This document is a Statement of Work (SOW) and Work Plan for light asphalt rehabilitation construction services at the Erwin National Fish Hatchery in Erwin, Tennessee (Project No. T25R1). The work includes rehabilitation of Route #010 (Federal Hatchery Road), Route #900 (Visitor Parking), Route #901 (Overflow Parking), and Route #902 (Museum Parking) located at 520 Federal Hatchery Road.
The project involves surface preparation, crack and pothole repair, tack coat application, hot-mix asphalt paving, seal coat application, and thermoplastic pavement markings. Route #010 requires milling 1.5 inches and placing 1.5-inch overlay (approximately 1,876 square yards for the road and 418 square yards for the loop); Routes #900, #901, and #902 require scarifying and placement of 2-inch overlays (1,480, 119, and 217 square yards respectively). Hot-mix asphalt must be produced from all new materials with compaction to at least 91% of maximum theoretical density. The contractor must complete seven full-depth core samples for density and thickness testing. Road traffic disruption limitations are strict: Federal Hatchery Road shutdown cannot exceed five business days for milling/overlay/protection, three business days for seal coat, and three business days for pavement marking, with a maximum total of fifteen business days shutdown for any asset. The Period of Performance is 180 days from Notice to Proceed, with potential extensions for weather delays. The work is subject to USFWS Region 4 IMB Division 01 Specifications for Construction Projects, USFWS Erwin NFH Transportation Assets Specifications for Asphalt Overlay, and Tennessee Department of Transportation Standard Specifications for Road and Bridge Construction (2021). A Pre-Construction Meeting is required, and the contractor must coordinate with the Hatchery Manager regarding scheduling, equipment storage, and site access.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_140FGA26Q0013_TC_34pp.pdf | ||
| Attch3_SectionB_QuoteSchedule.docx | DOCX document | |
| Attch2_WD-DBA_TN20260147_260102_5pp.pdf | ||
| Sol_140FGA26Q0013.pdf | ||
| Attch4_T25R1_QuoteSchedule_2026-02-03_1p.xlsx | XLSX spreadsheet | |
| Attch5_RelevantExperienceSurvey_4pp.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
-for-
CONSTRUCTION SERVICES
-of-
Light Asphalt Rehabilitation -at the-
Erwin National Fish Hatchery -to include-
Route #010: Federal Hatchery Road
Route #900: Visitor Parking Route #901: Overflow Parking Route #902: Museum Parking
520 Federal Hatchery Road, Erwin, TN 37650
Project No: T25R1
1 DESCRIPTION OF THE WORK
A. This Work includes light asphalt rehabilitation on the entire existing footprint of several assets at the Erwin National Fish Hatchery. A description of these assets [Table 1] and a plan view of the entire site [Figure 4] are provided.
Existing footprint of all assets included in the Work to include edges of pavement covered by soil and/or grass (typically 1-IN to 3-IN), which is to be exposed and cleaned prior to any subsequent Work.
Table 1: Description of Assets in Work Route Name Route No. Description
Federal Hatchery Road #010
Road: From west side of intersection with Quarters Driveway, excluding Ditch, to 5-FT setback from North Main Road (Road 107), including turning radius areas.
Loop: From west side of intersection with Quarters Driveway through and including the Loop
Ditch: Southwest edge of Road from Route #800 to Route # 801
Visitor Parking #900 All
Overflow Parking #901 All
Museum Parking #902 All
B. A noncomprehensive overview of the Work [Table 2] and a detailed Work Plan [1] are provided.
Table 2: Overview of the Work Component #010-Road #010-Loop #900 #901 #902
Approximate Area (SY) 1876 418 1480 119 217 Surface Preparation Mill 1.5-IN Scarify N/A Scarify Scarify
Crack and Pothole Repair ✔ ✔ ✔ ✔ ✔
Tack Coat ✔ ✔ N/A ✔ ✔
Asphalt Paving and Compaction 1.5-IN 2-IN N/A 2-IN 2-IN Seal Coat ✔ ✔ ✔ ✔ ✔
Thermoplastic Markings ✔ N/A ✔ N/A ✔
2 SPECIFICATIONS
A. Unless specified in this Statement of Work, all work must conform to specifications outlined in the USFWS R4 IMB Division 01 Specifications for Construction Projects [2], USFWS Erwin NFH Transportation Assets Specifications for Asphalt Overlay [3]; and Tennessee Department of Transportation Standard Specifications for Road and Bridge Construction, 2021 [4]. In any conflict between specifications, the more stringent shall govern.
B. Hot-mix asphalt overlay pavement shall be produced from all new materials; no reclaimed asphalt pavement shall be used in the asphalt overlay work.
C. Asphalt shall be compacted to at least 91% of the maximum theoretical density.
D. Refer to FWS Asphalt Specification §1(6)(E) and FWS Construction
Specification §01 45 23 for independent testing.
E. Refer to FWS Asphalt Specification §3(7) for joints and junctions, which include those within and between assets involved in the Work and between those assets and all other at-grade junctions with side-roads.
F. Crack and pothole repair shall include junctions with other asphalt pavement assets.
G. Inspections may be made a requirement both after the overlay and subsequent testing component of this Work as well as after the seal coat application component.
3 DIMENSIONS AND QUANTITIES
A. Dimensions have not been field-verified via survey by the Government. Bidders shall make their own measurements in preparation of their bid. Contractor is responsible to determine exact quantities in preparation for the Work. The line items listed on the associated Bid Schedule are not intended to be fully comprehensive of all Work details which may be included in the Specifications, Bid Schedule, or this Statement of Work.
4 ROAD TRAFFIC DISRUPTION
A. The maximum permissible duration of complete shutdown of Federal Hatchery Road (Route #010) between North Main Avenue (Road 107) and the south corner of the Main Hatchery Building [Figure 2] shall be no longer than:
a. five (5) business days during milling, overlay, and subsequent protection
b. three (3) business days during seal coat application and subsequent protection
c. three (3) business days during pavement marking and subsequent protection
B. The maximum permissible duration of shutdown of any asset shall be no longer than a total of fifteen (15) business days.
C. The Contractor shall send written notice of proposed dates of partial and complete shutdowns of any asset to the COR and Hatchery Manager no less than seven (7) calendar days prior to the start of any such shutdowns.
D. Rescheduling of such shutdown periods will be permitted, within reason, due to weather delays.
Figure 1: Designated area for 5-day (mill and overlay), 3-day (seal coat application), and 3-day (pavement marking) maximum shutdown durations
5 PERIOD OF PERFORMANCE (POP)
A. The period of performance for this work shall be 180 days commencing after notice to proceed (NTP) with construction has been issued. A POP extension may be considered for construction delays outside the control of the USFWS and the Contractor, including weather delays.
6 LOCATION
A. The work site is located on the Erwin National Fish Hatchery and is accessible via North Main Avenue (Road 107). Project coordinates of the corner of Federal Hatchery Road (Route #010) and North Main Avenue are approximately 36.164846, -82.386262. The physical address is:
Erwin National Fish Hatchery 520 Federal Hatchery Road Erwin, TN 37650
7 COORDINATION AND WORK PHASES
A. This work effort will require a collaborative approach to complete construction, scheduling and coordination, materials, inspections, acceptance, and close-out requirements.
B. An onsite Pre-Construction Meeting shall be scheduled between USFWS personnel and the Contractor prior to the start of the Work.
C. The phases of work under this contract will consist of:
a. Phase 1 – Submittals. The Contractor shall be responsible for submitting information regarding the product, mix design, and materials for construction for acceptance.
b. Phase 2 – Demolition and Construction. The Contractor will be responsible for scheduling and conducting the physical demolition and construction of the Project and for executing effective quality control in accordance with the contract documents. The Contractor shall notify the USFWS at least seven (7) days prior to the start of any construction.
c. Phase 3 – Inspections, Acceptance, and Close-Out. Following the completion of construction with final inspection and acceptance by the U.S. Fish and Wildlife Service, the Contractor shall submit final close-out documents.
8 LAYOUT WORK
A. The Contractor is responsible for laying out the work as called for by the contract documents, including this Statement of Work and attachments.
9 PERMITTING
A. There are no required permits for this work.
10 WORKING CONDITION
A. The Contractor may leave equipment at the worksite during the construction period; however, the Contractor must coordinate with the Hatchery Manager as to location and available space.
B. The Contractor may not drive over or park vehicles or equipment on the u-shaped ditch alongside Route #010.
C. The Contractor shall be responsible for repairing damages caused by its operations to U.S. Fish and Wildlife Service land and property.
D. The Contractor shall repair all vegetated areas disturbed by the Work by placing 3” of topsoil, seed, mulch, and fertilizer at cost to Contractor.
E. The Contractor shall remove all debris from premises and all areas shall be left in clean condition at all times. All debris and leftover material shall be hauled offsite at cost to Contractor.
ATTACHMENTS AND REFERENCES
1 Work Plan 2 FWS Construction Specifications:
USFWS R4 IMB Division 01 Specifications for Construction Projects, December
3 FWS Asphalt Specifications:
USFWS Erwin NFH Transportation Assets Specifications for Asphalt Overlay
4 TDOT:
Tennessee Department of Transportation Standard Specifications for Road and Bridge Construction, 2021:
https://www.tn.gov/content/dam/tn/tdot/construction/2021-standard-specifications/January_1_2021_Standard_Specifications.pdf https://www.tn.gov/content/dam/tn/tdot/construction/2021-standard-specifications/January_1_2021_Standard_Specifications.pdf https://www.tn.gov/content/dam/tn/tdot/construction/2021-standard-specifications/January_1_2021_Standard_Specifications.pdf
Figure 2: Plan view of the site, which includes assets in Work and neighboring assets
– END OF STATEMENT OF WORK FOR CONSTRUCTION SERVICES –
WORK PLAN
-for-
CONSTRUCTION SERVICES
-of-
Light Asphalt Rehabilitation -at the-
Erwin National Fish Hatchery -to include-
Route #010: Federal Hatchery Road
Route #900: Visitor Parking Route #901: Overflow Parking Route #902: Museum Parking
520 Federal Hatchery Road, Erwin, TN 37650
Project No: T25R1
1 FEDERAL HATCHERY ROAD (ROUTE #010)
FIGURE 1. STATUS ASSESSMENT FOR ROUTE #010
COMPONENT #010-ROAD #010-LOOP
SURFACE PREPARATION MILL 1.5-IN SCARIFY
CRACK AND POTHOLE REPAIR ✔ ✔
TACK COAT ✔ ✔
ASPHALT PAVING AND COMPACTION 1.5-IN 2-IN
SEAL COAT ✔ ✔
THERMOPLASTIC MARKINGS ✔ N/A
ROUTE #010 NOTES:
1. REMOVE (4) SPEED HUMPS AND (2) GATE ACCESS LOOPS. ELECTRICAL POWER
TO THE GATE WILL BE DISCONNECTED FROM THE MAIN BREAKER PANEL PRIOR
TO THE START OF THE WORK. HOWEVER, CONTRACTOR SHALL STILL TAKE ALL
NECESSARY SAFETY PRECAUTIONS.
2. SAW CUT AND RETAIN DITCH. DITCH TO RECEIVE ONLY CRACK AND POTHOLE
REPAIR AND SEAL COAT APPLICATION.
3. EXPOSE AND CLEAN AREA AROUND STORM SEWER GRATE. REPAIR AND GRADE
ASPHALT TO PREVENT PONDING OR SEEPAGE.
4. ROAD–LOOP JUNCTION SHALL BE PERPENDICULAR TO THE ROADWAY TO
MEET THE WEST CORNER OF THE QUARTERS DRIVEWAY.
FIGURE 2. ROUTE #010 ROAD FACING SOUTH
FIGURE 3. ROUTE #010 SPEED BUMPS
FIGURE 4. JUNCTION BETWEEN ROUTE #010 AND
ROUTE #900
FIGURE 5. ROUTE #010 GATE ACCESS LOOPS
FIGURE 6. JUNCTION BETWEEN ROUTE #010 AND
NORTH MAIN AVENUE
FIGURE 7: ROUTE #010 LOOP FACING NORTH
FIGURE 8. JUNCTION BETWEEN ROUTE #010 ROAD
AND ROUTE #010 LOOP
FIGURE 9. JUNCTION BETWEEN ROUTE #010 LOOP
AND ROUTE #901
FIGURE 10. ROUTE #010 DITCH
FIGURE 11. ROUTE #010 DITCH GRATE
2 VISITOR PARKING (ROUTE #900)
FIGURE 12. STATUS ASSESSMENT FOR ROUTE #900
COMPONENT #900
SURFACE PREPARATION N/A
CRACK AND POTHOLE REPAIR ✔
TACK COAT N/A
ASPHALT PAVING AND COMPACTION N/A
SEAL COAT ✔
THERMOPLASTIC MARKINGS ✔
FIGURE 13. JUNCTION BETWEEN ROUTE #900 AND
ROUTE #802
FIGURE 14. JUNCTION BETWEEN ROUTE #900 AND
ROUTE #802
3 OVERFLOW PARKING (ROUTE #901)
FIGURE 15. STATUS ASSESSMENT FOR ROUTE #901
COMPONENT #901
SURFACE PREPARATION SCARIFY
CRACK AND POTHOLE REPAIR ✔
TACK COAT ✔
ASPHALT PAVING AND COMPACTION 2-IN
THERMOPLASTIC MARKINGS N/A
ROUTE #901 NOTES:
1. PATCH AND REPAIR CRUMBLED PAVEMENT ON WEST EDGE ALONG FENCE.
FIGURE 16. ROUTE #901 FACING EAST
FIGURE 17. ROUTE #901, FACING WEST
FIGURE 18. JUNCTION BETWEEN ROUTE #901 AND
ROUTE #010
4 MUSEUM PARKING (ROUTE #902)
FIGURE 19. STATUS ASSESSMENT FOR ROUTE #902
COMPONENT #902
SURFACE PREPARATION SCARIFY
CRACK AND POTHOLE
REPAIR ✔
TACK COAT ✔
ASPHALT PAVING AND
COMPACTION 2-IN
THERMOPLASTIC MARKINGS ✔
ROUTE #902 NOTES:
1. GRIND OR REMOVE STUMP AND PROVIDE MISSING OR INADEQUATE BASE
MATERIAL AS NEEDED.
2. ENSURE ADEQUATE SLOPING TO PREVENT PONDING ON PARKING AREA OR
LOOP AND SUPPORT DRAINAGE AWAY FROM THE RETAINING WALL.
FIGURE 20. ROUTE #902 STUMP AND OVERGROWTH
FIGURE 21. ROUTE #902 RETAINING WALL
5 GENERAL NOTES
1. Retain 50-CY of millings (D100 between 0.75-IN and 1-IN), equally dispersed between two designated onsite stockpile areas [FIGURES 1–2]. Haul remaining millings offsite for safe and legal disposal, reuse, or salvage.
2. Pavement marking layout requirements [TDOT §716] to be provided by USFWS COR and to be approved via submittal prior to application.
3. A total of seven (7) full-depth core samples shall be collected and tested from the completed asphalt overlay for thickness and in-place density by an independent testing agency arranged by the Contractor and then patched once completely dried.
Testing locations will be determined by the COR at time of testing.
4. Contractor is responsible for the mix design. Prior to any construction, the mix design shall be submitted to and accepted by the USFWS COR.
5. All weight tickets shall be provided to the USFWS onsite representative.
Figure 22. South Stockpile Area
Figure 23. North Stockpile Area
– END OF WORK PLAN FOR CONSTRUCTION SERVICES –
SPECIFICATIONS FOR CONSTRUCTION PROJECTS
DIVISION 01
GENERAL REQUIREMENTS
U.S. FISH AND WILDLIFE SERVICE
SOUTHEAST REGION (4)
VERSION: DECEMBER 2025
01 11 00 SUMMARY OF WORK
A. The Contractor shall furnish all labor, equipment, materials, and supplies necessary to result in fully complete and usable systems and facilities. The Contractor shall bring any discrepancies to the attention of the Contracting Officer (CO) during tendering. Failure to notify the CO of any discrepancies during tendering shall be the responsibility of the Contractor during construction.
B. The Contractor shall not take advantage of any apparent error, omission, discrepancy, or ambiguity on the Statement-of-Work or any other Solicitation Documents. If any error, omission, discrepancy, or ambiguity is found by the Contractor in the Drawings or Specifications, the Contractor shall immediately refer the same to the CO prior to beginning Work on affected task(s), for interpretation and decision via Request-for-Information (RFI), and such decision shall be final.
C. The CO shall have the right to correct apparent errors or omissions in the Statement of Work and to make such interpretations as they may deem necessary for the proper fulfillment of the Contract Documents. During the course of the Work, should any party discover any unaddressed conflicts, ambiguities, or discrepancies between the Drawings and the Specifications to which the Contractor has failed to call attention prior to submitting the offer, then the CO will interpret the intent of the Drawings and Specifications and the Contractor hereby agrees to abide by the interpretation of the CO and agrees to carry out the Work in accordance with the decision of the CO. In such event, the Contractor will be held to have included in the offer the most expensive material and/or method of construction.
D. Schedule of Items
1. Base Bid Tasks shall be included at Contract Award.
2. Option Bid Tasks may be exercised at the time of award or during the Contract Period of
Performance.
3. The price of any necessary ancillary Work (any trade) shall be included as incidental to the price offered for the principal price line(s) listed in the solicitation.
4. The solicitation may include multiple Work Items (price lines), and the USFWS reserves the right to award any (or any combination of) Work Items to the extent of available funds.
E. Unless otherwise stated, the Contractor shall be solely responsible for carrying out all tasks, duties, and obligations specified throughout the General Requirements in fulfillment of the Work.
01 11 10 INSTRUCTIONS
A. Provide a written Action Plan for Demolition, Disposal, Recycling, and Construction Activities, which shall be approved by the CO and the COR before any demolition, disposal, recycling, and construction activities can begin in the area in its entirety. Demolition, disposal, recycling, and construction activities on the Station shall be coordinated with the Station Manager.
B. The procedures, means, and methods of construction are solely the responsibility of the Contractor, and the Contractor may choose any that follow general best practices and are calculated to secure results that satisfy the requirements of the contract; however, this is subject to the right of the CO to reject means and methods proposed which, in their opinion:
1. Constitute a hazard to the Project, Work, persons, or property.
2. Will not produce finished Work in accordance with terms of the Contract.
3. Are contrary to specified means or methods included in the Contract.
C. Unless directly specified in the Solicitation Documents, the Government shall not provide or furnish any products, labor, equipment, materials, utilities, or security.
01 11 20 PRE-OFFER BID MEETING
A. Pre-Offer Bid Meeting: Refer to Solicitation for scheduled meeting day and time.
01 11 25 INQUIRIES
A. Questions shall be directed to the CO; refer to Solicitation.
01 11 30 SPECIAL NOTICES
A. Period of Performance: Refer to Solicitation.
B. Comply with Davis-Bacon Wage Rates and Buy American. The Contractor shall ensure employees and
Subcontractors are paid on time according to a predetermined pay period or pay schedule. The pay period or pay schedule shall be mutually agreeable between the Contractor and its employees and/or Subcontractors.
C. The Contractor or the Contractor’s designated representative (who will directly oversee the construction Work) shall attend a Preconstruction Meeting with the COR prior to mobilization onto the site. The Contractor or the Contractor’s designated representative shall be on site while any contract-related Work is in progress.
D. Remove and dispose of all demolition items in a legal manner off the USFWS property and in accordance with all Federal, State, and Local Regulations.
01 11 40 WORK RESTRICTIONS
A. Accomplish the Construction Work in a manner that does not interfere with ongoing field station operations.
B. Habitat Restrictions: Wildlife habitat issues may restrict building seasons. The Contractor shall coordinate with the COR and the Station Manager for requirements.
C. Work Hours: Unless otherwise specified, onsite construction Work shall be conducted during normal business hours of operation for that facility, except on Federal holidays, unless approved otherwise.
Requests to change working hours shall be submitted in writing to the CO at least 48 hours in advance.
D. Site Access: The Contractor shall have limited use of premises for construction operations during the construction period. The Contractor's use of premises is limited by the need of the USFWS for uninterrupted operations and the right to perform Work in affected areas.
1. Use of Site: Limit use of Project site to areas indicated within the Contract limits or approved of by the Contracting Officer (CO). Do not disturb portions of Project site beyond areas in which the Work is indicated.
2. Time Log: The Contractor shall submit a log recording the time of entrance and time of exit of all personnel, including any Subcontractors and Suppliers.
3. Condition of Existing Building: The Contractor shall maintain portions of existing buildings affected by construction operations in a weather-tight condition throughout construction period. The Contractor shall repair damage caused by construction operations.
E. Housing for Workers and campsites are not available on site unless explicitly indicated otherwise in the Task Order.
F. Government buildings and other facilities are not available for storage of the Contractor’s materials, equipment, or tools. Government-owned equipment is not available for the Contractor’s use to accomplish any Work.
G. Existing Utility Interruptions:
1. Maintain in operating condition all active utilities servicing other facilities.
2. Repair any damage to active utilities servicing remaining facilities.
3. All work will be in accordance with local, state and national building codes and local regulations governing the utility concerned.
4. Limit all service outages to a maximum of 4 hours unless written permission is obtained from the COR and the Station Manager.
5. Do not interrupt utilities serving facilities occupied by the USFWS or others, unless having arranged to provide temporary utility services according to the requirements indicated and under the following conditions:
i. Notify the COR not less than 10 calendar days in advance of proposed utility interruptions.
ii. Do not proceed with utility interruptions without written permission from both the USFWS and the utility company.
01 20 00 PAYMENT PROCEDURES
A. No measurement of the Work shall be made unless unit prices are included in the Project.
B. Payment: Monthly payment shall be made for approved Work performed in accordance with the contract requirements under the items listed in the Schedule of Items and on the basis of the approved Schedule-of-Values.
C. Application for Payment:
1. Schedule of Values:
i. Prepare a Schedule-of-Values in the format (or approved equivalent format) of the USFWS Form E15.
ii. Submit a detailed Schedule-of-Values within seven (7) days prior to the start of onsite construction Work and shall format the Schedule-of-Values to match the Pricing Schedule and provide sufficient additional detail to allow accurate calculation of monthly progress payments.
2. Certified Payrolls: Submit certified payrolls to CO, current to within 1 week of payment application period.
3. Invoicing:
i. Submit the preliminary pay request to the COR via e-mail prior to uploading their pay request to the Internet Processing Platform (IPP) Website (https://www.ipp.gov/). The pay request shall include a Schedule-of-Values with percentage of Work completed.
https://www.ipp.gov/
ii. The COR will return a signed and approved invoice to the Contractor, who shall upload it into IPP.
01 31 00 PROJECT MANAGEMENT AND COORDINATION
A. The Government Standard Forms, specifications, associated plans, solicitation provisions, and contract clauses made a part of the contract are essential parts thereof; the requirements in one are as binding as though contained in all. They are intended to be mutually supplementary to describe and provide for a completed Project.
1. The provisions of Government Standard Forms shall govern in cases of conflict with specifications, contract provisions, and supplemental agreements forms. In all cases of dispute, the CO shall decide which part or parts of the specifications apply to any given parts of the Work with respect to such conflict.
B. Coordination
1. Coordinate scheduling, submittals, and Work of the various sections of specifications to ensure efficient and orderly sequence of installation of interdependent construction elements.
2. Verify that utility requirement characteristics of operating equipment to be delivered in the
Work are compatible with building utilities.
3. Provide field surveying to accurately establish the horizontal and vertical locations of the Work.
C. Government-furnished drawings shall not be scaled to obtain missing or conflicting dimensions. The Contractor shall monitor dimensions and details throughout the progression of the Work. Any errors or discrepancies discovered shall be promptly reported to the COR.
D. Accomplish construction Work in a manner that does not interfere with ongoing station operations, nor allow any construction material, soil, or debris to enter waters of the State.
E. Record Drawings and Specifications: Maintain one set of working drawings and specifications, for record purposes, on the project site while work is in progress. Clearly and accurately record the as-constructed work in red. Record swing-tie distances from permanent points for all underground items. Include modifications and RFIs.
01 31 10 CONTRACT ADMINISTRATION
A. Authority of the COR is limited to the following functions:
1. Inspect, and either accept or reject Construction Work and Materials, including approval or disapproval of materials, submittals, and shop drawings.
2. Ensure compliance with technical contract terms and conditions.
3. Clarify specifications and drawings in which clarification would not result in modifications of contract cost or time. Any resulting disagreements are to be immediately referred to the CO.
4. Verify and recommend payment estimates on progress payments and forward progress payments to the CO for approval.
5. Enforce safety requirements in accordance with the Federal Acquisition Regulations (FAR), OSHA regulations, and any applicable Solicitation Documents and USFWS policies.
6. The COR may perform any duties of the Inspector in Section D.
B. The COR is not authorized to take the following actions, all of which remain the sole responsibility of the CO:
1. Make any changes to the contract provisions, period of performance, or contract terms and conditions.
2. Make decisions concerning any claims and disputes.
C. The COR shall immediately notify the CO of any problems encountered, including, but not restricted to, maintaining completion schedules.
D. Authority of the Inspector: An Inspector employed by the Government may assist the COR in observing the Work, obtaining measurements, and enforcing strict compliance with the terms and conditions of the Contract.
1. The Inspector shall have free access to the jobsite at all times while construction Work is in progress, and the Contractor shall furnish such information and assistance as is necessary.
2. The Inspector shall record the construction Work accomplished.
3. Unsuitable materials or construction Work that does not comply with the terms and conditions of the contract may be rejected by the CO as a result of inspections.
4. The Inspector shall observe and ensure construction is performed in conformance with the contract health and safety requirements.
5. The Inspector shall conduct wage rate interviews and report suspected labor standard violations to the CO.
6. The Inspector shall check and verify the progress payment requests.
E. Do not initiate extra work without written notification to the CO and the COR and receiving written approval in response from the CO.
01 31 20 PERFORMANCE OF WORK BY THE CONTRACTOR
A. Provide the COR all reasonable facilities for obtaining information respecting the character of the materials and progress of the Work. Furnish information to include the number of Workers employed, their pay rate, time worked, and other elements of cost requested by the COR. No personal information from personnel should be included for PII purposes.
01 31 30 GENERAL TECHNICAL REQUIREMENTS
A. Perform the Work in accordance with all Contract documents, including but not limited to drawings and technical specifications, and all provisions of the Contract.
B. The Contractor shall field-verify and validate dimensions, elevations, and Project area features before commencing construction. The Contractor shall promptly notify the CO and the COR of any conflicts upon discovery.
C. The Contractor shall maintain a General Contractor licensure, or equivalent depending on the scope of the work, in the State in which the Project is located.
D. Comply with all State requirements for licensure in the State in which the Project is located.
E. Maintain on staff a Professional Engineer or Professional Architect licensed in the State in which the
Project is located.
F. All Work of each trade must be overseen by individuals licensed and/or certified in that trade in the
State in which the Project is located.
G. Welding shall be performed only by licensed welders and in compliance with American Welding Society
(AWS) recommended practices. Welds shall have structural integrity and be neat in appearance.
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION
A. Weekly Construction Reports: Submit weekly to COR, to include:
1. Construction Daily Reports: For the Duration of the Construction Contract, submit a
Construction Daily Report for each Work Day, which includes the Contract Number, Title and Location of Project, Report Number, Contractor Designation, Subcontractor Designation, Superintendent Designation, Morning Weather Description, Afternoon Weather Description, Maximum Daily Temperature, and Minimum Daily Temperature. Also, include the Day’s Scheduled Activity Number(s), Work Location(s), Work Description(s), Employer(s), Number of Worker(s), Trade(s), Number of Work Hour(s), Work Item(s) Completed, and Job Safety Checklist(s). The Contractor may include additional entry fields on their Construction Daily Reports at their own discretion.
2. Site Observation and Inspection Reports: For the Duration of the Construction Contract, prepare and submit Site Observation and Inspection Reports for each Work Day. Site Observation and Inspection Reports shall be prepared and submitted by the Third Party Testing Company under Subcontract to the Contractor. Where necessary, the Contractor will take corrective actions if the Inspection Company notes any deficiencies.
3. Provide daily activity logs and checklists to record daily activities and submit them weekly to the CO and COR.
4. Provide construction photographs of the Work on a weekly basis and a final set of photographs after date of Substantial Completion and all temporary structures have been removed.
5. Time Logs as per §01 11 40 (D) (2).
B. Schedule:
1. Submit an initial schedule at the Preconstruction Meeting.
2. Develop schedule on commercially available computer scheduling software.
3. Provide schedule showing Work breakdown structure or precedence diagram.
4. Identify day, date, duration, and float for each Work activity.
5. Break down activities by skillset or trade and by geographic location within Work
6. Identify all interfaces with Government that may impact schedule. Keep Government interfaces away from critical path to maximum extent practical.
7. Promptly update schedule to reflect any changes or delays in the Work.
8. Provide 3–4 week look-ahead Schedules. Update Schedule monthly and submit to the COR.
Coordinate activities with Station Manager.
C. Project meetings
1. Preconstruction Meeting: COR will arrange a Preconstruction Meeting prior to start of any construction. Require attendance by all parties affected by the Work. Take and distribute meeting notes to all affected parties.
2. Progress Meetings: Coordinate progress job meetings as required by the progress of the Work and shall require attendance by all parties affected by the Work.
3. Record and distribute meeting notes to all affected parties. Notes shall be distributed within 72 hours of meetings.
01 33 00 SUBMITTAL PROCEDURES
A. Master Submittal List: Submit comprehensive submittal register identifying all submittals required.
Submit register at Preconstruction meeting. Identify each submittal by title and appropriate specification section along with responsible party to review and approve. Sequentially number each submittal.
B. Electronically transmit submittals with the Government-furnished Submittal Form 4-18 that will also be used as the document for approving or disapproving submittals. Government shall furnish R1-67 in Word format for use. Submit R1-67 form in Word format for transmittal sheet of each submittal. Obtain written approval before items are ordered. Use a separate R1-67 form for each broad category of material to avoid confusion should a re-submittal be necessary.
C. Submit all submittals to the COR, viewed and signed by the Contractor, indicating they comply with the contract requirements. Submittals without the Contractor’s signature will be returned without action.
D. Submittals shall contain detailed product literature, shop drawings, material samples, and/or finish samples fully describing the items proposed for installation.
E. Conspicuously mark the item submitted to explicitly indicate the specific options, models, mechanical/electrical characteristics, trim styles, colors, sizes, etc. Annotate the submittal to cross reference to the mark numbers/group numbers shown on the drawings and/or specification.
F. Tab and index submittals containing more than ten pages.
G. Explicitly and clearly indicate all features that differ from the contract requirements.
H. Submittals will be returned to the Contractor within 21 calendar days of the date received by the COR.
I. Submit documentation for all products, materials, and equipment proposed for use.
J. Material Certifications:
1. Submit manufacturer’s certificate indicating that the material or product conforms or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
2. Certificates may be recent or previous test results on material or product but must be acceptable to the COR.
K. Samples:
1. Submit exact product or material to be used.
2. Submit product sample of size specified and of sufficient size to clearly show the characteristics, integral parts, and attachment of the product or system.
3. Submit interior and exterior color and texture samples at one time for coordinated review by the COR.
L. Submittal reviews by the Government do not waive or alter the contract requirements. Submittal acceptance is not Government certification of materials or products. Any deviation from the contract requirements must be specifically brought to the attention of the CO and the COR in writing and upon the drawings, or by appropriate change order.
01 34 00 BASELINE SUBMITTAL LIST
A. Descriptive Product Literature: Provide Descriptive Product Literature for the principal components of any trade Work. See also individual design drawings and technical specifications for specific requirements.
B. Progress Schedule: Submit the proposed progress Work schedule for approval within 15 days after award of contract. Itemize each principal component/phase of Work and the calendar days of anticipated performance. Submit a revised schedule any time the actual Work progress delays the scheduled time by more than 14 calendar days.
C. Schedule of Values: Submit a detailed Schedule-of-Values within 7 days prior to the start of onsite Work.
Format the Schedule-of-Values to match the Schedule-of-Items and show sufficient additional detail to allow accurate calculation of monthly progress payments. Lump sum items shall be broken down into their component parts as applicable with a cost shown for each, such as mobilization, bond and insurance, and the principal components of the Work.
D. Subcontract List: Submit each proposed Subcontractor on a SF 1413 (Statement and Acknowledgment) in accordance with Paragraph (d)(1) of FAR Clause 52.222-11. SF 1413s within 14 days after award of the contract.
E. Key Personnel Names: Within 14 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list work addresses, telephone numbers, and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Project Superintendent with a minimum of five (5) years of experience in coordinating Subcontractors in the construction industry.
F. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience; include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
G. Permits, Licenses, and Certificates: Submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
H. Quality Control Plan (QCP): Prepare and submit a Quality Control Plan (QCP). Provide delineation of Laboratory and Institute (Onsite) Tests and Inspections to be performed by the Contractor’s Independent Testing Agency under Subcontract. Refer to Technical Specifications for Scope and Quantity of Tests and Inspections required for the Project.
1. Refer to General Requirements Division 1, Section 01 44 00 Testing and Inspection and related Technical Specifications for specific requirements.
I. Quality Control Test Reports: For the Duration of the Construction Contract, perform Quality Control Tests and prepare and submit Quality Control Test Reports for each material to be provided and installed.
J. Close-Out Documents: Submit documents listed in Specification 01 78 00.
01 35 00 SPECIAL PROCEDURES
A. Immediately stop Work and notify the Inspector, the COR, and the CO if paleontological, archaeological, or historical remains, including burials or skeletal material, are encountered. The CO will notify the Regional Archaeologist so that the provisions of the National Historic Preservation Act, 16 USC 470f, 54 USC 306108, 36 CFR 800, and other relevant laws, regulations, and standards are followed. Work will cease in the immediate vicinity until permitted to resume by written order from the CO. Work in other areas may proceed as approved by the Regional Archaeologist.
B. Site Safety:
1. The Contractor is responsible for safety on the Project site at all times, from issuance of the
Notice to Proceed until final completion and acceptance of the Work by the CO.
2. The Contractor is responsible for ensuring that all onsite activities, equipment, and facilities constructed by the Contractor, Subcontractor, or Supplier conform fully to the Department of Labor, Occupational Safety and Health Administration (OSHA) standards 29 CFR 1910 (Occupational Safety and Health Standards) and 29 CFR 1926 (Safety and Health Regulations for Construction); and any applicable the DOI policies and the USFWS policies.
3. Adhere to all current Federal, State, and Local safety requirements. In the event where any safety standard referenced herein conflicts with another, the more stringent shall govern.
4. Prepare and submit a Site-Specific Safety Plan, a Job Hazards Analysis (JHA), and a Health and Safety Plan (HSP) that is to include detailed Project data provisions for the identification, evaluation, prevention and control of general Work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods, conditions, and Site conditions, as well as providing a competent person to conduct frequent and regular inspections.
5. Initiate and maintain, throughout the performance of this contract, an effective safety program that provides adequate policies, procedures, and practices to protect their employees from, and allow them to recognize, job-related safety and health hazards.
6. Each employee of the Contractor and all Subcontractors must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the Work environment.
7. Where Work affects transportation assets, provide traffic control conforming to the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD) as published by the US Department of Transportation, Federal Highway Administration as necessary to safeguard the Public, Workers, and Government personnel, to include:
i. Furnishing, transporting, and installing barricades, warning signs, and delivery truck routing signs.
ii. Furnishing, transporting, and installing traffic control devices, such as cones, drums, flashers, barricades, and signs to safely channel or direct traffic.
iii. Flag persons in conjunction with traffic control devices when necessary.
8. Unless otherwise specified, buried utilities have not been located by the Government. The
Contractor shall have all underground hazards and utilities investigated and located prior to construction and shall protect all utilities throughout the Work. Notification of effected utility companies is the responsibility of the Contractor.
C. Hazardous Materials: The proposed Work areas are believed not to contain any materials regulated as “hazardous” or similar designation. However, immediately stop Work and notify the COR in writing should any unknown hazardous materials be encountered.
01 40 00 QUALITY REQUIREMENTS
A. The Contractor shall be responsible for Quality Control (QC), but such authority may be delegated to Subcontractors or construction managers to ensure the construction process and final product meet specified standards. QC involves on-site inspections, material testing, and monitoring workmanship to identify and address defects or issues promptly. The Contractor and Subcontractors are responsible for detecting and rectifying deficiencies to prevent any compromise to the overall quality of the Project.
Detailed records of inspections, observations, corrective actions, and completion must be maintained throughout the QC process.
1. The Contractor is responsible for ensuring the overall quality of all its own Work and the Work performed by their Subcontractors under this contract.
2. All Work performed must meet or exceed the standards outlined in the technical divisions of this specification.
3. If the CO identifies Work that does not comply with the specifications or drawings, the Contractor will be notified in writing of the nonconformance. The Contractor must correct the deficiencies and provide the CO with written documentation of the corrective actions taken within seven (7) calendar days.
4. Supervision: During all onsite Work, maintain onsite at least one qualified Project Manager or Project Superintendent with a thorough understanding of the Project and capable of reading, write, and conversing fluently in the English language.
B. Noncompliance with Quality Control Requirements: Failure of the Contractor to comply with the above requirements may be cause for Termination-for-Default.
C. Quality Control Procedures:
1. Monitor quality control over the Contractor staff, Subcontractors, Suppliers, manufacturer's, products, services, site conditions, and workmanship.
2. Comply fully with manufacturer's published instructions, including each step-in-sequence of installation.
3. Request clarification from CO before proceeding if manufacturer's published instructions conflict with Contract Documents.
D. Comply with specified standards as a minimum quality for Work, except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Perform Work by persons who are thoroughly qualified and trained in their respective trade, to produce workmanship of specified quality.
F. Perform tests required by governing authorities and utilities having jurisdiction.
G. Maintain check-off list of Work that does not comply with Contract Documents, stating specifically what is non-complying, the date on which faulty Work was originally discovered, and the date on which faulty Work was corrected. There is no requirement to report deficiencies corrected same day it was discovered. Submit copy of Non-Compliance Check-Off List of non-complying Work items to CO on a weekly basis.
H. Prior to final acceptance by CO, submit a certification signed by the Contractor to the CO stating that all Work has been inspected and all Work, except as specifically noted, is complete and in compliance with Contract Documents.
01 41 00 REGULATORY REQUIREMENTS
A. Regulatory Requirements:
1. Comply with all applicable Federal, State, and Local environmental laws, regulations, and standards, including but not limited to the Federal Acquisition Regulation (FAR) and those related to building design and construction, noise levels, air and water quality, and cultural resources.
2. Design and construct in accordance with all applicable Federal, State and Local codes and regulations (latest edition at the time of contract award), with the following establishing the minimum requirements:
i. International Building Code
ii. National Fire Protection Association (NFPA) 101 Life Safety Code
iii. National Electrical Code
iv. International Plumbing Code
v. International Mechanical Code
vi. ASHRAE Handbook of Fundamentals
vii. ASHRAE/IENSA 90.1 - 2016 Energy Standard for Buildings.
viii. ASHRAE Standard 55-2017, Thermal Environmental Conditions for Human Occupancy
ix. ASHRAE 62.1 -2016 Ventilation for Acceptable Indoor Air Quality
x. AASHTO Policies and Guidelines for the Design of Highways, Streets, Pavements, and
Roadside Safety
xi. OSHA Regulations (Federal and State)
xii. Consumer Product Safety Commission 16CFR 1201 Safety Standards for Architectural
Glazing Materials
xiii. Clean Water Act
xiv. Architectural Barriers Act (ABA)
xv. Americans with Disabilities Act (ADA) Accessibility Guidelines
xvi. American Welding Society Standards
xvii. American Concrete Institute Codes
xviii. American Institute of Steel Construction Manual
xix. American Society of Civil Engineers Design Loads on Structures During Construction
xx. Portland Cement Association Design and Control of Concrete Mixtures
xxi. US DOT FHWA Manual on Uniform Traffic Control Devices for Streets and Highways
xxii. U.S. Fish and Wildlife Service Prescriptive Specifications
3. The more stringent code provision(s) shall govern in any conflict between code provisions. In any instances where the Design Drawings and Technical Specifications do not specify explicit materials or methods, the Contractor shall perform the Work in accordance with the minimum requirements of the code applicable to the Work.
4. Failure of this document to provide all applicable codes does not absolve the Contractor from such requirement. It is the responsibility of the Contractor to identify and apply all applicable codes to the Work.
B. Permit Responsibility:
1. Customary mechanical and electrical trade permits may be required. The Contractor shall arrange for, obtain, and pay for any customary mechanical and electrical trade permits and licenses.
2. Include fees for items above as a line item in the Schedule-of-Values.
3. The Contactor shall obtain natural resource permits associated with in-stream Work.
4. The Contractor is solely responsible for paying any fees, permits, inspections, taxes, and similar associated with the Work, unless otherwise specified.
01 42 00 REFERENCES
A. Acronyms
1. United States Fish and Wildlife Service, U.S. Fish and Wildlife Service, USFWS, US FWS, US
FWS, FWS, Owner, Government, and Service, are all intended to mean:
ATTN: Scott Gronbach (NWRS/IMB)
United States Fish and Wildlife Service, Southeast Region (4) 1875 Century Boulevard NE, Suite 222 Atlanta, GA 30345
2. CO: Contracting Officer
3. COR: USFWS Contracting Officer’s Technical Representative
4. JAO: Joint Administrative Operations
5. DOI: Department of the Interior
6. D/B: Design–Builder or Design–Build entity
7. FF&E: Furnishings, Fixtures, and Equipment
8. NWR: National Wildlife Refuge
9. NWRC: National Wildlife Refuge Complex
10. NFH: National Fish Hatchery
11. NFHC: National Fish Hatchery Complex
12. RFI: Request-for-Information
B. Definitions
1. Work: Includes all necessary management, fees, assessments, ancillary or required design, permitting, construction, and other services required by the Contract Documents, including procuring and furnishing all materials, equipment, services, labor, and labor superintendence reasonably inferable from the Contract Documents.
2. Work is comprised of costs to design and construct the Project or portion of the Project in accordance with the contract documents.
3. Project: Cumulative effort of all Work to be completed on behalf of the U.S. Fish and Wildlife Service, which may include one or multiple Scopes of Work.
4. Allowance(s): A specific monetary sum included in the basic contract amount for a contract element that is undefined. Allowance includes all labor, materials, incidental expenses, taxes, and contractor markups for incorporation of the element into the Project. Should the allowance amount exceed the actual cost, savings will accrue to the USFWS. Should the allowance not cover the cost, an equitable contact modification may be issued.
5. Authority Having Jurisdiction: Infrastructure Management Branch, Region 4, United States Fish and Wildlife Service
6. Industry Standard: A reference standard that establishes a level of quality, performance, or other characteristic of a material or system.
7. Local Authority Having Jurisdiction: Duly adopted Local code authority, agency, or serving utility governing or serving the location of the Project.
8. Remove and Replace (RR): Remove existing component or assembly and replace in kind with new materials of same type, design, quality, and operating characteristics.
9. Remove and Salvage (RSALV): Remove component, equipment or assembly intact and turn over to Government for their use.
10. Refurbish (RFR): Restore component, equipment, or assembly “as new”. Refurbishing includes, but is not limited to, cleaning, restoring finishes, making inoperable items operable, rewiring, relamping, custom manufacturing unavailable parts, and replacing missing parts. If necessary for refurbishment, remove component, equipment, or assembly intact, refurbish, and reincorporate it into the Project.
11. Remove and Reinstall (RSR): Remove component, equipment, or assembly intact. Store and protect removed items, and reincorporate them into the Project in same condition prior to removal.
12. Unit Price: Establishment of a price based on a per unit basis or task basis for Work to be provided in the Project. Unit prices will be good for the duration of the Project. Quantities will be measured and only actual quantities installed will be paid for. Unit prices should include all costs, including taxes and fees, for furnishing and installing into the Project. When unit prices are within 10% of estimated amounts, the initial unit price will be valid. When unit price quantity exceeds 10% of estimated amounts, unit price may be renegotiated.
01 45 23 TESTING AND INSPECTION
A. Subcontract and pay for services of an independent third-party testing agency or laboratory acceptable to the USFWS to perform specified testing.
1. Prior to start of Work, submit name, address, and telephone number of testing laboratory, and the names of the full-time specialist(s) and the responsible officer. Submit copy of report of laboratory facilities inspection made by Materials Reference Laboratory of National Bureau of Standards during most recent inspection, with memorandum of remedies of deficiencies reported by inspection.
B. The independent firm will perform tests, inspections and other services specified in individual specification sections and as required by AHJ.
1. Laboratory: Authorized to operate in the State in which the work is being performed.
2. Laboratory Staff: Maintain full time specialist on staff to review services.
3. Testing Equipment: Calibrated at reasonable intervals with devices of an accuracy traceable to
NIST or accepted values of natural physical constants.
C. Testing, inspections, and source quality control may occur on or off Project site, as appropriate. Perform testing as required.
D. Reports will be submitted by independent firm to the USFWS, the Contractor, and local authority having jurisdiction, indicating observations and results of tests, and indicating compliance or noncompliance with…