Attachment O - Construction Schedule.xls.xls
XLS spreadsheet 47 KB Posted
- Attached to
- New Germany Communications Tower
- Solicitation number
- BPM054089
- Issued by
- Harford County, Maryland
About this file
This is a construction schedule attachment for the New Germany Communications Tower project, a master contractor (FA 13) procurement by Maryland's Department of Information Technology (DoIT) for construction and installation of a communications tower and site improvements at New Germany State Park in Garrett County, Maryland. The project is structured in two phases with specific deliverables and timelines. Phase 1 requires submission of final reports and site plans within a contractor-determined number of business days following notice to proceed. Phase 2 encompasses eight sequential line items: clearing and grading, shelter and tower foundation pouring, tower delivery, shelter delivery, tower erection (which triggers a tower inspection request), final grounding (which triggers R56 and punch list inspection requests), site completion including punch list and R56 corrections, and closeout document submission for state review. Each Phase 2 item requires completion within a contractor-specified number of business days from the respective NTP issuance.
Contractors must submit this signed and sealed schedule as part of their bid proposal, with the submitted construction completion timeline serving as the binding project schedule. The schedule will be used as an evaluation criterion for bid comparison. Any project delays beyond the scheduled completion date will result in assessment of liquidated damages to the contractor. Contractors are responsible for determining and entering the number of days required for each line item in the designated boxes on the schedule.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Attachment #O
CATS + FA 13
Construction Schedule New Germany State Forest Communications Facility
| Line | Item | TO Contractor submitted schedule | Date requirements (Business Days) |
| -------- | Notice to proceed [NTP] (Provided by DoIT with approved purchase order) | ----------------------------------- | ------------------------ |
| Phase 1 | |||
| 1 | Phase 1 Final Report & Site Plans | Phase 1 NTP + # Days | |
| Phase 2 | |||
| 1 | Clearing and Grading | Phase 2 NTP + # Days | |
| 2 | Shelter/Tower Foundation poured | Phase 2 NTP + # Days | |
| 3 | Tower Delivery | Phase 2 NTP + # Days | |
| 4 | Shelter Delivery | Phase 2 NTP + # Days | |
| 5 | Tower Erection (will trigger request for tower inspection) | Phase 2 NTP + # Days | |
| 6 | Final Grounding (will trigger request for R56 and punch list inspection) | Phase 2 NTP + # Days | |
| 7 | Site Completion (to include punch list and R56 corrections) | Phase 2 NTP + # Days | |
| 8 | Closeout documents submitted for state review | Phase 2 NTP + # Days | |
| TO Contractor Signature | |||
| Instructions: TO Contractors will submit this document with their signed/sealed bid proposal. Construction completion will be used to compare and evaluate supplied bids. The submitted schedule will also serve as the contractor's binding schedule for the project. Projects not completed within the scheduled completion shown on the schedule will be subject to an assessment for liquidated damages. |
The TO Contractor will write the number of days past the NTP in the boxes provided.