This document is the SABER Master Specifications for a simplified acquisition of base engineering requirements (SABER) and base paving program at Vandenberg Space Force Base (VSFB) in California.

The key details are:

  • The contract will cover a broad range of maintenance, repair, and minor construction work on various real property facilities at VSFB, Orcutt Hill, Santa Ynez Peak, Naval Base Ventura County Port Hueneme/Point Mugu, Pillar Point Air Force Station, and Anderson Peak Tracking Station. Work will require multiple trades including carpentry, plumbing, electrical, mechanical, painting, and more.
  • The contract is expected to be awarded to three 8(a) contractors through sealed bidding under FAR Part 14. Task orders will be awarded on a Lowest Price Technically Acceptable, Highest Technically Rated Offer, or Best Value basis.
  • Contractors will be required to use RSMeans Facilities Construction Cost Data and cost estimating software to prepare proposals. Contractors must also provide RSMeans training to government personnel.
  • The contract has specific requirements for as-built drawings, project coordination, utility outages, safety, and environmental protection.

View the file

Other files for this federal contract opportunity

Other files attached to Invitation for Bid: Simplified Acquisition of Base Engineering Requirements (SABER) Program, Vandenberg SFB, newest first.
File Type Posted
VSFB SABER_RFI Responses_Rev 20240730.pdf PDF
VSFB SABER_RFI Responses_20240723.pdf PDF
VSFB SABER 2024_Pre-Bid Conference_Attendance List.xlsx XLSX spreadsheet
VSFB SABER 2024_Pre-Bid Conference Slides.pptx PPTX presentation
VSFB SABER 2024_Pre-Bid Conference Recording.mp4 MP4 file
Solicitation - FA461024B0003.pdf PDF
Attch 02_Wage Determination CA20240014 Santa Barbara County.pdf PDF
Attch 04_Wage Determination CA20240018 Monterey_San Mateo.pdf PDF
Attch 03_Wage Determination CA20240015 Ventura County.pdf PDF
Attch 06_Coefficient Worksheet.xlsx XLSX spreadsheet
Attch 05_Executive Summary Sheet.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Master Specifications for Simplified Acquisition of Base Engineering Requirements

(SABER)

System Space Command (SSC), U.S. Space Force (USSF) Vandenberg Space Force Base (VSFB)

California

Prepared by:

30th Civil Engineer Squadron

Engineering Flight, Project Management, Project Execution (SABER Section)

18 January 2024

FA461024B0003

Attachment 1 - SABER Master Specifications

THIS PAGE INTENTIONALLY LEFT BLANK

FA461024B0003

TABLE OF CONTENTS

SECTION TITLE

DIVISION 1: GENERAL REQUIREMENTS

01 00 00 Construction General Requirements 01 04 00 Unit Price Book and Software Requirements 01 31 01 Project Management 01 33 00 Submittal Procedures 01 35 00 Special Provisions for Working on/Near the Airfield/Airfield Hangars 01 35 29 Safety and Occupational Health Requirements 01 45 00 Contractor’s Quality Control 01 55 01 Security Requirements (Vandenberg Space Force Base) 01 57 20 Environmental Protection 01 78 00 Delivery Order Close-out Requirements 01 78 23 Operation and Maintenance Data

DIVISION 2 through 48:

The Contractor shall conform to the provisions of the most current revision of all standards or publications. UFGS standard specifications can be obtained from the Whole Building Design Guide website: http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

Caltrans standard specifications can be obtained from the California Department of Transportation website: https://dot.ca.gov/programs/design/october-2022-ccs-standard-plans-and-standard-specifications.

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://dot.ca.gov/programs/design/october-2022-ccs-standard-plans-and-standard-specifications

ACRONYM LIST

AF Air Force AFB Air Force Base AFCEC AF Civil Engineering Center AFI Air Force Instruction AFS Air Force Station AFSPC AF Space Command APCD Air Pollution Control Division APEN Air Pollutant Emission Notice APP Affirmative Procurement Program BCE Base Civil Engineer CAD Computer Aided Draft CALTRANS California Department of Transportation CCI City Cost Index CCTV Closed-Circuit Television CD Compact Disk CDPHE Colorado Department of Public Health and Environment CE Civil Engineering CES Civil Engineering Squadron CFC Chlorofluorocarbon CNG Compressed Natural Gas CO Contracting Officer COMSEC Communications Security COR Contracting Officer’s Representative CPG Comprehensive Procurement Guidelines CS Contract Specialist CSI Construction Specification Institute CSO Contractor Security Officer CUI Controlled Unclassified Information dBA "A" Weighted Decibels DISCO Defense Investigative Service Cognizant Security Office DOD Department of Defense DODI Department of Defense Instruction DOT Department of Transportation: Caltrans DPW Director of Public Works DV Distinguished Visitor EMSEC Emission Security EPA Environmental Protection Agency EPDM Elastomeric Roofing ETL Engineering Technical Letter FAA Federal Aviation Agency FFP Firm Fixed-Price FOD Foreign Object Damage FOPR Fair Opportunity Proposal Request GP Government Property

FA461024B0003

GFE Government Furnished Equipment GFM Government Furnished Materials HAZMAT Hazardous Material HAZWASTE Hazardous Waste HCFC Hydrochlorofluorocarbon HMA Hot-Mixed Asphalt HQ Head Quarters HVAC Heating, Ventilating and Air Conditioning IAW In Accordance With IBC International Building Code LAN Local Area Network LBP Lead-Based Paint MR Mechanical Room MSDS Material Safety Data Sheet MSG Mission Support Group MVACIS Mobile Vehicle and Cargo Inspection System NAC National Agency Check NFPA National Fire Protection Agency NORAD North American Aerospace Defense Command NPDES National Pollutant Discharge Elimination System NPI Non-Pre-priced Item NBVC Naval Base Ventura County NRC Nuclear Regulatory Commission NTP Notice to Proceed O&M Operation and Maintenance ODS Ozone Depleting Substances PC Power Center PCB Polychlorinated Biphenyls PEL Permissible Exposure Limit POV Personally Owned Vehicle PPAFS Pillar Point Air Force Station QC Quality Control RMAN Recovered Material Advisory Notices ROM Read Only Memory RFP Request for Proposal SABER Simplified Acquisition of Base Engineering Requirements SFS Security Forces Squadron SLD Space Launch Delta SOW Statement of Work SSSMR Structural Standing Seam Metal Roof TO Task Order UFC Unified Facilities Criteria UFGS Unified Facilities Guide Specifications UPB Unit Price Book US United States USAF United States Air Force

FA461024B0003

USSF United States Space Force VSFB Vandenberg Space Force Base VIN Vehicle Identification Number

FA461024B0003

Section 01 00 00 – General Requirements

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 DEFINITION OF INSTALLATION

1.1.1 Installation is defined as the property and facilities located within the jurisdiction of the particular base, post, air station, or compound where work is being accomplished. Work performed under this contract shall be bound by rules, laws, and regulations of each particular installation as well as local, state, federal, and Air Force regulations. This contract covers Air Force construction efforts at Vandenberg Space Force Base (VSFB), Orcutt Hill, Santa Ynez Peak, Naval Base Ventura County (NBVC) Port Hueneme/Point

Mugu, Pillar Point Air Force Station (PPAFS) and Anderson Peak Tracking Station.

VSFB and Santa Ynez Peak are located in Santa Barbara County; Naval Base Ventura

County Port Hueneme/Point Mugu is located in Ventura County; PPAFS in San Mateo

County; and Anderson Peak in Monterey County, California.

1.2 PROJECT DESCRIPTION

1.2.1 The Contractor shall furnish all management, supervision, labor, materials, equipment, and incidentals required for a broad range of maintenance, repair, and minor construction work on various real property facilities at installations covered under this contract, including design and engineering services incidental to construction. The Contracting

Officer (CO) will conduct negotiations with the Contractor and issue individual Task

Orders (TO) for maintenance, repair and minor construction projects identified by the

Base Civil Engineer (BCE) as part of this Simplified Acquisition of Base Engineering

Requirements (SABER) and Base Paving Requirement program. Individual TO projects will vary in size, with the majority expected to be less than $750,000. The work to be performed will require the use of multiple trades including, but not limited to trades such as carpentry, plumbing, electrical, mechanical, painting, pipe fitting, sheet metal, welding, roofing, site work, site utilities, excavation, concrete, masonry, pavement repair, asbestos abatement, lead paint removal, security hardware installation, and demolition.

1.3 CONTRACT DOCUMENTS, REFERENCE STANDARDS, AND PUBLICATIONS

1.3.1 The following documents are part of the solicitation and resultant contract. The

Contractor shall utilize the referenced documents in the accomplishment of task prescribed in TOs. The standards and publications listed in each section of the specifications, form part of these specifications to the extent referenced. The Contractor shall conform to the provisions of the most recent issue of all standards or publications.

1.3.1.1 SABER and Base Paving Master Specifications

a. UFGS standard specifications can be obtained from the Whole Building Design Guide website: http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs. The

FA461024B0003

Attachment 1 - SABER Master Specifications https://usaf-my.dps.mil/personal/albert_thompson_2_spaceforce_mil/_layouts/15/Doc.aspx?sourcedoc=%7BE8DC8C2C-750E-4BE0-804D-22C0800D2926%7D&file=SABER%20Coefficient%20OY3_4.xlsx&action=default&mobileredirect=true http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

Unified Facilities Guide Specifications (UFGS) and the following documents are hereby incorporated into the solicitation and any resultant contract. Caltrans standard specifications can be obtained from the California Department of Transportation website:

https://dot.ca.gov/programs/design/october-2022-ccs-standard-plans-and-standard-specifications. The Caltrans Specifications and the following documents are hereby incorporated into the solicitation and any resultant contract.

01 00 00 Construction General Requirements

01 04 00 Unit Price Book and Software Requirements

01 31 01 Project Management

01 33 00 Submittal Procedures

01 35 00 Special Provisions For Working on/Near the Airfield and Hangars

01 35 29 Safety and Occupational Health Requirements

01 45 00 Contractor’s Quality Control

01 55 01 Security Requirements (Vandenberg Space Force Base)

01 57 20 Environmental Protection

01 78 00 Task Order Closeout Requirements

01 78 23 Operation and Maintenance Data

b. These SABER and Base Paving Master Specifications are numbered and organized in accordance with the Construction Specification Institute’s (CSI) Master Format.

1.3.1.2 Unit Price Book

a. The Unit Price Book (UPB) is described in Section 01 04 00. The UPB shall be furnished by each of the awarded Contractors.

1.3.1.3 Unified Facilities Criteria (UFC)

a. The UFC shall be used as the standard building code for all construction under this contract (http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc). Any and all latest changes to the UFC will immediately become requirements of this contract. The UFC references the International Building Code (IBC) and the International Existing Building

Code (IEBC) as the basic requirement. However, the current adopted version of the IBC and IEBC shall be used as the minimum standard. The UFC modifies those basic requirements in UFC 01-200-01.

1.3.1.4 Building Codes

a. As a minimum, Federal, State, and Local Building Codes shall be used for all construction under this contract as supplemented by the use of the International Building

Code (IBC) and the International Existing Building Code (IEBC). The most current editions and supplements of these standards shall apply. The Contractor shall have a copy of each of these documents available for use during the term of this contract. If there is a conflict between these codes and regulations, the most stringent requirements apply at all times.

FA461024B0003

Attachment 1 - SABER Master Specifications https://dot.ca.gov/programs/design/october-2022-ccs-standard-plans-and-standard-specifications http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc).

1.3.1.5 Installation Design Standards

a. The most current and latest Installation Facility Standards (IFS) for Vandenberg SFB shall be adhered to on all construction projects. The IFS can be found at the Whole

Building Design Guide site (http://www.wbdg.org). Any possible deviations from these standards shall be brought to the CO before implementation.

1.3.1.6 Explosive Safety

a. Facilities that involve DoD Ammunition and Explosives (AE) storage, handling, maintenance, manufacture, or disposal, as well as facilities within the explosives safety quantity distance (ESQD) arcs of AE facilities, must comply with the requirements found in DoDM 6055.09, as well as DESR6055.09_AFMAN91-201.

1.3.1.7 Antiterrorism

a. Antiterrorism is defined as defensive measures used to reduce the vulnerability of individuals and property to terrorist acts. UFC 4-010-01 sets the minimum requirements for DoD buildings.

1.3.1.8 Physical Security.

a. Physical security is defined as that part of security concerned with physical measures designed and placed to safe guard personnel; to prevent unauthorized access to installations, equipment, material, and documents, and to safeguard them against espionage, sabotage, damage, and theft. Many buildings require some level of physical security. When required, integrate physical measures into the site, building, room, or area as applicable. DoD requirements for physical security related to specific assets are documented in DoD publications, directives, manuals, and instructions. The Services have related documents that implement the DoD policy for the Services. The main DoD documents that contain the physical security requirements for the protection of specific

DoD assets are shown in Table 1-1.

Table 1-1 Policy Related to Physical Security

Asset Policy and Documents

Classified Information DoDM 5200.01, Volume 3, DoD Information Security

Program: Protection of Classified Information;

https://www.esd.whs.mil/DD/DoD-Issuances/

Sensitive Compartmented

Information (SCI)

DoDM 5105.21-Volume 1, Sensitive Compartmented

Information(SCI) Administrative Security Manual:

Administration of Information and Information Systems

Security; https://www.esd.whs.mil/DD/DoD-Issuances/

DoDM 5105.21-Volume 2, Sensitive Compartmented

Information (SCI) Administrative Security Manual:

Administration of Physical Security, Visitor Control, and

FA461024B0003

Attachment 1 - SABER Master Specifications http://www.wbdg.org/

Technical Security; https://www.esd.whs.mil/DD/DoD-

Issuances/

UFC 4-010-05, Sensitive Compartmented Information

Facilities Planning, Design, and Construction;

https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05/

Special Access Program (SAP)

Information

DoDM 5205.07, Volume 3, DoD Special Access Program

(SAP)Security Manual: Physical Security;

Arms, Ammunition, and

Explosives

DoDM 5100.76, Physical Security of Sensitive Conventional

Arms, Ammunition, and Explosives (AA&E);

https://safe.menlosecurity.com/https://www.esd.whs.mil/DD/

DoD-Issuances/

Weapon Systems and

Platforms

DoD 5200.08-R, Physical Security Program;

https://safe.menlosecurity.com/https://www.esd.whs.mil/DD/

DoD-Issuances/

Bulk Petroleum Products

Communications Systems

Controlled Inventory Items

1.4 EXECUTION

1.4.1 Pre-Performance Construction Meeting

a. Before work begins on this contract, the CO will arrange for a meeting with the

Contractor to discuss the contract in general, including administrative matters, performance requirements, submittal procedures, approval and payment schedule, quality control expectations, Request for Proposal (RFP) or Fair-Opportunity Proposal Request

(FOPR) and TO procedures, traffic control, construction access requirements, as-built criteria, performance requirements, security procedures, accident prevention, safety, and fire prevention briefings. The Contracting Officer may issue a letter to the Contractor in-lieu of holding a face-to-face Pre-Performance Construction Meeting for individual TOs.

1.4.2 Business Telephone

a. At the beginning of this contract, the Contractor shall provide the applicable CO’s a contractor personnel telephone number, e-mail, and website for regular working hours.

The Contractor shall also provide after hours (emergency) telephone numbers for

Contractor’s Program Manager and Project Manager(s) as a minimum. The Contractor shall provide the CO with an updated phone list whenever changes in personnel or phone numbers occur. The Contractor is required to provide a means of mobile communications (i.e., cellular phone and/or pager) for Contractor’s Program Manager, FA461024B0003

Attachment 1 - SABER Master Specifications https://www.esd.whs.mil/DD/DoD-Issuances/ https://www.esd.whs.mil/DD/DoD-Issuances/ https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05/ https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05/ https://www.esd.whs.mil/DD/DoD-Issuances/ https://safe.menlosecurity.com/https:/www.esd.whs.mil/DD/DoD-Issuances/ https://safe.menlosecurity.com/https:/www.esd.whs.mil/DD/DoD-Issuances/ https://safe.menlosecurity.com/https:/www.esd.whs.mil/DD/DoD-Issuances/ https://safe.menlosecurity.com/https:/www.esd.whs.mil/DD/DoD-Issuances/

Project Manager(s), Superintendent, Quality Control Officer, and their respective

Alternates for the life of the contract. Communications equipment, to include but not limited to landline telephones and land mobile radios, will require special coordination and clearance with installation communications authorities.

1.4.3 Work Hours

a. The Contractor shall complete the work of this project between the hours of 7:00am –

4:30pm, Pacific Time (PT), excluding Saturdays, Sundays, Federal Holidays, and Family

Days. Access to work sites may be restricted to these hours and days. All other times shall be considered non-standard hours. Unless required by the CO in writing or

Statement of Objectives (SOO), the Government will not pay additional costs for non-standard hours. The Contractor may not work during non-standard hours unless the request and justification is approved by the CO. The Contractor must submit a request and justification for working non-standard hours to the CO at least three (3) working days prior to working non-standard hours. Work that requires inspection during accomplishment or that prevents inspection of other work after accomplishment must be coordinated with and approved in advance by the CO. Inclement weather, operational delays and security related delays might affect the Contractor’s work periods. The

Contractor must make allowances for these events, as resulting lost time will not be reimbursable.

1.4.4 Federal Holidays

1.4.4.1 The Government only recognizes the following legal holidays established by federal statue:

a. New Years Day (January 1st)

b. Martin Luther King, Jr. Birthday Day (Third Monday in January)

c. President’s Day (Third Monday in February)

d. Memorial Day (Last Monday in May)

e. Juneteenth National Independence Day (June 19th)

f. Independence Day (July 4th)

g. Labor Day (First Monday in September)

h. Columbus Day (Second Monday in October)

i. Veteran’s Day (November 11th)

j. Thanksgiving Day (Fourth Thursday in November)

k. Christmas Day (December 25th)

1.4.4.2 Any of the legal holidays falling on Saturday will be observed on the preceding Friday;

legal holidays falling on Sunday will be observed on the following Monday. In addition, the

Government may dictate the workday before or the workday after an observed holiday as a

“Family Day.”

1.4.4.3 The Contractor should not perform work on observed legal holidays or Family Days unless authorized by the CO. In the event work is authorized on observed legal holidays, the

FA461024B0003

Contractor shall pay all applicable overtime and/or holiday pay rates required by law.

1.4.5 Work Interruptions and Delays

1.4.5.1 The Contractor may be required to temporarily stop work for operational requirements, special events, installation exercises, or while Distinguished Visitor (DV) familiarization visits/tours are conducted. The Contractor must make allowances for these events and resulting lost time will not be reimbursable. Notification to the Contractor shall be provided by the applicable CO.

1.4.6 Construction Wage Rate Requirements Statute

1.4.6.1 The most current Construction Wage Rate Requirements Statute wage determination will be incorporated into the contract at the time of award. This wage determination will be effective for all TOs issued during the base contract period. Concurrent with the exercise of each option, the current wage determination at the time of modification will be incorporated and shall be effective for all TOs issued during the option. If a

FOPR is issued prior to the exercise of an option, but not awarded until after the option is exercised, the Contractor will be given the opportunity to update its proposal to incorporate any changes caused by the update to the wage determination.

1.4.7 PERFORMANCE AND PAYMENT BONDS – APPLICABLE TO INDIVIUAL TO’s

1.4.7.1 Contractors shall furnish Performance and Payment Bonds (Standard Form 25/25A) with good and sufficient surety or sureties, acceptable to the Government on all TO’s regardless of dollar value. The bonds shall be equal 100% of the contract price for each

TO. If the TO price increases after initial award, the Contractor shall provide additional bonding protection by increasing the penal sum of the existing bond, or obtaining an additional bond. Bonds shall be submitted within 10 calendar days of receipt of the TO.

1.4.8 Safety Requirements

1.4.8.1 See Section 01 35 29

1.4.9 Fire Protection

1.4.9.1 The Contractor shall be responsible for furnishing adequate and proper fire protection for all phases of the contract work in accordance with the latest and most current UFCs and National Fire Protection Agency (NFPA) Standards. See Section 01 35 29, Safety and Occupational Health Requirements.

1.4.10 Fair Opportunity Proposal Request (FOPR)

1.4.10.1 For each project or solicitation, the Contractor will be furnished with one (1) copy of the Government’s Statement of Objectives (SOO) from the CO or his/her designated

FA461024B0003

Contracting Specialist. The Contractor may be provided with one (1) set of drawings and specifications as required or applicable. The level of the design provided to the

Contractor may be anywhere from a 35% design (basic concept) to a 95% design (a complete design package which requires the Contractor to verify actual conditions and make any necessary corrections). Although the Contractor is given a design package, it is still the Contractor’s responsibility to verify/validate existing site conditions prior to submitting their proposal package to the Government. The Contractor may reproduce the drawings & specifications at the Contractor’s own expense if additional copies are needed. The Contractor shall check all drawings and specifications immediately upon receipt for discrepancies and notify the CO or his/her designated representative immediately of any and all discrepancies found in the form of a Request for

Information (RFI). The RFI shall be forwarded to the CO for review and in-turn forwarded to the assigned SABER and Base Paving Project Manager(s) for review, clarification, and response. Enlarged plans and details shall govern where the same work is shown at smaller scales. The Contractor shall compare all drawings and verify the installation before laying out the work and shall be responsible for any errors which might have been avoided thereby. Where drawings are not provided as part of the

FOPR, the Contractor shall provide the field investigation, historical record research, design including construction drawings, and constructability review necessary to ensure the drawings are complete.

1.4.10.2 The design required for this contract is at the level normally expected of a general construction contractor and considered incidental to the accomplishment of the scope of work provided by the Government. Examples of services required from the contractor include sizing and selection of electrical and mechanical equipment and systems; sizing of electrical circuits (i.e., wiring and cable sizing; to include pole mount and pad mount transformers sizing), electrical devices, heating and ventilating air ducts, fluid piping systems and light structural framing members; lighting layout; fire detection systems;

surveying; computer aided drafting, etc. If the design requires the services of a registered architect or professional engineer, it should be considered outside the parameters of the SABER program and the Contractor shall notify the CO immediately.

1.4.11 Project Site Visit

1.4.11.1 After the release of an FOPR, the Government and the Contractor will schedule and conduct a pre-proposal site visit for project. Discussions held during the site visit may include, but are not limited to: scope of work, method of construction, sequence of operations, progress schedule, means of access to project site, delivery and storage of materials and equipment, work restrictions, coordination requirements, project goals, liquidated damages and potential difficulties/problems. The Contractor shall email detailed site visit minutes to the CO within one (1) business day following the day of the site visit. The CO or designated Contracting Specialist shall provide consolidated site visit minutes to all Contractors and the Civil Engineer Squadron (CES) SABER and

Base Paving Project Manager(s) within two (2) business days following the site visit.

The Contractor shall comply with the requirements of the clause at FAR 52.236-3, Site

Investigation and Conditions Affecting the Work.

FA461024B0003

1.4.11.2 As part of meeting the requirements of this clause, the Contractor shall research all historical drawings related to the project site or facility. Historical records and drawings (if they are available) are located in the 30th CES, Bldg. 11433, Drawing

Vault. Contractors will be required to bring a copy of the FOPR signed by the CO to the Drawing Vault in order to be authorized access. Contractors shall not use the

Drawing Vault to research any building/project for which they do not have a signed

FOPR or contract/TO. Contractors found violating this policy may have their access to the Drawing Vault restricted and/or have further actions taken including but not limited to receiving a lower CPARS rating or the Government not exercising their contract option(s). NOTE: Available historical records or drawings may or may not be accurate, therefore; it is the Contractor’s responsibility to perform diligent site investigation prior to the preparation of their project proposal to the Government.

1.4.11.3 Any questions asked during the site visit or identified after the site visit should be submitted as a Request for Information (RFI) to the CO and designated Contract

Specialist within three (3) calendar days after the site visit.

1.4.12 On-Site Conditions

1.4.12.1 Drawings may not be available or provided. Drawings showing the location of equipment, piping, ducts, and conduit, are diagrammatic and may not show every detail required. In addition, site conditions will not always permit installation in the locations shown on the concept drawings. Drawings showing equipment, piping, ducts, conduit, etc. to be removed, altered, or installed may require deviation from the configuration of the demolition or installation drawings due to existence of conflicting ducts, conduits, hangers, light fixtures, structural items, and temporary walls, etc. All such minor details of work which are not shown on the drawings, as well as such items not specifically mentioned in the specifications, but which are essential and necessary for the completion of the work, and to make all systems or equipment operational, shall be considered as incidental and shall be included as part of the work. When this situation occurs, the final placement of permanently installed items shall be subject to approval by the CO. The Contractor shall be responsible for inspecting to his satisfaction all areas/items of possible conflict. Failure to verify the dimensions and locations will be at the contractor’s risk and shall not relieve the Contractor from accomplishing the work required by the TO.

1.4.13 Project Proposal

1.4.13.1 For every FOPR associated with a new TO, the Contractor shall provide a written Firm

Fixed-Priced (FFP) proposal describing the Contractor’s approach to the proposed project work described in the Government’s Statement of Objectives (SOO) and project drawings, if any. The proposal shall include at a minimum: a Cover Letter, a Statement of Work narrative describing their approach to the proposed project work as described in the Government’s SOO to include all major components of the project; a detailed cost estimate for all work to be performed and all major components of the project; an

FA461024B0003

Schedule of Material Submittals; a detailed project schedule in Microsoft Project, or equivalent, and Adobe PDF that includes all major components of the project, their associated costs and percentage of effort; an AF Form 3065 detailing the major components and the associated percentage of the construction effort; and any other information as needed to demonstrate a complete and thorough understanding of construction effort. The Contractor shall submit the proposal within 14 calendar days of the site visit.

a. Cover Page. The cover page or pages shall include project title, total project cost, list of requirements, performance period, material lead times, and any special considerations such as phasing of construction. A list of assumptions and exemptions are identified separately. The Contractor’s proposals shall be complete and concise.

b. Statement of Work (SOW). The Contractor shall provide, as part of the proposal, a SOW. The SOW shall provide a written narrative describing the Contractor’s approach and shall document the Contractor’s basic design solution to the subject project. The Contractor shall not simply re-state the goals of the Government SOO, but provide sufficient information to demonstrate to the Government a complete and thorough understanding of the requirement and all applicable codes and regulations.

c. Design Documentation. Design incidental to accomplishing the required tasks outlined in each TO project may be required. The extent of these designs will depend upon the complexity of each TO project. Under the scope of this contract, the complexity will not require the services of a registered architect or engineer.

However, the Contractor shall provide sufficient design documentation to substantiate the proposed approach for the task. Design documentation shall provide enough detail to verify line-item quantities in the cost proposal are accurate and enough detail to clearly convey to the Government what the Government will be receiving. All designs shall clearly illustrate compliance with local, state, and federal building and construction codes. After the site validation visit, the

Contractor shall begin preparation of design documentation that clearly illustrates the proposed design solution, quantities, dimensions, materials etc. This documentation may include any or all of the following, but is not limited to the following:

(1) Drawings. When required, design drawings submitted by the Contractor shall show the basic layout and planning of work. Shop drawings shall show in detail the proposed fabrication and assembly of structural elements and/or the installation (i.e., form fit, and attachment details) of materials or equipment.

Drawings must have sufficient detail to enable both the Contractor and the

Government to understand the work to be accomplished.

i. For the purpose of this requirement, the term drawings includes actual construction drawings, shop drawings, fabrication drawings, erection

FA461024B0003

drawings, diagrams, layouts, schematics, descriptive literature, illustrations, room finish schedules, lighting/panel schedules, lighting level analysis plans, load/distribution schedules/calculations, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions as may be required by an individual TO.

ii. The Government may indicate minimum drawings that are necessary for each individual TO project. Typical types of drawings required on TOs include the following: Title/Location/Legend/Index Sheets, Site Plans, Grading/Landscaping Plans, Underground Utility Plan and Profiles, Demolition Floor Plans, New Work Floor Plans, Wall Sections, Building

Section, Finish Schedules, Window and Door Schedules, Mechanical Plans and Equipment Schedules, Plumbing Plans and HVAC Riser Diagrams, Electrical Plans and Wiring Diagrams, Electrical Equipment and Panel

Schedules, Lighting Plans and Schedules, Communications Plans, Fire

Protection Plans, Structural Plans, Roofing Plans, Wall and Roof Sections, Reflected Ceiling Plans, Elevations (Interior and Exterior), and Associated details.

(2) Design Calculations. The Contractor shall provide, as part of the proposal, design calculations to substantiate appropriate equipment or material selection/sizing, component assembly, proposed layout and sizing of utilities and structural elements (i.e., HVAC Loads, Lighting, Platform Supports, etc.).

The Contractor shall supply the following calculations per each TO project, as applicable:

i. Mechanical: HVAC load analysis and unit sizing, pipe sizing and duct sizing.

ii. Electrical: Electrical system capacity, conductor, conduit, protective devices, and other equipment sizing.

iii. Structural: Structural system and foundation sizing.

iv. Pavement/Site Work: Area run-off quantities, drainage capacities and grading slopes.

v. Lighting: Lighting level analysis and lumen/foot-candle levels for each room or area.

vi. Energy: Provide energy savings and Return on Investment (ROI).

d. Cost Estimates. All TOs shall be estimated, negotiated, and awarded based upon prices in the Unit Price Book (UPB, see Section 01 04 00). The cost estimate portion of the Contractor’s proposals shall be prepared and produced using the cost estimating software described in Cost Estimating Software Requirements (Section

FA461024B0003

01 04 00 paragraph 1.1). This applies to all work done on SABER and Base Paving

TOs, even if work is done by subcontractors.

(1) Items not in the UPB, known as Non-Priced Items (NPI), may be proposed in accordance with the policy outlined below. The cost estimate portion of the

Contractor’s proposals shall be in CSI format and shall be prepared and produced using the cost estimating software described in Unit Price Book and

Software Requirements (UPB, see Section 01 04 00). Cost estimates must be logical, demonstrating a reasonable approach in construction methodology in both line items and quantities proposed. The elements of the cost estimate should correlate to the construction elements identified in the Statement of

Work. Only authorized cost adjustment factors identified in Section 01 04 00 and included in the UPB shall be utilized to adjust line-item costs. The

Contractor shall not utilize any other cost adjustment factors.

(2) The use of an NPI should be kept to a minimum; use will be determined on a case-by-case basis by the CO and SABER/ Base Paving Management. For negotiating and determining the price reasonableness for the NPI, the Contractor will submit at least three (3) quotes from suppliers with their proposal for review. The Government (assigned SABER/ Base Paving Project Managers or

SABER/Base PAVING Management) will then select one of the suppliers from which the Contractor will be authorized to purchase the NPI. The Contractor and the Government will negotiate the labor hours required to install the NPI and any other appropriate mark-ups and the fixed co- efficient. If three (3) suppliers cannot be found, the Contractor shall submit at least one invoice with their proposal. If the NPI has a commercially available price list, the Contractor shall submit that with the proposal. The CO will conduct market research to determine price reasonableness. Once price reasonableness has been determined, the Contractor and the Government (to include SABER/Base

Paving Project Managers) will negotiate the labor hours to install the NPI and any other appropriate mark-ups and the fixed co-efficient. If price reasonableness cannot be determined and the material cost is significant, the

Contractor will have to break down each unit of cost the Contractor will pay for the NPI to facilitate the price reasonableness determination. If the NPI is a custom-made item, the manufacturer will have to submit their itemized costs.

e. Schedule of Material Submittals. The Contractor shall prepare and provide as part of the proposal package a Schedule of Material Submittals, or equivalent. The

Schedule of Material Submittals shall include all reports, construction materials, and documentation that have a material effect on the construction effort including, but not limited to: large purchase items; long-lead items; required reports; and as-built drawings. Submittal requirements are identified in specification Section 01 33 00.

f. Construction Schedule.

(1) The Contractor shall submit the construction schedule in two (2) formats, an AF

Form 3064, Progress Schedule, and a critical path Gantt chart schedule. The progress schedule shall be submitted on an AF Form 3064, Progress Schedule, and completed in accordance with the instructions on the reverse side of the form, or as directed by the CO. In addition to the progress schedule, the

Contractor shall submit a critical path Gantt chart schedule with milestones in

Microsoft Project, or an equivalent format, and Adobe PDF. After TO award, the Contractor shall provide bi-weekly construction updates on an AF Form

3065, Progress Report.

(2) The construction schedule shall identify all major tasks of construction effort, their associated cost, and associated percentage of the work effort. The construction schedule should demonstrate a logical progression of the work effort from award to close-out.

1.4.14 Quick Response Requirements

1.4.14.1 The Government at its discretion may classify a requirement as a Quick Response

Requirement. If a project is determined to be a quick response requirement the timelines listed in paragraphs 1.4.11 and 1.4.13 may be shortened based on the CO’s discretion. The shortened timelines will be identified on the FOPR and the Contractors shall comply with the timelines.

1.5 TASK ORDER SELECTION PROCEDURES

1.5.1 The Government anticipates awarding three (3) SABER and Base Paving IDIQ contracts.

TOs issued under each contract award are subject to the requirements of Federal

Acquisition Regulation (FAR) 16.505, Orders under Multiple Award Contracts. All contractors will be given a fair opportunity to be considered for each order. All contractors will be required to submit proposals for evaluation on every TO. The CO will select one contractor to receive the TO award. No protest under FAR subpart 33.1 is authorized in connection with the issuance or proposed issuance of task order, except as authorized by FAR 16.505(a)(1).

1.5.2 The selection for TO award will either be based on Lowest Price Technically Acceptable

(LPTA), Highest Technically Rated Offer (HTRO) or Best Value (BV) at the discretion of the CO with CONCURRENCE of the CES, Engineering Flight (30 CES/CENMP).

The LPTA method will be the primary selection method with HTRO and BV being used on a by-exception basis. Under LPTA, TO awards will be made to the lowest priced proposal determined technically acceptable. Proposals will be determined technical acceptable when they demonstrate a complete understanding of the TO requirement based upon a review of each of the submitted documents. Inconsistencies and/or a lack of sufficient detail may cause TO proposals to be determined technically unacceptable.

Under HTRO, TO awards will be made to the TO proposal which is determined to be the highest technically rated with a reasonable price (reasonable price may not be the lowest

FA461024B0003

price). Under BV, TO awards will be made to the TO proposal which is determined to be the best value to the Government considering price and other factor. The factors used in the Best Value determination will be identified on the FOPR. The following factors may be considered when making a decision in the selection and may include other factors the

CO determines relevant or in the best interest of the government in selecting an awardee.

All factors are considered equal, except price, with no order of precedence. Price will be considered slightly less important than all other factors. The CO shall exercise broad discretion in selecting the Contractor.

a. Completeness of proposal

b. Design

c. Construction methodology

d. Scheduling

e. Past performance

f. Quality of deliverables

1.5.3 After considering the above factors, and before or after selection of the contractor, the

CO may require further evaluation or negotiations of the proposal.

1.5.4 The CO using a DD Form 1155 will then issue TOs. Each TO will include the following information:

a. Date of the TO

b. Contract number and TO number

c. Item number and description, quantity, and unit prices for pre-priced and non-pre-priced items and total

d. TO price, delivery, or performance data

e. Accounting and appropriation data

f. Liquidated Damages, if applicable

g. Design, if applicable

h. Sketches/Drawings, if applicable

i. Contractor’s Statement of Work

j. Construction Schedule; period of performance

1.6 TASK ORDER FUNDING

1.6.1 Proposals may be requested and processed up to the point of award, in advance of funding. Proposals processed up to award may remain on hold, pending funding, for a period of one year, or until the exercise of the next option period. It is the government’s intent to award a TO for each proposal processed up to the point of award; however, due to changes in the construction program, congressional budget changes or world events, some projects may be canceled. No compensation for cancelled projects will be granted to the contractor.

1.7 WORK CLEARANCE REQUEST

1.7.1 Upon TO award and prior to start of the project the Contractor shall obtain and process an

AF Form 103, BCE Work Clearance Request for each project. The Contractor shall go to the 30th CES, Operations Flight, Customer Service Unit (work order service desk) located in Bldg. 11439 along Iceland Ave. (CES Complex) in order to start the AF Form

103 process and then shall coordinate with appropriate Government agencies for review and coordination to properly complete the form. Once all coordination is completed, the

Contractor shall return the AF Form 103 to the work order service desk to receive approval signature. Government agencies will annotate the form with special instructions or requirements. The AF Form 103 with drawings, floor plans or sketches, shall be submitted a minimum of 10 workdays prior to construction start date. Work shall not begin until the AF Form 103 is fully approved and, if applicable, coordination is received from each of the coordination agencies which noted “Monitor required” on the AF Form

103.

1.7.1.1 Environmental monitors may be required from 30th CES, Environmental Flight. A minimum of 72 hours advance notice for environmental monitors is required. Work shall not begin until the monitors are coordinated and present.

1.7.1.2 When any digging is performed in the vicinity of utilities or communication cables, 30th CES and/or 30th Space Communications Squadron monitors will be present, as required. No mechanical digging shall be performed within 15 feet of utilities or communication cables until they are physically exposed by hand digging. If a utility or communication cable is damaged, notify the Contracting Officer immediately. A minimum of 72 hours advance notice for CES monitors and SCS monitors as indicated on AF Form 103 is required. Work shall not begin until the monitors are notified and present.

1.7.1.3 Due to the nature of the mission at VSFB, a “SLD 30 Framelight Restriction” period may occur during special operations. The period imposed can range from one day to two weeks. The Contractor should anticipate delays in obtaining a waiver to excavate.

Framelight Restriction events may occur several times during the year.

1.7.1.4 Any welding, torching, or spark producing work on VSFB requires a welding permit.

The Contractor shall obtain a welding permit from the 30th CES, Fire Prevention office. A permit will be issued within five (5) workdays with instructions for welding fire prevention. Refer to Section 01 35 29 Safety and Occupational Health

Requirements for additional information.

1.7.1.5 In all cases the Contractor shall have contingency plans for continuing work during utility outages caused by the Contractor or outside forces. The plan must also include procedures for promptly repairing utility breaks/interruptions made or caused by the

Contractor.

1.7.1.6 Contractor shall be responsible for contacting utility owners to coordinate work, identify, locate, and mark all utility lines in the vicinity of the project work site

(commercial and military utility lines). The Contractor will be required to mark the limits of site work/excavation to indicate location, direction, length, and depth of site work/excavation in order to facilitate the utility owner’s field marking of existing utilities.

1.7.1.7 The Contractor shall provide, as attachment to the AF Form 103, drawings showing exact location and description of the work to be accomplished. Should any of the coordination points indicate additional utility lines or structures to those already shown on the drawings, by sketch on the Contractor’s drawing or by field location marking, the Contractor shall be responsible for the protection of each of the indicated items. It is the responsibility of the Contractor to verify the exact location of all indicated utility lines and structures, and for the protection of the same, in the project work area.

Should damage occur to any utility line or structure, the Contractor shall be responsible for the prompt repair of the damage to return the item to its original working condition.

1.7.1.8 Special care and coordination shall be taken in any high-visibility area so as not to unnecessarily damage surfaces. The Contractor shall consult with the Civil Engineer

Representative before any markings are placed in these areas. In all high-visibility locations, the paint used to locate utilities will be fully removed from sidewalks, pavements, and plazas at the end of the project. The Contractor shall be responsible for any damages.

1.7.1.9 The Contractor shall have a copy of the fully coordinated, approved and signed AF

103, Base Civil Engineer Work Clearance Request (aka “digging permit) at the project site at all times.

1.8 ELECTRICAL SERVICE AND COMMUNICATIONS FACILITIES

1.8.1 The Contractor shall not disturb electrical and/or communications facilities and wiring not discussed in the Statement of Work (SOW) or drawings. Where such facilities require removal for accomplishment of the project work, the Contractor shall notify the

Contracting Officer in writing at least seven calendar days in advance of the requirement, for the accomplishment of such removal work by the Government. The Contractor shall allow the utility owner to remove the systems required. If the lines are damaged by the contractor’s construction activities, the Contractor shall restore service within 24-hours with no cost to the Government.

1.9 CONDITIONS OF WORK

1.9.1 Disruptions:

1.9.1.1 The Contractor shall perform his work in a manner that will minimize disruption to normal VSFB operations.

FA461024B0003

1.9.1.2 Disruptions to sprinkler or alarm systems may require either the evacuation of the building or fire watch. This will be coordinated by the Contractor with the 30 CES Fire

Prevention office.

1.9.2 Area of work:

1.9.2.1 The Contractor will be allowed a reasonable working area when possible.

1.9.3 Regulations and Policies

1.9.3.1The Contractor shall comply with all applicable VSFB regulations pertaining to safety, health, security, traffic control, fire prevention, and environmental protection.

1.10 RECORD DRAWINGS

1.10.1 During the progress of the contract, the Contractor shall keep a set of red-line drawings on the job site at all times. Red-line drawings shall be based on the shop drawings and/or design drawings provided by the Contractor as part of its proposal package IAW SABER

Specifications Section 01 00 00, paragraph 1.4.12.1c.(1). These drawings shall be used to create as-built drawings meeting the requirements of paragraph 1.3.3 of SABER

Specifications Section 01 78 00, TO Closeout Requirements. If the Contractor fails to maintain the record drawings as required, the CO will consider that satisfactory progress has not been achieved for the period in question. Final payment will be withheld until as-built Drawings, in PDF and AutoCAD format, are submitted and approved by the CO.

1.10.2 Final As-Built Drawings

1.10.2.1 Prior to final inspection, submit one (1) CD/DVD-ROM copy of the as-built drawings in AutoCAD file format (*.dwg) and in Adobe PDF file format (*.pdf) as detailed in subsequent paragraph “As-Built Deliverables” to both the SABER and Base Paving

Project Manager and CO. As-built drawings will only contain data applicable to the project. All work will conform to the parameters described in this specification.

Unless otherwise noted, the latest published version and/or revision shall be used.

1.11 AS-BUILT DELIVERABLES

1.11.1 Delivery Specifications

1.11.1.1 All as-built drawings shall be delivered on a CD/DVD-ROM in *.dwg and *.pdf formats. The *.pdf file shall be condensed into a single file with the multiple pages.

The Contractor shall submit electronically to the CO and one (1) CD/DVD-ROM disc to the Project Manager. The *.dwg file shall be created in the most current version of

AutoCAD, or as is acceptable by the drawings vault. The *.pdf file shall be created in

FA461024B0003

Adobe Acrobat. A PCO.TXT file shall contain a valid POC for questions about the file and shall be included on a CD/DVD-ROM. Topographic survey data shall also be submitted electronically to the CO and delivered on the CD/DVD-ROM in a *.csv format. (Preferably PNEZD – comma delimited format). Accuracy level of data provided shall be +/- .02 foot. All projects shall clearly indicate survey site control basis of bearings statement with the control monuments used to establish that control.

All plans shall reflect mean combination ground to grid factor, be printed upon any calculation sheets anytime ground (modified) state plane coordinates are used and can be noted in the bearing source statement. Digital media must have an external label listing the name of the project, contract and TO number, the words “As-Built Record

Set,” and be labeled Controlled Unclassified Information (CUI). The folder shall contain drawings, indexes and X-REF files related to the as-built. A drawing called

BINDED.DWG shall be created. This drawing shall be bound and have no external references.

1.11.2 Final As-Built Preparation for *.DWG files.

1.11.2.1 The following procedures must be performed before a file is placed on the delivery media:

a. When opened, the drawing shall be seen exactly as it should be plotted. Include all files, both graphic and non-graphic, required for the project.

b. Make sure all files are in the same directory, and that references to those files do not include device or directory specifications.

c. Ensure all reference (external reference) files are attached and without device or directory specifications.

d. Remove all extraneous…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .