ATTACHMENTS A THRU H - SECIFICATIONS -B1689 .pdf

PDF 9 MB Posted

Attached to
Bldg 1869 Concrete at NAS Corpus Christi, TX
Solicitation number
N6945021Q0021
Issued by

View the file

Other files

File Type Posted
N6945021Q0021-0002.pdf PDF
N6945021Q0021-0001.pdf PDF
ATTACHMENT I - UFC -B1869.pdf PDF
N6945021Q0021.pdf PDF
SECNAV5512 Base Access form Highlighted WITH EDIPI.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Location

ATTACHMENT A

Revised - October 2018

NAVAL AIR STATION CORPUS CHRISTI TEXAS - WASTE SUMMARY SHEET

Name:

Project

Title: POC/Phone:

Number:

Delivery

Order:

Project

Location:

Activity*:

Date of

Project:

Start: End:

Landfill Incinerated **Recycled ***CompostedTypes of Wastes Tons Cost Tons Cost Tons Cost Revenue Tons Cost Revenue

Metals Glass Paper & Paperboard Plastic Wood Asbestos Yard/Green Waste Other Ethylene Glycol Antifreeze Lead-Acid Batteries Used Motor Oil Construction& Demolition General Refuse

*Recycling Facility used:_______________________ **Composting Facility used:______________________ *** Asbestos Disposal Facility:_____________________ **** Waste (Hazardous/Non-Hazardous) Disposal Facility:________________________

Contact Mike Stultz @ 361-961-3776 or michael.r.stultz@navy.mil for details.

john.phillips7 Text Box john.phillips7 Text Box

REMOVE ASPHALT & REPLACE W/CONCRETE

john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box

BLDG. 1869

john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box john.phillips7 Text Box michael.quintanilla Typewritten Text

ATTACHMENT B

Photo -1

Photo -2

ATTACHMENT C

Area A

Area B

Existing concrete surrounding drain to remain. Contractor shall clean existing concrete and seal cracks with concrete sealer. New concrete shall gradually slope towards drain.

Photo -3

Photo -4

Area B

Area B

Contractor shall slope new concrete in similar fashion as existing asphalt by door.

Start slope up starting from this point.

Whole width of the door plus a minimum 8 inches towards the right side of door.

Contractor shall remove and reinstall all concrete splash blocks within the project area.

Photo -5

Area C

Area C

Existing equipment concrete pad to remain.

Existing concrete surrounding drain to remain. Contractor shall clean existing concrete and seal cracks with concrete sealer. New concrete shall gradually slope towards drain.

After placement on new concrete, contractor shall repaint foot traffic path. Color and pattern shall be same as existing. New concrete shall have same slope as existing.

Photo-6

Photo -7

Area D

To avoid new concrete cracking in this area, contractor shall remove approximately 4’ X 4’ section of existing concrete and replace with new concrete. This section shall be part of Area D. Slope new concrete similar to existing slope.

Photo - 8

Remove asphalt overlay, concrete, and replace with new concrete in this area and on the opposite side of this driveway.

Photo - 9

Area E

Photo - 10

Remove bollards and replace with 3 each new bollards, see Attachment H for bollard details. Replace a/c unit pad with new 4” thick reinforced concrete pad.

Contractor shall demolish/remove concrete protrusion shown in photo.

Note: remove abandoned wiring and cap conduit below grade.

Photo - 11

Photo -12

Photo - 13

Photo - 14

Photo - 15

Area F

Area F

New placed concrete shall have the same elevation as existing asphalt and shall gradually slope towards drain.

New placed concrete shall have a gradual slope towards drain.

Photo -16

Area F

Area G

Area G

New placed concrete to gradually slope towards drains.

Concrete driveway and 4 each bollards to remain.

Photo -17

Photo - 18

Area G

Area H

4 each bollards and existing driveway concrete to remain.

AutoCAD SHX Text A

AutoCAD SHX Text B

AutoCAD SHX Text C

AutoCAD SHX Text D

AutoCAD SHX Text E

AutoCAD SHX Text F

AutoCAD SHX Text G

AutoCAD SHX Text H

AutoCAD SHX Text Bldg 1869

AutoCAD SHX Text Bldg 11

AutoCAD SHX Text Approximate Square Feet By Area A - 139 SF B - 1,034 SF C - 1,324 SF D - 1,150 SF E - 1,850 SF F - 1,227 SF G - 1,046 SF H - 252 SF

AutoCAD SHX Text 13'

AutoCAD SHX Text A/C Unit

AutoCAD SHX Text Air Compressor

ATTACHMENT D

6" Aggregate Base Compacted to 98% Maximum Density ASTM D1557

AutoCAD SHX Text 6" Compacted Subgrade 95% Maximum Density ASTM D1557

AutoCAD SHX Text 6"-4,000 PSI Concrete, #4 Rebar @ 12" O.C. Each Way

AutoCAD SHX Text

TYPICAL CONCRETE SECTION N.T.S.

AutoCAD SHX Text Concrete Surface Shall have a Broom Finish

AutoCAD SHX Text *7.5" Thickened-Edge

AutoCAD SHX Text Existing Pavement This Side

AutoCAD SHX Text Notch W/Joint Sealer Between New and Existing Concrete. Coat Surface With Bonding Material

AutoCAD SHX Text *Thickened-Edge Shall Be Used Only Where New Concrete Abuts Concrete Roadways and Driveways.

ATTACHMENT E

1 -0"

2"

ATTACHMENT F

- 1" Crown Concrete Fill

-18 11 1

� 6 11 Gnl vnnized Steel Pipe Filled with concrete, Pnint pipe w/yellow pnint

-Slope concrete nwny froM post

AutoCAD SHX Text 1" Crown Concrete Fill

AutoCAD SHX Text 6" Galvanized Steel Pipe Filled with concrete. Paint pipe w/yellow paint

AutoCAD SHX Text Slope concrete away from post

ATTACHMENT H

"R

PREFORMED EXPANSION

JOINT MATERIAL

JOINT SEALANT

EXPANSION JOINT DETAIL

Not To Scale

3/8"

" DIA BACKER ROD FIT SNUG

INTO JOINT

JOINT SEALANT

SAWED CONTRACTION JOINT DETAIL

Not To Scale

1/2"

BACKER ROD TO FIT SNUG

INTO JOINT

ATTACHMENT F -Cont.

ATTACHMENT G – HAUL ROUTE

B1869

BLDG 1869 PAVEMENT REPAIR

Corpus Christi, Texas

SECTION 32 01 19.61

SEALING OF JOINTS IN RIGID PAVEMENT

11/19

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C603 (2014; R 2019) Standard Test Method for Extrusion Rate and Application Life of Elastomeric Sealants

ASTM C639 (2015; R 2020)Standard Test Method for Rheological (Flow) Properties of Elastomeric Sealants

ASTM C661 (2015) Indentation Hardness of Elastomeric-Type Sealants by Means of a Durometer

ASTM C679 (2003; E 2009; R 2009) Tack-Free Time of Elastomeric Sealants

ASTM C719 (2014; R 2019) Standard Test Method for Adhesion and Cohesion of Elastomeric Joint Sealants Under Cyclic Movement (Hockman Cycle)

ASTM C792 (2015; R 2020) Effects of Heat Aging on Weight Loss, Cracking, and Chalking of Elastomeric Sealants

ASTM C793 (2005; R 2017) Standard Test Method for Effects of Laboratory Accelerated Weathering on Elastomeric Joint Sealants

ASTM C920 (2018) Standard Specification for Elastomeric Joint Sealants

ASTM C1016 (2014) Standard Test Method for Determination of Water Absorption of Sealant Backing (Joint Filler) Material

ASTM C1193 (2013) Standard Guide for Use of Joint Sealants

ASTM D412 (2016) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension

ASTM D789 (2015) Determination of Relative Viscosity

SECTION 32 01 19.61 Page 1

ATTACHMENT H

and Moisture Content of Polyamide (PA)

ASTM D903 (1998; R 2017) Standard Test Method for Peel or Stripping Strength of Adhesive Bonds

ASTM D5249 (2010; R 2016) Standard Specification for Backer Material for Use with Cold-and Hot-Applied Joint Sealants in Portland-Cement Concrete and Asphalt Joints

ASTM D5329 (2016) Standard Test Methods for Sealants and Fillers, Hot-Applied, for Joints and Cracks in Asphalt Pavements and Portland Cement Concrete Pavements

ASTM D5893/D5893M (2016) Standard Specification for Cold Applied, Single Component, Chemically Curing Silicone Joint Sealant for Portland Cement Concrete Pavements

ASTM D6690 (2015) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements

U.S. ARMY CORPS OF ENGINEERS (USACE)

COE CRD-C 525 (1989) Corps of Engineers Test Method for Evaluation of Hot-Applied Joint Sealants for Bubbling Due to Heating

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

Sealants

Submit catalog cuts, specifications, Safety Data Sheets and other information documenting conformance to Contract requirements.

Manufacturer's Recommendations

SD-04 Samples

Sealants

Provide for testing a 5-gal sample of each sealant with associated primer to the Contracting Officer a minimum of 60 days prior to its use on the job. Provide factory-sealed containers with a factory applied label showing the following information:

Name of sealant

Identification of component, or primer

SECTION 32 01 19.61 Page 2

Specification number and type

Manufacturer's name

Manufacturer's lot and batch number

Date of Manufacture (month and year)

Shelf life retest date (month and year)

List of hazardous components

Quantity of material in container (volume)

Storage instructions

Instructions for use

Blocking Media/Backup Materials

Backer Rod

Bond Breaking Tapes

SD-06 Test Reports

Sealants

SD-07 Certificates

Equipment List

SD-08 Manufacturer's Instructions

Sealants

Provide instructions that include, but not limited to: storage requirements, ambient temperature and humidity ranges, and moisture condition of joints for successful installation;

requirements for preparation of joints; safe heating temperature;

mixing instructions; installation equipment and procedures;

application and disposal requirements; compatibility of sealant with filler material; curing requirements; and restrictions to be adhered to in order to reduce hazards to personnel or to the environment. Submit instructions at least 30 days prior to use.

1.3 QUALITY ASSURANCE

1.3.1 Test Requirements

Test the sealant and backup or separating material for conformance with the referenced material specification. Perform testing of the materials in an approved independent laboratory and submit certified copies of the test reports for approval 10 days prior to the use of the materials at the job site. Submit samples to be retained by the Government for possible future testing if the materials appear defective during or after application.

Conformance with the requirements of the laboratory tests specified does not constitute final acceptance of the materials. Base final acceptance

SECTION 32 01 19.61 Page 3 on the performance of the in-place materials. Submit samples of the materials (sealant, primer if required, and backup material), in sufficient quantity for testing and approval 10 days prior to the beginning of work. Do not use material until it has been approved.

1.4 DELIVERY, STORAGE, AND HANDLING

Inspect materials delivered to the site for visible damage, and unload and store with a minimum of handling. Deliver joint materials in original sealed containers and protect from freezing or overheating. Provide jobsite storage facilities capable of maintaining temperature ranges within manufacturers recommendations.

1.5 ENVIRONMENTAL REQUIREMENTS

Do not proceed with work when weather conditions detrimentally affect the quality of cleaning joints or applying sealants. Proceed with joint preparation and sealing only when weather conditions are in accordance with manufacturer's instructions. Install joint sealant to dry surfaces and protect sealant and bond breakers from moisture.

1.6 TRAFFIC CONTROL

Do not permit vehicular or heavy equipment traffic on the pavement in the area of the joints being sealed during the protection and curing period of the sealant. Permit traffic on the pavement at the end of the curing period.

PART 2 PRODUCTS

2.1 SEALANTS

Use materials for sealing cracks in accordance with ASTM D6690 and ASTM D5893/D5893M based on the type of area as follows:

Area Sealing Material

TRANSVERSE OR LONGITUDINAL JOINTS ASTM D6690, Type II and ASTM D5329/

COE CRD-C 525

Use self leveling, non-acid curing silicone sealant meeting the following requirements in accordance with ASTM C920 or ASTM C1193:

TEST TEST METHOD REQUIREMENTS

Weight Loss ASTM C792 Modified (see Note 1 below)

10 percent max.

Flow ASTM C639 (Type I) Smooth and level

SECTION 32 01 19.61 Page 4

TEST TEST METHOD REQUIREMENTS

Extrusion Rate ASTM C603 30 sec. max.

Tack Free Time ASTM C679 5 hours max.

Hardness (Shore 00) (see Note 2 below)

ASTM C661 30 - 80

Tensile Stress at 150 Percent Elongation (see Note 2 below)

ASTM D412 (Die C) 30 psi max.

Percent Elongation (see Note 2 below)

ASTM D412 (Die C) 700 min.

Accelerated Weathering ASTM C793 Pass 5000 hours

Bond and Movement Capability ASTM C719 Pass 10 cycles at plus 50 percent movement (no adhesion or cohesion failure)

Peel ASTM D903 Minimum 20 psi of width with at least 75 percent cohesive failure

NOTES:

1. Percent weight loss of wet (uncured) sample after placing in forced-draft oven maintained at 158 degrees plus 1 degree F for two hours.

2. Specimen cured 21 days at 73 degrees plus 1 degree F and 50 percent plus 5 percent humidity.

ACCELERATED WEATHERING FACTORY TEST REPORT. For the Accelerated Weathering test, in lieu of testing of actual sealant to be used on the project, it is permitted to submit a report of a factory test, performed within two years of Contract award.

2.2 PRIMERS

Use primers in accordance with the recommendation of the manufacturer.

2.3 BOND BREAKERS

2.3.1 Blocking Media/Backup Materials

Provide backup (joint filler) material that is a compressible, nonshrinking, nonstaining, nonabsorbing, nonreactive material with the sealant. Use backup material compliant with ASTM D5249. Use material with a melting point at least 5 degrees F greater than the pouring temperature of the sealant being used when tested in accordance with ASTM D789. Use material with a water absorption of not more than 5 percent of the sample weight when tested in accordance with ASTM C1016.

Use backup (joint filler) material that is 25 plus or minus 5 percent larger in diameter than the nominal width of the crack. Use blocking media consistent with the sealant manufacturer's installation instructions.

SECTION 32 01 19.61 Page 5

2.3.2 Bond Breaking Tapes

Provide a bond breaking tape or separating material that is a flexible, nonshrinkable, nonabsorbing, nonstaining, and nonreacting adhesive-backed tape. Use material with a melting point at least 5 degrees F greater than the pouring temperature of the sealant being used when tested in accordance with ASTM D789. Use bond breaker tape approximately 1/8 in wider than the nominal width of the joint and that does not bond to the sealant. Use bond breaking tape shall be consistent with the sealant manufacturer's installation instructions.

PART 3 EXECUTION

3.1 EXECUTING EQUIPMENT

Submit equipment list and description of the equipment to be used and a statement from the supplier of the sealant that the proposed equipment is acceptable for installing the specified sealant. Use equipment for heating, mixing, and installing seals in accordance with the instructions provided by the sealant manufacturer. Provide equipment, tools, and accessories necessary to clean existing joints and install liquid joint sealants. Maintain machines, tools, and other equipment in proper working condition. Submit a list of proposed equipment to be used in performance of construction work including descriptive data, 10 days prior to use on the project.

3.1.1 Joint Cleaning Equipment

3.1.1.1 Concrete Saw

Provide a self-propelled power saw, with water-cooled diamond or abrasive saw blades, for cutting joints to the depths and widths specified, for refacing joints, cleaning sawed joints where sandblasting does not provide a clean joint, widening, or deepening existing joints as specified without damaging the sides, bottom, or top edge of joints. Permit single or gang type blades with one or more blades mounted in tandem for fast cutting.

Select saw adequately powered and sized to cut specified opening with not more than two passes of the saw through the joint.

3.1.1.2 Sandblasting Equipment

Due to the location of this project on an active airfield, sandblasting is not permitted.

3.1.1.3 Waterblasting Equipment

Include with the waterblasting equipment a trailer-mounted water tank, pumps, high-pressure hose, wand with safety release cutoff control, nozzle, and auxiliary water resupply equipment. Provide water tank and auxiliary resupply equipment of sufficient capacity to permit continuous operations. Use a nozzle with an adjustable guide that holds the nozzle aligned with the joint approximately 1 in above the pavement surface.

Adjust the height, angle of inclination and the size of the nozzle to obtain satisfactory results. Use a pressure gauge mounted at the pump that shows the pressure in psi at which the equipment is operating.

3.1.1.4 Hand Tools

Permit the use of hand tools, such as brooms and chisels, when approved, for removing defective sealant from a crack and repairing or cleaning the

SECTION 32 01 19.61 Page 6 crack faces.

3.1.2 Sealing Equipment

Use joint sealing equipment of a type required by the sealant manufacturer's installation instructions. Use equipment capable of installing sealant to the depths, widths and tolerances indicated. Do not proceed with joint sealing when malfunctions are noted until the malfunctions are corrected.

3.1.2.1 Hot-Poured Sealing Equipment

Use mobile unit applicators equipped with a double-boiler, agitator-type kettle with an oil medium in the outer space for heat transfer for heating and installing ASTM D6690 joint sealant materials; a direct-connected pressure-type extruding device with a nozzle shaped for inserting in the joint to be filled; positive temperature devices for controlling the temperature of the transfer oil and sealant; and a recording thermometer for indicating the temperature of the sealant. Use an applicator unit designed so that the sealant circulates through the delivery hose and returns to the inner kettle when not in use.

3.2 SAFETY

Do not place sealant within 25 ft of LOX equipment, LOX storage, or LOX piping. Clean joints in this area and leave them unsealed.

In accordance with the provisions of the Contract respecting "Accident Prevention," take appropriate measures to control worker exposure to toxic substances during the work. Provide personnel protective equipment as required. Make Material Safety Data Sheets (Department of Labor Form OSHA-20 or comparable form) available on the site.

3.3 PREPARATION OF JOINTS

Unless otherwise indicated, remove existing material, saw, clean and reseal joints. Do not proceed with final cleaning operations by more than one working day in advance of sealant. Clean joints by removing existing joint sealing compound, bond-breakers, dirt, laitance, curing compound, filler, and protrusions of hardened concrete from the sides and upper edges of the joint space to be sealed and other foreign material with the equipment. Do not permit cleaning procedures that damage joints or previously repaired patches by chipping or spalling. Remove existing sealant to the required depth. Precise shape and size of existing joints vary, and conditions of joint walls and edges vary and include but are not limited to rounding, square edges, sloping, chips, voids, depressions, and projections.

3.3.1 Existing Sealant Removal

Cut loose the in-place sealant from both joint faces and to the required depth, using the waterblaster as specified in paragraph EQUIPMENT.

Provide a depth sufficient to accommodate blocking media and bond breakers that are required to maintain the depth of new sealant to be installed.

For expansion joints, remove existing sealant to a depth of not less than the indicated depth. When existing preformed expansion-joint material is more than 1 in below the surface of the pavement, remove existing sealant to the top of the preformed joint filler. Prior to further cleaning operations, remove loose old sealant remaining in the joint opening by

SECTION 32 01 19.61 Page 7 blowing with compressed air. Permit use of hand tools to remove sealant from random cracks. Do not permit chipping, spalling, or other damage to the concrete. Clean pavement surface with vacuum sweeper. Protect previously cleaned joints from being contaminated by subsequent cleaning operations.

3.3.2 Sawing

3.3.2.1 Refacing of Joints

Accomplish refacing of joints using a concrete saw as specified in paragraph EQUIPMENT to remove residual old sealant and a minimum of concrete from the joint face to provide exposure of newly cleaned concrete, and, if required, to enlarge the joint opening to the width and depth shown on the drawings. Provide exposure of newly clean concrete through removal. Remove burrs and irregularities from sides of joint faces. Stiffen the blade with a sufficient number of dummy (used) blades or washers. Clean, immediately following the sawing operation, the joint opening using a water jet to remove saw cuttings and debris and adjacent concrete surface. Protect adjacent previously cleaned joint spaces from receiving water and debris during the cleaning operation.

a. Joint Widening (Except Expansion Joints): Saw joints having grooves less than 3/8 in wide and less than 1 in deep to a minimum width of 3/8 in and to the minimum depth, of 1 in .

3.3.3 Final Cleaning of Joints

3.3.3.1 Water blasting

The newly exposed concrete joint faces and the concrete pavement surface extending a minimum of 1/2 inch from the joint edge shall be waterblasted clean. use a multiple-pass technique until the surfaces are free of dust, dirt, curing compound, or any foreign debris that might prevent the bonding of the sealant to the concrete. After final cleaning and immediately prior to sealing, blow out the joints with compressed air and leave them completely free of debris and water. Use of a heated lance may be required to ensure the reservoir is free of water and sufficiently dry to receive the hot pour sealant.

3.3.4 Bond Breaker

At the time the joints receive the final cleaning and are dry, install bond breaker material as indicated with a steel wheel or other approved device.

3.3.4.1 Blocking Media ( Backer Rod ) (Except for Expansion Joints)

When the joint opening is of a greater depth than indicated for the sealant depth, plug or seal off the lower portion of the joint opening using a blocking media/back-up material to prevent the entrance of the sealant below the specified depth. Take care to ensure that the blocking media/backup material is placed at the specified depth and is not stretched or twisted during installation.

3.3.4.2 Bond Breaking Tape

Where inserts or filler materials contain bitumen, or the depth of the joint opening does not allow for the use of a backup material, insert a

SECTION 32 01 19.61 Page 8 bond breaker separating tape to prevent incompatibility with the filler materials and three-sided adhesion of the sealant. Bond the tape to the bottom of the joint opening to prevent it from floating up into the new sealant.

3.3.5 Rate of Progress of Joint Preparation

Limit the stages of joint preparation, including sandblasting, air pressure cleaning and placing of the back-up material to only that lineal footage that can be sealed during the same day.

3.3.6 Disposal of Debris

Sweep pavement surface to remove excess joint material, dirt, water, sand, and other debris by vacuum sweepers or hand brooms. Remove the debris immediately to a designated area. .

3.4 PREPARATION OF SEALANT

3.4.1 Hot-Poured Sealants

Heat hot-poured sealing materials in accordance with ASTM D6690 and with safe heating temperature ranges recommended by the manufacturer. Withdraw and waste sealant that has been overheated or subjected to heating for over 3 hours or that remain in the applicator at the end of the day's operation. Heat sealant in specified equipment.

3.5 INSTALLATION OF SEALANT

3.5.1 Time of Application

After approval of the test section, seal joints immediately following final cleaning and placing of bond breakers. Commence sealing joints when walls are dust free and dry, and when weather conditions meet sealant manufacturer's instructions. If the above conditions cannot be met, or when rain interrupts sealing operations, reclean and permit the joints to dry prior to installing the sealant.

3.5.2 Sealing Joints

Do not install joint sealant until joints to be sealed have been inspected and approved. Install bond breaker just prior to pouring sealant. Fill the joints with sealant from bottom up until joints are uniformly filled solid from bottom to top using the specified equipment for the type of sealant required. Fill joints to 1/8 in plus or minus 1/16 in below top of pavement, and without formation of voids or entrapped air. Do not permit gravity methods or pouring pots to be used to install the sealant material. Except as otherwise permitted, tool the sealant immediately after application to provide firm contact with the joint walls and to form the indicated sealant profile below the pavement surface. Remove excess sealant that has been inadvertently spilled on the pavement surface. Do not permit traffic over newly sealed pavement until authorized. When a primer is recommended by the manufacturer, apply it evenly to the joint faces in accordance with the manufacturer's recommendations . Check sealed joints frequently to ensure that newly installed sealant is cured to a tack-free condition within the specified time. Protect new sealant from rain during curing period.

SECTION 32 01 19.61 Page 9

3.6 INSPECTION/FIELD QUALITY CONTROL

3.6.1 Joint Cleaning

Inspect joints during the cleaning process to correct improper equipment and cleaning techniques that damage the concrete pavement in any manner.

Approve cleaned joints prior to installation of the separating or back-up material and joint sealant.

3.6.2 Sampling Sealant

Obtain a one gal sample of each type of sealant on the project from material used for each 10,000 linear ft or less of joints sealed. Store samples according to sealant manufacturer's instructions. Retain samples until final acceptance of the work.

3.6.3 Sealant Application Equipment

Inspect the application equipment to ensure conformance to temperature requirements, proper proportioning and mixing (if two-component sealant) and proper installation. Suspend operations if there is evidences of bubbling, improper installation, or failure to cure or set until causes of the deficiencies are determined and corrected.

3.6.4 Joint Sealant

Inspect the joint sealant for proper rate of cure and set, bonding to the joint walls, cohesive separation within the sealant, reversion to liquid, entrapped air and voids. Remove sealants exhibiting these deficiencies prior to the final acceptance of the project from the joint, wasted, and replace at no additional cost to the Government. Obtain approval for each joint seal installation.

3.7 ACCEPTANCE

Reject sealer that fails to cure properly, or fails to bond to joint walls, or reverts to the uncured state, or fails in cohesion, or shows excessive air voids, blisters, surface defects, swelling, or other deficiencies, or is not properly recessed within indicated tolerances.

Remove rejected sealer and reclean and reseal joints. Perform removal and reseal work promptly by and at the expense of the Contractor.

3.8 CLEAN-UP

Upon completion of the project, remove unused materials from the site and leave the pavement in a clean condition.

-- End of Section --

SECTION 32 01 19.61 Page 10

SECTION 32 11 23

AGGREGATE BASE COURSES

08/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO T 88 (2013) Standard Method of Test for Particle Size Analysis of Soils

AASHTO T 180 (2017) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop

AASHTO T 224 (2010) Standard Method of Test for Correction for Coarse Particles in the Soil Compaction Test

ASTM INTERNATIONAL (ASTM)

ASTM C117 (2017) Standard Test Method for Materials Finer than 75-um (No. 200) Sieve in Mineral Aggregates by Washing

ASTM C127 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate

ASTM C128 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Fine Aggregate

ASTM C131/C131M (2020) Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine

ASTM C136/C136M (2019) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates

ASTM D75/D75M (2019) Standard Practice for Sampling Aggregates

ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method

SECTION 32 11 23 Page 1

ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D2167 (2015) Density and Unit Weight of Soil in Place by the Rubber Balloon Method

ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)

ASTM D4318 (2017; E 2018) Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils

ASTM D5821 (2013; R 2017) Standard Test Method for Determining the Percentage of Fractured Particles in Coarse Aggregate

ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

ASTM E11 (2020) Standard Specification for Woven Wire Test Sieve Cloth and Test Sieves

1.2 DEFINITIONS

For the purposes of this specification, the following definitions apply.

1.2.1 Aggregate Base Course

Aggregate base course (ABC) is well graded, durable aggregate uniformly moistened and mechanically stabilized by compaction.

1.2.2 Degree of Compaction

Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum laboratory dry density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum dry density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve will be expressed as a percentage of the laboratory maximum dry density in accordance with AASHTO T 180 Method D and corrected with AASHTO T 224 .

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

SECTION 32 11 23 Page 2

Plant, Equipment, and Tools ; G Waybills and Delivery Tickets

SD-06 Test Reports

Initial Tests ; G In-Place Tests ; G

1.4 EQUIPMENT, TOOLS, AND MACHINES

All plant, equipment, and tools used in the performance of the work will be subject to approval by the Contracting Officer before the work is started. Maintain all plant, equipment, and tools in satisfactory working condition at all times. Submit a list of proposed equipment, including descriptive data. Use equipment capable of minimizing segregation, producing the required compaction, meeting grade controls, thickness control, and smoothness requirements as set forth herein.

1.5 QUALITY ASSURANCE

Sampling and testing are the responsibility of the Contractor. Perform sampling and testing using a laboratory approved in accordance with Section 01 45 00.00 20 QUALITY CONTROL. Work requiring testing will not be permitted until the testing laboratory has been inspected and approved. Test the materials to establish compliance with the specified requirements and perform testing at the specified frequency. The Contracting Officer may specify the time and location of the tests.

Furnish copies of test results to the Contracting Officer within 24 hours of completion of the tests.

1.5.1 Sampling

Take samples for laboratory testing in conformance with ASTM D75/D75M.

When deemed necessary, the sampling will be observed by the Contracting Officer.

1.5.2 Tests

1.5.2.1 Sieve Analysis

Perform sieve analysis in conformance with ASTM C117 and ASTM C136/C136M using sieves conforming to ASTM E11. Perform particle-size analysis of the soils in conformance with AASHTO T 88 .

1.5.2.2 Liquid Limit and Plasticity Index

Determine liquid limit and plasticity index in accordance with ASTM D4318.

1.5.2.3 Moisture-Density Determinations

Determine the laboratory maximum dry density and optimum moisture content in accordance with paragraph DEGREE OF COMPACTION.

1.5.2.4 Field Density Tests

Measure field density in accordance with ASTM D1556/D1556M , ASTM D2167 or ASTM D6938. For the method presented in ASTM D1556/D1556M use the base

SECTION 32 11 23 Page 3 plate as shown in the drawing. For the method presented in ASTM D6938 check the calibration curves and adjust them, if necessary, using only the sand cone method as described in paragraph Calibration, of the ASTM publication. Tests performed in accordance with ASTM D6938 result in a wet unit weight of soil and ASTM D6938 will be used to determine the moisture content of the soil. Also check the calibration curves furnished with the moisture gauges along with density calibration checks as described in ASTM D6938. Make the calibration checks of both the density and moisture gauges using the prepared containers of material method, as described in paragraph Calibration of ASTM D6938, on each different type of material being tested at the beginning of a job and at intervals as directed. Submit calibration curves and related test results prior to using the device or equipment being calibrated.

1.5.2.5 Wear Test

Perform wear tests on ABC course material in conformance with

ASTM C131/C131M.

1.6 ENVIRONMENTAL REQUIREMENTS

Perform construction when the atmospheric temperature is above 35 degrees F .

When the temperature falls below 35 degrees F , protect all completed areas by approved methods against detrimental effects of freezing. Correct completed areas damaged by freezing, rainfall, or other weather conditions to meet specified requirements.

PART 2 PRODUCTS

2.1 AGGREGATES

Provide ABC consisting of clean, sound, durable particles of crushed stone, crushed gravel, crushed recycled concrete, angular sand, or other approved material. Provide ABC that is free of lumps of clay, organic matter, and other objectionable materials or coatings. The portion retained on the No. 4 sieve is known as coarse aggregate; that portion passing the No. 4 sieve is known as fine aggregate. When the coarse and fine aggregate is supplied form more than one source, provide aggregate from each source that meets the specified requirements.

2.1.1 Coarse Aggregate

Provide coarse aggregates with angular particles of uniform density.

Separately stockpile coarse aggregate supplied from more than one source.

a. Crushed Gravel: Provide crushed gravel that has been manufactured by crushing gravels and that meets all the requirements specified below.

b. Crushed Stone: Provide crushed stone consisting of freshly mined quarry rock, meeting all the requirements specified below.

c. Crushed Recycled Concrete: Provide crushed recycled concrete consisting of previously hardened portland cement concrete or other concrete containing pozzolanic binder material. Provide recycled concrete that is free of all reinforcing steel, bituminous concrete surfacing, and any other foreign material and that has been crushed and processed to meet the required gradations for coarse aggregate.

Reject recycled concrete aggregate exceeding this value. Provide crushed recycled concrete that meets all other applicable requirements

SECTION 32 11 23 Page 4 specified below.

2.1.1.1 Aggregate Base Course

The percentage of loss of ABC coarse aggregate must not exceed 50 percent when tested in accordance with ASTM C131/C131M. Provide aggregate that contains no more than 30 percent flat and elongated particles. A flat particle is one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than

3. In the portion retained on each sieve specified, the crushed aggregates must contain at least 50 percent by weight of crushed pieces having two or more freshly fractured faces determined in accordance with ASTM D5821. When two fractures are contiguous, the angle between planes of the fractures must be at least 30 degrees in order to count as two fractured faces. Manufacture crushed gravel from gravel particles 50 percent of which, by weight, are retained on the maximum size sieve listed in TABLE 1.

2.1.2 Fine Aggregate

Provide fine aggregates consisting of angular particles of uniform density.

2.1.2.1 Aggregate Base Course

Provide ABC fine aggregate that consists of screenings, angular sand, crushed recycled concrete fines, or other finely divided mineral matter processed or naturally combined with the coarse aggregate.

2.1.3 Gradation Requirements

Apply the specified gradation requirements to the completed base course.

Provide aggregates that are continuously well graded within the limits specified in TABLE 1. Use sieves that conform to ASTM E11.

TABLE 1. GRADATION OF AGGREGATES

Percentage by Weight Passing Square-Mesh Sieve

Sieve Designation No. 3

2 inch ---- 1-1/2 inch ---- 1 inch 100 1/2 inch 40-70 No. 4 20-50 No. 10 15-40 No. 40 5-25 No. 200 0-8

NOTE 1: Particles having diameters less than 0.02 mm must not be in excess of 3 percent by weight of the total sample tested as determined in accordance with AASHTO T 88 .

NOTE 2: The values are based on aggregates of uniform specific gravity.

SECTION 32 11 23 Page 5

If materials from different sources are used for the coarse and fine aggregates, test the materials in accordance with ASTM C127 and ASTM C128 to determine their specific gravities. Correct the percentages passing the various sieves as directed by the Contracting Officer if the specific gravities vary by more than 10 percent.

2.2 LIQUID LIMIT AND PLASTICITY INDEX

Apply liquid limit and plasticity index requirements to the completed course and to any component that is blended to meet the required gradation. The portion of any component or of the completed course passing the No. 40 sieve must be either nonplastic or have a liquid limit not greater than 25 and a plasticity index not greater than 5.

2.3 TESTS, INSPECTIONS, AND VERIFICATIONS

2.3.1 Initial Tests

Perform one of each of the following tests, on the proposed material prior to commencing construction, to demonstrate that the proposed material meets all specified requirements when furnished. Complete this testing for each source if materials from more than one source are proposed.

a. Sieve Analysis including 0.02 mm material.

b. Liquid limit and plasticity index.

c. Moisture-density relationship.

d. Wear.

e. .

f. .

g. .

Submit certified copies of test results for approval not less than 30 days before material is required for the work.

2.3.2 Approval of Material

Tentative approval of material will be based on initial test results.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

When the ABC is constructed in more than one layer, clean the previously constructed layer of loose and foreign matter by sweeping with power sweepers or power brooms, except that hand brooms may be used in areas where power cleaning is not practicable. Provide adequate drainage during the entire period of construction to prevent water from collecting or standing on the working area.

3.2 OPERATION OF AGGREGATE SOURCES

Clearing, stripping, and excavating are the responsibility of the Contractor. Condition aggregate sources on Government property to readily

SECTION 32 11 23 Page 6 drain and leave in a satisfactory condition upon completion of the work.

3.3 STOCKPILING MATERIAL

Clear and level storage sites prior to stockpiling of material. Stockpile all materials, including approved material available from excavation and grading, in the manner and at the locations designated. Stockpile aggregates on the cleared and leveled areas designated by the Contracting Officer to prevent segregation. Stockpile materials obtained from different sources separately.

3.4 PREPARATION OF UNDERLYING COURSE OR SUBGRADE

Clean the underlying course or subgrade of all foreign substances prior to constructing the base course(s). Do not construct base course(s) on underlying course or subgrade that is frozen. Construct the surface of the underlying course or subgrade to meet specified compaction and surface tolerances. Correct ruts or soft yielding spots in the underlying courses, areas having inadequate compaction, and deviations of the surface from the specified requirements set forth herein by loosening and removing soft or unsatisfactory material and adding approved material, reshaping to line and grade, and recompacting to specified density requirements. For cohesionless underlying courses or subgrades containing sands or gravels, as defined in ASTM D2487, stabilize the surface prior to placement of the base course(s). Stabilize by mixing ABC into the underlying course and compacting by approved methods. Consider the stabilized material as part of the underlying course and meet all requirements of the underlying course. Do not allow traffic or other operations to disturb the finished underlying course and maintain in a satisfactory condition until the base course is placed.

3.5 GRADE CONTROL

Provide a finished and completed base course conforming to the lines, grades, and cross sections shown. Place line and grade stakes as necessary for control.

3.6 MIXING AND PLACING MATERIALS

Mix the coarse and fine aggregates in a stationary plant. Make adjustments in mixing procedures or in equipment, as directed, to obtain true grades, to minimize segregation or degradation, to obtain the required water content, and to insure a satisfactory base course meeting all requirements of this specification. Place the mixed material on the prepared subgrade or subbase in layers of uniform thickness with an approved spreader. Place the layers so that when compacted they will be true to the grades or levels required with the least possible surface disturbance. Where the base course is placed in more than one layer, clean the previously constructed layers of loose and foreign matter by sweeping with power sweepers, power brooms, or hand brooms, as directed.

Make adjustments in placing procedures or equipment as may be directed by the Contracting Officer to obtain true grades, to minimize segregation and degradation, to adjust the water content, and to insure an acceptable base course.

3.7 LAYER THICKNESS

Compact the completed base course to the thickness indicated. No individual layer may be thicker than 6 inches nor be thinner than 3 inches

SECTION 32 11 23 Page 7 in compacted thickness. Compact the base course(s) to a total thickness that is within 1/2 inch of the thickness indicated. Where the measured thickness is more than 1/2 inch deficient, correct such areas by scarifying, adding new material of proper gradation, reblading, and recompacting as directed. Where the measured thickness is more than 1/2 inch thicker than indicated, the course will be considered as conforming to the specified thickness requirements. The average job thickness will be the average of all thickness measurements taken for the job and must be within 1/4 inch of the thickness indicated. Measure the total thickness of the base course once per pad . Measure total thickness using 3 inch diameter test holes penetrating the base course.

3.8 COMPACTION

Compact each layer of the base course, as specified, with approved compaction equipment. Maintain water content during the compaction procedure to within plus or minus 2 percent of the optimum water content determined from laboratory tests as specified in this Section. Begin rolling at the outside edge of the surface and proceed to the center, overlapping on successive trips at least one-half the width of the roller. Slightly vary the length of alternate trips of the roller.

Adjust speed of the roller as needed so that displacement of the aggregate does not occur. Compact mixture with hand-operated power tampers in all places not accessible to the rollers. Continue compaction until each layer is compacted through the full depth to at least 98 percent of laboratory maximum density. Make such adjustments in compacting or finishing procedures as may be directed by the Contracting Officer to obtain true grades, to minimize segregation and degradation, to reduce or increase water content, and to ensure a satisfactory base course. Remove any materials found to be unsatisfactory and replace with satisfactory material or rework, as directed, to meet the requirements of this specification.

3.9 EDGES OF BASE COURSE

Place the base course(s) so that the completed section will be a minimum of 6 inch wider, on all sides, than the next layer that will be placed above

it. Place approved material along the outer edges of the base course in sufficient quantity to compact to the thickness of the course being constructed. When the course is being constructed in two or more layers, simultaneously roll and compact at least a 2 foot width of this shoulder material with the rolling and compacting of each layer of the base course, as directed.

3.10 FINISHING

Finish the surface of the top layer of base course after final compaction by cutting any overbuild to grade and rolling with a steel-wheeled roller. Do not add thin layers of material to the top layer of base course to meet grade. If the elevation of the top layer of base course is 1/2 inch or more below grade, scarify the top layer to a depth of at least 3 inches and blend new material in and compact to bring to grade. Make adjustments to rolling and finishing procedures as directed by the Contracting Officer to minimize segregation and degradation, obtain grades, maintain moisture content, and insure an acceptable base course.

Should the surface become rough, corrugated, uneven in texture, or traffic marked prior to completion, scarify the unsatisfactory portion and rework and recompact it or replace as directed.

SECTION 32 11 23 Page 8

3.11 SMOOTHNESS TEST

Construct the top layer so that the surface shows no deviations in excess of 3/8 inch when tested with a 12 foot straightedge. Take measurements in each direction approximately 1-foot from the edges and at the one-third and two-third points (total of 8 points) . Correct deviations exceeding this amount by removing material and replacing with new material, or by reworking existing material and compacting it to meet these specifications.

3.12 FIELD QUALITY CONTROL

3.12.1 In-Place Tests

Perform each of the following tests on samples taken from the placed and compacted ABC . Take samples and test at the rates indicated. Perform sampling and testing of recycled concrete aggregate at twice the specified frequency until the material uniformity is established.

a. Perform density tests on every lift of material placed and at a frequency of one set of tests for each pad constructed .

b. Perform sieve analysis including 0.02 mm size material on every lift of material placed and at a frequency of one sieve analysis for every 5 pads .

c. Perform liquid limit and plasticity index tests at the same frequency as the sieve analysis.

d. Measure the thickness of the base course one per pad . Measure the thickness using a test hole, at least 3 inch in diameter through the base course.

3.12.2 Approval of Material

Final approval of the materials will be based on tests for gradation, liquid limit, and plasticity index performed on samples taken from the completed and fully compacted course(s).

3.13 TRAFFIC

Completed portions of the base course may be opened to limited traffic, provided there is no marring or distorting of the surface by the traffic.

Do not allow heavy equipment on the completed base course except when necessary for construction. When it is necessary for heavy equipment to travel on the completed base course, protect the area against marring or damage to the completed work.

3.14 MAINTENANCE

Maintain the base course in a satisfactory condition until the full pavement section is completed and accepted. Immediately repair any defects and repeat repairs as often as necessary to keep the area intact.

Retest any base course that was not paved over prior to the onset of winter to verify that it still complies with the requirements of this specification. Rework or replace any area of base course that is damaged as necessary to comply with this specification.

SECTION 32 11 23 Page 9

3.15 DISPOSAL OF UNSATISFACTORY MATERIALS

Dispose of any unsuitable materials that have been removed as directed .

No additional payments will be made for materials that have to be replaced.

-- End of Section --

SECTION 32 11 23 Page 10

SECTION 32 13 14.13

CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS

08/19

PART 1 GENERAL

1.1 UNIT PRICES

1.1.1 Measurements

The quantity of concrete to be paid for will be the volume of concrete in cubic yards including thickened edges, where required, placed in the completed and accepted pavement. Concrete will be measured in place in the completed and accepted pavement only within the neat line dimensions shown in the plan and cross section. No deductions will be made for rounded or beveled edges or the space occupied by pavement reinforcement, dowel bars, or electrical conduits, nor for any void, or other structure extending into or through the pavement slab, measuring 3 cubic feet or less in volume. No other allowance for concrete will be made unless placed in specified locations in accordance with the approved contract modification. The quantity of other materials specified herein, and used in the construction of the work covered by this section, will not be measured for payment, but will be considered a subsidiary obligation, covered under the price per cubic yard for concrete.