Attch 2c UFGS 32 01 11.51 Runway Rubber Removal.pdf

PDF 92 KB Posted

Attached to
Rubber Removal and Paint Striping Federal contract opportunity
Solicitation number
FA441821R0008
Issued by
Department of the Air Force Air Mobility Command

View the file

Other files for this federal contract opportunity

Other files attached to Rubber Removal and Paint Striping, newest first.
File Type Posted
FA441821R0008 - PPQ - Rubber Removal.pdf PDF
20210809 Revised Schedule B Price Schedule.pdf PDF
Attch 2c UFGS 32 01 11.51 Runway Rubber Removal - Rev 20210809.pdf PDF
20210809 SOW - Statement of Work.pdf PDF
Sign in Sheet.pdf PDF
Solicitation Amendment FA441821R00080001 SF 30.pdf PDF
Q and A FA441821R0008 Rubber Removal and Paint Striping.pdf PDF
Solicitation - FA441821R0008 7.19.21.pdf PDF
Attch 2a UFC_3_260_04_2018 Airfield Markings.pdf PDF
Attch 2g JBCGS 01 57 19.00 31 Temporary Environmental Controls.pdf PDF
Attch 2h JBCGS 01 57 20.00 31 Environmental Protection.pdf PDF
Attch 6 Schedule B - Price Schedule.pdf PDF
Attch 3 Wage Determination SC20210034 dated 01.01.2021.pdf PDF
Attch 2b TSPWG_M_3-270-01_04-10 Rubber Removal.pdf PDF
Attch 5 Green Procurement.pdf PDF
Attch 1 Statement of Work SOW Rubber Removal and Paint Striping.pdf PDF
Attch 2d 32 17 23 Pavement Markings.pdf PDF
Attch 2e UFGS 32 01 19.61 Sealing of Joints in Rigid Pavement.pdf PDF
Attch 2f JBCGS 01 54 00.00 31 Green Procurement.pdf PDF
Attch 2i JBCGS 01 74 19.00 31 Construction and Demolition Waste Mgt.pdf PDF
Attch 4 Wage Determination SC20210040 dated 01.01.2021.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 32 01 11.51 Page 1

SECTION 32 01 11.51

RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS

05/16

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only.

Submit the following in accordance with contract requirements:

SD-03 Product Data

Mechanical rubber and paint removal equipment; G

Chemical Rubber and paint removal equipment; G

Rubber and Paint Removal Detergents or Chemicals; G

1.2 MECHANICAL REMOVAL EQUIPMENT

Submit product data for mechanical rubber and paint removal equipment including area of coverage per pass, range of water pressures, and water tank capacity.

Mechanical removal equipment includes waterblasting or other approved non-chemical systems. Control the equipment used on asphalt or tar concrete to remove rubber and paint accumulations while minimizing disturbances to asphalt or tar mixtures. Control the equipment used on portland cement concretes to remove rubber and paint accumulations and prevent removal of hardened paste from the concrete. Basic hand tools and the following major types of mechanical equipment are considered acceptable for this project:

a. Waterblasting Equipment.

1.2.1 Waterblasting Equipment

Provide mobile waterblasting equipment capable of producing a pressurized stream of water that effectively removes rubber and paint from the pavement surface without significantly damaging the pavement. Provide equipment, tools, and machinery which are safe and and in good working order at all times. Provide equipment interlocks to prohibit high pressure water discharge when the vehicle or cleaning head is stationary (not moving forward or side to side).

1.3 CHEMICAL REMOVAL EQUIPMENT

Submit product data for chemical rubber and paint removal equipment. Use chemical equipment capable of applying and removing chemicals from the pavement surface while leaving only non-toxic biodegradable residue.

1.4 TEST SECTION

Prior to the start of work, remove rubber and paint on designated test areas. Use procedures, water pressures, nozzle height, nozzle spacings, nozzle angle, and equipment movement rate to achieve the required degree of rubber and paint removal. Methods included in paragraph COMPLIANCE TESTING shall be used to determine if the rubber and paint was successfully removed from the test section. The test will examine seven

SECTION 32 01 11.51 Page 2 random locations within the test section. Submit the test section results before conducting any further removal work. Provide photos of seven random locations within the test area taken before and after the removal. Provide photos of four random locations at joint seals within the test area taken before and after removal.

1.5 DELIVERY, STORAGE, AND HANDLING

Deliver required materials in original manufacturer's containers labeled with appropriate EPA, OSHA, or other agency warnings, if applicable, and Safety Data Sheets. Protect materials from degrading until their use is required during execution of the work.

1.6 PROJECT/SITE CONDITIONS

1.6.1 Environmental Requirements

Ensure pavement surface is free of snow, ice or slush. Ensure surface temperature is at least 40 degrees F and rising at the beginning of operations and in accordance with manufacturer’s written recommendations, whichever is more stringent. Cease operation during thunder and lightning storms. Cease operation during rainfall except for waterblasting and removal of previously applied chemicals. Cease waterblasting where surface water accumulation alters the effectiveness of material removal.

1.6.2 Airfield Traffic Control

Coordinate performance of all work in the controlled zones of the airfield with the Contracting Officer’s Representative and with the Airfield Manager. Neither equipment nor personnel can use any portion of the airfield without permission of these officers unless the runway is closed.

1.6.3 Radio Communication

No personnel or equipment will be allowed in the controlled zones of the airfield until radio contact has been made with the control tower and permission is granted by the control tower. A radio for this purpose will be provided by the Government. The Contractor is responsible for the radio and must reimburse the Government for repair or replacement of the radio if it is lost, damaged, or destroyed. Maintain contact with the control tower at all times during work in vicinity of the airfield.

Notify the control tower when work is completed and all personnel, equipment and materials have been removed from all aircraft operating surfaces.

1.6.4 Emergency Landing and Takeoff

Emergencies take precedence over all operations. Upon notification from the Control Tower of an emergency landing or imminent takeoff, stop all operations immediately and evacuate all personnel and equipment to an area not utilized for aircraft traffic which is at least 250 feet measured perpendicular to and away from the near edge of the runway unless otherwise authorized by the Contracting Officer or the Contracting Officer's Representative. Equipment and chemicals or detergents as well as excess water must be able to clear the work area within 3 minutes.

SECTION 32 01 11.51 Page 3

1.6.5 Airfield Lighting

When night operations are necessary, provide all necessary lighting and equipment. Direct or shade lighting to prevent interference with aircraft, the air traffic control tower, and other base operations.

Provide lighting and related equipment capable of being removed from the runway within 15 minutes of notification of an emergency. Night work must be coordinated with the Airfield Manager and approved in advance by the Contracting Officer or Contracting Officer’s Representative.

PART 2 PRODUCTS

2.1 RUBBER AND PAINT REMOVAL DETERGENTS OR CHEMICALS

The use of environmentally acceptable detergents or chemical agents must be considered on a case-by-case basis. Submit the Safety Data Sheet (SDS) for detergents or chemicals in the rubber and paint removal process. Use of any detergents or chemicals in the rubber and paint removal process must be approved in advance by the Contracting Officer. The Government specifically reserves the right to reject the use of any process which the Contracting Officer determines may pose unnecessary risks to human health, the environment, the pavement, aircraft or NAVAIDS due to corrosion or foreign object damage (FOD) potential as a result of its use, storage, or disposal.

PART 3 EXECUTION

3.1 RUBBER AND PAINT REMOVAL

Prior to any work being completed, submit a Rubber and Paint Removal Process Plan for approval by the Contracting Officer.

a. The pavement surface type may be of portland cement, tar or asphalt.

b. Chemical methods used must be compatible with pavement materials, the environment and working personnel.

c. Exercise close control of water pressure and blasting time/duration to prevent damage to joints, existing markings that are not intended for removal, or the wearing surface.

d. Demonstrate the ability to remove rubber at a touchdown area of the runway selected by the Contracting Officer; at least one site per runway will be chosen. Rubber removal must not damage the pavement surface. The surface texture of the cleaned demonstration area will be compared to that of non-rubber traffic areas to determine satisfactory completion of the removal operation.

e. After approval of the Contractor's operations by the Contracting

Officer, the cleaned sample area will become the standard for rubber

SECTION 32 01 11.51 Page 4 removal and final surface texture for the remainder of work.

f. Compliance testing for the amount of rubber and paint to be removed must conform to the requirements in paragraph COMPLIANCE TESTING.

3.2 WATER PRESSURE

Provide water pressure impact upon the indicated pavement areas sufficient to remove the designated rubber and paint to the required degree of removal without damaging the existing pavement, joint sealant, or other airfield appurtenances. The Contractor is responsible for repairing any damage caused by the removal work.

3.3 CLEANUP AND WASTE DISPOSAL

Keep the worksite clean of by-products, debris and waste from rubber and paint removal operations. Perform cleanup operations continuously. Remove all residue from the pavement. Obtain the approval of residue removal and disposal method from the Contracting Officer prior to beginning work. Submit a Waste Collection, Identification and Disposal Plan describing proposed actions regarding waste collection, control, identification, and disposal to the Contracting Officer's Representative for approval prior to the start of work. The plan will address disposal methods and requirements for hazardous and non-hazardous wastes.

3.4 COMPLIANCE TESTING

a. Compliance with the rubber and paint removal requirements must be determined by direct testing within the designated work area.

b. Use a one square foot section of transparent material inscribed with a grid of 100 equal squares as a tool for quantitative measure of the percent removal. Place the grid pattern on the pavement surface at random locations. Then count the squares which contain rubber and/or paint deposits. The number of squares containing rubber and/or paint deposits must not exceed the allowed percentage in each of the randomly selected locations as required by the individual Task Order Statements of Work.

c. Divide each work area designated for rubber and paint removal into at least four equal zones for the purpose of compliance testing. The layout of each zone must be approved by the Contracting Officer.

Within each zone, a minimum of seven random locations must be evaluated. The amount of rubber and paint removed at each of the randomly selected test locations within each zone must meet the requirement described in the individual Task Order Statements of Work. Evaluate each zone independently. A zone not meeting the required percentage must be recleaned by the Contractor at the Contractor's expense.

d. Deposits of rubber or rubber buildup and paint are defined as any surface deposit that can be removed by scratching the deposit with a flat sharp object (such as a pocket knife) without damaging the pavement surface. Stains are defined as materials in the pavement surface microtexture that cannot be removed without damaging the pavement surface. Stain is generally embedded in the surface of the pavement below the horizontal plane of the surface texture. The Contractor is not responsible for stain removal.

SECTION 32 01 11.51 Page 5

3.5 DAMAGE REPAIR

Repair any damage to the pavement surface, joint, joint and crack seals, or other Government property caused during the performance of the work at the Contractor's expense. Submit a repair plan to include methods and material to the Contracting Officer's Representative for approval prior to performance of the repairs. Complete the repairs within the performance period of the Contract.

-- End of Section --