This document contains a price schedule attachment for the RESER DAM RECONSTRUCTION federal contract opportunity. The schedule of items lists various construction tasks required for the project including mobilization, excavation, embankment, backfill, riprap, spillway work, and habitat restoration. Pricing is provided for unit costs and total costs for each line item. The total bid price is also included. The related federal contract opportunity notice identifies the solicitation number as 140L0621R0024 for the RESER DAM RECONSTRUCTION project issued by the Bureau of Land Management National Office within the Department of the Interior.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L0621R0024_Amd_0002.pdf | ||
| Attch_7_Amend_0002_Questions_Answers_0002.pdf | ||
| Attch_6_Amend_0002_Pre-Bid_Meeting_Attendees_Site_Tour_Notes_0002.pdf | ||
| Sol_140L0621R0024_Amd_0001.pdf | ||
| Attch_5_Amend_0001_Questions_Answers_0001.pdf | ||
| Attch_3_Wage_Determinations.pdf | ||
| Attch_2_RESER_DAM_DRAWINGS.pdf | ||
| Sol_140L0621R0024.pdf | ||
| Attch_1_RESER_DAM_TECHSPECS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reser BidSched
| RESER DAM RECONSTRUCTION |
| SCHEDULE OF ITEMS |
| Item | |||||
| No. | Description | Quantity* | 0 | Unit Price | Total Cost |
| 1 | Mobilization & Preparatory Work | 1 | LS | ||
| 2 | Topsoil Stripping & Replacement | 1 | LS | ||
| 3 | Outlet Demolition | 1 | LS | ||
| 4 | Common Excavation | 18,121 | CY | ||
| 5 | Muck Excavation | 1,500 | CY | ||
| 6 | Compacted Embankment | 15,695 | CY | ||
| 7 | Lime Amended Backfill | 2,494 | CY | ||
| 8 | Filter Sand | 556 | CY | ||
| 9 | Drain Gravel | 182 | CY | ||
| 10 | Road Gravel | 232 | Ton | ||
| 11 | Salvage and Replace Riprap | 1 | LS | ||
| 12 | New Riprap Slope Protection | 1,252 | Ton | ||
| 13 | Riprap Bedding | 2,830 | Ton | ||
| 14 | Riprap Outlet Basin | 1 | LS | ||
| 15 | Spillway Tower and Low-Level Inlet | 1 | LS | ||
| 16 | Outlet Conduit | 1 | LS | ||
| 17 | Stabilization Fabric | 500 | SY | ||
| 18 | Water Control/Dewatering | 1 | LS | ||
| 19 | Access Trails | 1 | LS | ||
| 20 | Boat Ramp | 1 | LS | ||
| 21 | Channel Excavation | 300 | CY | ||
| 22 | Spawning Bed Gravel | 500 | CY | ||
| 23 | Fish Structures | 401 | Ton | ||
| TOTAL BID | |||||
| Total Bid (words): |
| *Pricing offered must include all materials, equipment, supplies, appurtenances; all construction plant, equipment, and tools; all labor and supervision, profit and overhead necessary to fully complete the work. Bonds and insurance costs shall be included in the mobilization line item. |
| *All measured items are estimated and subject to contract clause 52.211-18 Variation in Estimated Quantity. |