The document is a Request for Consultant Qualifications (RFCQ) issued by the Port of Newport in Oregon, related to the redesign, permitting, and construction management of the new Port Dock 7. The project includes design and mitigation work, as well as possible replacement of a public fishing pier in South Beach. The key features of the proposed concept include a 20-foot dredged channel, a 41% increase in linear moorage space, two 360-foot side tie docks capable of accommodating large fishing vessels, 50-amp electrical service, a bilge pump-out station, and upland improvements such as additional restrooms, showers, and laundry facilities. The RFCQ covers the jurisdictions of Lincoln County and the City of Newberg.

The RFCQ does not provide specific details on pricing, set-asides, incumbents, funding sources, or contract term. However, it indicates that the project aims to address the current need for moorage of vessels greater than 80 feet in length, provide assigned moorage for vessels up to 70 feet, and incorporate accessibility features for diverse users.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposed Concept Features -20’ channel as part of Army Corps

CAP Section 107 program dredged and maintained by Corps (new-start feasibility study set to start this year)

41% increase in linear moorage space

Total 7,460’ proposed

Total 5,265’ currently

Two 360’ side tie docks deep enough for large fishing vessels that cannot currently use this area at all

50 amp electrical service

Bilge pump-out station

Upland work is necessary (additional restrooms, showers, laundry)

Conceptual Design &

Side tie space provides immediate relief to current need for moorage of vessels greater than 80’ in length

60’ slips provide assigned moorage for vessels up to 70’ in length

Ample space for the smaller number of vessels less than 50’ in length

Port Dock 5 is not part of

Proposed Concept

New steel pilings eliminate need for cross bracing, which is a significant snag hazard for crab pots

New pier runs parallel to current, allowing for crabbing and fishing on both sides of pier during flood or ebb currents

Pathway will complete the walking circuit around the marina, which is a desirable amenity as expressed by OSMB; creates additional funding source

Provides waterside access throughout entire marina

At least one third of the existing pier extends over mudflat; this will be an improvement for public access

Design to focus on accessibility by diverse users; not only ADA compliant, but incorporate every best practice possible