This is a Statement of Work for the Old RT 30 Streambank Stabilization project at Townshend Lake in Townshend, Vermont, administered by the U.S. Army Corps of Engineers. The document provides informational photos and schematics illustrating the streambank stabilization work area and construction methodologies required for the project.
The project involves stabilizing approximately 0.6 miles of eroding streambank along the Deerfield River near the Yellow Gate area at Townshend Lake. The work requires construction of stone toe walls using placed rip rap, with materials placed according to specified dimensions and design standards outlined in technical schematics. Key construction requirements include: stone toe walls constructed with stones of specified size (no stone smaller than 3 inches), staggered joints between adjacent tiers, footer rock embedded minimum 4 feet below channel bottom with 6 feet maximum stacked section exposure, careful stone placement to maximize contact between adjacent stones, and stones dipping toward embankment to resist sliding. The stabilization work also involves rip rap slope protection along portions of the streambank. A separate silt storage area is designated for material management during construction. The document references the Vermont Rivers and Roads Field Manual and Vermont Standard River Management Practices as design standards. Informational photographs show the existing unstabilized streambank conditions, detailed cross-sectional schematics of the proposed toe wall and slope protection systems, and the broader project area boundaries marked along the stream corridor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ26QA069-0002.pdf | ||
| Amendment W912WJ26QA069-0001.pdf | ||
| Solicitation W912WJ26QA069.pdf | ||
| Solicitation Survey 26QA069.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OLD RT 30 STREAMBANK STABILIZATION
U.S. ARMY CORPS OF ENGINEERS
TOWNSHEND LAKE
TOWNSHEND, VERMONT
STATEMENT OF WORK
Informational Photos
Informational Photo 1: Map of area
TOWNSHEND LAKE
Informational Photo 2: Map of area showing silt storage area.
TOWNSHEND LAKE
Informational Photo 3: Toe Wall Schematic (Guardrail is not applicable to this contract)
TOWNSHEND LAKE
Informational Photo 4: Toe Wall Example and Notes
TOWNSHEND LAKE
Informational Photo 5: Rip Rap Slope Schematic (Guardrail is not applicable to this contract)
TOWNSHEND LAKE
Informational Photo 6: Rip Rap Slope Example and Notes
TOWNSHEND LAKE
Informational Photo 7: Subject Streambank Up-Stream
TOWNSHEND LAKE
Informational Photo 8: Subject Streambank Downstream
TOWNSHEND LAKE
Informational Photo 9: Subject Streambank
TOWNSHEND LAKE
Informational Photo 10: Subject Streambank
TOWNSHEND LAKE
Informational Photo 11: Subject Streambank
File details come from the government source that posted it. Updated .