06/21/2021 FAA-CAE-20-10a

SCOPE OF WORK

FOR THE

REFURBISHMENT OF FOUR RESTROOMS

AT THE

ATCT FACILITY

MYRTLE BEACH, SOUTH CAROLINA

1. GENERAL.

1.1. These specifications cover the requirements of the Federal Aviation Administration for the refurbishment of four restrooms, located in the FAA ATCT facility at the Myrtle Beach International Airport, Myrtle Beach, SC.

1.2. The requirements of these specifications are intended to be in conformity with all current building and ADA codes. If they are found to be in conflict, the contractor shall notify the pertinent FAA official prior to continuing. The contractor shall also adhere to all Federal, state, and local labor and safety statutes that may apply.

1.3. ACRONYMS AND ABBREVIATIONS.

ADA – Americans with Disabilities Act AF - Airway Facilities AT – Air Traffic ATCT – Air Traffic Control Tower CFM - Contractor Furnished Material CO - Contracting Officer COR - Contracting Officer's Representative DO – District Office FAA - Federal Aviation Administration GFM - Government Furnished Material LF – Linear feet MAX - Maximum MIN – Minimum MYR – Identifier for Myrtle Beach, SC NTP - Notice To Proceed SSC - System Support Center (local FAA) SF – Square feet SY – Square yards

2. CONDITIONS AFFECTING WORK.

2.1. SCOPE OF WORK. The scope of work shall include, but is not limited to, furnishing all labor, materials, tools, equipment, and services as necessary to refurbish the four existing restrooms (two in the base building, men’s and women’s, and two in the ATCT shaft, non-gender) in accordance with this Scope Of Work, the project drawings and in compliance with governing documents (e.g., ADA). The scope of work for the restroom refurbishment is as follows:

TEMPORARY FACILITIES:

a) Installation of temporary restroom facilities for the duration of the project. The restrooms shall be the mobile/trailer type with minimum three separate toilets, set up adjacent to the facility, with running water, power and holding tanks. Utilities shall be set up by contractor.

BASE BUILDING-Women’s:

b) Remove the fixed wall stall, door frame and door. Repair adjacent drywall to match existing.

c) Remove existing floor tile and cove base and install new tile and cove base. Color and pattern to be determined by local FAA. Floor drain cover to be replaced as well.

d) Remove the existing floor toilet, and install new, similar toilet.

e) Install new stall, per the new layout on the drawings.

Stall installation shall include grab bars and paper dispenser.

e) Remove and replace the existing sink fixture; color and style to be determined by local FAA. Sink shall remain.

f) Repair any wall holes and repaint walls with two coats interior satin paint. Color determined by local FAA.

BASE BUILDING-Men’s:

g) Remove of the fixed wall stall, door frame and door.

Repair adjacent drywall to match existing.

h) Remove existing floor toilet. Sawcut concrete floor, install drain pipe and connect to existing toilet drain, and cover with new, smoothed concrete, so as to accommodate new toilet location.

i) Remove existing floor tile and cove base and install new tile and cove base. Color and pattern to be determined by local FAA. Floor drain cover to be replaced as well.

j) Install new floor toilet, in new location per the drawings. Toilet installation will require extending the water supply piping, and subsequent possible drywall repair.

k) Remove existing urinal and repair drywall, so as to accommodate sink.

l) Relocate existing sink, mirror and paper dispenser to new location. Sink relocation entails repiping cold and hot water supplies and reconnecting drain. Repair drywall from old sink location. Replace existing sink fixture; color and style to be determined by local FAA.

m) Install two new urinals and partition as shown on the drawings. This will include extending water supply and drain piping to accommodate both urinals.

n) Install new stall, per the new layout on the drawings.

Stall installation shall include grab bars and paper dispenser.

o) Repair any wall holes and repaint walls with two coats interior satin paint. Color determined by local FAA.

ATCT shaft-3rd floor:

p) Removing the existing floor toilets and install new similar toilet.

q) Removing the existing sink, and install new similar sink with new fixtures. Style and color of fixtures to be determined by local FAA.

r) Repair any wall holes and repaint walls with two coats interior satin paint. Color determined by local FAA.

ATCT shaft-7th floor:

s) Repeat steps p) q) and r).

Other misc refurbishments:

t) Replacement of roof-mounted exhaust fan, with new fan, of similar size and horsepower. Fan shall wired to match existing configuration, and fan duct and duct grill cleaning is required.

Reattach existing grounding.

u) Repaint TRACON door exterior, two coats, and install new stainless steel pushplate, above door handle.

v) Trash receptacles, feminine dispenser and overhead lighting shall remain in place.

w) Some work in the restrooms, including water shutoffs, may require nighttime and/or weekend work, so as to minimize impact to FAA employees. This will be clarified and coordinated during contractor pre-bid site visit.

2.2. SCHEDULING OF WORK. The scope of work under this contract requires working on operational FAA facilities. The contractor, therefore, will be required to coordinate his activities with the COR who will be identified at the preconstruction conference. The COR or his designated representative shall escort the contractor, and shall remain on site whenever the contractor is onsite. All work, including daily cleanup, shall be performed between the hours of 8:00 AM to 5:00 PM, Monday through Friday, unless otherwise coordinated with the local FAA.

2.3. EXISTING CONDITIONS.

2.3.1. ASBESTOS. No asbestos will be impacted during this

contract.

2.3.2. LEAD. No lead will be impacted during this contract.

2.3.3. RESTROOMS. Restroom facilities will be available at the site.

2.3.4. WATER. Limited water can be made available on a

coordinated basis. Coordinate this need at the preconstruction conference.

2.3.5. ELECTRICITY. Power may be made available to the

contractor at the site on a day by day basis. Coordinate this need at the preconstruction conference.

2.3.6. DUMPSTER. There are no available dumpster or disposal

facilities onsite.

2.4. SITE VISIT. The bidder is expected to carefully examine the site and all areas of proposed work to see firsthand the extent of work involved. The submission of a proposal will be considered prima facie evidence that the bidder has made such an examination and is satisfied as to the conditions to be encountered in performing the work. It shall be the responsibility of the bidder to make his own interpretations of existing site conditions as the drawings and specifications may not reflect all site characteristics. To schedule a site visit, contact Greg Clemmons, FAA MYR SSC Manager, at (904)537-3855.

2.5. WORK LOCATION. The contractor will be responsible for

obtaining all required insurance, bonding, badges, etc. as required by the CO.

2.6. WORK ACCESS. Access to the site requires passing through a security gate and secured doors. Therefore, the local FAA will escort the contractor to and from the site on a daily basis, unless alternate arrangements are agreed upon at the preconstruction conference. The contractor shall coordinate his schedule to the local FAA in order to secure a daily escort.

2.7. WORKERS. Due to security regulations, no foreign national workers will be allowed on the job site without 30 day notification and approval. Contact the SSC Manager for further information.

2.8. DEMOLITION. Any equipment or material to be removed, unless specified to remain the property of the FAA, shall become the property of the contractor and shall be transported from the site and disposed of in a legal manner. Demolition and removal work shall be performed in compliance with safety procedures, applicable requirements of the State and local regulations, and with Federal and FAA requirements.

2.9. SAFETY STANDARDS. Contractors shall comply with all

applicable federal, state, and local requirements for protecting the safety of the contractors’ employees, building occupants, and the environment. In particular, all applicable standards of the Occupational Safety and Health Administration (OSHA) shall be followed when working in accordance with this specification.

2.10. WORKING CONDITIONS. Construction/demolition shall in no way interfere with Air Traffic Control Operations. Extreme care shall be exercised so as not to cause any interference or interruption of service from this facility. It is absolutely mandatory that the contractor protects FAA personnel, communication, electrical and mechanical equipment both inside and outside the building from damage caused by work impact, water, debris or dust. The contractor shall have the overall responsibility for the performance and enforcement of all forms of protection within the premises against any damages due to work performed under this contract. Any damages incurred, as a result of construction activity during the performance of this contract will be repaired/replaced immediately by the contractor at no cost to the FAA.

3. MATERIALS. All material shall adhere to the guidelines and specifications set forth in the latest editions of the UL, ADA and ASTM publications. General material requirements are as follows:

3.1. FLOOR TILE. Ceramic, minimum 12” x 12”, waterproof, smooth glazed finish, with manufacturer’s recommended thin set adhesive and grout, with matching tile covebase (base building only).

Color and style of both to be determined by local FAA.

3.2. FLOOR DRAIN COVER. Round, brass, with matching diameter and bolt pattern to existing (base building only).

3.3. TOILET.

3.3.1. BASE BUILDING. Floor-mount, elongated bowl with seat, bottom outlet, manual lever flush with chrome finish, 1.28GPF, ADA Height, Zurn EcoVantage Z5665-BWL1 or equal (2 req’d). Minor piping work may be necessary.

3.3.2. 3RD & 7TH FLOOR. Two piece, floor-mount with tank, elongated bowl with seat, bottom outlet, 1.28GPF, Zurn EcoVantage Z5535-K or equal (2 req’d). To include new supply flex pipe.

3.4. URINAL. Wall-mounted, 26” high x 18” wide (+/-), manual

level flush with chrome finish, 1.0GPF, Zurn Omni-Flo or equal (2 req’d, base building men’s only). Urinal relocation will require supply and drain plumbing work.

3.5. STALL. Brushed stainless steel, wall & floor mounted, 12” above floor, configured per the drawings (base building only).

Stall shall include grab bars (installed per ADA), paper dispenser similar to existing, with coat hook and auto-close hinge. Urinal partition shall match stalls.

3.6. SINK. Wall-hung, vitreous white china lavatory, 4” faucet holes, Zurn Z5350 Series, or equal (2 req’d, 3rd & 7th floor only). Fixture (4” spacing) to be included; local FAA will determine fixture type.

3.7. PAINT. Interior acrylic latex, satin finish, color to be selected by local FAA, two coats. Sherwin-Williams “Emerald”, or approved equal. MSDS submittal required.

3.8. EXHAUST FAN. Exterior, roof-mounted, 115V, direct drive, 1/20HP, similar to existing (Greenheck GB-80-4-X).

3.9. PUSH PLATE. For TRACON door, 8” x 16”, stainless steel with mounting screws, as manufactured by Everbilt, or equal.

4. CLEANUP.

4.1. Before final inspection, the contractor shall thoroughly clean within the construction limits and the surrounding areas affected by this work, including the following:

a. All construction facilities, debris, and rubbish shall be removed from the buildings and the site on a daily basis.

b. All tools, scaffolding, temporary utility connections, building, etc., belonging to the contractor or used under his direction shall be removed from the site.

4.2. All grounds, walkways, and other areas adjacent to the work shall be restored to the original condition before the contractor is released.

5. INSPECTIONS. The contractor shall allow the COR, or other persons designated by the CO, complete access to all portions of the work. The COR shall coordinate and schedule a final inspection date. All work shall be accepted when all work required by this contract, including punch list items, is finished and has passed inspection.

6. PHOTOS.

Women’s restroom: Remove wall stall and install new s.s. stall, replace floor tile and drain cover, Replace toilet, repaint walls.

Women’s restroom: Repalce sink fixture and repaint walls. Trash receptacle and paper dispense to remain.

Men’s restroom: Remove wall stall and install new s.s. stall, replace floor tile and drain cover, Replace toilet, repaint walls.

Men’s restroom: replace toilet, grab bars, floor tile and repaint walls.

Men’s restroom: Remove urinal and relocate sink in it’s spot. Trash receptacle to remain. Repaint walls and replace floor tile.

Men’s restroom: Relocate sink and paper dispenser, remove wall stall, install new urinals on this wall, replace floor tile and repaint walls.

3rd & 7th floor restrooms (virtually identical): replace toilet, sink and sink fixture, repaint walls

Roof-mounted exhaust fan, to be replaced

TRACON door, to be repainted and new push plate installed (above door handle, atop worn area)