About this file
This is a Pricing Worksheet for the Salt Lake City OPC (Operations and Transition & Activation) contract opportunity issued by the Department of Veterans Affairs Technology Acquisition Center Austin. The document outlines a detailed pricing structure for IOTA (Information, Operations, Transition, and Activation) services across four contract periods from 10/17/2025 to 01/16/2029, with labor categories including Program Manager, Senior Designer, and Senior Transition Planner. The pricing worksheet covers multiple PWS (Performance Work Statement) tasks such as Project Management Services, with defined labor rates increasing incrementally from $100-$150 per hour in Period 1 to $140-$275 per hour in Period 4.
The total base evaluated price for the project is $273,375.00, covering 1,300 total hours across the specified labor categories. The worksheet provides instructions for contractors to complete the pricing template, emphasizing that labor rates must be provided for all years, travel costs should not be included, and that the pricing should mirror Section B.3 of the solicitation document. Optional tasks include warehousing services, and the document notes that the government will separately add travel costs to the final contract award. The solicitation number is 36C77625Q0257, targeting a contract for operational and transitional services for the Salt Lake City location.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing-BOE
| LABOR CATEGORY | Provider (Prime/Sub) | LABOR RATE Period 1 | LABOR RATE Period 2 | LABOR RATE Period 3 | LABOR RATE Period 4 | HOURS Period 1 | PRICE Period 1 | HOURS Period 2 | PRICE Period 2 | HOURS Period 3 | PRICE Period 3 | HOURS Period 4 | PRICE Period 4 | Total Hours | Total Price |
| YEAR 1 | YEAR 2 | YEAR 3 | YEAR 4 | ||||||||||||
| LIN 0001 - IOTA SERVICES | 10/17/2025-10/16/2026 | 10/17/2026-10/16/2027 | 10/17/2027-10/16/2028 | 10/17/2028-01/16/2029 | 1,300 | $ 273,375.00 | |||||||||
| PWS Task 16.1 --- PROJECT MANAGEMENT SERVICES | 325 | $ 57,500.00 | 325 | $ 65,625.00 | 325 | $ 71,500.00 | 325 | $ 78,750.00 | 1,300 | $ 273,375.00 | |||||
| *Program Manager (Activation) | Sub | $100.00 | $125.00 | $140.00 | $150.00 | 25 | $ 2,500.00 | 25 | $ 3,125.00 | 25 | $ 3,500.00 | 25 | $ 3,750.00 | 100 | $ 12,875.00 |
| *Senior Designer | Prime | $150.00 | $175.00 | $180.00 | $200.00 | 100 | $ 15,000.00 | 100 | $ 17,500.00 | 100 | $ 18,000.00 | 100 | $ 20,000.00 | 400 | $ 70,500.00 |
| *Senior Transition Planner | Prime | $200.00 | $225.00 | $250.00 | $275.00 | 200 | $ 40,000.00 | 200 | $ 45,000.00 | 200 | $ 50,000.00 | 200 | $ 55,000.00 | 800 | $ 190,000.00 |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | - 0 | $ - 0 | ||||||||||
| PWS Task 16.2 --- INTERIOR DESIGN, FF&E & SPACE PLANNING SERVICES | - 0 | $ - 0 | - 0 | $ - 0 | |||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| PWS Task 16.3 --- CONOPS, TRANSITION PLANNING & PROJECT STAFFING PLANNING | - 0 | $ - 0 | - 0 | $ - 0 | |||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| PWS Task 16.4 --- ACQUISITION PLANNING SERVICES | - 0 | $ - 0 | - 0 | $ - 0 | |||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| PWS Task 16.5 --- ACQUISITION PACKAGES DEVELOPMENT | - 0 | $ - 0 | - 0 | $ - 0 | |||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| PWS Task 16.6 --- RELOCATION OF PERSONNEL FILES | - 0 | $ - 0 | - 0 | $ - 0 | |||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| PWS Task 16.7 --- ACTIVATION SERVICES & POST OCCUPANCY SUPPORT | - 0 | $ - 0 | - 0 | $ - 0 | |||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| PWS TASK 16.8 --- STAFF TRAINING & ORIENTATION | - 0 | $ - 0 | - 0 | $ - 0 | |||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| $ - 0 | - 0 | $ - 0 | |||||||||||||
| LIN 0002 - TRAVEL - In support of IOTA Services |
OPTIONAL TASK
| LIN 0003 - WAREHOUSING SERVICES | 02/25/2028-10/24/2028 | - 0 | $ - 0 | ||
| PWS Task 17.1 --- WAREHOUSING & WAREHOUSING MANAGEMENT SERVICES | - 0 | $ - 0 | - 0 | $ - 0 | |
| $ - 0 | - 0 | $ - 0 | |||
| $ - 0 | - 0 | $ - 0 | |||
| $ - 0 | - 0 | $ - 0 | |||
| $ - 0 | - 0 | $ - 0 | |||
| $ - 0 | - 0 | $ - 0 | |||
| Warehouse Rent (all inclusive-to include insurance) - FIXED PRICE - Qty. 1 | 1 | $ - 0 | $ - 0 |
| PROJECT: | ||
| SALT LAKE CITY OPC IOT&A | ||
| LIN DESCRIPTION | HOURS | PRICE |
| LIN 0001 - IOTA SERVICES | 1300 | $273,375.00 |
| LIN 0003 - WAREHOUSING SERVICES | - 0 | $0.00 |
| *Total Base + Optional Task (Total Evaluated Price) | 1300 | $273,375.00 |
| *Total Evaluated Price Exclusive of Cost-Reiumbursable Travel (LIN 0002) |
Instructions
| INSTRUCTIONS |
| ***EXAMPLE LABOR CATEGORIES, RATES, AND HOURS ARE PROVIDED FOR UNDER PROJECT MANAGEMENT SERVICES AS AN ILLUSTRATION ONLY, AND SHOULD BE REPLACED WITH QUOTER INFORMATION*** |
| 1. Labor Category: Fill in appropriate Labor Category (using industry standard titles) for each Task. All Key Personnel must be identified. Project Management Services is an example of how to fill in each section. |
| 2. Notate if the personnel being proposed is a Sub or Prime. |
| 3. Fill in the labor rates for Period 1, Period 2, Period 3, and Period 4 for each of the labor categories proposed for each specific task. |
| 4. Notate the total hours for each labor category for each task in the base and option periods. Those tasks which do not require pricing in either the base or the option are greyed out. |
| 5. The total CLIN price and Total Labor Hours will auto populate - but it is ulimately the responsibility of the Contractor to verify cell formulas |
| 6. The Government will add travel into the final contract award. Travel is not included in the Total Evaluated Price. Quotes should not include any travel costs in the pricing. |
| 7. Regardless of which period (base or option periods) a task is to be completed, Labor Rates must be provided for all years. |
| 8. Confirm that the pricing for each task, provided in the Pricing Workbook, mirrors that of the pricing provided for in Section B.3 "Price/Cost Schedule" of the solicitation document |
| 9. ODCs can be entered within each task as a Firm Fixed Price amount - example, Warehouse Rent. |
| 10. DO NOT submit this pricing workbook as a whole for the Basis of Estimate. If you use this worksheet for your Basis of Estimate, NO LABOR RATES OR COST CAN BE INCLUDED. |
| WE WILL NOT EVALUATE A BASIS OF ESTIMATE WHICH INCLUDE LABOR RATES AND LIN COSTS |
****LABOR CATEGORIES AND LABOR RATES PROVIDED IN PROJECT MANAGEMENT SERVICES ARE EXAMPLES ONLY!!!******