This bid schedule is for a federal construction contract to build a 12th Street Detention Structure in Cleveland, Tennessee. The project involves building a concrete spillway and box culvert, constructing an earthen berm up to 10 feet high along both sides of the spillway, grading the upstream terrain with a 2% slope, installing a stilling basin downstream of the spillway, and armoring the downstream portion of the spillway with articulated concrete block for 25 feet to prevent erosion. The bid schedule lays out 12 line items with quantities and unit pricing for the work, including items for mobilization, traffic control, water control, cast-in-place concrete, seeding, excavation, fill, articulated concrete block, and turf reinforcement mat. Bidders will provide unit pricing for each item that will be used to calculate the total base task order price.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12th Street Detention Structure Cleveland, Tennessee

BID SCHEDULE

ITEM

NO. DESCRIPTION QTY. UNIT PRICE AMOUNT

0001 MOBILIZATION/DEMOBILIZATION 1 JOB $ - $ -

0002 TRAFFIC CONTROL 1 JOB $ - $ -

0003 WATER CONTROL 1 JOB $ - $ -

0004 CAST-IN-PLACE CONCRETE 1 JOB $ - $ -

0005 PERMANENT SEEDING 1 JOB $ - $ -

0006 PERMANENT SEEDING (BORROW SITE) 1 JOB $ - $ -

0007 EXCAVATION (12TH STREET) 1,600 CY $ - $ -

0008 FILL (FROM 12TH STREET MATERIAL) 1,400 CY $ - $ -

0009 EXCAVATION (BORROW SITE) 1,300 CY $ - $ -

0010 FILL (FROM BORROW SITE MATERIAL) 1,100 CY $ - $ -

0011 ARTICULATED CONCRETE BLOCK (ACB) 160 SY $ - $ -

0012 HIGH PERFORMANCE TURF REINFORCEMENT MAT (HP-TRM) 300 SY $ - $ -

BASE TASK ORDER TOTAL AMOUNT (CLIN's 0001 through 0012): $ -

BASE TASK ORDER

Page 1 of 2 PRICE SCHEDULE

12th Street Detention Structure Cleveland, Tennessee

BID SCHEDULE

Page 2 of 2 PRICE SCHEDULE

File details come from the government source that posted it. Updated .