Attachment1 _SolicitationTermsConditions.pdf
PDF 802 KB Posted
- Solicitation number
- 1240LU26Q0012
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Request for Quotation (RFQ) for Fairy Lake Phase 2 Road and Recreation Improvements on the Bozeman Ranger District of the Custer Gallatin National Forest. The USDA Forest Service, Construction & A&E Division issued the solicitation (1240LU26Q0012) on March 13, 2026, with offers due April 15, 2026 at 1600 hours local time. This is a Total Small Business Set-Aside with an estimated contract value between $1,000,000 and $5,000,000. The project scope includes excavation, drainage, road reconditioning, surface stabilization, trail reconditioning and surfacing, installation of new turnouts, vault toilet(s), aggregate and two AOP culverts, and work will be performed in accordance with FP-24 Forest Service Supplemental Specifications. The contractor must begin performance within 10 calendar days of award notice to proceed and complete all work by October 30, 2027, following the completion of Phase 1 (anticipated September 2026). Performance and payment bonds are required at 100% of the original contract award price, due 10 days after award, with options for irrevocable letters of credit or SF-25A and SF-25 forms per FAR 52.228-13.
Offerors must submit: (1) Attachment 2—Schedule of Items/Pricing with pricing for all base items; (2) signed Standard Form 1442; (3) relevant experience and past performance documentation showing work similar to the project completed within the last five years; (4) a written plan and schedule of work; and (5) a bid guarantee/bond equal to 20% of total price. The Government intends to award a firm fixed-price contract to one offeror representing the best value based on evaluation of experience and past performance (including five relevant contract references within the preceding five years) and price. Offerors must hold prices firm for 60 calendar days from the offer deadline. Progress payments will be authorized monthly for work meeting contract quality standards, with retainage up to 10% if satisfactory progress is not achieved. Final payment is due upon completion, acceptance of all work, presentation of a properly executed voucher, and release of all claims against the Government. Questions must be submitted by April 8, 2026 at 4:00 PM Mountain Time to lisa.rakich@usda.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_Amendment0001.pdf | ||
| Amend1_FillableScheduleofItems_Attachment2.xlsx | XLSX spreadsheet | |
| QuestionsAnswers_4-09-26.pdf | ||
| Attachment5_Plans.pdf | ||
| Attachment4_Specifications_FSSS.pdf | ||
| Attachment 6 DavisBaconWageDetermination.pdf | ||
| Attachment2_PriceScheduleOfItems.pdf | ||
| Attachment7_AreaMap_FairyLakeRd.png | PNG image | |
| Attachment3_SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1160174
USDA-Forest Service, Construction & A &E Division 420 Barrett Street Dillon, MT 59725
40LU 8. ADDRESS OFFER TO
Lisa Rakich USDA, FS Construction & A&E Division lisa.rakich@usda.gov Dillon, MT 59725
LISA RAKICH 406-491-0561
103/13/2026
1240LU26Q0012
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Fairy Lake Phase 2 Road and Recreation Improvements on the Bozeman RD of the Custer Gallatin National Forest. This project will include excavation, drainage, road reconditioning, surface stabilization, trail reconditioning and surfacing, and installation of new turnouts, vault toilet(s), aggregate and 2 AOP culverts. Work will be performed in accordance with FP-24, Forest Service Supplemental Specifications and project specific requirements. The work anticipated under any contract resulting from the solicitation will be started following Phase 1 which is currently anticipated to be completed by September 2026. Work under this contract requirement is planned for completion by October 2027.
Magnitude of Construction is between $1,000,000 and $5,000,000 This acquisition is a Total Small Business Set-Aside. All responsible small businesses may submit a quotation which will be considered by the agency.
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 395 calendar days and complete it within ________________ ________________ calendar days after receiving
04/15/2026
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 8/2014)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within _____60_______________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA-FS Construction & A&E Division
420 BARRETT STREET
DILLON MT 59725
40LU
LISA M. RAKICH
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 8/2014) BACK
All funded - Continued...
www.IPP.gov
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 19
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
1240LU26Q0012
Delivery: 10/30/2027
Delivery Location Code: 0398
USDA FOREST SERVICE
CUSTER GALLATIN NATIONAL FOREST
10 EAST BABCOCK AVENUE
BOZEMAN MT 59715 US
Period of Performance: 10/01/2026 to 10/30/2027
0001 Fairy Lake Phase 2 Road and Recreation
Improvements on the Bozeman Ranger District of the Custer Gallatin National Forest
Product/Service Code: Z2LB
Product/Service Description: REPAIR OR ALTERATION
OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Fairy Lake Phase 2 Road & Recreation Improvements Solicitation Number: 1240LU26Q0012
Attachment 1 - Solicitation Terms and Conditions with applicable clauses, instructions, and evaluation criteria.
Description - This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Part 12. This announcement constitutes the only solicitation; offers are being requested, and a separate written solicitation will not be issued.
Solicitation number 1240LU26Q0012 is issued as a Request for Quotation (RFQ) for Fairy Lake Phase 2 Road & Recreation Improvements to Fairy Lake Road #74 on the Bozeman Ranger District.
Performance & Payment Bonds (FAR 52.228-15) s: Both required 100% of original contract award price. Due 10 days after an award. Irrevocable letter or credit or Payment Bond form SF-25A & Performance Bond Form SF-25 are allowed per FAR 52.228-13.
This acquisition is set-aside for small business concerns. This solicitation incorporates provisions and clauses by reference. The full text of provisions and clauses may be accessed electronically at www.acquisition.gov.
The applicable North American Industry Classification Standard Code is 237310 Highway, Street & Bridge Construction. The small business size standard is $45 million. This acquisition is a Total Small Business Set-Aside. All responsible small businesses may submit a quotation which will be considered by the agency.
Definitization of Equitable Adjustments for Change Orders
“Pursuant to FAR 36.101-4(b), information regarding USDA’s definitization of equitable adjustments for change orders under construction contracts may be found at FAR 36.211 | USDA.
USDA’s procedures that apply to the definitization of equitable adjustments for change orders under construction contracts may be found in 443.304 -70 http://www.acquisition.gov/ https://www.usda.gov/da/ocp/ppd/policies-regulations/far
Technical data and supporting documentation associated with this solicitation are available through the following documents:
Technical Attachments The following documents are included as attachments to this solicitation and can be accessed via the “Attachments/Links” section of the SAM.gov posting.
• Attachment 2 – Price Schedule of Items
• Attachment 3 – SOW - Statement of Work
• Attachment 4 – Specifications_FSSS
• Attachment 5 – Plans & Drawings
• Attachment 6 – Davis Bacon Wage Determination
• Attachment 7 - Area Map
Federal Acquisition Regulation (FAR) and United States Department of Aquiculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.
Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.
As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
52.252-2 Clauses Incorporated by Reference Feb 1998 This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52
52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025)
This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:
(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).
(d) Changes. Changes will be handled in accordance with the following FAR clause(s):
☒ FAR 52.243-4, Changes (Nov 2025) FAR 52.246-21, Warranty of Construction is applicable to this contract.
https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52
52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)
The following clauses are applicable if checked:
☒ 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) with Alternate I (Nov 2021) of 52.203-6 ☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☒ 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) ☒ 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov 2025) ☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025) ☒ 52.219-9 Small Business Subcontracting Plan (Nov 2025)
☒ Alternate IV (Nov 2025) of 52.219-9 ☒ 52.219-14 Limitations on Subcontracting (Nov 2025) ☒ 52.219-33 Nonmanufacturer Rule (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☒ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025) ☒ 52.222-35 Equal Opportunity for Veterans (Nov 2025) ☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025) ☒ 52.222-37 Employment Reports on Veterans (Nov 2025) ☒ 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) ☒ 52.222-54 Employment Eligibility Verification (Nov 2025) ☒ 52.222-55 Minimum Wages for Construction Workers under Executive Order 14026 (Nov 2025) ☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☒ 52.223-23 Sustainable Products and Services ☒ 52.223-2 Reporting of Biobased Products under Service & Construction Contracts (Nov 2025) ☒ 52.225-1 Buy American-Supplies (Nov 2025) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018)
The Contractor shall comply with the following FAR Clauses for Commercial Construction.
52.222-6 Construction Wage Rate Requirements 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certificate of Eligibility 52.236-5 Material and Workmanship
The following clauses are applicable when checked:
☒ 52.225-9 Buy American-Construction Materials (Nov 2025) ☒ 52.225-11 Notice of Buy American Requirement-Construction Materials under Trade Agreements (Nov 2025) ☒ 52.228-2 Additional Bond Security (Oct 1997) ☒ 52.228-5 Insurance-Work on Government Installation (Jan 1997) ☒ 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) ☒ 52.228-14 Irrevocable Letter of Credit (Nov 2014) ☒ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☒ 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) ☒ 52.236-2 Differing Site Conditions (Jul 2025) ☒ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☒ 52.236-6 Superintendent by the Contractor (Jul 2025) ☒ 52.236-7 Permits and Responsibilities (Jul 2025) ☒ 52.236-8 Other Contracts (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☒ 52.336-10 Operations and Storage Areas (Jul 2025) ☒ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☒ 52.236-13 Accident Prevention (Jul 2025) ☒ Alternate I (Nov 1991) of 52.236-13 ☒ 52.236-15 Schedules for Construction Contracts (Jul 2025) ☒ 52.236-17 Layout of Work (Jul 2025) ☒ 52.236-21 Specifications and Drawings for Construction (Jul 2025) ☒ Alternate II (Apr 1984) of 52.236-21 ☒ 52.242-14 Suspension of Work (Apr 1984) ☒ 52.248-3 Value Engineering (Oct 2025)
☐ Alternate I (Apr 1984) of 52.248-3
AGAR Clauses
452.204–70 Modification for Contract Closeout (Nov 2025)
(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) shall issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but will not be required to provide a signature. The Contracting Officer shall immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(b) Upon contract closeout for contracts utilizing SAP: if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation.
The contractor will receive a copy of the modification and will be required to provide a signature.
(The Contracting Officer may also request a “Contractor Release of Claims” be completed by the contractor, although not required for contracts and orders using SAP.) If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 60 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(c) Upon contract closeout for contracts utilizing anything other than cost reimbursement, if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and a ‘‘Contractor Release of Claims’’ and will be required to provide a signature on both forms. If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 120 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.
(End of Clause)
452.222-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)
(a) By entering into this contract, the Contractor certifies that:
(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.
(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the Contractor and any subcontractor or teaming partner will not do so for the duration of the contract.
(b) If the Contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the Contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.
(c) The Contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the Contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.
(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.
(e) Submission of a knowing false statement relating to Contractor’s compliance with the above requirements and/or eligibility for the contract may subject the Contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.
(f) The Contractor must include the provisions of this clause in all subcontract solicitations.
(g) Failure on the part of the Contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.
(End of Clause)
452.232-71 Progress Payments for Commercial Construction Contracts (Dec 2025)
(a) Contractor entitlement to progress payments. The Contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.
(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:
(3) Materials delivered on site and preparatory work;
(4) Materials delivered to the Contractor at locations other than the site, if:
i. Specifically authorized by the contract; and
ii. The Contractor provides satisfactory evidence of title and intended use in the contract.
(c) Contractor request for progress payments. The Contractor’s request for progress payments shall include the following:
(1) An itemization of the amounts requested, related to the various elements of work required by the contract.
(2) A listing of the amount included for work performed by each subcontractor.
(3) A listing of the total amount of each subcontract.
(4) A listing of the amounts previously paid to each subcontractor; and
(5) Additional supporting data in a form and detail required by the Contracting Officer.
(d) Contractor Certification. Each request for progress payment shall be accompanied by the following certification:
I hereby certify, to the best of my knowledge and belief, that—
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.
________________________________________________(name) ________________________________________________(title) ________________________________________________(date)
(e) Access for verification of payment entitlement. To verify the Contractor’s entitlement to progress payments under this contract, the Contractor shall provide the Government, upon request and during normal business hours, access to the following:
(1) Records and Documentation:
(i) Certified progress payment requests and supporting documentation.
(ii) Subcontractor and supplier invoices, payment records, and lien waivers.
(iii)Updated schedule of values and progress schedules.
(iv) Quality assurance and inspection reports.
(v) Payroll records, if applicable under labor provisions.
(2) Facilities and Worksite Access:
(i) Physical access to the construction site for inspection of work progress.
(ii) Access to off-site storage locations for materials billed but not yet incorporated into the work; or (iii)Access to any fabrication facilities where contract-related work is being performed.
(3) Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.
(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests shall be paid within 30 days of submitting a proper request for payment.
(g) Liquidation of progress payments. Progress payments shall be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item shall be clearly delineated in each request for progress payment submitted by the Contractor.
(h) Security for progress payments. In the event the Contractor fails to provide adequate security as required in this contract, no progress payment shall be made under this contract. Upon receipt of adequate security, progress payments shall be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the contract. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided and suspend further payments to the Contractor; the Contractor shall repay to the Government the amount of unliquidated progress payments as the Contracting Officer at his sole discretion deems repayable.
(i) Special terms regarding termination for cause. If this contract is terminated for cause, the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments. The Government shall be liable for no payment except as provided by the Termination for Cause paragraph of the clause at Federal Acquisition Regulation 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services.
(j) Reservation of rights.
(1) No payment, vesting of title under this clause, or other action taken by the Government under this clause shall-
(i) Excuse the Contractor from performance of obligations under this contract; or
(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.
(2) The Government’s rights and remedies under this clause-
(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and
(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(k) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(l) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(m) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all the terms of the contract.
(3) The Government’s rights and remedies under this clause-
(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and
(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(n) Reimbursement for bond premiums. In making these payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (l) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(o) Final payment. The Government shall pay the amount due the Contractor under this contract after-
(1) Completion and acceptance of all work.
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).
(p) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(End of clause)
Award Type
It is anticipated that a firm fixed price contract will be awarded because of this synopsis/solicitation.
The Government intends to make one award from this solicitation. Therefore, to be considered responsive, contractors must submit pricing for all items.
Evaluation and Basis for Award
The provision at FAR 52.212-2, Evaluation—Commercial Products and Commercial Services is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the offeror representing the best value to the Government.
Definitions:
a. Relevant Experience – Offerors shall submit written documentation of Relevant Experience.
The Government will consider the extent to which the vendor demonstrates experience performing work similar in scope, size, and complexity to the requirements of this solicitation. Greater consideration will be given to vendors whose experience reflects a strong alignment with the Government’s needs.
b. Past Performance - Offerors shall provide written documentation of Past Performance for five (5) relevant contracts (references) completed within the last five (5) year period.
Evaluation Factors
1. Experience and Past Performance - Offerors shall submit relevant Experience and Past Performance to include five (5) relevant references completed within the preceding five (5) year period. Additional written documents with details regarding any critical subcontractors, entity (subcontractor, teaming Contractor) other than the offeror itself that will perform at least 20% or more of the total proposed contract.
http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3727&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section6305&num=0&edition=prelim
If no relevant contracts are available, the five (5) most recent contracts completed in the last five (5) years shall be used. Contracts listed may include those with the Federal Government, State and Local Governments or their agencies, and Commercial Customers. If an offeror has no relevant past performance history, the offeror must affirmatively state that it possesses no relevant past performance history.
The Government will evaluate the offeror’s past performance to assess the degree of confidence that the offeror will successfully perform this required effort. The evaluation will consider recency, relevancy of experience, and quality of past performance.
Recency: Past performance information must be from efforts carried out within the last five (5) years from the date of solicitation issuance. More recent performance may be given greater weight.
Relevancy: The Government will assess how closely the offeror’s past performance aligns with the scope, size, complexity, and type of work described in this solicitation. The Government will make an independent determination of relevancy of the data provided or obtained. Experience Relevancy will be rated as:
Very Relevant – Essentially the same scope and complexity.
Relevant – Similar in scope and complexity.
Somewhat Relevant – Some similarities in scope or complexity.
Not Relevant – Little or no similarity.
Quality of Performance: The Government will evaluate the quality of the offeror’s performance on prior contracts, including:
Timeliness of performance Technical quality Cost control (if applicable) Business relations Customer satisfaction
Sources may include CPARS, past performance questionnaires, and other verifiable references. The Government reserves the right to limit or expand the number of references it decides to contact and to contact references other than those provided by the offeror.
Confidence Assessment: Based on the recency, experience relevancy, and quality of past performance, the Government will assign one of the following confidence ratings:
High Confidence – Government has a high expectation of successful performance.
Some Confidence – Government has a reasonable expectation of success.
Low Confidence – Government has concerns about successful performance.
Neutral Confidence – No relevant past performance available; no positive or negative inference will be made.
Note: Offerors without relevant experience and past performance will not be rated favorably or unfavorably but will receive a Neutral Confidence rating.
2. Price - Any quantity price discounts and discounts for prompt payment should be included in your item pricing sections. The offeror shall provide pricing as requested in the attached Schedule of Items (Attachment 2). Total price evaluation will be for all of the base items within the performance period, and in accordance with FAR 52.217-8, up to a six-month extension period. Failure to propose pricing for all the base line items may result in a quotation being excluded from further consideration. The offeror’s quotation will be evaluated in accordance with FAR 12.204, to determine if it is fair and reasonable.
Evaluation Method:
The Government intends to evaluate quotations using a comparative evaluation methodology. This means quotations will be compared against one another to determine which provides the best value to the Government, based on the evaluation factors outlined in this solicitation.
The Government may consider quotations that exceed minimum requirements and offer additional value or benefits, even if they are not the lowest priced. However, formal trade-off procedures will not be conducted.
52.252-1 Solicitation Provisions Incorporated by Reference Feb 1998 This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52
52.212-1 Instructions to Offerors - Commercial Products & Commercial Services (Nov 2025)
Return the following with your quote:
1. Attachment 2 – Schedule of Items/Pricing
2. Signed, SF-1442
3. Experience and Past performance showing Recent and Relevant = work similar to this project.
4. Your written plan and schedule of work order.
5. Bid Guarantee/Bond = 20% of your total price
Period for acceptance of offers.
The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.
Questions Questions shall be submitted via email to lisa.rakich@usda.gov and are due no later than April 8, 2026, at 4:00 PM Mountain Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email.
52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017)
52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025)
The following provisions are applicable if checked:
☒ 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sep 2024)
☒ 52.204-7 System for Award Management—Registration (Nov 2025) ☒ 52.225-2 Buy American Certificate (Oct 2022)
52.225-10 Notice of Buy American Requirement - Construction Materials (May 2014) 52.233-2 Service of Protest (Sep 2025)
When checked, the Contractor shall comply with the following FAR Clauses for Commercial Construction.
☒ 52.222-5 Construction Wage Requirements, Secondary Site of the Work (Nov 2025) ☒ 52.225-10 Notice of Buy American Requirement- Construction Materials (May 2014)
☒ 52.225-12 Notice of Buy American Requirement-Construction Materials under Trade Agreements (May 2014) https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52 https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52 mailto:lisa.rakich@usda.gov
☒ 52.228-1 Bid Guarantee (Sep 1996)
AGAR Provisions
452.203-70 Anti-Discrimination & Diversity, Equity, & Inclusion (DEI) Certification (Dec 2025)
(a) By submission of its offer, the offeror certifies that:
(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution.
(2) Neither it nor any proposed subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution.
(b) If the offeror participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, by submission of its offer, the offeror certifies that it is compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.
(c) The offeror affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the offeror will not be eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.
(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.
(e) Submission of a knowing false statement relating to offeror’s compliance with the above requirements and/or eligibility for the contract may subject the offeror to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.
(f) Failure on the part of the offeror or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate the contract for default.
(End of Provision)
NOTICE FOR FILING AGENCY PROTESTS
United States Department of Agriculture (USDA) Ombudsman Program
The USDA is committed to issuing solicitations and awarding contracts in a fair and prompt manner.
The Ombudsman Program for Agency Protests (OPAP) was established to address protest issues within the agency, providing an alternative to costly and time-consuming litigation. Operating independently, OPAP offers relief comparable to that granted by the Government Accountability Office (GAO). Interested parties are encouraged to resolve concerns through USDA’s internal Alternative Dispute Resolution (ADR) process before pursuing external forums such as the GAO.
Concerns may be addressed informally or through a formal agency protest filed with either the Contracting Officer or the Ombudsman.
Informal Forum with the Ombudsman
1. Initial Point of Contact: Interested parties who believe a specific USDA procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer.
2. Escalation: If the Contracting Officer is unable to address their concerns, interested parties are encouraged to contact the USDA Ombudsman for Agency Protests. Under this informal process, the agency is not required to suspend contract award performance. Utilization of the informal forum does not suspend any time requirement for filing a formal protest with the agency or other forums.
3. Required Information: To ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).
Formal Agency Protest with the Ombudsman
1. Effort to Resolve: Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions.
2. Independent Review: If the protester’s concerns remain unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest with either the Contracting Officer whom awarded or, alternatively, with the Ombudsman under the OPAP program. Contract awards or performance will be suspended during the protest period unless justified in writing for urgent and compelling reasons or determined in writing to be in the best interest of the Government.
3. Resolution Timeline: The agency’s goal is to resolve protests within 35 calendar days from the date of filing.
4. Required Information: Protests shall include the information set forth in FAR 33.104(a)(3).
Failure to submit the required information may result in a delay or dismissal of the protest.
5. Timeliness: Protests must be filed within the timeframes specified in FAR 33.104.
6. Submission: Formal protests under the OPAP program should be submitted electronically to SPE.inquiry@usda.gov and the Contracting Officer.
Election of Forum. By initiating a protest with the USDA, the protester agrees not to pursue the same matter with the Government Accountability Office (GAO) or any other external forum while the agency protest is pending. If a protest is filed externally, the agency protest will be dismissed.
mailto:SPE.inquiry@usda.gov
| SF_1442 |
| Attachment1 _SolicitationTermsConditions |
File details come from the government source that posted it. Updated .