Attachment_No__7_JOTR_250023_Entrance_Station_100_CD_Structural_Calcs_220121.pdf
PDF 4 MB Posted
- Solicitation number
- 140P8523R0001
About this file
This document provides structural calculations for a new entrance station at Joshua Tree National Park. It includes load calculations, material specifications, design details, and structural analysis for various building components including the canopy, rafters, columns, beams, joists, headers, and foundations. Load combinations are analyzed according to ASCE 7-16 standards. Material strengths and stress ratios are verified to meet code requirements. Deflection and reinforcement sizing are checked for adequacy. The document demonstrates the structural design and integrity of the proposed entrance station.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bluestone Engineering, Inc. 1990 N. California Blvd., 8th Floor Tel 925.932.7053 www.bluestoneeng.com Walnut Creek, CA 94596
JOSHUA TREE NATIONAL PARK WEST ENTRANCE STATION
Final Design
Structural Calculations
January 3, 2022
Item Page
Calculations
Table of Contents 1
Layout 2
Building Loads 7
Shear Wall Design 12
Kiosk Cant. Columns 19
Canopy Column Design 20
Diaphragm Design 23
Vertical Framing Design 25
Foundations 30
Anchorage 35
Equipment Pad 40
Enercalc Output 43
JOSHUA TREE NATIONAL PARK
STRUCTURAL CALCULATIONS
TABLE OF CONTENTS
2 Index
BLUESTONE ENGINEERING, INC.
Bluestone Engineering, Inc. Job 20023.1 Sht.
Walnut Creek, California Date 12/16/21 By TMS
Layout
Shade Canopies
Layout
Service Building
Layout
Kiosk #1
Layout
Kiosk #2
Layout
Kiosk #3 (Kiosk #4 Similar)
Loading
Self Weight
Shade Canopy
20 Ga Metal Deck 3.1 psf
HSS Rafters 3.44 psf
HSS Beams 2.60 psf
HSS Columns 0.88 psf
PV Panels 4.00 psf
Total Self Wt 14.0 psf Use 14.00 psf
Roof Live Load 20.00 psf
Kiosk and Comfort Stations
Conventional Wood Framed Building w/ Plywood Roof and Walls
Use Self Wt 15.00 psf at Roof
12.00 psf at Walls
Wind Load
Shade Canopy Use Chapter 29: Other Structures
Risk Category II
Basic Wind Speed 100 MPH
Directionality Factor, kd 0.85
Exposure D
Topographic Factor, kzt 1.0
Ground Elevation Factor, ke 0.9 for elevation = 3000'
Gust Factor 0.85
Velocity Pressure Coeff, kz 1.03 (h=15')
Velocity Pressure , qz 20.1715 psf
Force Coefficient, Cf 1.95
Horizontal Force, Fh 33.43 psf
(GCr) for Rooftop structures 1.0
Vertical Force, Fv 20.17 psf
Loading
Wind Load
Buildings Use Chapter 28 Part 2
Comfort Station
Use Wind Pressures for design:
Wall Pressure 21.0 psf
Horz. Roof Pressure 11.0 psf
Vert Roof Pressure 25.3 psf
Eave Pressure 35.5 psf
Loading
Seismic Loading
Loading
Shade Canopy
Seismic Coefficients:
SS 1.701 SMS 1.701
S1 0.6 SM1 1.53
FA 1.0 SDS 1.134
FV 1.7 SD1 1.020
Roof Height, hn 18.0 feet
Table 12.8-2 Coeff., Ct 0.02
Table 12.8-2 Coeff., x 0.75 ==> Tn = 0.175 seconds
Redundancy Factor, R 1.25 Cantilever Column System
Importance Factor, Ie 1.0
Seismic Coeff., CS 0.907 <== Controls
CS max 4.669
CS min 0.24
Seismic Base Shear, V 0.907 *W (Strength Design)
Kiosk and Comfort Stations
Roof Height, hn 10.0 feet
Table 12.8-2 Coeff., Ct 0.02
Table 12.8-2 Coeff., x 0.75 ==> Tn = 0.112 seconds
Redundancy Factor, R 6.50 Wood Shear Walls
Importance Factor, Ie 1.0
Seismic Coeff., CS 0.174 <== Controls
CS max 1.395
CS min 0.0462
Seismic Base Shear, V 0.174 *W (Strength Design)
Note: for Cantilever Columns in Buildings, use 0.907W
Loading
Seismic Loading for Equipment
Seismic Coefficients for Non-Structural Components:
Pump Skid: ap = 1.0
Rp = 1.5
Ip = 1.0
Height above grade, Z = 0.0
Fp = 0.3024 *Wp
Fp max = 1.8144 *Wp
Fp min = 0.3402 *Wp <== controls
Solar Panels
Solar Panel Weight 2.3 psf
Unistrut Support Bracket Weight 1.7 psf
Total 4.0 psf
Shear Walls
Service Building
Aroof 909.40 ft
Abldg 562.13 ft
LPerimWall 96.67 ft
HWallAve 10.00 ft
Roof Wt 15.00 psf
Wall Wt 12.00 psf
Seismic Loading:
Cs 0.174
Wind Loading:
Roof 11 psf
Walls 21 psf
N-S Loading:
Ldiaph 45.67 ft
Lbldg 28.83 ft
Hroof 3.67 ft
E-W Loading:
Ldiaph 19.92 ft
Lbldg 19.50 ft
Hroof 1.00 ft
Dist. Seis Load, plf Dist. Wind Load, plf
Roof Walls Roof Walls
N-S 119.17 51.76 40.33 105.00
E-W 51.97 35.01 21.00 105.00
Wall
# (Grid) Tribroof, ft Tribwall, ft E W
1 (Gr E) 9.96 9.75 1691.38 1425.40
2 (Gr F) 9.96 9.75 1691.38 1425.40
3 (Gr 5) 27.25 14.50 1923.81 2094.75
4 (Gr 8) 18.42 14.50 1464.73 1909.25
Reactions, lb
Shear Walls
Kiosk #1
Aroof 245.46 ft
Abldg 160.61 ft
LPerimWall 53.13 ft
HWallAve 10.00 ft
Roof Wt 15.00 psf
Wall Wt 12.00 psf
Seismic Loading:
Cswall 0.174
CsCantCol 0.907
Wind Loading:
Roof 11 psf
Walls 21 psf
N-S Loading:
Ldiaph 9.75 ft
Lbldg 9.33 ft
Hroof 1.00 ft
E-W Loading:
Ldiaph 25.21 ft
Lbldg 17.21 ft
Hroof 2.17 ft
Dist. Seis Load, plf Dist. Wind Load, plf
Roof Walls Roof Walls
N-Swalls 25.41 32.23 21.00 105.00
N-SCantCol 132.47 168.00 21.00 105.00
E-W 65.71 59.43 23.83 105.00
Wall
# (Grid) Tribroof, ft Tribwall, ft E W
5 (A.2) 12.58 8.58 3108.90 1165.50
6 (A.8) 12.75 8.58 600.65 1169.00
7 (1) 4.67 4.67 583.97 601.22
8 (1+) 4.67 4.67 583.97 601.22
Shear Walls
Kiosk #2
Aroof 201.55 ft
Abldg 134.88 ft
LPerimWall 52.83 ft
HWallAve 10.00 ft
Roof Wt 15.00 psf
Wall Wt 12.00 psf
Seismic Loading:
Cswall 0.174
CsCantCol 0.907
Wind Loading:
Roof 11 psf
Walls 21 psf
N-S Loading:
Ldiaph 7.33 ft
Lbldg 6.92 ft
Hroof 1.00 ft
E-W Loading:
Ldiaph 27.58 ft
Lbldg 19.50 ft
Hroof 2.33 ft
Dist. Seis Load, plf Dist. Wind Load, plf
Roof Walls Roof Walls
N-Swalls 19.07 28.28 21.00 105.00
N-SCantCol 99.41 147.44 21.00 105.00
E-W 71.73 79.74 25.67 105.00
Wall
# (Grid) Tribroof, ft Tribwall, ft E W
9 (B-) 13.75 9.75 2804.41 1312.50
10 (B+) 13.83 9.75 539.59 1314.25
11 (2) 3.46 3.46 523.85 451.89
12 (2+) 3.46 3.46 523.85 451.89
Shear Walls
Kiosk #3/#4
Aroof 201.55 ft
Abldg 134.88 ft
LPerimWall 52.83 ft
HWallAve 10.00 ft
Roof Wt 15.00 psf
Wall Wt 12.00 psf
Seismic Loading:
Cswall 0.174
CsCantCol 0.907
Wind Loading:
Roof 11 psf
Walls 21 psf
N-S Loading:
Ldiaph 7.33 ft
Lbldg 6.92 ft
Hroof 1.00 ft
E-W Loading:
Ldiaph 27.58 ft
Lbldg 19.50 ft
Hroof 2.33 ft
Dist. Seis Load, plf Dist. Wind Load, plf
Roof Walls Roof Walls
N-Swalls 19.07 28.29 21.00 105.00
N-SCantCol 99.41 147.45 21.00 105.00
E-W 71.73 79.75 25.67 105.00
Wall
# (Grid) Tribroof, ft Tribwall, ft E W
13 (C-) 13.75 9.75 538.02 1312.50
14 (C.6) 13.83 9.75 2812.78 1314.25
15 (1+) 3.46 3.46 523.87 451.89
16 (1++) 3.46 3.46 523.87 451.89
Shear Walls
Summary of Wall Loading
Wall
# (Gr) Length (ft) Height (ft) DL E W
1 (E) 16.33 10.42 140 1691 1425
2 (F) 14.83 10.42 140 1691 1425
3 (5) 19.50 12.42 283 1924 2095
4 (8) 16.17 9.17 238 1465 1909
5 (A.2) 9.33 3.33 167 3109 1166 Cant. Column + Short Shear Wall
6 (A.8) 3.25 10.75 256 601 1169 Simpson Strong Wall
7 (1) 8.58 10.17 137 584 601
8 (1+) 8.58 10.08 136 584 601
9 (B-) 6.92 3.33 176 2804 1313 Cant. Column + Short Shear Wall
10 (B+) 2.67 10.67 264 540 1314 Simpson Strong Wall
11 (2) 10.92 10.33 139 524 452
12 (2+) 8.25 10.25 138 524 452
13 (C-) 2.83 9.00 244 538 1313 Simpson Strong Wall
14 (C.6) 6.92 3.33 176 2813 1314 Cant. Column + Short Shear Wall
15 (1+) 10.92 9.42 128 524 452
16 (1++) 7.25 9.42 128 524 452
Bluestone Engineering, Inc. Job Sht.
Walnut Creek, California Date By T. Swenson
PLYWOOD SHEAR WALLS
1.134 (LRFD Stress Design) ρ = 1.0
Seismic Loading
Sheathing:
15/32 CD Exp I
ASD
Forces
Wall
ID
Shear
Len (ft)
HD Len
(ft)
Ht.
(ft)
Force
(lbs) h/b
Ratio
Shear
(plf)
Spacing of Common
Nails (in)
DL
(plf)
EQ or
Wind
Mr
(ft-k)
Mot
(ft-k)
Comp
(kips)
Uplift
(kips)
HD
Reqd
1 16.33 15.83 10.4 1,691 0.64 104 10d @ 6 - one side 140 EQ 8.2 17.6 1.7 0.4 HDU2
2 14.83 14.33 10.4 1,691 0.70 114 10d @ 6 - one side 140 EQ 6.8 17.6 1.7 0.5 HDU2
3 19.50 19.00 12.4 1,924 0.64 99 10d @ 6 - one side 283 EQ 23.7 23.9 3.2 0.0 N/A
4 16.17 15.67 9.2 1,465 0.57 91 10d @ 6 - one side 238 EQ 13.7 13.4 2.2 0.0 N/A
5 9.33 8.83 3.3 3,109 0.36 333 10d @ 6 - one side 167 EQ 3.2 10.4 1.5 0.6 HSS
6 3.25 2.75 10.8 601 3.31 306 10d @ 6 - one side 256 EQ 0.6 6.5 2.0 1.5 HTT4
7 8.58 8.08 10.2 584 1.18 68 10d @ 6 - one side 137 EQ 2.2 5.9 1.0 0.3 HDU2
8 8.58 8.08 10.1 584 1.17 68 10d @ 6 - one side 136 EQ 2.2 5.9 1.0 0.3 HDU2
9 6.92 6.42 3.3 2,804 0.48 405 10d @ 6 - one side 176 EQ 1.9 9.3 1.6 0.8 HSS
10 2.67 2.17 10.7 540 4.00 NG NG-Use Strong Wall 264 EQ 0.4 5.8 2.2 1.7 WSW
11 10.92 10.42 10.3 524 0.95 48 10d @ 6 - one side 139 EQ 3.7 5.4 1.0 0.1 HDU2
12 8.25 7.75 10.3 524 1.24 63 10d @ 6 - one side 138 EQ 2.1 5.4 1.0 0.3 HDU2
13 2.83 2.33 9.0 538 3.18 302 10d @ 6 - one side 244 EQ 0.4 4.8 1.8 1.3 WSW
14 6.92 6.42 3.3 2,813 0.48 407 10d @ 6 - one side 176 EQ 1.9 9.4 1.6 0.8 HSS
15 10.92 10.42 9.4 524 0.86 48 10d @ 6 - one side 128 EQ 3.4 4.9 0.9 0.1 HDU2
16 7.25 6.75 9.4 524 1.30 72 10d @ 6 - one side 128 EQ 1.5 4.9 0.9 0.4 HDU2
Holdowns
HD Anchor Capacity
HDU2 5/8 3,075 lbs
HTT4 5/8 4,445 lbs
Strongwalls
WSW Wall # Shear Capacity Anchor W de
WSW18x10 6 1,590 lbs 7/8 19 7.0
WSW24x10 10 3,295 lbs 7/8 13 6.0
WSW24x9 13 3,670 lbs 7/8 13 6.0
20023.10
12/16/2021
SDS =
Shear walls at level
Bluestone Engineering, Inc. Job Sht.
Walnut Creek, California Date By T. Swenson
Wind Loading
Sheathing:
15/32 CD Exp I
ASD
Forces
Wall
ID
Shear
Len (ft)
HD Len
(ft)
Ht.
(ft)
Force
(lbs) h/b
Ratio
Shear
(plf)
Spacing of Common
Nails (in)
DL
(plf)
EQ or
Wind
Mr
(ft-k)
Mot
(ft-k)
Comp
(kips)
Uplift
(lbs)
HD
Reqd
1 16.33 15.83 10 1425 0.64 87 10d @ 6 - one side 140 W 11.2 14.8 1.0 0.2 N/A
2 14.83 14.33 10 1425 0.70 96 10d @ 6 - one side 140 W 9.2 14.8 1.0 0.3 HDU2
3 19.5 19.00 12 2095 0.64 107 10d @ 6 - one side 282.7 W 32.3 26.0 1.7 -0.2 N/A
4 16.17 15.67 9.2 1909 0.57 118 10d @ 6 - one side 238 W 18.7 17.5 1.3 -0.1 N/A
5 9.3333 8.83 3.3 1166 0.36 125 10d @ 6 - one side 166.8 W 4.4 3.9 0.5 0.0 HSS
6 3.25 2.75 11 1169 3.31 595 10d @ 4 - one side 255.8 W 0.8 12.6 3.3 3.0 HTT4
7 8.5833 8.08 10 601 1.18 70 10d @ 6 - one side 137 W 3.0 6.1 0.7 0.3 HDU2
8 8.5833 8.08 10 601 1.17 70 10d @ 6 - one side 136 W 3.0 6.1 0.7 0.3 HDU2
9 6.9167 6.42 3.3 1313 0.48 190 10d @ 6 - one side 176.2 W 2.5 4.4 0.6 0.2 HSS
10 2.6667 2.17 11 1314 4.00 NG NG-Use Strong Wall 264.2 W 0.6 14.0 4.6 4.3 WSW
11 10.917 10.42 10 452 0.95 41 10d @ 6 - one side 139 W 5.0 4.7 0.5 0.0 HDU2
12 8.25 7.75 10 452 1.24 55 10d @ 6 - one side 138 W 2.8 4.6 0.6 0.2 HDU2
13 2.8333 2.33 9 1313 3.18 736 10d @ 4 - one side 244.2 W 0.6 11.8 3.6 3.4 WSW
14 6.9167 6.42 3.3 1314 0.48 190 10d @ 6 - one side 176.2 W 2.5 4.4 0.6 0.2 HSS
15 10.917 10.42 9.4 452 0.86 41 10d @ 6 - one side 128 W 4.6 4.3 0.5 0.0 HDU2
16 7.25 6.75 9.4 452 1.30 62 10d @ 6 - one side 128 W 2.0 4.3 0.6 0.2 HDU2
12/16/2021
20023.10 Page 18
Cantilever Columns at Kiosks
Cantilever Columns - Seismic
Seismic Demand, E 3109 lbf
Number of Columns 2
Shear per column = 1554.5 lbf
Cantilever length of Column 5.6667 ft
Moment at Steel Beam = 8808.83 lb-ft (LRFD)
6166.18 lb-ft (ASD)
HSS 4x4x1/4 Properties
S = 3.90 in
I = 7.80 in
Fy = 42.00 ksi ==> Fb = 25.2 ksi
E = 29000.00 ksi
Bending Stress, fb = 18.97 ksi < 25.2 ksi OK
Elastic Deflection = 0.72 in
Cd = 1.25 ==> δx = 0.9004 in
Shear Wall Defl., ∆m 0.45 in Total Defl = 1.35 in
Allowable Deflection = 2.16 in
OK
Walnut Creek, California Date 1/3/22 By TMS
Cantilever Columns at Canopy
Cantilever Columns - Lateral Seismic Design Controls
Width 48 ft
Length 52 ft
Canopy Weight 14.0 psf ==> W = 34.94 kips
Base Shear Coeff. 0.907 ==> Vb = 31.69 kips
Trial Column Size: HSS 10x8x5/8
Area, A 18.70 in
Inertia, Ix 252.52 in
Inertia, Iy 178.05 in
Modulus, Sx 50.50 in
Modulus, Sy 44.51 in
Radius of gyration, rx 3.68 in Radius of gyration, ry 3.07 in
Column deflections per kip for ENERCALC Diaphragm Model Shear from Model
Col H(ft) dX dY V_X V_Y
1 15.09 0.2702691 0.3833101 6.738 6.106 kips
2 16.75 0.369635 0.5242361 4.917 4.414 kips
3 14.84 0.2570576 0.3645728 6.138 6.407 kips
4 16.5 0.35333 0.5011115 4.469 4.616 kips
5 14.59 0.2442838 0.3464562 6.952 6.759 kips
6 16.26 0.3381352 0.4795613 5.019 4.818 kips
15.6717 average height
Walnut Creek, California Date 01/03/22 By TMS
Cantilever Columns at Canopy
Column Design See Enercalc for distribution of forces
Loading Summary:
V (kips) M(kip-ft) ∆(in) V (kips) M(kip-ft) ∆(in)
Col
1 6.74 101.68 1.82 6.11 92.14 2.34
2 4.92 82.36 1.82 4.41 73.93 2.31
3 6.14 91.09 1.58 6.41 95.08 2.34
4 4.47 73.74 1.58 4.62 76.16 2.31
5 6.95 101.43 1.70 6.76 98.61 2.34
6 5.02 81.61 1.70 4.82 78.34 2.31
Design Properties:
Steel Yield Strength, Fy 46.00 ksi
Modulus, E 29000.00 ksi
Slenderness Factor, K 2.00
Amplification, Cd 1.25
Axial Capacity
Col Cc KL/r Fa (ksi) fa (ksi) fa/Fa
1 111.554 118.04 10.72 0.31 0.03
2 111.554 131.03 8.70 0.31 0.04
3 111.554 116.09 11.08 0.31 0.03
4 111.554 129.07 8.96 0.31 0.03
5 111.554 114.13 11.46 0.31 0.03
6 111.554 127.20 9.23 0.31 0.03
Flexural Capacity (w/Compact Section)
Col Fb (ksi) fb (ksi) fb/Fb Fb (ksi) fb (ksi) fb/Fb
1 30.360 16.911 0.557 30.360 17.388 0.573
2 30.360 13.698 0.451 30.360 13.952 0.460
3 30.360 15.150 0.499 30.360 17.943 0.591
4 30.360 12.264 0.404 30.360 14.373 0.473
5 30.360 16.870 0.556 30.360 18.610 0.613
6 30.360 13.573 0.447 30.360 14.784 0.487
X-Direction Y-Direction
X-Direction Y-Direction
Cantilever Columns at Canopy
Combined axial + bending stress
Col X-Dir Y-Dir
1 0.586 0.602
2 0.487 0.495 Max Stress ratio: 0.640 OK
3 0.527 0.619
4 0.439 0.508
5 0.583 0.640
6 0.481 0.521
Deflections
Allowable
Col ∆x (in) ∆y (in) δm (in) δa (in) Check
1 1.82 2.34 2.926 3.761 OK
2 1.82 2.31 2.892 3.761 OK
3 1.58 2.34 2.920 3.761 OK
4 1.58 2.31 2.891 3.761 OK
5 1.70 2.34 2.927 3.761 OK
6 1.70 2.31 2.888 3.761 OK
Separation at Kiosk
Kiosk Deflection, δm 0.55 in
Kiosk Roof Height 11.5 ft
Canopy Defl. At Kiosk Ht 2.148 in
Reqd Separation 2.22 in
Diaphragms
Buildings
Diaph Load Diaph
Wall Length (ft) (lb) Shear
1 27 1691 62.64
2 27 1691 62.64
3 14.25 2095 147.00
4 14.25 1909 133.98 Controlling Shear = 406.67 plf
5 9.33 3109 333.10
6 9.33 1169 125.25 Plywood thickness = 15/32
7 17.17 601 35.02 Blocked ? no
8 17.17 601 35.02 Nailing 10d
9 6.92 2804 405.46 Spacing, EN 6 in
10 6.92 1314 190.01
11 19.50 524 26.86 Nominal Capacity 510 plf
12 19.50 524 26.86 φ factor 0.8
13 6.92 1313 189.76
14 6.92 2813 406.67 φ Vn 408 plf
15 19.50 524 26.87 OK
16 19.50 524 26.87
Canopy
Vb = 31.69 kips
Min. Diaph Length = 48 ft
Diaph Shear Demand = 330.15 plf (LRFD)
231.10 plf (ASD)
Capacity of 20 Ga Metal Deck 239 plf OK with BP connections at 6" O.C.
Diaphragms
Check for Flexible/Rigid diaphragm
G' 46 kip/in
Span 24 ft
∆diaph 1.44691 in 2*∆diaph 2.894 in
Support Deflection 2.9 in > 2.894 in
Rigid Diaph
Vertical Loading
Building Framing
Support Building Roof Joists, J1:
Size: 2x8 Dead Load: 15 psf
Spacing: 2'-0" Live Load: 20 psf
Material: DF #1 Wind Load: 25 psf
Span: 10'-6" Wind Load (OH): 0 psf
Overhang: 0 Snow Load: 0 psf
See Enercalc for design
Support Building Roof Joists, J2:
Size: 2x8 Dead Load: 15 psf
Spacing: 2'-0" Live Load: 20 psf
Material: DF #1 Wind Load: 25 psf
Span: 9'-8" Wind Load (OH): 35.5 psf
Overhang: 4'-8" Snow Load: 0 psf
See Enercalc for design
Support Building Roof Beams, BM1:
Size: 6x14 Dead Load: 15 psf
Trib Width: 9.75 ft Live Load: 20 psf
Material: DF #1 Wind Load: 25 psf
Span: 18'-10" Wind Load (OH): 0 psf
Overhang: 0 Snow Load: 0 psf
See Enercalc for design
Support Building Porch Joists, PJ1:
Size: 6x4x1/4 Dead Load: 15 psf
Trib Width: 4'-0" Live Load: 20 psf
Material: A500 Gr B Wind Load: 25 psf
Span: 19'-0" Wind Load (OH): 0 psf
Overhang: 0 Snow Load: 0 psf
See Enercalc for design
Vertical Loading
Comfort Station Porch Beams, PBM1:
Size: 6x4x1/4 Dead Load: 15 psf
Trib Width: 9.96 Live Load: 20 psf
Material: A500 Gr B Wind Load: 25 psf
Span: 9'-2" Wind Load (OH): 35.5 psf
Overhang: 3'-7" Snow Load: 0 psf
See Enercalc for design
Kiosk Roof Joists, KJ1:
Size: 2x8 Dead Load: 15 psf
Spacing: 2'-0" Live Load: 20 psf
Material: DF #1 Wind Load: 25 psf
Span: 9'-6" Wind Load (OH): 35.5 psf
Overhang: 4'-4" Snow Load: 0 psf
See Enercalc for design
Kiosk Roof Beams, KBM1:
Size: 4x8 Dead Load: 15 psf
Trib Width: 8.50 ft Live Load: 20 psf
Material: DF #1 Wind Load: 25 psf
Span: 8'-2" Wind Load (OH): 0 psf
Overhang: 0 Snow Load: 0 psf
See Enercalc for design
ALL Headers, HDR1:
Size: 6x8 flat Dead Load: 15 psf
Trib Width: 8.75 ft Live Load: 20 psf
Material: DF #1 Wind Load: 25 psf
Span: 8'-0" Wind Load (OH): 0 psf
Overhang: 0 Snow Load: 0 psf
Vertical Loading
Canopy Framing
Canopy Rafters:
Size: 8x6x5/16 Dead Load: 14 psf
Trib Width: 8'-0" Live Load: 20 psf
Material: A500 Gr B Wind Load: 20.2 psf
Span: 24'-5" Wind Load (OH): 20.2 psf
Overhang: 2'-0" Snow Load: 0 psf
See Enercalc for design
Canopy Beams:
Size: 12x8x3/8 Dead Load: 14 psf
Trib Width: 24.00 ft Live Load: 20 psf
Material: A500 Gr B Wind Load: 20.2 psf
Span: 28'-10" Wind Load (OH): 20.2 psf
Overhang: 11'-2"/8'-0" Snow Load: 0 psf
Vertical Loading
Metal Decking
HSN3-32 Acoustical Metal Deck by Verco
Dead Load on decking 4 psf (PV panels)
Live Load on decking 26 psf, Note: same as wind load
30 psf
Span Conditions: 2 or more spans
Typ Span Length 8 ft
Cant. Span Length 4 ft
Deck Properties:
Fy 50 ksi
Gage 20
Weight 2.4 psf
Sneg 0.471 in /ft
I 0.833 in /ft
Vertical Loading
Metal Decking
Allowable uniform load 143 psf OK
Check Cantilever Condition (Add 300 lb point load (2' trib) at roof edge - Conservative)
Distributed Load 32.4 psf
Point Load 300 lbs
Bending Moment 859.2 lb-ft/ft
OK
fb 21.89 ksi < Fb 30 ksi
Deflection 0.3031 in
L/240 Limit 0.4 in OK
Use 16 gauge x 3" deep HSN3 Perf metal deck
Foundations
Typical Bearing/Shear Wall Foundations
Max Roof Trib Width: 8.915 ft
Max Wall Height: 12.42 ft
Dead Load: 15 psf roof
12 psf walls
Live Load: 20 psf roof
Wind Load: 35.5 psf roof overhang
Load to footing: Load factor
DL 282.77 plf 1
Lr 178.30 plf 0.75
W 316.48 plf 0.45
Factored Design Load 558.91 plf
Bearing Capacity
Footing Width 1.5 ft
Footing Depth below grade 2 ft
Bearing Capacity = 4690 psf
Demand = 373 psf OK
Overturning at wall ends:
Compression Demand 6.1 kips
1016.67 psf OK
Grade Beam ok for uplift by inspection
Foundations
Canopy Footings
Footing Length 8.5 ft Cover 0.75 ft
Footing Width 8.5 ft
Footing Depth 3.25 ft Footing Weight 35.22 kips
Cover Weight 6.50 kips
Loading: Trib Roof Area 609.6 sf
Load
Dead Load 14 psf 8.53 kips
Roof Live Load 20 psf 12.2 kips
Wind 20.2 psf 12.3 kips
Seismic Shear 6.759 kips
Seismic Moment 98.61 kip-ft
Controlling Load Combination: 0.6D +/- 0.7E(Ωo) Ωo 1.25
Vert Load 30.155 kips
Moment 86.287 kip-ft
Shear 5.914 kips
Foundations
For seismic load case, allow eccentricity of resultant to be outside the kern. Check bearing pressure for this condition.
Resultant eccentricity, e 3.499 ft
Length of bearing. l' 2.254 ft
Maximum bearing stress 3.149 ksf
Allowable bearing stress 11.157 ksf OK
Check Sliding
Passive Resistance 6.768 kips
Shear Resistance 10.727 kips OK
17.495 kips > 5.914 kips
Foundations
Footing Flexural Reinforcement
Controlling Load Combination: 0.9D +/- 1.0E
Vert Load 45.233 kips
Moment 123.267 kip-ft
Shear 6.759 kips
Bar Size 6 diam 0.75 in area 0.44 in
Num Bars 8 As 3.534 in
Cover 3 in d 35.63 in
Concrete Strength, f'c 4 ksi
Steel Strength, fy 60 ksi
Strength Reduction factor, φ 0.9
OK
φMn 561.73 kip-ft > 145.23 kip-ft
Minimum S&T Reinforcement 6.54 in ==> 7.5 bars T&B
(Each Face)
Curbs at Bearing Walls
Curb Width 7.25 in
Max. Curb Height 14.00 in (above F.G.)
Lateral Earth Pressure 40.00 pcf
Surcharge Pressure 80.00 psf
Foundations
Active Surcharge
Flexural Demand on stem 10.586 54.444 lb-ft/ft
Total 65.031 lb-ft/ft
0.78 kip-in
Reinforcement Size #4 bar diameter 0.5 in
Spacing 12 in
Depth 3.625 in
Concrete Strength 4 ksi
Area of Steel 0.20 in /ft
OK
Capacity, φMn 36.90 kip-in > 0.78 kip-in
Use #4 bars at 12" O.C. in stem
Anchorage
Canopy Column Base Plate Note: Seismic Load Controls
Column Loads/Demands to Base Plate:
Dead Load 8.534 kips
LC1 LC2
X-Dir Y-Dir
Seismic Shear 6.95 6.76 kips
Seismic Moment 101.676 98.61 kip-ft
Load Combination: 0.9D + E(Ωo)
Load Case 1
X-Dir
Anchorage
Canopy Column Base Plate
Anchorage
Canopy Column Base Plate
Load Case 2
Y-Dir
Anchorage
Anchorage
Column to Base Plate Connection
Mu 127.10 kip-ft
Vu 8.69 kips
Pu 7.68 kips
Fillet Weld Size 0.375 in Effective Shear width 0.265 in
Column Dimension 10 in
Weld Strength 70 ksi
Shear on effective Area φfw 8.353 kip/in
Tension Demand 148.67 kips lweld >= 17.800 in
Shear Demand 8.69 kips lweld >= 1.040 in
Stiffener plate length 6 in (2) plates each side of column
Total weld length for tension 34 in > 17.800 in OK
Total weld length for shear 20 in > 1.040 in OK
Equipment Pad
Booster Pump at (E) Comfort Station
Model QFMV2-1LH by Flowtherm
Skid Mounted
Operating Weight 690 lb
Mounting Per Manuf. 5/8" dia holes for 1/2" dia A.B.
Trans Spacing = 26 in
Long Spacing = 36 in
Num of Bolts = 4
Heigth of C.G. 36 in
Seismic Demands:
Seismic Coeff. 0.34 *Wp ==> Fp = 234.6 lb
Shear on A.B. 58.65 lb/anchor
Uplift on A.B. 162.42 lb/anchor
Equipment Pad
Booster Pump at (E) Comfort Station
Equipment Pad
Booster Pump at (E) Comfort Station
Wood Beam LIC# : KW-06015314, Build:20.21.10.4 Bluestone Engineering (c) ENERCALC INC 1983-2021
DESCRIPTION: Joist J1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
CODE REFERENCES
Calculations per NDS 2018, IBC 2018, CBC 2019, ASCE 7-16 Load Combination Set : ASCE 7-16
Material Properties
Beam Bracing : Beam is Fully Braced against lateral-torsional buckling Repetitive Member Stress Increase
Allowable Stress Design
Douglas Fir-Larch No.1
1,000.0 1,000.0 1,500.0
625.0
1,700.0 620.0
180.0
675.0 31.210
Analysis Method :
Eminbend - xx ksi Wood Species :
Wood Grade :
Fb + psi psi
Fv psi
Fb -
Ft psi
Fc - Prll psi psiFc - Perp
E : Modulus of Elasticity Ebend- xx ksi
Density pcf
Load Combination : ASCE 7-16
.Applied Loads Service loads entered. Load Factors will be applied for calculations.
Uniform Load : D = 0.0150, Lr = 0.020, W = 0.0250 ksf, Tributary Width = 2.0 ft
.DESIGN SUMMARY Design OK Maximum Bending Stress Ratio 0.426: 1
Load Combination +D+Lr
Span # where maximum occurs Span # 1 Location of maximum on span 5.250ft
45.14 psi=
2,070.00psi
2x8Section used for this span
Span # where maximum occurs Location of maximum on span
Span # 1=
Load Combination +D+Lr
225.00 psi==
Section used for this span 2x8 Maximum Shear Stress Ratio 0.201 : 1
0.000 ft=
880.95psi
Maximum Deflection
0 <360
Ratio = 0 <180
Max Downward Transient Deflection 0.170 in 741Ratio = >=360 Max Upward Transient Deflection 0 in Ratio = Max Downward Total Deflection 0.280 in Ratio = >=180 Max Upward Total Deflection 0 in fb: Actual Fb: Allowable fv: Actual Fv: Allowable
Span: 1 : W Only n/a Span: 1 : +D+0.750Lr+0.450W n/a
.Maximum Forces & Stresses for Load Combinations
Span # Moment ValuesLoad Combination
C i CLC CCCF/V mr td Shear ValuesMax Stress Ratios
M CV fbM fvF'b V F'vSegment Length D Only 0.00 0.00 0.000.00
1.00Length = 10.50 ft 1 0.253 0.119 0.90 1.200 1.15 1.00 1.00 0.41 377.55 1490.40 0.14 162.001.00 19.35 1.00+D+Lr 1.200 1.15 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 10.50 ft 1 0.426 0.201 1.25 1.200 1.15 1.00 1.00 0.96 880.95 2070.00 0.33 225.001.00 45.14 1.00+D+0.750Lr 1.200 1.15 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 10.50 ft 1 0.365 0.172 1.25 1.200 1.15 1.00 1.00 0.83 755.10 2070.00 0.28 225.001.00 38.69 1.00+D+0.60W 1.200 1.15 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 10.50 ft 1 0.285 0.134 1.60 1.200 1.15 1.00 1.00 0.83 755.10 2649.60 0.28 288.001.00 38.69 1.00+D+0.750Lr+0.450W 1.200 1.15 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 10.50 ft 1 0.392 0.185 1.60 1.200 1.15 1.00 1.00 1.14 1,038.26 2649.60 0.39 288.001.00 53.20 1.00+D+0.450W 1.200 1.15 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 10.50 ft 1 0.249 0.118 1.60 1.200 1.15 1.00 1.00 0.72 660.71 2649.60 0.25 288.001.00 33.85 1.00+0.60D+0.60W 1.200 1.15 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 10.50 ft 1 0.228 0.107 1.60 1.200 1.15 1.00 1.00 0.66 604.08 2649.60 0.22 288.001.00 30.95
DESCRIPTION: Joist J1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
Maximum Forces & Stresses for Load Combinations
Span # Moment ValuesLoad Combination
C i CLC CCCF/V mr td Shear ValuesMax Stress Ratios
M CV fbM fvF'b V F'vSegment Length 1.00+0.60D 1.200 1.15 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 10.50 ft 1 0.085 0.040 1.60 1.200 1.15 1.00 1.00 0.25 226.53 2649.60 0.08 288.001.00 11.61
Location in SpanLoad CombinationMax. "-" Defl Location in SpanLoad Combination Span Max. "+" Defl Overall Maximum Deflections
+D+0.750Lr+0.450W 1 0.2803 5.288 0.0000 0.000
Load Combination Support 1 Support 2 Vertical Reactions Support notation : Far left is #1 Values in KIPS
Overall MAXimum 0.433 0.433 Overall MINimum 0.263 0.263 D Only 0.158 0.158 +D+Lr 0.368 0.368 +D+0.750Lr 0.315 0.315 +D+0.60W 0.315 0.315 +D+0.750Lr+0.450W 0.433 0.433 +D+0.450W 0.276 0.276 +0.60D+0.60W 0.252 0.252 +0.60D 0.095 0.095 Lr Only 0.210 0.210 W Only 0.263 0.263
DESCRIPTION: Joist J2
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
CODE REFERENCES
Calculations per NDS 2018, IBC 2018, CBC 2019, ASCE 7-16 Load Combination Set : ASCE 7-16
Material Properties
Beam Bracing : Beam is Fully Braced against lateral-torsional buckling
Allowable Stress Design
Douglas Fir-Larch No.1
675 31.21
Analysis Method :
Eminbend - xx ksi Wood Species :
Wood Grade :
Fb + psi psi
Fv psi
Fb -
Ft psi
Fc - Prll psi psiFc - Perp
E : Modulus of Elasticity Ebend- xx ksi
Density pcf
Load Combination : ASCE 7-16
.Applied Loads Service loads entered. Load Factors will be applied for calculations.
Load for Span Number 1
Uniform Load : D = 0.0150, Lr = 0.020, W = 0.0250 ksf, Extent = 0.0 -->> 9.670 ft, Tributary Width = 2.0 ft Load for Span Number 2
Uniform Load : D = 0.0150, Lr = 0.020, W = 0.03550 ksf, Extent = 0.0 -->> 4.670 ft, Tributary Width = 2.0 ft .DESIGN SUMMARY Design OK
Maximum Bending Stress Ratio 0.397: 1
Load Combination+D+0.750Lr+0.750L+0.450W+H, LL Comb Run (*L)
Span # where maximum occurs Span # 1 Location of maximum on span 9.670ft
51.83 psi=
2,304.00psi
2x8Section used for this span
Span # where maximum occurs Location of maximum on span
Span # 1=
Load Combination +D+Lr+H, LL Comb Run (LL)
225.00 psi==
Section used for this span 2x8 Maximum Shear Stress Ratio 0.230 : 1
9.076 ft=
915.63psi
Maximum Deflection
746 >=360
Ratio = 934 >=180
Max Downward Transient Deflection 0.191 in 586Ratio = >=360 Max Upward Transient Deflection -0.150 in Ratio = Max Downward Total Deflection 0.241 in Ratio = >=180 Max Upward Total Deflection -0.120 in fb: Actual Fb: Allowable fv: Actual Fv: Allowable
Span: 2 : Lr Only, LL Comb Run (*L) Span: 2 : Lr Only, LL Comb Run (L*) Span: 2 : +D+0.750Lr+0.750L+0.450W+H, LL Comb Run Span: 2 : +D+Lr+H, LL Comb Run (L*)
.Maximum Forces & Stresses for Load Combinations
Span # Moment ValuesLoad Combination
C i CLC CCCF/V mr td Shear ValuesMax Stress Ratios
M CV fbM fvF'b V F'vSegment Length +D+H 0.00 0.00 0.000.00
1.00Length = 9.670 ft 1 0.231 0.137 0.90 1.200 1.00 1.00 1.00 0.33 298.74 1296.00 0.16 162.001.00 22.21 1.00Length = 4.670 ft 2 0.231 0.137 0.90 1.200 1.00 1.00 1.00 0.33 298.74 1296.00 0.12 162.001.00 22.21 1.00+D+L+H, LL Comb Run (*L) 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.207 0.123 1.00 1.200 1.00 1.00 1.00 0.33 298.74 1440.00 0.16 180.001.00 22.21 1.00Length = 4.670 ft 2 0.207 0.123 1.00 1.200 1.00 1.00 1.00 0.33 298.74 1440.00 0.12 180.001.00 22.21 1.00+D+L+H, LL Comb Run (L*) 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.207 0.123 1.00 1.200 1.00 1.00 1.00 0.33 298.74 1440.00 0.16 180.001.00 22.21 1.00Length = 4.670 ft 2 0.207 0.123 1.00 1.200 1.00 1.00 1.00 0.33 298.74 1440.00 0.12 180.001.00 22.21 1.00+D+L+H, LL Comb Run (LL) 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.207 0.123 1.00 1.200 1.00 1.00 1.00 0.33 298.74 1440.00 0.16 180.001.00 22.21
DESCRIPTION: Joist J2
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
Maximum Forces & Stresses for Load Combinations
Span # Moment ValuesLoad Combination
C i CLC CCCF/V mr td Shear ValuesMax Stress Ratios
M CV fbM fvF'b V F'vSegment Length 1.00Length = 4.670 ft 2 0.207 0.123 1.00 1.200 1.00 1.00 1.00 0.33 298.74 1440.00 0.12 180.001.00 22.21 1.00+D+Lr+H, LL Comb Run (*L) 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.387 0.175 1.25 1.200 1.00 1.00 1.00 0.76 697.05 1800.00 0.28 225.001.00 39.30 1.00Length = 4.670 ft 2 0.387 0.175 1.25 1.200 1.00 1.00 1.00 0.76 697.05 1800.00 0.28 225.001.00 39.30 1.00+D+Lr+H, LL Comb Run (L*) 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.336 0.203 1.25 1.200 1.00 1.00 1.00 0.66 605.26 1800.00 0.33 225.001.00 45.61 1.00Length = 4.670 ft 2 0.166 0.203 1.25 1.200 1.00 1.00 1.00 0.33 298.74 1800.00 0.12 225.001.00 45.61 1.00+D+Lr+H, LL Comb Run (LL) 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.387 0.230 1.25 1.200 1.00 1.00 1.00 0.76 697.05 1800.00 0.38 225.001.00 51.83 1.00Length = 4.670 ft 2 0.387 0.230 1.25 1.200 1.00 1.00 1.00 0.76 697.05 1800.00 0.28 225.001.00 51.83 1.00+D+S+H 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.16 207.001.00 22.21 1.00Length = 4.670 ft 2 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.12 207.001.00 22.21 1.00+D+0.750Lr+0.750L+H, LL Comb Run (* 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.332 0.150 1.25 1.200 1.00 1.00 1.00 0.65 597.48 1800.00 0.24 225.001.00 33.68 1.00Length = 4.670 ft 2 0.332 0.150 1.25 1.200 1.00 1.00 1.00 0.65 597.48 1800.00 0.24 225.001.00 33.68 1.00+D+0.750Lr+0.750L+H, LL Comb Run (L 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.278 0.177 1.25 1.200 1.00 1.00 1.00 0.55 499.78 1800.00 0.29 225.001.00 39.76 1.00Length = 4.670 ft 2 0.166 0.177 1.25 1.200 1.00 1.00 1.00 0.33 298.74 1800.00 0.12 225.001.00 39.76 1.00+D+0.750Lr+0.750L+H, LL Comb Run (L 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.332 0.197 1.25 1.200 1.00 1.00 1.00 0.65 597.48 1800.00 0.32 225.001.00 44.43 1.00Length = 4.670 ft 2 0.332 0.197 1.25 1.200 1.00 1.00 1.00 0.65 597.48 1800.00 0.24 225.001.00 44.43 1.00+D+0.750L+0.750S+H, LL Comb Run (*L 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.16 207.001.00 22.21 1.00Length = 4.670 ft 2 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.12 207.001.00 22.21 1.00+D+0.750L+0.750S+H, LL Comb Run (L* 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.16 207.001.00 22.21 1.00Length = 4.670 ft 2 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.12 207.001.00 22.21 1.00+D+0.750L+0.750S+H, LL Comb Run (LL 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.16 207.001.00 22.21 1.00Length = 4.670 ft 2 0.180 0.107 1.15 1.200 1.00 1.00 1.00 0.33 298.74 1656.00 0.12 207.001.00 22.21 1.00+D+0.60W+H 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.314 0.161 1.60 1.200 1.00 1.00 1.00 0.79 722.95 2304.00 0.34 288.001.00 46.39 1.00Length = 4.670 ft 2 0.314 0.161 1.60 1.200 1.00 1.00 1.00 0.79 722.95 2304.00 0.30 288.001.00 46.39 1.00+D+0.750Lr+0.750L+0.450W+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.397 0.179 1.60 1.200 1.00 1.00 1.00 1.00 915.63 2304.00 0.37 288.001.00 51.62 1.00Length = 4.670 ft 2 0.397 0.179 1.60 1.200 1.00 1.00 1.00 1.00 915.63 2304.00 0.37 288.001.00 51.62 1.00+D+0.750Lr+0.750L+0.450W+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.268 0.201 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.42 288.001.00 57.89 1.00Length = 4.670 ft 2 0.268 0.201 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.25 288.001.00 57.89 1.00+D+0.750Lr+0.750L+0.450W+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.397 0.217 1.60 1.200 1.00 1.00 1.00 1.00 915.63 2304.00 0.45 288.001.00 62.56 1.00Length = 4.670 ft 2 0.397 0.217 1.60 1.200 1.00 1.00 1.00 1.00 915.63 2304.00 0.37 288.001.00 62.56 1.00+D+0.750L+0.750S+0.450W+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.268 0.140 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.29 288.001.00 40.34 1.00Length = 4.670 ft 2 0.268 0.140 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.25 288.001.00 40.34 1.00+D+0.750L+0.750S+0.450W+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.268 0.140 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.29 288.001.00 40.34 1.00Length = 4.670 ft 2 0.268 0.140 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.25 288.001.00 40.34 1.00+D+0.750L+0.750S+0.450W+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.268 0.140 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.29 288.001.00 40.34 1.00Length = 4.670 ft 2 0.268 0.140 1.60 1.200 1.00 1.00 1.00 0.68 616.89 2304.00 0.25 288.001.00 40.34 1.00+0.60D+0.60W+0.60H 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.262 0.130 1.60 1.200 1.00 1.00 1.00 0.66 603.45 2304.00 0.27 288.001.00 37.50 1.00Length = 4.670 ft 2 0.262 0.130 1.60 1.200 1.00 1.00 1.00 0.66 603.45 2304.00 0.25 288.001.00 37.50 1.00+D+0.70E+0.60H 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.16 288.001.00 22.21 1.00Length = 4.670 ft 2 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.12 288.001.00 22.21 1.00+D+0.750L+0.750S+0.5250E+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00
DESCRIPTION: Joist J2
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
Maximum Forces & Stresses for Load Combinations
Span # Moment ValuesLoad Combination
C i CLC CCCF/V mr td Shear ValuesMax Stress Ratios
M CV fbM fvF'b V F'vSegment Length 1.00Length = 9.670 ft 1 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.16 288.001.00 22.21 1.00Length = 4.670 ft 2 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.12 288.001.00 22.21 1.00+D+0.750L+0.750S+0.5250E+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.16 288.001.00 22.21 1.00Length = 4.670 ft 2 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.12 288.001.00 22.21 1.00+D+0.750L+0.750S+0.5250E+H, LL Comb 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.16 288.001.00 22.21 1.00Length = 4.670 ft 2 0.130 0.077 1.60 1.200 1.00 1.00 1.00 0.33 298.74 2304.00 0.12 288.001.00 22.21 1.00+0.60D+0.70E+H 1.200 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 9.670 ft 1 0.078 0.046 1.60 1.200 1.00 1.00 1.00 0.20 179.24 2304.00 0.10 288.001.00 13.33 1.00Length = 4.670 ft 2 0.078 0.046 1.60 1.200 1.00 1.00 1.00 0.20 179.24 2304.00 0.07 288.001.00 13.33
Location in SpanLoad CombinationMax. "-" Defl Location in SpanLoad Combination Span Max. "+" Defl Overall Maximum Deflections
+D+Lr+H, LL Comb Run (L*) 1 0.1308 4.646 0.0000 0.000 +D+Lr+H, LL Comb Run (L*)+D+0.750Lr+0.750L+0.450W+H, LL C2 0.2412 4.670 -0.0168 0.522
Load Combination Support 1 Support 2 Support 3 Vertical Reactions Support notation : Far left is #1 Values in KIPS
Overall MAXimum 0.329 0.932 Overall MINimum 0.162 0.653 +D+H 0.111 0.319 +D+L+H, LL Comb Run (*L) 0.111 0.319 +D+L+H, LL Comb Run (L*) 0.111 0.319 +D+L+H, LL Comb Run (LL) 0.111 0.319 +D+Lr+H, LL Comb Run (*L) 0.066 0.551 +D+Lr+H, LL Comb Run (L*) 0.305 0.512 +D+Lr+H, LL Comb Run (LL) 0.260 0.744 +D+S+H 0.111 0.319 +D+0.750Lr+0.750L+H, LL Comb Run (* 0.077 0.493 +D+0.750Lr+0.750L+H, LL Comb Run (L 0.256 0.464 +D+0.750Lr+0.750L+H, LL Comb Run (L 0.222 0.638 +D+0.750L+0.750S+H, LL Comb Run (*L 0.111 0.319 +D+0.750L+0.750S+H, LL Comb Run (L* 0.111 0.319 +D+0.750L+0.750S+H, LL Comb Run (LL 0.111 0.319 +D+0.60W+H 0.208 0.711 +D+0.750Lr+0.750L+0.450W+H, LL Comb 0.150 0.787 +D+0.750Lr+0.750L+0.450W+H, LL Comb 0.329 0.758 +D+0.750Lr+0.750L+0.450W+H, LL Comb 0.295 0.932 +D+0.750L+0.750S+0.450W+H, LL Comb 0.184 0.613 +D+0.750L+0.750S+0.450W+H, LL Comb 0.184 0.613 +D+0.750L+0.750S+0.450W+H, LL Comb 0.184 0.613 +0.60D+0.60W+0.60H 0.164 0.583 +D+0.70E+0.60H 0.111 0.319 +D+0.750L+0.750S+0.5250E+H, LL Comb 0.111 0.319 +D+0.750L+0.750S+0.5250E+H, LL Comb 0.111 0.319 +D+0.750L+0.750S+0.5250E+H, LL Comb 0.111 0.319 +0.60D+0.70E+H 0.067 0.191 D Only 0.111 0.319 Lr Only, LL Comb Run (*L) -0.045 0.232 Lr Only, LL Comb Run (L*) 0.193 0.193 Lr Only, LL Comb Run (LL) 0.148 0.425 W Only 0.162 0.653 H Only
DESCRIPTION: BM1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
CODE REFERENCES
Calculations per NDS 2018, IBC 2018, CBC 2019, ASCE 7-16 Load Combination Set : ASCE 7-16
Material Properties
Beam Bracing : Beam is Fully Braced against lateral-torsional buckling
Allowable Stress Design
Douglas Fir-Larch (North) No.1
1,300.0 1,300.0
925.0 625.0
1,600.0 580.0
170.0
675.0 30.590
Analysis Method :
Eminbend - xx ksi Wood Species :
Wood Grade :
Fb + psi psi
Fv psi
Fb -
Ft psi
Fc - Prll psi psiFc - Perp
E : Modulus of Elasticity Ebend- xx ksi
Density pcf
Load Combination : ASCE 7-16
.Applied Loads Service loads entered. Load Factors will be applied for calculations.
Uniform Load : D = 0.0150, Lr = 0.020, W = 0.0250 ksf, Tributary Width = 9.750 ft
.DESIGN SUMMARY Design OK Maximum Bending Stress Ratio 0.677: 1
Load Combination +D+Lr
Span # where maximum occurs Span # 1 Location of maximum on span 9.415ft
57.33 psi=
1,603.87psi
6x14Section used for this span
Span # where maximum occurs Location of maximum on span
Span # 1=
Load Combination +D+Lr
212.50 psi==
Section used for this span 6x14 Maximum Shear Stress Ratio 0.270 : 1
0.000 ft=
1,086.39psi
Maximum Deflection
0 <360
Ratio = 0 <180
Max Downward Transient Deflection 0.384 in 587Ratio = >=360 Max Upward Transient Deflection 0 in Ratio = Max Downward Total Deflection 0.634 in Ratio = >=180 Max Upward Total Deflection 0 in fb: Actual Fb: Allowable fv: Actual Fv: Allowable
Span: 1 : W Only n/a Span: 1 : +D+0.750Lr+0.450W n/a
.Maximum Forces & Stresses for Load Combinations
Span # Moment ValuesLoad Combination
C i CLC CCCF/V mr td Shear ValuesMax Stress Ratios
M CV fbM fvF'b V F'vSegment Length D Only 0.00 0.00 0.000.00
1.00Length = 18.830 ft 1 0.403 0.161 0.90 0.987 1.00 1.00 1.00 6.48 465.60 1154.79 1.22 153.001.00 24.57 1.00+D+Lr 0.987 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 18.830 ft 1 0.677 0.270 1.25 0.987 1.00 1.00 1.00 15.12 1,086.39 1603.87 2.84 212.501.00 57.33 1.00+D+0.750Lr 0.987 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 18.830 ft 1 0.581 0.231 1.25 0.987 1.00 1.00 1.00 12.96 931.19 1603.87 2.43 212.501.00 49.14 1.00+D+0.60W 0.987 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 18.830 ft 1 0.454 0.181 1.60 0.987 1.00 1.00 1.00 12.96 931.19 2052.96 2.43 272.001.00 49.14 1.00+D+0.750Lr+0.450W 0.987 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 18.830 ft 1 0.624 0.248 1.60 0.987 1.00 1.00 1.00 17.83 1,280.39 2052.96 3.34 272.001.00 67.56 1.00+D+0.450W 0.987 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 18.830 ft 1 0.397 0.158 1.60 0.987 1.00 1.00 1.00 11.34 814.79 2052.96 2.13 272.001.00 42.99 1.00+0.60D+0.60W 0.987 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 18.830 ft 1 0.363 0.145 1.60 0.987 1.00 1.00 1.00 10.37 744.95 2052.96 1.95 272.001.00 39.31
DESCRIPTION: BM1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
Maximum Forces & Stresses for Load Combinations
Span # Moment ValuesLoad Combination
C i CLC CCCF/V mr td Shear ValuesMax Stress Ratios
M CV fbM fvF'b V F'vSegment Length 1.00+0.60D 0.987 1.00 1.00 1.00 0.00 0.00 0.001.00 0.00 1.00Length = 18.830 ft 1 0.136 0.054 1.60 0.987 1.00 1.00 1.00 3.89 279.36 2052.96 0.73 272.001.00 14.74
Location in SpanLoad CombinationMax. "-" Defl Location in SpanLoad Combination Span Max. "+" Defl Overall Maximum Deflections
+D+0.750Lr+0.450W 1 0.6342 9.484 0.0000 0.000
Load Combination Support 1 Support 2 Vertical Reactions Support notation : Far left is #1 Values in KIPS
Overall MAXimum 3.787 3.787 Overall MINimum 2.295 2.295 D Only 1.377 1.377 +D+Lr 3.213 3.213 +D+0.750Lr 2.754 2.754 +D+0.60W 2.754 2.754 +D+0.750Lr+0.450W 3.787 3.787 +D+0.450W 2.410 2.410 +0.60D+0.60W 2.203 2.203 +0.60D 0.826 0.826 Lr Only 1.836 1.836 W Only 2.295 2.295
Steel Beam
DESCRIPTION: PJ1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
CODE REFERENCES
Calculations per AISC 360-16, IBC 2018, CBC 2019, ASCE 7-16 Load Combination Set : ASCE 7-16
Material Properties Analysis Method :
ksi Bending Axis : Major Axis Bending
Beam is Fully Braced against lateral-torsional buckling Allowable Strength Design Fy : Steel Yield : 46.0 ksi
Beam Bracing : E: Modulus : 29,000.0
.Service loads entered. Load Factors will be applied for calculations.Applied Loads Beam self weight NOT internally calculated and added
Uniform Load : D = 0.0150, Lr = 0.020, W = 0.0250 ksf, Tributary Width = 4.0 ft
.Design OKDESIGN SUMMARY Maximum Bending Stress Ratio = 0.380 : 1
Load Combination +D+0.750Lr+0.450W
Span # where maximum occurs Span # 1 Location of maximum on span 9.500ft
1.568 k Mn / Omega : Allowable 19.580 k-ft Vn/Omega : Allowable
HSS6x4x1/4Section used for this span
Span # where maximum occurs Location of maximum on span
Span # 1
Load Combination +D+0.750Lr+0.450W
40.826 k
Section used for this span HSS6x4x1/4 Ma : Applied
Maximum Shear Stress Ratio = 0.038 : 1
0.000 ft
7.446 k-ft Va : Applied
0 <360
Ratio = 0 <180
Maximum Deflection Max Downward Transient Deflection 0.485 in 469Ratio = >=360 Max Upward Transient Deflection 0.000 in Ratio = Max Downward Total Deflection 0.802 in Ratio = >=180 Max Upward Total Deflection 0.000 in
Span: 1 : W Only Span: 1 : +D+0.750Lr+0.450W
.Maximum Forces & Stresses for Load Combinations
Span # Summary of Moment ValuesLoad Combination Summary of Shear ValuesMax Stress Ratios
M V Mmax -Mmax + Rm VnxMa Max Mnx/Omega Cb Va MaxMnx Vnx/OmegaSegment Length D Only
Dsgn. L = 19.00 ft 1 0.138 0.014 2.71 2.71 32.70 19.58 1.00 1.00 0.57 68.18 40.83 +D+Lr
Dsgn. L = 19.00 ft 1 0.323 0.033 6.32 6.32 32.70 19.58 1.00 1.00 1.33 68.18 40.83 +D+0.750Lr
Dsgn. L = 19.00 ft 1 0.277 0.028 5.42 5.42 32.70 19.58 1.00 1.00 1.14 68.18 40.83 +D+0.60W
Dsgn. L = 19.00 ft 1 0.277 0.028 5.42 5.42 32.70 19.58 1.00 1.00 1.14 68.18 40.83 +D+0.750Lr+0.450W
Dsgn. L = 19.00 ft 1 0.380 0.038 7.45 7.45 32.70 19.58 1.00 1.00 1.57 68.18 40.83 +D+0.450W
Dsgn. L = 19.00 ft 1 0.242 0.024 4.74 4.74 32.70 19.58 1.00 1.00 1.00 68.18 40.83 +0.60D+0.60W
Dsgn. L = 19.00 ft 1 0.221 0.022 4.33 4.33 32.70 19.58 1.00 1.00 0.91 68.18 40.83 +0.60D
Dsgn. L = 19.00 ft 1 0.083 0.008 1.62 1.62 32.70 19.58 1.00 1.00 0.34 68.18 40.83
Location in SpanLoad CombinationMax. "-" Defl Location in SpanLoad Combination Span Max. "+" Defl Overall Maximum Deflections
+D+0.750Lr+0.450W 1 0.8019 9.554 0.0000 0.000
DESCRIPTION: PJ1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
Load Combination Support 1 Support 2 Vertical Reactions Support notation : Far left is #1 Values in KIPS
Overall MAXimum 1.568 1.568 Overall MINimum -0.342 -0.342 D Only 0.570 0.570 +D+Lr 1.330 1.330 +D+0.750Lr 1.140 1.140 +D+0.60W 1.140 1.140 +D+0.750Lr+0.450W 1.568 1.568 +D+0.450W 0.998 0.998 +0.60D+0.60W 0.912 0.912 +0.60D 0.342 0.342 Lr Only 0.760 0.760 W Only 0.950 0.950
DESCRIPTION: PBM1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
CODE REFERENCES
Calculations per AISC 360-16, IBC 2018, CBC 2019, ASCE 7-16 Load Combination Set : ASCE 7-16
Material Properties Analysis Method :
ksi Bending Axis : Major Axis Bending
Beam is Fully Braced against lateral-torsional buckling Allowable Strength Design Fy : Steel Yield : 46.0 ksi
Beam Bracing : E: Modulus : 29,000.0
.Service loads entered. Load Factors will be applied for calculations.Applied Loads Beam self weight NOT internally calculated and added Load for Span Number 1
Uniform Load : D = 0.0150, Lr = 0.020, W = 0.0250 ksf, Tributary Width = 10.0 ft
Load for Span Number 2 Uniform Load : D = 0.0150, Lr = 0.020, W = 0.03550 ksf, Tributary Width = 10.0 ft
.Design OKDESIGN SUMMARY Maximum Bending Stress Ratio = 0.173 : 1
Load Combination+D+0.750Lr+0.750L+0.450W+H, LL Comb Run (L*)
Span # where maximum occurs Span # 1 Location of maximum on span 4.048ft
2.234 k Mn / Omega : Allowable 19.580 k-ft Vn/Omega : Allowable
HSS6x4x1/4Section used for this span
Span # where maximum occurs Location of maximum on span
Span # 1
Load Combination+D+0.750Lr+0.750L+0.450W+H, LL Comb Run (LL)
40.826 k
Section used for this span HSS6x4x1/4 Ma : Applied
Maximum Shear Stress Ratio = 0.055 : 1
9.200 ft
3.384 k-ft Va : Applied
1,297 >=360
Ratio = 1148 >=180
Maximum Deflection Max Downward Transient Deflection 0.056 in 1,569Ratio = >=360 Max Upward Transient Deflection -0.068 in Ratio = Max Downward Total Deflection 0.079 in Ratio = >=180 Max Upward Total Deflection -0.077 in
Span: 2 : Lr Only, LL Comb Run (L*) Span: 2 : Lr Only, LL Comb Run (*L) Span: 2 : +D+0.750Lr+0.750L+0.450W+H, LL Comb Run Span: 2 : +D+Lr+H, LL Comb Run (L*)
.Maximum Forces & Stresses for Load Combinations
Span # Summary of Moment ValuesLoad Combination Summary of Shear ValuesMax Stress Ratios
M V Mmax -Mmax + Rm VnxMa Max Mnx/Omega Cb Va MaxMnx Vnx/OmegaSegment Length +D+H
Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+L+H, LL Comb Run (*L) Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+L+H, LL Comb Run (L*) Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+L+H, LL Comb Run (LL) Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+Lr+H, LL Comb Run (*L) Dsgn. L = 9.20 ft 1 0.120 0.031 0.63 -2.36 2.36 32.70 19.58 1.00 1.00 1.28 68.18 40.83 Dsgn. L = 3.67 ft 2 0.120 0.031 -2.36 2.36 32.70 19.58 1.00 1.00 1.28 68.18 40.83
+D+Lr+H, LL Comb Run (L*) Dsgn. L = 9.20 ft 1 0.164 0.042 3.22 -1.01 3.22 32.70 19.58 1.00 1.00 1.72 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
DESCRIPTION: PBM1
Project File: EC.ec6
Project Title: Joshua Tree National Park Engineer: T. Swenson Project ID: 20023.10 Project Descr: West Entrance Station
Maximum Forces & Stresses for Load Combinations
Span # Summary of Moment ValuesLoad Combination Summary of Shear ValuesMax Stress Ratios
M V Mmax -Mmax + Rm VnxMa Max Mnx/Omega Cb Va MaxMnx Vnx/OmegaSegment Length +D+Lr+H, LL Comb Run (LL)
Dsgn. L = 9.20 ft 1 0.134 0.046 2.62 -2.36 2.62 32.70 19.58 1.00 1.00 1.87 68.18 40.83 Dsgn. L = 3.67 ft 2 0.120 0.031 -2.36 2.36 32.70 19.58 1.00 1.00 1.28 68.18 40.83
+D+S+H Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.750Lr+0.750L+H, LL Comb Run (* Dsgn. L = 9.20 ft 1 0.103 0.027 0.74 -2.02 2.02 32.70 19.58 1.00 1.00 1.10 68.18 40.83 Dsgn. L = 3.67 ft 2 0.103 0.027 -2.02 2.02 32.70 19.58 1.00 1.00 1.10 68.18 40.83
+D+0.750Lr+0.750L+H, LL Comb Run (L Dsgn. L = 9.20 ft 1 0.137 0.036 2.69 -1.01 2.69 32.70 19.58 1.00 1.00 1.49 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.750Lr+0.750L+H, LL Comb Run (L Dsgn. L = 9.20 ft 1 0.115 0.039 2.24 -2.02 2.24 32.70 19.58 1.00 1.00 1.60 68.18 40.83 Dsgn. L = 3.67 ft 2 0.103 0.027 -2.02 2.02 32.70 19.58 1.00 1.00 1.10 68.18 40.83
+D+0.750L+0.750S+H, LL Comb Run (*L Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.750L+0.750S+H, LL Comb Run (L* Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.750L+0.750S+H, LL Comb Run (LL Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.60W+H Dsgn. L = 9.20 ft 1 0.125 0.040 2.07 -2.44 2.44 32.70 19.58 1.00 1.00 1.65 68.18 40.83 Dsgn. L = 3.67 ft 2 0.125 0.033 -2.44 2.44 32.70 19.58 1.00 1.00 1.33 68.18 40.83
+D+0.750Lr+0.750L+0.450W+H, LL Comb Dsgn. L = 9.20 ft 1 0.158 0.041 1.44 -3.10 3.10 32.70 19.58 1.00 1.00 1.69 68.18 40.83 Dsgn. L = 3.67 ft 2 0.158 0.041 -3.10 3.10 32.70 19.58 1.00 1.00 1.69 68.18 40.83
+D+0.750Lr+0.750L+0.450W+H, LL Comb Dsgn. L = 9.20 ft 1 0.173 0.052 3.38 -2.09 3.38 32.70 19.58 1.00 1.00 2.12 68.18 40.83 Dsgn. L = 3.67 ft 2 0.107 0.028 -2.09 2.09 32.70 19.58 1.00 1.00 1.14 68.18 40.83
+D+0.750Lr+0.750L+0.450W+H, LL Comb Dsgn. L = 9.20 ft 1 0.158 0.055 2.95 -3.10 3.10 32.70 19.58 1.00 1.00 2.23 68.18 40.83 Dsgn. L = 3.67 ft 2 0.158 0.041 -3.10 3.10 32.70 19.58 1.00 1.00 1.69 68.18 40.83
+D+0.750L+0.750S+0.450W+H, LL Comb Dsgn. L = 9.20 ft 1 0.107 0.035 1.83 -2.09 2.09 32.70 19.58 1.00 1.00 1.43 68.18 40.83 Dsgn. L = 3.67 ft 2 0.107 0.028 -2.09 2.09 32.70 19.58 1.00 1.00 1.14 68.18 40.83
+D+0.750L+0.750S+0.450W+H, LL Comb Dsgn. L = 9.20 ft 1 0.107 0.035 1.83 -2.09 2.09 32.70 19.58 1.00 1.00 1.43 68.18 40.83 Dsgn. L = 3.67 ft 2 0.107 0.028 -2.09 2.09 32.70 19.58 1.00 1.00 1.14 68.18 40.83
+D+0.750L+0.750S+0.450W+H, LL Comb Dsgn. L = 9.20 ft 1 0.107 0.035 1.83 -2.09 2.09 32.70 19.58 1.00 1.00 1.43 68.18 40.83 Dsgn. L = 3.67 ft 2 0.107 0.028 -2.09 2.09 32.70 19.58 1.00 1.00 1.14 68.18 40.83
+0.60D+0.60W+0.60H Dsgn. L = 9.20 ft 1 0.104 0.032 1.62 -2.04 2.04 32.70 19.58 1.00 1.00 1.33 68.18 40.83 Dsgn. L = 3.67 ft 2 0.104 0.027 -2.04 2.04 32.70 19.58 1.00 1.00 1.11 68.18 40.83
+D+0.70E+0.60H Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.750L+0.750S+0.5250E+H, LL Comb Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.750L+0.750S+0.5250E+H, LL Comb Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+D+0.750L+0.750S+0.5250E+H, LL Comb Dsgn. L = 9.20 ft 1 0.057 0.020 1.12 -1.01 1.12 32.70 19.58 1.00 1.00 0.80 68.18 40.83 Dsgn. L = 3.67 ft 2 0.052 0.013 -1.01 1.01 32.70 19.58 1.00 1.00 0.55 68.18 40.83
+0.60D+0.70E+H Dsgn. L = 9.20 ft 1 0.034 0.012 0.67 -0.61 0.67 32.70 19.58 1.00 1.00 0.48 68.18 40.83 Dsgn. L = 3.67 ft 2 0.031 0.008 -0.61 0.61 32.70 19.58 1.00 1.00 0.33 68.18 40.83
DESCRIPTION: PBM1
Project File: EC.ec6
Project Title:…