The document provided is a set of attachments related to a State and Local contract opportunity from the Illinois Department of Natural Resources (IDNR) for the installation of two new above-ground fuel storage tanks (ASTs) with dispensing systems. The scope of work includes the installation of one 1,500-gallon unleaded fuel tank and one 500-gallon diesel fuel tank, along with associated concrete pads, bollards, electrical work, and site preparation. The work must be performed in accordance with IEPA and OSFM regulations, and the contractor is required to provide a site plan submittal for review and permitting.
The contract opportunity requires the successful vendor to remove the existing underground storage tanks (USTs) in accordance with regulations, backfill the excavated areas, and install the new concrete pads and ASTs. The contractor is responsible for providing new electrical service to the fuel tanks and pumps as needed. The project location is the Chain O'Lakes site, and the contract is being issued by the Illinois Department of Natural Resources.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Standard Terms and Conditions~8.pdf | ||
| Standard Certifications V.18.1~99.doc | DOC document | |
| 335613_spec_aboveground fuel storage tanks_final.docx | DOCX document | |
| Scope of Work - Installation - Large.docx | DOCX document | |
| SMALL CONSTRUCTION BID FORM~67.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Work Loca on
Tanks Installa on Loca on:
• Elec in conduit
• Bollards
• No fuel loading within
30’ offset area
30’ BLDG OFFSET REQ’D
30’ BLDG OFFSET REQ’D
Preserve lightpole and func onality
Limits of New Conc Pad at
Re-Fueling Area
UST REMOVAL AREA,
BY OTHERS
Contractor shall V.I.F. limits of compacted backfill at
UST removal area, and ne-cessity for sawcuts to extg pavement .
Work Loca on
BACKGROUND: ORIGINAL INSTALLATION DESIGN PLANS, 1999
REMOVE
REMOVE BOTH TANKS REMOVE
REMOVAL PER IEPA AND OSFM
REGULATIONS.
BACKFILL EXCAVATED TANK AREA
WITH COMPACTED CA-6.
REMOVE
REMOVE
PRESERVE
New Conc Paving, 6” thickness, reinforced, and thickness as re-quired under tank for support.
Es mated size 25’ x 30’. Addi-onal 25’ x 30’ paving at UST re-moval area.
NOTES:
INSTALLATION PER IEPA AND OSFM REGULA-
TIONS.
CONTRACTOR TO PROVIDE SITE PLAN SUB-
MITTAL FOR REVIEW AND PERMIT.
PROVIDE NEW ELEC SERVICE TO FUEL TANKS
AND PUMPS AS NEEDED
FINAL LOCATIONS OF SITE PLAN ELEMENTS
PER REVIEW, PERMIT, AND SITE SUPT. INPUT
#1
#2
#3
LEGEND:
#1 = 1500 GAL FUEL TANK (GASOLINE)
#2 = 500 GAL OR UNDER FUEL TANK (DIESEL)
#3 = RE-FUELING PARKING PAD, MIN. 13’ WIDE
Extg Site Light with new elec ser-vice in conduit if required aGer
UST Removal
Concrete filled pipe bollard, 4” dia x 4’ height x 3.5’ deep in 12” dia conc sonotube foo ng. Final qty per approved site plan submiIal and codes. 17 @ 5’ 0.C.