Attachment L - BCF Schedule.pdf

PDF 172 KB Posted

Attached to
Beverly Cleary Fernwood Seismic Rehabilitation
Solicitation number
148045
Issued by
Multnomah County, Oregon

About this file

This is a project schedule attachment (Attachment L - BCF Schedule) for the Beverly Cleary Fernwood Seismic Rehabilitation project in Oregon. The schedule outlines a comprehensive construction and procurement timeline spanning from June 2026 through March 2029. Key milestones include the identification and design of a swing site from June through January 2027, with construction at the swing site running from January through June 2027. The construction procurement phase includes an RFP issued on November 5, 2026, with a bid walk scheduled for November 17, 2026, an addendum deadline of December 4, 2026, and RFP submissions due December 17, 2026. Bid reviews are scheduled for December 18, 2026 through January 15, 2027, with potential interviews occurring January 12-15, 2027. Board approval is anticipated for February 16, 2027, with a Notice to Proceed (NTP) issued February 17-18, 2027. The main construction phase is scheduled to commence April 20, 2027 and continue through March 2, 2029, with mobilization, active construction, demobilization, and closeout activities spanning this period.

The schedule reflects a phased approach to project delivery, with swing site activities occurring concurrently with the main construction procurement and execution. The pre-construction meeting is scheduled for April 20, 2027, followed by mobilization on June 12, 2027, with the primary construction work running from June 14, 2027 through August 4, 2028. Demobilization is allocated for August 7-18, 2028, with project closeout and final completion activities extending from August 21, 2028 through March 2, 2029. This extended schedule reflects the complexity of the seismic rehabilitation work and the coordination required between swing site operations and primary construction activities.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Duration Start Finish

1 Swing Site Activities BY PPS 580 days Mon 6/1/26 Fri 8/18/28

2 Identify Swing Site 5 mons Mon 6/1/26 Fri 10/16/26

3 design at Swing Site 3 mons Mon 10/19/26 Fri 1/8/27

4 Construction at Swing Site 6 mons Mon 1/11/27 Fri 6/25/27

5 Move to Swing Site 2 wks Mon 6/14/27 Fri 6/25/27

6 Return Swing to Bev Cleary 2 wks Mon 8/7/28 Fri 8/18/28

7 Construction Procurement

BY PPS

76 days Thu 11/5/26 Thu 2/18/27

8 RFP Issued 6.2 wks Thu 11/5/26 Thu 12/17/26

9 Bid Walk 1 day Tue 11/17/26 Tue 11/17/26

10 Addendum Deadline 1 day Fri 12/4/26 Fri 12/4/26

11 RFP Due 1 day Thu 12/17/26 Thu 12/17/26

12 Bid Reviews 21 days Fri 12/18/26 Fri 1/15/27

13 Interviews (if necessary) 4 days Tue 1/12/27 Fri 1/15/27

14 Board Deadline 1 day Tue 1/26/27 Tue 1/26/27

15 Pre Contract Meeting- date tbd4 days Tue 2/2/27 Fri 2/5/27

16 Board Approval 1 day Tue 2/16/27 Tue 2/16/27

17 Anticipated NTP Issued 2 days Wed 2/17/27 Thu 2/18/27

18 Construction 489 days Tue 4/20/27 Fri 3/2/29

19 pre-construction meeting 1 day Tue 4/20/27 Tue 4/20/27

20 mobilization 1 day Sat 6/12/27 Sat 6/12/27

21 construction 300 days Mon 6/14/27 Fri 8/4/28

22 demobilization 2 wks Mon 8/7/28 Fri 8/18/28

23 Closeout 5 mons Mon 8/21/28 Fri 1/5/29

24 Final Completion 2 mons Mon 1/8/29 Fri 3/2/29

2629 1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 2 5 8 111417202326 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 121518212427 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 1013161922252831 3 6 9 121518212427 2 5 8

June 2026 July 2026 August 2026 September 2026 October 2026 November 2026 December 2026 January 2027 February 2027 March 2027 April 2027 May 2027 June 2027 July 2027 August 2027 September 2027 October 2027 November 2027 December 2027 January 2028 February 2028 March 2028 April 2028 May 2028 June 2028 July 2028 August 2028 September 2028 October 2028 November 2028 December 2028 January 2029 February 2029 March 2029

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress

Project: Beverly Cleary Seismic

Date: Tue 10/20/26

Attachment L