Attachment J-5 - 8 Color Press Chiller Specs.pdf
PDF 976 KB Posted
- Attached to
- Canon ProStream Press Installation Design Build
- Solicitation number
- 040ADV-26-R-0029
- Issued by
-
Government Publishing Office
About this file
This document is a technical specification and installation guide for a Dry Cooler DCA-V 179/35(40)/L fluid cooling system designed for the US Government Printing Office (US GPO).
Equipment Specifications and Scope: The dry cooler has a capacity of 179 kW with a glycol outlet temperature of 40°C and glycol concentration of 35(45)%. Key technical parameters include an air flow rate of 100,600 m³/h, speed of 750 rpm, five fans, noise level of 58 dB(A), dry weight of 1,253 kg (2,762 lbs), and operating weight of 3,119 lbs. The unit measures approximately 1,720 mm in height and 6,700 mm in overall length. Electrical connection requires 460V/3Ph/60Hz via pump station. The fluid cooler includes four lapped flanges (DN 65/64.5 PN 10) with brazing neck connections per DIN 2642, and connections for fresh water inlet, thermal contacts, and fan power. Accessories include epoxy-coated fins and spraying systems for adiabatic function.
Installation Responsibilities: Technotrans is responsible for providing piping (60 linear feet one way/120 feet total) between the fluid cooler and pump station, piping to water-cooled peripherals, system checkout and startup, and operator training. The US GPO must provide equipment lift and placement, unit securing, aerial or scissor lift access, ladders, electrical outlets, house air supply, all required penetrations and resealing, building transport, safe working environment, roof access with ceiling tile management, clear access around the unit year-round, secure storage for materials, adequate installation time during normal hours, and packing material removal. The mezzanine structure must be sound and level to support the unit's weight under normal operating conditions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Install DCA-V179 (W-C) 10/12/23
Service Department
Install Conditions: US GPO
Water Cooling System: DCA-V 179 Fluid Cooler technotrans america Inc.
1441 E. Business Center Drive
Mount Prospect, IL 60056 to be provided by technotrans:
o Piping to/from fluid cooler to technotrans pump station (60 linear feet one way - 120 ft. total) o Piping to/from pump station to water cooled peripherals o System checkout and start-up o Training on the operation and maintenance of the water cooling system and major components technotrans Fluid Cooler installation recommendations:
One penetration for all piping connections One penetration for all electrical connections Unit shall be level, for proper operation Mezzanine shall be structurally sound to accept the overall weight, of the unit, under normal operating conditions Fluid penetrations to be made within a 4 foot radius of the fluid end, 24 inches from unit, either side of center
WARNING: Penetrations should not be made over actual press area.
NOTE: Recommendations shall be superseded by any local codes/ordinances.
technotrans DCA-V 179 Fluid Cooler penetration requirements:
Two openings to accommodate 3" (3 1/8" OD) copper pipes (fluid ends - in/out) One opening to accommodate a 3/4" (7/8" OD) copper pipe (fresh water in) One opening to accommodate a small conduit to run 4 x 2-wire (24VDC) for the fan thermal contacts One opening to accommodate a large conduit to run 4 x 3-phase + 1 ground for fan power
NOTE: Electrical contractor shall determine actual conduit size based on local codes/ordinances.
NOTE: Requirements and recommendations are to be completed/supplied by the end user and do not fall under technotrans' scope of supply
Install DCA-V179 (W-C) 10/12/23 to be provided by US Government Printing Office:
Lift/placement of fluid cooler Securing fluid cooler once in position Aerial or scissor lift, based on actual install space limits and/or height restraints Ladder(s) for a working height of up to (10) ten feet 120VAC outlet(s) for tool use House air for glycol fill pump Any/all penetrations and the resealing of said penetrations Transport into the building and setting down of equipment and/or materials Safe working environment, for any/all personnel, for the duration of the installation Clear/safe access to roof (inside) for pipe install, including removal/reinstall of any/all ceiling tiles Clear/safe access all around fluid cooler, along with a clear/safe path during winter months Secure area to store tools, materials, and equipment, within close proximity of installation Allowing adequate time, during normal working hours, to accomplish the installation Removal and discard of any/all packing/crating materials Access to Wi-Fi network america, inc.
PR
EL
IM
IN
AR
Y
RE
VI
SE
D
10/ /23
RA106X-8+L ALV3
RE
VI
SE
D
10/ /23
RA106X-8+L ALV3
Technotrans AG
400-0000660602
1:25
FV1051466
DCA-V 179/35(40)/L
lgortva
16.05.2017 ogergely
Artikel Nr. 10069795
11.05.2017
W-Block Rückkühler
101049026
Baan-No.
DIN A3paper size material weight [kg] scale type name notice drawing number customer project/ quantity order/ postion namedate namedate drawn:
certified:
index revision
DRY 2762 LBS. / WET 3119 LBS.