0.00 | |||
| Chipper | Total Labor Costs | $0.00 | |||
| Electrician | Material | ||||
| Engineering Services | Tech Rep | ||||
| Fire watch | Equipment | ||||
| General Labor | Other (Specify) | ||||
| Joiner | Total Costs Other Than Labor | $0.00 | |||
| Lagger | Grand Total | $0.00 | |||
| Machinist Inside | Remarks: | ||||
| Machinist Outside | |||||
| NDT | |||||
| Painter | |||||
| Pipefitter | |||||
| QA | |||||
| Rigger | |||||
| Sheet Metal | |||||
| Shipfitter | |||||
| Welder | |||||
| Total | 0.0 | ||||
| Job Title: | Item 4 | ||||
| Labor Costs | Summary of Costs | ||||
| Trade | Manhours | Labor Hours | Labor Rate/Hour | Total | |
| Blacksmith | Straight Time | $0.00 | |||
| Boiler maker | Premium Time (1-1/2) | $0.00 | |||
| Burner | Premium Time (2) | $0.00 | |||
| Carpenter | Travel Time | $0.00 | |||
| Chipper | Total Labor Costs | $0.00 | |||
| Electrician | Material | ||||
| Engineering Services | 200.0 | Tech Rep | |||
| Fire watch | Equipment | ||||
| General Labor | Other (Specify) | ||||
| Joiner | Total Costs Other Than Labor | $0.00 | |||
| Lagger | Grand Total | $0.00 | |||
| Machinist Inside | Remarks: | ||||
| Machinist Outside | |||||
| NDT | |||||
| Painter | |||||
| Pipefitter | |||||
| QA | |||||
| Rigger | |||||
| Sheet Metal | |||||
| Shipfitter | |||||
| Welder | |||||
| Total | 200.0 | ||||
| Job Title: | Item 5 | ||||
| Labor Costs | Summary of Costs | ||||
| Trade | Manhours | Labor Hours | Labor Rate/Hour | Total | |
| Blacksmith | Straight Time | $0.00 | |||
| Boiler maker | Premium Time (1-1/2) | $0.00 | |||
| Burner | Premium Time (2) | $0.00 | |||
| Carpenter | Travel Time | $0.00 | |||
| Chipper | Total Labor Costs | $0.00 | |||
| Electrician | Material | ||||
| Engineering Services | 200.0 | Tech Rep | |||
| Fire watch | Equipment | ||||
| General Labor | Other (Specify) | ||||
| Joiner | Total Costs Other Than Labor | $0.00 | |||
| Lagger | Grand Total | $0.00 | |||
| Machinist Inside | Remarks: | ||||
| Machinist Outside | |||||
| NDT | |||||
| Painter | |||||
| Pipefitter | |||||
| QA | |||||
| Rigger | |||||
| Sheet Metal | |||||
| Shipfitter | |||||
| Welder | |||||
| Total | 200.0 |