Attch1_SOW_BobcatCreekFence-Phase1.pdf

PDF 2 MB Posted

Attached to
MT-CHARLES M RUSSELL NWR-FENCE
Solicitation number
140FGA26Q0034
Issued by

About this file

This is a Solicitation for a fence construction project at Charles M. Russell National Wildlife Refuge in Montana. The contract number is 140FGA26Q0034, issued June 11, 2026.

The U.S. Fish and Wildlife Service requires comprehensive fence work on the Bobcat Creek Habitat Management Unit, including approximately 1.6 miles of new boundary fence construction, 1.8 miles of old fence removal and replacement, 2 miles of fence modification (replacing bottom barbed wire with smooth wire), and 9 miles of complete fence removal. All new fence construction must consist of four strands with the top three strands as barbed wire and the bottom strand as barbless wire. The contractor is fully responsible for all personnel, equipment, supplies, materials, transportation, tools, and supervision necessary to complete the work. The project must start as soon as possible after notice to proceed with completion required by June 30, 2027. The work site is located on Bobcat Point near Fort Peck, Montana, in McCone and Garfield Counties. Site visits are encouraged; prospective bidders may contact the CMR Fort Peck Field Station at 406-526-3464, extension 201 during normal business hours (Monday-Friday, 7:00 a.m. - 4:30 p.m.).

Construction specifications detail precise installation requirements: T-posts spaced at 1 rod (16.5 feet) intervals with allowable deviations of 6 inches except where topography requires closer spacing; wire heights at 18, 24, 30, and 42 inches above ground level with maximum 2-inch deviations; corner, end, and stress panels constructed with steel tubing; and gate construction using steel tubing instead of wood. All old fence materials, including wire, posts, braces, hardware, and debris, must be removed and disposed of at approved off-site locations. The contractor must clear fence lines of trees and brush to a maximum of 4 feet on each side while minimizing disturbance to existing vegetation. Final completion requires on-ground inspection by refuge personnel to verify compliance with specifications, proper gate function, and restoration of disturbed areas.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

June 11, 2026

140FGA26Q0034

1 | P a g e

U.S. Fish and Wildlife Service

Charles M. Russell National Wildlife Refuge Bobcat Creek Boundary Fence Construction

Location: Work is located on the Charles M. Russell National Wildlife Refuge (CMR) in McCone and Garfield Counties, State of Montana. Prospective bidders may inspect the site by contacting the CMR Fort Peck Field Station, 270 MT Hwy 117. Telephone 406-526-3464, ext.

201. Normal duty hours for Refuge staff is Monday thru Friday 7:00 a.m. - 4:30 p.m. Work location is shown on attached map.

Contractors are urged to visit the work site and become familiar with existing conditions.

Failure of the contractor to ascertain the nature, location, and conditions which will affect the work will not relieve them from the responsibility of successfully performing the requirements of the contract without additional expense to the U.S. Fish and Wildlife Service.

Description of work: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to construct, modify, and remove boundary and interior fence in the Habitat Unit referred to as Bobcat Creek Habitat Management Unit.

Project includes approximately 1.6 miles of new boundary fence construction (where fence doesn’t currently exist), 1.8 miles of old fence removal/replace with new, 2 miles of fence modification (replace bottom barbed wire with smooth wire), and 9 miles of complete fence removal, (see attached map). The fence is generally located on Bobcat Point near the town of Fort Peck, MT.

Construction of new fence will be with 4 strands; the top 3 wires will be barbed wire and the bottom wire will be barbless. The Contractor is responsible for removing all old fence materials, including wire, wood posts, braces, hardware, and associated debris, and disposing of materials at an approved off-site disposal location.

Period of Performance: Project will start as soon as possible after notice to proceed with completion of project by June 30, 2027.

Job conditions: Fence lines traverse terrain that may be wet, muddy or uneven. There are numerous drainages, both small and large, rises and falls, loose, rocky and compacted soil. Access can be limited by weather as roads are often impassable when wet.

The contractor will, if necessary, clear fence lines of trees, brush, and other obstructions large enough to hinder construction operations. Fence lines may be cleared to a maximum of 4 feet on each side of the fence. On interior fence lines where there is U.S. Fish and Wildlife Service (USFWS) Federal land on both sides, clearing may be done on either or both sides of the fence.

On boundary fence lines where there is USFWS Federal land on only one side, clearing may only be done on the USFWS Federal land side. Existing grass, sod, and other vegetation shall be disturbed as little as possible.

2 | P a g e

Construction Specifications:

See Appendix 1 for further specifications.

General: T-Posts (Steel) shall not be used for end-panel, corner-panel, gate-panel, or stress-panel. Posts shall be installed plumb, to the designated depth, and the lateral alignment shall be within plus or minus ½ inch. T-Post spacing shall be 1 rod (16 1/2 feet) between posts. T-posts may only deviate 6 inches from the 1 rod spacing except (due to the topography of the ground) when closer spacing is needed to attain specified wire heights. Drive T-Posts into the ground until the anchor plate is slightly below the ground surface.

Corner Panel, End Panel, and Stress Panel Assemblies: All structures shall be constructed with steel tubing.

Wire: Fence shall consist of four (4) strands of wire at heights of 18 inches, 24 inches, 30 inches, and 42 inches above ground level. The bottom strand (18”) shall be barbless wire. The upper three strands (24”, 30” and 42”) shall be barbed wire. Stretch tightly and securely attach to steel post or structures. Wire shall be stretched to manufacturer-recommended tension sufficient to prevent sagging while maintaining elasticity. Terminate wire at each end post, gate post, corner post, or stress panel by wrapping around the post a minimum of two times and tie off by wrapping incoming wire a minimum of five times.

Wire Gates: Replace wood gate sticks with steel tubing.

Panel or dead man at minor depression: Dead man shall be constructed of barbless wire bent in two and wound around the three wires in the fence and attached to a full length steel post. The wire shall be wrapped around the steel post a minimum of 2 times, and then wrapped around itself a minimum of five times. The post shall be driven 4 feet underground at a 45-degree angle with 1-1/2 feet extended above ground level. In extreme conditions, two steel posts shall be used and shall be positioned opposite one another to form a 90-degree angle between the two posts for maximum holding power.

Deviations:

Line post may not deviate more than 6 inches on spacing, except closer when needed to achieve specified wire heights All posts shall not deviate more than 1 inch from plumb or specified height above ground Wire spacing may not deviate more than 2 inches from that specified The center of no post shall be more than 3 inches out of alignment between quarter-mile stakes set by government Splicing – Use wrap or telephone-type splice using at least five complete turns in each direction. Do not pull wire around corners

3 | P a g e

End Results/Deliverables: The Contractor will arrange an on-ground inspection with Refuge personnel to assure that the fence is constructed/modified according to the contract specifications, including materials and placement. The finished work should be sturdy with the posts secure, and all components properly installed. All gates shall be properly hung with hinges aligned and secure. Latches shall function without binding and allow secure closure. Upon completion of the project, the work area shall be free of rubbish and debris, and if there are any disturbed areas they be restored to their original condition. Contractor shall immediately notify Refuge personnel of any unstable soils, erosion features, or safety hazards encountered during construction that may require alignment adjustment.

4 | P a g e

Appendix 1. Construction Specifications

5 | P a g e

6 | P a g e

7 | P a g e

8 | P a g e

9 | P a g e

10 | P a g e

File details come from the government source that posted it. Updated .