Attchment D - Deliverables Schedule.pdf

PDF 143 KB Posted

Attached to
PANG Archaeological Survey
Solicitation number
S-24800-00017876
Issued by
Oregon

About this file

This is a Deliverables Schedule for the PANG Archaeological Survey contract in Oregon, involving the National Guard Bureau (NGB) divisions A4FR, A4VN, and A4VR, along with the Cultural Resources Program Manager, Contracting Officer's Representative (COR), Oregon State Historic Preservation Office (SHPO), and federally recognized Tribes. The contract encompasses a phased archaeological survey project with multiple deliverables spanning from initial work plan development through final report submission. Key deliverables include a Draft Work Plan due within five working days of kickoff, a Final Work Plan within five working days of government comments, a Management Summary within ten working days of fieldwork completion, a Preliminary Draft Report within twenty-one days of fieldwork completion, a Check Draft Report within fifteen days of government review, a Draft Survey Report for Tribal and SHPO consultation within ten working days, a Check Final Survey Report following the consultation review period, and a Final Survey Report upon acceptance by all parties. The project requires extensive coordination with multiple stakeholders, including submission of preliminary eligibility recommendations, GIS shapefiles, and technical data compendium materials throughout the process.

The deliverables are required in specified digital formats, including PDF, Word documents, tracked-changes versions, and GIS shapefiles, with the Final Survey Report requiring both hard copies (three physical copies) and digital media (one CD/DVD copy and two electronic copies). All documents must include Comment Resolution Matrices addressing stakeholder feedback, and the project incorporates a formal fifteen-day government review period for the Preliminary Draft Report followed by additional review periods for SHPO and Tribal consultation. Distribution requirements specify delivery to NGB/A4FR, NGB/A4VN, the COR, and coordinated delivery to Oregon SHPO and federally recognized Tribes for consultation purposes. The contract emphasizes compliance with Section 106 consultation requirements and includes provisions for multiple review and revision cycles to ensure stakeholder input is incorporated throughout the project lifecycle.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment D: Deliverables Schedule

Deliverable ID PWS Task

Reference

Deliverable

Title

Due Date /

Timeline

Format & Media

Requirements

Distribution &

Recipients

3.1 Element 1, Task 1

Draft Work

Plan

Within five (5) working days of the Kickoff

Meeting.

• Digital format

(PDF/Word)

• Must include project schedule and communications plan

NGB/A4FR,

NGB/A4VN Cultural

Resources Program

Manager (CRM), and other POCs as necessary.

3.2 Element 1, Task 2

Final Work

Plan

Within five (5) working days of receiving

Government comments on the Draft

Work Plan.

Two (2) digital versions:

• 1 Clean version

• 1 Tracked-changes version

• Comment

Resolution Matrix

(CRM) addressing

Draft comments

NGB/A4FR,

NGB/A4VN CRM,

and other POCs as necessary.

4.1 Element 2, Task 3

Management

Summary

Within ten

(10) working days of the completion of fieldwork.

• Digital document

• Preliminary eligibility recommendations for each resource

• Associated GIS shapefiles

COR, NGB/A4VR,

and NGB/A4VN.

5.1 Element 3, Task 1

Preliminary

Draft Report

Within twenty-one

(21) days of the completion of fieldwork.

• Digital copies of the draft technical report

• Supporting data compendium materials

(Initiates a 15-day

Government review period)

COR, NGB/A4FR,

and NGB/A4VR.

5.2 Element 3, Task 2

Check Draft

Report

Within fifteen

(15) days of receiving

Government review comments.

• Digital copies incorporating all

Government revisions

(May be preceded by an MS TEAMS comment resolution conference)

COR, NGB/A4FR,

and NGB/A4VR.

5.3 Element 3, Task 3

Draft Survey

Report for

Consultation

Within ten

(10) working days of the

Check Draft

Report and data compendium being accepted.

Two (2) digital versions:

• 1 Clean version

• 1 Tracked-changes version

• CRM with responses to Check

Draft review comments

Coordinated via

COR/NGB to Oregon

SHPO and federally recognized Tribes.

5.4 Element 3, Task 4

Check Final

Survey Report

Following the completion of the SHPO and

Tribal review period (at the direction of the

COR/NGB).

Two (2) digital versions:

• 1 Clean version

• 1 Tracked-changes version

• CRM addressing

SHPO and Tribal comments

Coordinated via

COR/NGB to federally recognized

Tribes, ANG, and

Oregon SHPO (for backcheck review).

5.5 Element 3, Task 5

Final Survey

Report

Once all changes are accepted by the NGB, the

Tribes, and the

SHPO.

Hard Copies: 3 physical copies

Digital Media: 1

CD/DVD copy and

2 electronic copies

(1 searchable PDF and 1 MS Word).

Includes:

• 1 Clean version

• 1 Tracked-changes version

• Final CRM

Physical copies:

PANG COR

Digital copies: NGB

(to formally complete

Section 106 consultations).