Attachment No. 4 - Template Deliverable Schedule by Topic Area 2026.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Community Microgrid Assistance Partnership Direct Funding Opportunity
Solicitation number
RFX-2026-10006
Issued by

About this file

This file is a deliverable schedule template for the Community Microgrid Assistance Partnership (C-MAP) 2026 solicitation, outlining required tasks and quarterly reports across five topic areas over an 18-24 month period.

The template details deliverables for five distinct topic areas: TA1-Regional Microgrid Coordination (24 months), TA2-Microgrid Integration with Large Energy Consumers (18 months), TA3-Microgrid Development (18 months), TA4-Microgrid Transformation (18 months), and TA5-Microgrid Assessment for Industrial or Large Load Energy Consumers (12 months). Each topic area requires a Summary of Work Effort due at month one, followed by multiple task-specific deliverables and quarterly reports due at months 3, 6, 9, 12, 15, 18, and 21 as applicable. Quarterly reports must range between $2,000-$5,000 each across most topic areas, with TA3 capping quarterly reports at $4,000. TA5 requires a minimum 20% subcontractor price participation. All topic areas conclude with a final report at month 18 or 24. Proposers may submit additional deliverables beyond those specified, provided they remain within each topic area's general scope of work. The template uses a zero-dollar placeholder format, indicating that pricing will be specified elsewhere in the solicitation documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TA1-Regional Microgrid Coord

Attachment 4
Deliverable Summary Table
Topic Area 1 - Regional Microgrid Coordination
OccurrenceTaskOccurrences/Deliverables - DescriptionTotalMonths
11Summary of Work Effort1
6a6Q1 Report3
22Regional Community Needs Identification5
6b6Q2 Report6
33Collaboration Plan7
6c6Q3 Report9
6d6Q4 Report12
6e6Q5 Report15
6f6Q6 Report18
6g6Q7 Report21
44Results and Next Steps Report21
55Impact Report24
Total Price$0.00
Additional deliverables may be proposed but may not deviate from the topic area general scope of work.
Quarterly reports should be at least $2,000 each and not more than $5,000.

TA2 - Microgrid Integration

Attachment 4
Deliverable Summary Table
Topic Area 2 - Microgrid Integration with Large Energy Consumers
OccurrenceTaskOccurrences/Deliverables - DescriptionTotalMonths
11Summary of Work Effort1
7a1Q1 Report3
22Power System Collaboration Plan4
7b1Q2 Report6
33Technical Development Plan6
7c1Q3 Report9
7d1Q4 Report12
43Microgrid Transformational Design14
7e1Q5 Report15
55Microgrid Financial Assessment16
66Microgrid Development Final Report18
Total Price$0.00
Additional deliverables may be proposed but may not deviate from the topic area general scope of work.
Quarterly reports should be at least $2,000 each and not more than $5,000.

TA3 - Microgrid Development

Attachment 4
Deliverable Summary Table
Topic Area 3 - Microgrid Development
OccurrenceTaskOccurrences/Deliverables - DescriptionTotalMonths
11Summary of Work Effort1
9a1Q1 Report3
22Microgrid Design Specification3
33Microgrid Development Plan5
9b1Q2 Report6
44Microgrid Design Report9
9c1Q3 Report9
55Microgrid Performance Assessment11
9d1Q4 Report12
66Microgrid Financial Assessment13
9e1Q5 Report15
77Microgrid Construction Specification16
88Microgrid Development Final Report18
Total Price$0.00
Additional deliverables may be proposed but may not deviate from the topic area general scope of work.
Quarterly reports should be at least $2,000 each and not more than $4,000.

TA4 - Microgrid Transformation

Attachment 4
Deliverable Summary Table
Topic Area 4 - Microgrid Transformation
OccurrenceTaskOccurrences/Deliverables - DescriptionTotalMonths
11Summary of Work Effort1
6a1Q1 Report3
22Improvement Specification and Assessment Plan3
6b1Q2 Report6
33Microgrid Transformational Design7
Go / No-Go Decision
6c1Q3 Report9
6d1Q4 Report12
6e1Q5 Report15
44Microgrid Transformational Implementation15
55Microgrid Transformational Final Report18
Total Price$0.00
Additional deliverables may be proposed but may not deviate from the topic area general scope of work.
Quarterly reports should be at least $2,000 each and not more than $5,000.

TA5 - Asses. Indust. Microgrid

Attachment 4
Deliverable Summary Table
Topic Area 5 - Microgrid Assessment for Industrial or other Large Load Energy Consumers
OccurrenceTaskOccurrences/Deliverables - DescriptionNLR PortionSubcontractor Price ParticipationTotalMonths
11Summary of Work Effort$0.00$0.00$0.001
6a1Q1 Report$0.00$0.00$0.003
22Options Assessment$0.00$0.00$0.004
6b1Q2 Report$0.00$0.00$0.006
33Microgrid Design Specification$0.00$0.00$0.006
6c1Q3 Report$0.00$0.00$0.009
44Pre-feasibility Technical and Financial Assessment$0.00$0.00$0.0010
55Microgrid Development Final Report$0.00$0.00$0.0012
Total Price$0.00$0.00$0.00
Additional deliverables may be proposed but may not deviate from the topic area general scope of work.
Quarterly reports should be at least $2,000 each and not more than $5,000.
Subcontractor Price Participation should be captured for each deliverable as appropriate. 20% Price Participation required for this Topic Area.