This document is a Statement of Work (SOW) for the installation of a new Alarm and Monitoring System on the Training Ship FREEDOM STAR, a U.S. Government-owned vessel operated by the Maritime Administration (MARAD).
The key details are:
- The intent is to replace the existing obsolete I.S.I.S 700C Alarm and Monitoring System with a new ABS/USCG approved system. The new system will incorporate all existing alarms and monitoring points, plus an additional 10% digital and analog inputs/outputs.
- The period of performance is estimated from September 2024 through December 2024. The vessel is located at the Seafarer's Harry Lundeberg School of Seamanship in Piney Point, Maryland.
- The SOW includes requirements for removing the existing system, installing the new PLC-based system with HMI displays, upgrading the DC backup system if needed, and providing manuals and recommended spare parts.
- Additional requirements include installing low-level alarm switches for various engine and thruster systems, and implementing an independent tank level monitoring system.
- The solicitation also includes line items for supplemental labor (100 hours) and material (up to $5,000) that may be allocated by the Contracting Officer's Representative (COR).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| TSFS Alarm Amdmt 0002.pdf | ||
| Amdmt 0001 TSFS 6933A224Q000016 Alarm Install.pdf | ||
| TSFS Alarm Monitor Install Comb. Syn Sol.pdf | ||
| Attmt 2 Vendor Price Sheet TSFS FY24 Alarm and Monitoring Rev1.xls | XLS spreadsheet | |
| WD.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Training Ship
FREEDOM STAR
ALARM and MONITORING SYSTEM
TABLE OF CONTENTS
Vessel Info
Vessel Particulars
Synopsis
Work Items
Item # 1 ALARM and MONITORING SYSTEM, INSTALL
Item #2 SUPPLEMENTAL LABOR
Item #3 SUPPLEMENTAL MATERIALS
VESSEL INFO
MARITIME ADMINISTRATION
The Maritime Administration is the agency within the U.S. Department of Transportation dealing with waterborne transportation. Its programs promote the use of waterborne transportation and its seamless integration with other segments of the transportation system, and the viability of the U.S.
merchant marine. The Maritime Administration works in many areas involving ships and shipping, shipbuilding, port operations, vessel operations, national security, environment, and safety. The Maritime Administration is also charged with maintaining the health of the merchant marine, since commercial mariners, vessels, and intermodal facilities are vital for supporting national security, and so the agency provides support and information for current mariners, extensive support for educating future mariners, and programs to educate America’s young people about the vital role the maritime industry plays in the lives of all Americans.
The Maritime Administration also maintains a fleet of cargo ships in reserve to provide surge sea-lift during war and national emergencies, and is responsible for disposing of ships in that fleet, as well as other non-combatant Government ships, as they become obsolete.
The Maritime Administration recently realigned many of its functions, to revitalize its role as an industry facilitator, and to bring greater focus to the areas of environment and safety.
TRAINING SHIP FREEDOM STAR
The vessel serves as a back-up and supplementary training ship for the United States Merchant Marine Academy and the six state maritime academies. The vessel is normally berthed at the Seafarers Harry Lundeberg School of Seamanship (SHLSS). Located in Piney Point, MD, the SHLSS is a vocational school dedicated to preparing students for successful careers as U.S. merchant mariners.
Before being redesigned to serve as a training vessel for students, the Freedom Star served as a solid rocket booster recovery vessel for the National Aeronautics and Space Administration (NASA), retrieving solid rocket boosters following space shuttle launches.
The vessel was transferred to MARAD at the end of the space shuttle program and is berthed at the SHLSS under a Memorandum of Agreement that maintains vessel readiness for MARAD missions at a reduced cost to the government, while also supporting entry-level training for individuals who wish to begin a seafaring career.
VESSEL PARTICULARS
NAME: T.S. FREEDOM STAR
TYPE: Twin-screw Diesel CPP
OFFICIAL REGISTRY NUMBER: 629627
IMO Number 7925314
RADIO CALL SIGN: KRFB
CLASSIFICATION: ABS
BUILDER: Atlantic Marine Inc., Ft. George Island, FL.
DELIVERED: 01 September 1981
LENGTH OVERALL: 176’ 00”
LENGTH BETWEEN PERP. 166” 00”
BEAM: 37’ 01.5”
Depth Molded : 15’ 00”
DESIGN DRAFT: 12’ 00”
Docking Displacement: 725 Long Tons (ESTIMATED) Lightship Weight; 633.91 Long Tons VCG: 15.08 Ft. ABL LCG: 3.08 Ft. Aft of amidships USCG GROSS TONNAGE: 484 tons USCG NET TONNAGE: 329 tons CRUISING SPEED: 12 knots
COMPLEMENT: 24
USCG CERTIFICATION: Public Nautical School ship
ABS CLASSIFICATION: †A1;†AMS;†DPS-O
MAIN ENGINES: Two (2) GM-EMD 12-645E6A
MAIN GENERATORS: Two Kato 166 kW, 440 VAC, 3 Phase BOW THRUSTER: Verharr Omega OCP 400 STERN THRUSTER; Tees White Gill KAZ 906858 360 Degree Water Jet DIESEL FUEL CAPACITY: 46,781 U.S gallons WATER BALLAST CAPACITY: 30,904 U.S. gallons FRESH WATER CAPACITY: 5,128 U.S. gallons WASH WATER CAPACITY: 17,160 U.S. gallons
SYNOPSIS: TV FREEDOM STAR – FY24 ALARM and MONITORING SYSTEM
Intent: It is the intent of the Maritime Administration to solicit Industrial Support to install a new
ABS/USCG approved Alarm and Monitoring System to replace the existing obsolete I.S.I.S
700C System. All of the existing alarms and monitoring points will be part of the new system along with the requested additional tank levels. Designed into the new system will be 10 % additional digital and analog inputs and outputs.
Background: The TS FREEDOM STAR is a U.S. Government owned training ship provided to the Harry Lundeberg School of Seamanship for the purpose of training young men and women for a career in the U.S. Maritime Industry. The ship is part of the National Defense Reserve
Fleet (NDRF) and maintains a U.S. Coast Guard Certificate of Inspection (COI) and American
Bureau of Shipping (ABS) Classification.
As a Public Nautical School Ship and Cargo Ship (non-tanker), the regulations of 46 CFR 167, in addition to ABS Rules and SOLAS Regulations for a Cargo Ship (non-tanker), govern all work performed aboard.
Period of Performance: The overall period of performance for this SOW shall be from date of award estimated early in September 2024 through an estimated date of December 15, 2024
(both subject to adjustment).
Location: The TS FREEDOM STAR is moored alongside her pier at the Seafarer’s Harry
Lundeberg School of Seamanship located at 45353 Saint Georges Avenue, Piney Point, Maryland 20674-0075.
Contracting Office Address: Office of Acquisition Primary Point of Contact:
7737 Hampton Blvd, Building 19, Suite 300 William Wile, Contracting Officer Norfolk, Virginia 23505 (757) 322-5806
WORK ITEMS: ITEM 01 Alarm & Monitoring System
REFERENCE:
1) I.S.I.S. Booklet
2) Freedom Star-IO Present Design
3) RGM ISIS 550B Manual
STATEMENT OF WORK: Contractor to provide all materials and labor to install a new ABS/USCG approved Alarm and Monitoring System to replace the existing obsolete I.S.I.S 700C System. All of the existing alarms and monitoring points will be part of the new system along with the requested additional tank levels. Designed into the new system will be 10 % additional digital and analog inputs and outputs.
1) Remove existing, I.S.I.S 700C System components and replace with new Alarm & Monitoring System as follows:
a) Existing sensors to be inspected, tested and reused if functional or replaced as required. The existing system contains approximately 64-80 monitoring I/O points.
Some of these are Analog and some Digital. New PLC to be capable of processing the same number of I/O points or more. See attached I/O list as installed.
Contractor to use the ABS Type Approved Idec FC6A PLC or equivalent.
b) Existing wiring to be inspected, tested and reused if functional. If wiring is found to be deficient, it shall be replaced.
c) System to have trending capabilities for all Analog points. The new PLC will be installed in the existing panel that contains the DAU and main processing units of the existing A&M system.
d) Four (4) HMI display screens to be installed in Engine Room Control Panel, Wheelhouse Console, Chief Engineer Stateroom and Crew Lounge (located on Mess Deck). Contractor will will use the Idec 15” human machine interface (HMI) screens.
e) New audible and visual alarms to activate at all four (4) locations with local silence / mute switches. A second audible and visual alarm in the aft engine room, one in the stern thruster/steering gear, and one in the bow thruster space.
f) Upgrade of DC backup system to match emergency run time requirements of ABS and USCG if needed.
g) Two printed manuals and one electronic copy shall be provided to the vessel. These manuals shall include a list of all sensors and switches used with manufacturers and part numbers for future ordering and replacement.
h) The system must have the ability for the crew to replace and calibrate sensors without the need of a technical representative to attend. Any sensor calibration equipment shall be provided with the new system if applicable.
i) Recommended spares shall be supplied to the vessel.
ADDITIONAL:
a) The following points to have a Low-Level Alarm switch installed and added to the new A & M system:
1. Port Main Engine JW Expansion tank (Kings Pointer has this installed, but not wired in)
2. STBD Main Engine JW Expansion tank (Kings Pointer has this installed, but not wired in)
3. Port Generator Engine Lube Oil Sump
4. Port Generator Engine Jacket Water Level
5. STBD Generator Engine Lube Oil Sump
6. STBD Generator Engine Jacket Water Level
7. Bow Thruster Engine Lube Oil Sump
8. Bow Thruster Engine Jacket Water Level
9. Stern Thruster Engine Lube Oil Sump
10. Stern Thruster Engine Jacket Water Level
Generator Lube oil and Jacket Water level switches are to be installed in an area where they can be easily seen from the operating level. Bow and stern thruster lube oil levels will be below deck plate level and should be installed where they cannot be kicked or damaged during routine rounds of the space. Bow and stern thruster jacket water level switches shall be installed in areas easily seen from deck plate level (Near sight glasses).
Example Lube Oil Level Switch (Four Total). This switch allows for monitoring of lube oil levels while the engine is running: L129 - FW Murphy Production ControlsFW Murphy Production Controls https://www.fwmurphy.com/product/l129-series/
Example Jacket Water Level Switch (Six Total): L150 and EL150 Series - FW Murphy Production ControlsFW Murphy Production Controls
b) These points will require new sensors or floats and wiring to be installed for Low
Alarm indication. See below photos.
Generator Engine Sump ME JW Expansion Tank https://www.fwmurphy.com/product/l150-and-el150-series/ https://www.fwmurphy.com/product/l150-and-el150-series/
Example: Stern Tube Tank with Murphy switch
c) Wiring for any additional sensing points to be included. Wiring shall be of approved marine type shielded cable.
d) Any unused wiring is to be tagged and removed back to its source.
Tank Level Monitoring System
a) An independent tank level monitoring system to be installed to monitor Five (5) tank levels. The intent is to have an independent system that can be continuously powered and observed without powering up the main Engine Room Alarm & Monitoring system. The display for this system is to be installed in the E.R Control Panel. The existing tank level displays are to be removed. (Kings Pointer would not like the systems to be separated if possible and routinely leaves the main alarm system powered up)
b) These tanks will require new sensors and existing cabling to be reused if functional.
The following tanks to be monitored: (Capacities are approximate)
1. Port Sewage Storage Tank – 2000 gallons
2. Starboard Sewage Storage Tank – 2000 gallons
3. Sewage Day Tank – 1000 gallons
4. Port Fuel Oil Day Tank – 2000 gallons
5. Starboard Fuel Oil Day Tank – 2000 gallons
c) The three (3) sewage tanks currently have “sonic” type sensors mounted in top of tank.
d) The two (2) Fuel Oil Day tanks currently have local ‘flip’ type magnetic level indicators with a magnetic sensor at Hi and Low levels. See below photo.
Fuel Oil Day Tank- Magnetic Flip Indicator
Day tank visual indicator: catalog-d_alloy-standard.pdf (gemssensors.com)
e) High and low level alarms on the Emergency Generator Day Tank and a high level alarm on the Dirty Oil tank are to be installed (not continuous monitoring, just level alarms).
PERFORMANCE CRITERIA/DELIVERABLES:
Submit one legible copy, in electronic media, of a complete record of work performed listing the results of the testing to the COR. All alarms and monitoring systems are to be tested for proper operation upon completion to the satisfaction of the Chief Engineer.
NOTES:
Engine room temperatures can exceed 100°F and any electronic equipment installed in https://www.gemssensors.com/docs/default-source/resource-files/catalog-pages/catalog-d_alloy-standard.pdf?Status=Master&sfvrsn=bb172b2c_9 the engine room must be able to withstand high operating temperatures for prolonged periods of time.
New aluminum panels are to be provided to replace the panels in the existing engine room console to eliminate any holes left from the previous system.
An in person comprehensive training/review of the system shall be conducted with the crew members of the vessel. This training shall include:
1. General use/operation of system
2. Required maintenance
3. Troubleshooting
A list of discrepancies and recommended actions shall be provided upon completion.
Suggested sources:
ITEM : 2 SUPPLEMENTAL LABOR
Contractor shall furnish a unit price quote for 100 man-hours of supplemental labor. This shall be a fully burdened labor rate and is applicable seven days a week (i.e. no overtime, penalty time or other escalations will apply). These hours will only be allocated for industrial labor. Supervision, management, QA, and other such labor is considered part of the rate burden.
Supplemental hours, if authorized, will be allocated by the COR via Delivery Orders.
ITEM : 3 SUPPLEMENTAL MATERIAL
Contractor shall provide an allowance for up to $5,000.00 in Supplemental Material charges. There shall be no burden on these charges for either subcontracted costs or material charges. If Supplemental Material is required, it will be allocated by the COTR via Delivery Orders.
Supplemental material, if authorized, will be allocated by the COR via Delivery Orders.