This document is a solicitation for campground and boat launch paving project by the U.S. Army Corps of Engineers - New England District in Vermont. The contract requires a contractor to prepare existing gravel surfaces and install new hot mix bituminous concrete pavement in two primary locations: the Winhall Brook Camping Area and Ball Mountain Lake. The primary work involves preparing surfaces and installing asphalt pavement in turnaround and parking area expansion zones, with an optional task for repairs along the boat launch road at Ball Mountain Lake.
The procurement is set aside exclusively for small businesses, with a construction contract value between $25,000 and $100,000. The applicable NAICS code is 237310 with a small business size standard of $45 million. Critical vendor requirements include having an active SAM.gov registration at the time of submission, with any vendor lacking active registration being automatically rejected as non-responsive. The solicitation includes 15 informational photos documenting the specific work areas, surface conditions, and proposed paving locations across both project sites.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment W912WJ25QA066-0002.pdf | ||
| Attachments 25QA066_Revised.pdf | ||
| Amendment W912WJ25QA066-0001.pdf | ||
| Solicitation W912WJ25QA066.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BALL MOUNTAIN LAKE PAVING
U.S. ARMY CORPS OF ENGINEERS
BALL MOUNTAIN LAKE
JAMAICA, VERMONT
STATEMENT OF WORK
Informational Photos
Photo 1: Map showing work area within the Winhall Brook Camping Area.
Photo 2: Close up of work area and indications of Campsite S70 and gate for West River Trail.
Photo 3: Transition from paved access road to turnaround, leading to gate for West River
Trail.
Photo 4: Markings indicate where new pavement will end: 18ft before the gate to the West River Trail.
Photo 5: Road curving towards campsites.
Photo 6: Continuation of curve. Painted markings indicate the extent of the finished pavement.
Photo 7: Continuation of curve back towards access road.
Photo 8: Second joint with existing pavement. Painted markings indicate the extent of the finished pavement.
Photo 9: Existing parking area with lawn markings indicating the limit and angle of extension.
Photo 10: Section one- repair along boat launch road at Ball Mountain Lake. (Option
Task)
Photo 11: Section two-repair along boat launch road at Ball Mountain Lake. (Option Task)
Photo 12: Section three- repair along boat launch road at Ball Mountain Lake. (Option
Photo 13: Section four- repair along boat launch road at Ball Mountain Lake. (Option Task)
Photo 14: Section five- repair along boat launch road at Ball Mountain Lake. (Option
Photo 15: Location of boat launch road at Ball Mountain Lake(Option Task)