ID Task Task Name Duration Start Finish Predecessors 1 Construction Contract Award 0 days Tue 8/17/21 Tue 8/17/21 2 Notice to Proceed 0 days Mon 10/4/21 Mon 10/4/21 3 Construction (Contract: 1,554 calendar days; this schedule uses work days) 1111 days Mon 10/4/21 Mon 1/5/26 2
4 Construction Completion 0 days Mon 1/5/26 Mon 1/5/26 3FF 5 Coordinate Communication Connection with Contractor and Service Provider 180 days Tue 4/29/25 Mon 1/5/26 4FF
6 Communication Service Active, Demarc Room and Main Computer Room
0 days Mon 1/5/26 Mon 1/5/26 5
7 IOTA Contract PWS Solicitation Preparatio180 days Mon 10/4/21 Fri 6/10/22 2 8 IOTA Contract Solicitation Process 90 days Mon 6/13/22 Fri 10/14/22 7 9 IOTA Contract Award 0 days Fri 10/14/22 Fri 10/14/22 8 10 IOTA Contract Notice to Proceed 5 days Mon 10/17/22 Fri 10/21/22 9 11 Room‐by‐Room Master Equipment List
(MEL)
120 days Mon 10/24/22 Fri 4/7/23 10
12 Reuse Plan 60 days Mon 4/10/23 Fri 6/30/23 11 13 Activations Integrated Master Project
Schedule; initial, Schedule should be kept up to date through program
21 days Mon 10/24/22 Mon 11/21/22 10
14 Information Technology Plan 60 days Mon 4/10/23 Fri 6/30/23 11 15 Government and VA Specific Signage
Plan 240 days Mon 7/3/23 Fri 5/31/24 12
16 High Tech High Cost Procurement Package
300 days Mon 10/24/22 Fri 12/15/23 10
17 High Tech High Cost Equipment Requirements sent to NAC for procurement
0 days Fri 12/15/23 Fri 12/15/23 16
18 NAC Procurement High Tech High Cost Equipment
280 days Mon 12/18/23 Fri 1/10/25 17
19 Transition Plan 240 days Mon 7/3/23 Fri 5/31/24 12 20 Move‐In Plan 240 days Mon 7/3/23 Fri 5/31/24 12 21 Training Plan 240 days Mon 7/3/23 Fri 5/31/24 12 22 Micro (departmental) level CONOPs 300 days Mon 7/3/23 Fri 8/23/24 12 23 Macro (clinic wide operations) level
CONOPs 300 days Mon 7/3/23 Fri 8/23/24 12
24 Service Contract Plan 300 days Mon 7/3/23 Fri 8/23/24 12 25 Procurement Management Plan 300 days Mon 7/3/23 Fri 8/23/24 12 26 MCMs and other policies updated for new location 270 days Mon 8/26/24 Fri 9/5/25 22,23
27 Day in the Life Plan 30 days Mon 9/8/25 Fri 10/17/25 26 28 Procurement Packages for FF&E for the
New Medical Center 21 days Mon 8/26/24 Mon 9/23/24 25
29 Equipment Requirements sent to PCAC and NCO for procurement
21 days Mon 8/26/24 Mon 9/23/24 25
30 Service Contract requirements sent to NCO for action
21 days Mon 8/26/24 Mon 9/23/24 24
31 Information Technology requirements sent to OI&T for procurement
60 days Mon 7/3/23 Fri 9/22/23 14
32 Existing non‐reused FF&E disposal plan 180 days Mon 7/3/23 Fri 3/8/24 12 33 High Tech High Cost Equipment
Coordination with General Contractor (18 months prior to Construction
28 days Tue 5/13/25 Thu 6/19/25 4FS‐170 days
34 High Tech High Cost Equipment Installation and Certification
120 days Tue 7/22/25 Mon 1/5/26 35FF,33
35 High Tech High Cost Equipment Operation0 days Mon 1/5/26 Mon 1/5/26 39FF 36 Data, Telephone, and Cable Service
Available at New Medical Center 0 days Mon 1/5/26 Mon 1/5/26 4
37 Asset Management Software system operational
0 days Mon 1/5/26 Mon 1/5/26 4
38 FF&E O&M Manuals provided to appropriate Service
0 days Mon 1/5/26 Mon 1/5/26 4
39 Begin implementation of Activation Plans at New Medical Center location
0 days Mon 1/5/26 Mon 1/5/26 4
40 Activation of New Hospital 220 days Tue 1/6/26 Mon 11/9/26 4 41 Day one, see patients at New Hospital 0 days Mon 6/15/26 Mon 6/15/26 40SS+115 days 42 Last day of any Clinical Operations at
Zorn Avenue Location 0 days Mon 11/9/26 Mon 11/9/26 40FF
43 Certifications by regulatory agencies 180 days Tue 1/6/26 Mon 9/14/26 4 44 Complete FF&E Final Inventory 60 days Tue 11/10/26 Mon 2/1/27 40 45 Final BIM updated with Activation information 90 days Tue 2/2/27 Mon 6/7/27 44
46 All Training related to New Medical Center Activation complete
0 days Mon 12/21/26 Mon 12/21/26 40FS+30 days
47 Complete implementation of Activation Plans at New Medical center
0 days Mon 11/9/26 Mon 11/9/26 40
48 Removal of all FF&E from Zorn Avenue 500 days Tue 2/17/26 Mon 1/17/28 40SS+30 days
8/17 10/4
1/5
1/5
10/14
12/15
1/5 1/5
1/5
1/5
1/5
6/15 11/9
12/21
11/9
Week ‐2 Week 21 Week 43 Week 65 Week 87 Week 109 Week 131 Week 153 Week 175 Week 197 Week 219 Week 241 Week 263 Week 285 Week 307 W
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Manual Progress