This document contains a price schedule template for a federal contract solicitation to construct a new entrance station at a national park to reduce traffic and provide a safer work environment. The National Park Service Denver Service Center solicitation requests pricing for constructing the new entrance station, including site work and utilities, four kiosks, shade canopies, a power generation and storage system, and telecommunications and security infrastructure as base line items. It also contains optional line items for empty conduit and pull boxes for future fiber, a bypass lane extension, and accessible parking at an existing comfort station. Offerors are required to submit pricing for both the base line items and all option line items. The template provides space for offerors to include the quantity, unit of measure, unit price, and total price for each contract line item.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule Template

Contract Price Schedule Template
National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18
Solicitation Number:140P8523R0001
PARK - PMIS:JOTR 250023
(Project Management Information System)
Developed Area:West Entrance
Project Title:Construct New Entrance Station to Reduce Traffic and Provide a Safer Working Enviornment
Notice: Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQuantityUnit of MeasureUnit PriceTotal Price
0010Construct New Entrance Station
0010AASite Work and Utilities1LS$0.00
0010ABSupport Building1LS$0.00
0010ACMain Kiosk1LS$0.00
0010ADKiosk 21LS$0.00
0010AEKiosk 31LS$0.00
0010AFKiosk 41LS$0.00
0010AGShade Canopy West1LS$0.00
0010AHShade Canopy East1LS$0.00
0010AIPower Generation & Storage System1LS$0.00
0010AJTelecommunication & Security Systems Infrastructure1LS$0.00
TOTAL BASE PRICE (Contract Line Item Number 0010; subline 0010AA through 0010AJ) ---------------------------------------------------------------------------------$0.00
0020Empty Conduit and Pull Boxes for Future Fiber1LS$0.00
0030Bypass Lane - West Extension1LS$0.00
0040Accessible Parking at Existing Comfort Station1LS$0.00
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 0020 through 0040) -----------------------------------------------------------$0.00
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 0010 through 0040) --------------------------$0.00
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.