This is a Construction Schedule for replacing the parking garage sprinkler system at the Richard L. Roudebush VA Medical Center in Indianapolis, Indiana. The project is under VA Contract No. 36C25024C0191 and VA Project No. 583-24-525, prepared by Encorus Group with a start date of September 29, 2025, and a total project duration of approximately 122 days.

The construction schedule is broken into multiple phases: NTP and Construction Kickoff (5 days), Submittals (20 days), Mobilization (10 days), and five distinct construction phases ranging from 4-54 days, with the longest being Phase 4 Construction. The project is scheduled to conclude with a 5-day closeout period ending on January 28, 2026. Each phase has specific start and end dates, with dependencies between phases indicated in the predecessor columns, ensuring a structured and sequential approach to the sprinkler system replacement project.

View the file

Other files

File Type Posted
36C25026B0017 0004.docx DOCX document
RFI Responses - 12.19.2025.pdf PDF
Attendance Record.pdf PDF
36C25026B0017 0003.docx DOCX document
36C25026B0017 0002.docx DOCX document
36C25026B0017 0001.docx DOCX document
ATTACHMENT VIII - NEPA 583-24-525 Replace Parking Garage Sprinkler Sy.pdf PDF
ATTACHMENT VII- Submittal Log.pdf PDF
ATTACHMENT I - WAGE DETERMINATION.pdf PDF
ATTACHMENT V - RFI Form.docx DOCX document
ATTACHMENT IV - Instructions for VAAR 852.219-75.docx DOCX document
ATTACHMENT III- Drawing Set.pdf PDF
ATTACHMENT II - Combined Specifications.pdf PDF
36C25026B0017_1.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

716.592.3980 encorus.com

CONSTRUCTION SCHEDULE

For:

Replace Parking Garage Sprinkler System

Bid Documents

Prepared For:

Department of Veterans Affairs

Richard L. Roudebush VA Medical Center

1481 West 10th Street

Indianapolis, IN 46202

July 30, 2025

VA Contract No. 36C25024C0191

VA Project No. 583-24-525

1 NTP and Construction Kickoff 5 days 9/29/25 8:00 AM 10/3/25 5:00 PM

2 Submittals 20 days 10/1/25 8:00 AM 10/28/25 5:00 PM

3 Mobilization 10 days 10/6/25 8:00 AM 10/17/25 5:00 PM 1

4 Phase 1 Constrution 5 days 10/20/25 8:00 AM 10/24/25 5:00 PM 1;3

5 Phase 2 Construction 4 days 10/27/25 8:00 AM 10/30/25 5:00 PM 1;4

6 Phase 3 Construction 12 days 10/31/25 8:00 AM 11/17/25 5:00 PM 5

7 Phase 4 Construction 54 days 10/31/25 8:00 AM 1/14/26 5:00 PM 1;5

8 Phase 4 Level B 22 days 10/31/25 8:00 AM 12/1/25 5:00 PM

9 Phase 4 Level C 32 days 12/2/25 8:00 AM 1/14/26 5:00 PM 8

10 Phase 5 Construction 5 days 1/15/26 8:00 AM 1/21/26 5:00 PM 1;7

11 Closeout 5 days 1/22/26 8:00 AM 1/28/26 5:00 PM 10

Name Duration Start Finish Predecessors Resource Names F S S

28 Sep 25

M T W T F S S

5 Oct 25

M T W T F S S

12 Oct 25

M T W T F S S

19 Oct 25

M T W T F S S

26 Oct 25

M T W T F S S

2 Nov 25

Roudebush Sprinklers - page1

2 Nov 25

M T W T F S S

9 Nov 25

M T W T F S S

16 Nov 25

M T W T F S S

23 Nov 25

M T W T F S S

30 Nov 25

M T W T F S S

7 Dec 25

M T W T F S S

14 Dec 25

M T W T F S S

21 Dec 25

M T W T F S S

28 Dec 25

M T W T F S S

4 Jan 26

M T W T F S S

11 Jan 26

M T W T F S S

18 Jan 26

M T W T F S S

25 Jan 26

M T W T F S S

1 Feb 26

M T W T F S S

8 Feb 26

M T W

Roudebush Sprinklers - page2

T F S S

15 Feb 26

M T W T F S S

22 Feb 26

M T W T F

Roudebush Sprinklers - page3

File details come from the government source that posted it. Updated .