Attachment No. 4 - Template Deliverable Schedule by Topic Area 2026.xlsx
XLSX spreadsheet 28 KB Posted
- Solicitation number
- RFX-2026-10006
- Issued by
-
Department of Energy Office of Science
About this file
This file is a deliverable schedule template for the Community Microgrid Assistance Partnership (C-MAP) 2026 solicitation, outlining required tasks and quarterly reports across five topic areas over an 18-24 month period.
The template details deliverables for five distinct topic areas: TA1-Regional Microgrid Coordination (24 months), TA2-Microgrid Integration with Large Energy Consumers (18 months), TA3-Microgrid Development (18 months), TA4-Microgrid Transformation (18 months), and TA5-Microgrid Assessment for Industrial or Large Load Energy Consumers (12 months). Each topic area requires a Summary of Work Effort due at month one, followed by multiple task-specific deliverables and quarterly reports due at months 3, 6, 9, 12, 15, 18, and 21 as applicable. Quarterly reports must range between $2,000-$5,000 each across most topic areas, with TA3 capping quarterly reports at $4,000. TA5 requires a minimum 20% subcontractor price participation. All topic areas conclude with a final report at month 18 or 24. Proposers may submit additional deliverables beyond those specified, provided they remain within each topic area's general scope of work. The template uses a zero-dollar placeholder format, indicating that pricing will be specified elsewhere in the solicitation documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TA1-Regional Microgrid Coord
| Attachment 4 | ||||
| Deliverable Summary Table | ||||
| Topic Area 1 - Regional Microgrid Coordination | ||||
| Occurrence | Task | Occurrences/Deliverables - Description | Total | Months |
| 1 | 1 | Summary of Work Effort | 1 | |
| 6a | 6 | Q1 Report | 3 | |
| 2 | 2 | Regional Community Needs Identification | 5 | |
| 6b | 6 | Q2 Report | 6 | |
| 3 | 3 | Collaboration Plan | 7 | |
| 6c | 6 | Q3 Report | 9 | |
| 6d | 6 | Q4 Report | 12 | |
| 6e | 6 | Q5 Report | 15 | |
| 6f | 6 | Q6 Report | 18 | |
| 6g | 6 | Q7 Report | 21 | |
| 4 | 4 | Results and Next Steps Report | 21 | |
| 5 | 5 | Impact Report | 24 | |
| Total Price | $0.00 | |||
| Additional deliverables may be proposed but may not deviate from the topic area general scope of work. | ||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |
TA2 - Microgrid Integration
| Attachment 4 | ||||
| Deliverable Summary Table | ||||
| Topic Area 2 - Microgrid Integration with Large Energy Consumers | ||||
| Occurrence | Task | Occurrences/Deliverables - Description | Total | Months |
| 1 | 1 | Summary of Work Effort | 1 | |
| 7a | 1 | Q1 Report | 3 | |
| 2 | 2 | Power System Collaboration Plan | 4 | |
| 7b | 1 | Q2 Report | 6 | |
| 3 | 3 | Technical Development Plan | 6 | |
| 7c | 1 | Q3 Report | 9 | |
| 7d | 1 | Q4 Report | 12 | |
| 4 | 3 | Microgrid Transformational Design | 14 | |
| 7e | 1 | Q5 Report | 15 | |
| 5 | 5 | Microgrid Financial Assessment | 16 | |
| 6 | 6 | Microgrid Development Final Report | 18 | |
| Total Price | $0.00 | |||
| Additional deliverables may be proposed but may not deviate from the topic area general scope of work. | ||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |
TA3 - Microgrid Development
| Attachment 4 | ||||
| Deliverable Summary Table | ||||
| Topic Area 3 - Microgrid Development | ||||
| Occurrence | Task | Occurrences/Deliverables - Description | Total | Months |
| 1 | 1 | Summary of Work Effort | 1 | |
| 9a | 1 | Q1 Report | 3 | |
| 2 | 2 | Microgrid Design Specification | 3 | |
| 3 | 3 | Microgrid Development Plan | 5 | |
| 9b | 1 | Q2 Report | 6 | |
| 4 | 4 | Microgrid Design Report | 9 | |
| 9c | 1 | Q3 Report | 9 | |
| 5 | 5 | Microgrid Performance Assessment | 11 | |
| 9d | 1 | Q4 Report | 12 | |
| 6 | 6 | Microgrid Financial Assessment | 13 | |
| 9e | 1 | Q5 Report | 15 | |
| 7 | 7 | Microgrid Construction Specification | 16 | |
| 8 | 8 | Microgrid Development Final Report | 18 | |
| Total Price | $0.00 | |||
| Additional deliverables may be proposed but may not deviate from the topic area general scope of work. | ||||
| Quarterly reports should be at least $2,000 each and not more than $4,000. |
TA4 - Microgrid Transformation
| Attachment 4 | ||||
| Deliverable Summary Table | ||||
| Topic Area 4 - Microgrid Transformation | ||||
| Occurrence | Task | Occurrences/Deliverables - Description | Total | Months |
| 1 | 1 | Summary of Work Effort | 1 | |
| 6a | 1 | Q1 Report | 3 | |
| 2 | 2 | Improvement Specification and Assessment Plan | 3 | |
| 6b | 1 | Q2 Report | 6 | |
| 3 | 3 | Microgrid Transformational Design | 7 | |
| Go / No-Go Decision | ||||
| 6c | 1 | Q3 Report | 9 | |
| 6d | 1 | Q4 Report | 12 | |
| 6e | 1 | Q5 Report | 15 | |
| 4 | 4 | Microgrid Transformational Implementation | 15 | |
| 5 | 5 | Microgrid Transformational Final Report | 18 | |
| Total Price | $0.00 | |||
| Additional deliverables may be proposed but may not deviate from the topic area general scope of work. | ||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |
TA5 - Asses. Indust. Microgrid
| Attachment 4 | ||||||
| Deliverable Summary Table | ||||||
| Topic Area 5 - Microgrid Assessment for Industrial or other Large Load Energy Consumers | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NLR Portion | Subcontractor Price Participation | Total | Months |
| 1 | 1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 6a | 1 | Q1 Report | $0.00 | $0.00 | $0.00 | 3 |
| 2 | 2 | Options Assessment | $0.00 | $0.00 | $0.00 | 4 |
| 6b | 1 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 3 | 3 | Microgrid Design Specification | $0.00 | $0.00 | $0.00 | 6 |
| 6c | 1 | Q3 Report | $0.00 | $0.00 | $0.00 | 9 |
| 4 | 4 | Pre-feasibility Technical and Financial Assessment | $0.00 | $0.00 | $0.00 | 10 |
| 5 | 5 | Microgrid Development Final Report | $0.00 | $0.00 | $0.00 | 12 |
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Additional deliverables may be proposed but may not deviate from the topic area general scope of work. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. | ||||||
| Subcontractor Price Participation should be captured for each deliverable as appropriate. 20% Price Participation required for this Topic Area. |