Canon ProStream Press Installation Design Build
Solicitation number
040ADV-26-R-0029
Issued by

About this file

This is a Request for Proposal (RFP) for a design-build contract to support the installation of a Canon ProStream 2133 printing press at the Government Publishing Office (GPO) headquarters in Washington, DC.

The Government Publishing Office seeks a single firm to perform architectural and engineering design services combined with construction services to make Building C, 4th Floor compatible with the new printing press installation. The contractor must provide all labor, materials, equipment, and supervision for this firm fixed-price contract. Key deliverables include a detailed site assessment, design documents at 20%, 65%, 95%, and 100% completion milestones, construction phase work, and post-construction quality validation. The contractor is responsible for designing and installing supporting utilities, rigging and hoisting the air-cooled process chiller (Technotrans Xtend 2800), designing and installing exhaust and piping systems, designing electrical power distribution, and supporting Original Equipment Manufacturer (OEM) startup. All work must be completed within 180 days of Notice to Proceed, with design phases scheduled between days 0-142 and construction/closeout between days 163-180. Performance bonds are required. The contractor must attend mandatory site visits on July 22, 2026, and proposals are due by August 25, 2026, at 5:00 PM EST.

Evaluation will be based on technical approach and management plan, design management approach, key personnel qualifications, past performance, and cost/price reasonableness. The Government will award to the responsible offeror whose proposal represents best value. Two key personnel positions (Project Manager with 10 years' experience and PMP certification; Superintendent/Quality Control Lead with 5 years' experience and OSHA-30/CQM-C certifications) must be designated. Offerors must submit minimum three and maximum five past performance questionnaires from customer references. The contract is subject to Materials Management Acquisition Regulations (MMAR) and includes clauses for differing site conditions, warranties, construction wage requirements, and disputes resolution through the GAO Contract Appeals Board.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

040ADV-26-R-0029

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED

July 9, 2026

PAGE OF PAGES

1 56

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE GPO 8. ADDRESS OFFER TO

GPO

732 North Capitol St NW Washington, DC, 20401, US

9. FOR

INFORMATION CALL:

a. NAME

STEVENS, GARY L

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

Canon ProStream Press Installation Design Build

11. The contractor shall begin performance within 7 calendar days and complete it within 180 calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See ).

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

YES NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by 17:0 (hour) local time 08/25/2026

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than 120 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

AMOUNTS

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

See Schedule

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES

CODE AT

10 U.S.C. 3204(a) (

27. PAYMENT WILL BE MADE BY

) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY

TABLE OF CONTENTS:

1. Section B - Supplies or Services and Prices/Costs

2. Section C - Description/Specifications/Work Statement

3. Section D - Packaging and Marking

4. Section E - Inspection and Acceptance Terms

5. Section F - Delivery or Performance

6. Section G - Contract Administration Data

7. Section H - Special Contract Requirements

8. Section I - Contract Clauses

9. Section J - List of Documents, Exhibits, and other Attachments

10. Section K - Representations, Certifications, and Other Statements of Offerors

11. Section L - Instructions, Conditions and Notices to Offerors

12. Section M - Evaluation Factors for Award

Section B: Supplies or Services and Price/Cost

B.1 CONTRACT TYPE

The Government Publishing Office intends to issue a firm fixed price contract the Canon ProStream

Printing Press Installation Design-Build Project.

The successful offeror will provide all labor, material, equipment and supervision to meet this requirement.

Period of Performance: Al l work shall be completed and delivered within 180 days from Notice to

Proceed.

Price Breakdown – The price breakdown shall justify the contractor’s firm fixed price proposal.

Item Number Base Item Number

Supplies/Services Quantity Unit

0001 Canon ProStream Site Assessment

- Design and Design Documents

1 Lt

Contract Type :Firm Fixed Price Unit Price

Extended Price

Description:

Purchase Requisitions

IDC Type: Not Applicable

Supplies/Services Quantity Unit

0002 Construction Phase 1 Lt

Contract Type: Firm Fixed Price

Supplies/Services Quantity Unit

0003 Post Construction Quality Validation and Closeout

1 Lt

Contract Type: Firm Fixed Price

Section C: Description/Specifications/Work Statement

Statement of Work

Design-Build

Building C, 4th Floor Canon ProStream Press Installation Support

Table of Contents

I. Overview

II. Background and Facility

A. Existing Site Conditions

B. Pre-Bid Walkthrough

C. Government Furnished Information

III. Project

A. Tasks

B. General Contractor Requirements

IV. Design Period

A. Design Requirements

B. Submission Requirements

C. QA/QC

D. Code Compliance

V. Construction Period

A. General Requirements

B. Fire & Safety

C. Site Protection

D. Cleanup & Restoration

E. Government Furnishings

F. GPO Regulations

VI. Period of Performance

VII. Privacy Statement

VIII. Post Construction Quality Validation & Contract Closeout

IX. Technical Evaluation Criteria

I. Overview

The Government Integrated Printing Services (GIPS) requires a design-build project to support the installation of a new printing press at the Government Publishing Office (GPO) main campus in

Washington, DC. The installation site is on the fourth (4th) floor of Building C.

The contractor will perform A/E design services and construction services to make the building compatible with the recently acquired Canon ProStream 2133 Printing Press. The Press consists of two main components: (1) the press itself, which will be placed on the production floor, and (2) a cooling unit, which will be placed at a location to be determined (TBD) by the contractor.

The government will furnish both pieces of equipment. Canon will rig and assemble the press. The

Contractor shall provide all supporting utilities for the press and shall rig, hoist, place, anchor and connect the air-cooled process chiller at the designated installation location.

This project shall be delivered turnkey. The contractor assumes full responsibility for validating existing site conditions, coordinating with the equipment manufacturers, ensuring code compliance, and achieving successful Original Equipment Manufacturer (OEM) startup without infrastructure related deficiencies.

II. Background and Facility

A. Existing Site Conditions

1. GPO is located at 732 N. Capitol Street Washington, DC 20401.

2. The printing press being installed is manufactured by Canon;its trade name is the “ProStream 2000

Series”. Colloquially, it will be known as the Canon ProStream Press. Refer to Attachment #1 for more information on this press.

3. The Press will replace Asset #6906 on the provided drawings, which is between column rows 16 and

13 and column rows A and B. Refer to Attachment #2 for more information.

4. There is currently no equipment, stored materials, or any other obstructions occupying the space where the Canon Press will be installed. GPO will prevent any obstructions throughout the period of performance.

5. The press floor is constructed from concrete poured over the structural slab. Please refer to

Attachment #3 for detailed information on the GPO structure. A partial set is provided but a full set can be distributed later.

6. The cooler for the press is manufactured by Technotrans. Its trade name is the “Xtend 2800”.

Colloquially it will be known as the ‘Press Cooler.’ Refer to Attachment #4 for more information on this chiller

7. One proposed location for the Xtend 2800 is the existing mezzanine for Bridge 33. Bridge 33 connects Building B to Building C. The roof of bridge 33 is currently houses a chiller for another printing press.

(i) Refer to Attachment #2 for the location of the existing chiller and bridge.

(ii) Refer to Attachment #3 for structural information on this bridge.

(iii) Refer to Attachment #5 for information on the existing chiller.

8. A structural analysis was conducted on BLDG C and BR 33 roof for suitability to host the Canon

ProStream and the Xtend 2800, respectively. This report is for reference only. The contractor is responsible for field verifying all site conditions. Refer to Attachment #6 for this report.

9. The contractor is responsible for any further evaluations of the repairs, renovations, retentions, and additions and subsequently finalized by the COR.

B. Government Furnished Information

1. Pictures taken by the Contractor are only permitted of the spaces and equipment directly associated with the project.

2. Upon request from the Contractor, GPO will provide record drawings and/or as-built documentation if available and as reasonably obtainable. The Government’s efforts to locate and furnish such documentation shall not be construed as a guarantee of delivery within any specific timeframe. The availability, completeness, and accuracy of record drawings/as-built documentation is not guaranteed. These documents are provided for information only and shall not be considered definitive ‘as-built’ drawings. The Contractor shall not rely on record documentation as an accurate representation of existing conditions and shall independently verify all existing conditions, dimensions, and requirements necessary to perform the Work. Any discrepancies between record documentation and actual field conditions, or delays in the Government’s retrieval or transmittal of record documentation, shall not constitute a basis for additional compensation or schedule relief to the Contractor.

III. Project

A. Tasks

Unless otherwise noted, all tasks described below are to be included in the Base Contract. Optional

Tasks are to be executed at the discretion of the government.

1. Site Survey

Prior to design development, the Contractor shall perform a detailed site survey and field verification. The survey shall include, at a minimum:

(i) Structural Assessment

(a) Verification of the fourth-floor slab supporting the press.

(b) Verification of mezzanine framing capacity supporting the chiller.

(ii) Electrical Assessment

(iii) HVAC and Environmental Assessment

(iv) Process Cooling Assessment

(a) Evaluation of chiller placement location, airflow clearance, ambient conditions, and routing for supply and return piping.

(v) Compressed Air Assessment

(vi) Rigging and Access Assessment

(vii) Life Safety and Code Review

The Contractor shall document site survey findings and incorporate them into the Basis of Design.

2. Demolition

(i) The Contractor will construct and present a demolition plan prior to mobilization. The Demolition plan must include the following provisions:

(a) Proof of valid bond and insurance

(b) Proof of Escorting Capability

(c) Health and Safety Plan

(d) Site Mobilization Plan

3. Architectural/ Structural

(i) The contractor shall assess the Canon Press installation site for structural feasibility. Contractor will consider all possible factors such as weight, pressure, and vibrations from operation.

(ii) The contractor shall structurally and architecturally assess the GPO facility for a location to house the Xtend 2800. The primary candidate for this is Bridge the roof of 33.

(iii) If the existing structure fails the structural and/or architectural assessment, the contractor shall evaluate what modifications to the structure must be made for compatibility with the Xtend

2800.

4. Mechanical

(i) The contractor shall design an exhaust system for the press.

(ii) CONTRACT OPTION: The Contractor shall install an exhaust system for the press and procure labor/materials as necessary to complete this task.

(iii) The contractor shall design piping system from the Xtend 2800 to the Canon ProStream press that can provide the appropriate flow rate for the equipment.

(a) The piping system shall also contain sufficient insulation to deliver coolant at the desired temperature.

(iv) CONTRACT OPTION: The Contractor shall install a piping system for the press and procure materials as necessary to complete this task.

(a) The government will furnish up to 700 linear feet of 3" (3 1/8" OD) Copper Pipes. Additional materials shall be procured by the contractor.

(b) The piping system shall be pressure tested, flushed, and labeled.

(c) The contractor is responsible for the total run-length of minus 120 feet. Run length includes supply and return lines.

5. Electrical

(i) The Contractor shall design a power distribution system for the Canon ProStream Press that satisfies the machine’s electrical requirements while maintaining compatibility with the building’s electrical grid. The contractor shall do the same for the Press Chiller at its installation location.

(ii) CONTRACT OPTION: The Contractor shall install a power distribution system for the Canon

ProStream Press and Xtend 2800. The contractor shall procure materials as necessary to complete this task.

6. Miscellaneous

(i) The contractor shall provide craning and rigging of the Xtend 2800. The Contractor shall also secure the Xtend 2800 to its installation location. The installation location will be determined in the A/E design.

(ii) The contractor will consult with the press manufacturer and review any documentation to incorporate all specifications into the designs.

(iii) The Contractor shall support OEM startup.

(iv) Prior to execution of a design, the contractor will provide GPO with a rough order of magnitude

(ROM) cost estimate for all Xtend location options. GPO will deliberate and decide on which option to execute before administering a NTP for the 65% drawings

(v) The Contractor will provide GPO with an itemized cost estimate at the 95% submission milestone.

B. General Contractor Requirements

1. The Contractor will perform all work and provide all the labor, materials, and equipment needed to meet the objectives of the statement of work (SOW). The Government will not furnish any labor or equipment.

2. The Government is not responsible for costs incurred due to mismanagement of labor or lack of proper equipment.

3. The Contractor shall provide a certified Construction/Project Manager as outlined in the specifications to oversee and provide quality control during the construction period.

4. Project management, at minimum, must include:

(i) Capturing and sharing minutes for regular Owner-Architect-Contractor (OAC) meetings, milestone meetings, and other project critical gatherings.

(ii) Providing regular schedule updates. Frequency to be discussed with COR

(iii) Timely SharePoint set-up & maintenance for proper RFI and submittal tracking

5. Personnel assigned to perform services under this scope shall always be under the direction and control of the Contractor. The Contractor shall monitor the performance of its employees to ensure all aspects of this scope are properly fulfilled.

6. If the Contractor finds clarification necessary with respect to the scope of the services to be performed hereunder, he/she shall request, in writing, such clarification from the CO or COR.

7. The Contractor shall provide a minimum notice of 72 hours to the COR for any work that is required to be done by others so the COR can schedule the work in advance.

IV. Design Period

A. Design Requirements

1. The Contractor must develop plans from field verification on-site and supplementary drawings. The

Contractor bears full responsibility in the verification of existing conditions affecting design.

Verification may include inspections, discussions with GPO personnel, or testing.

2. The Contractor must not incorporate elements into the design that would require changes to be made to the Canon ProStream Press or the Xtend 2800. The machines are already manufactured, and changes are considered impossible.

3. The Contractor must consider adjacent systems and components (architectural as well as utility systems) to avoid construction change orders due to unforeseen site conditions.

4. The Contractor must attend four (4) interim review project meetings at 20%, 65%, 95% and 100% milestone deliverables with COR and designated GPO staff. The Contractor will record and provide meeting minutes within 35 hours to all attendees for review, comment, and concurrence. Incorporate appropriate comments, finalize the meeting minutes, and submit the final meeting minutes within one week of meetings. Minimum requirements for each design submission are listed below:

(i) 20% - Conceptual Design

(a) Finalized Site Survey Report

(b) Proposed course of action

(i) Design Narratives per discipline

(ii) 65% - Basis of Design

(a) Outline Specifications.

(b) Drawing Set (Overall)

(i) Codes, standards, and AHJ standards identified

(ii) Relevant Machine Requirements Identified

(iii)Consistency with design narratives

(iv) Site-conditions verified.

(c) Architectural Drawings

(i) Floor plans drafted

(ii) Major architectural features drafted.

(iii)Hardware selected and placed

(d) MEP Drawings

(i) Major equipment schedules drafted

(ii) Relevant Site conditions identified

(e) Structural Drawings

(i) Wall/Floor penetrations identified

(ii) Major Structural elements drafted.

(iii)Preliminary calculations

(iii) 95% - Fully Realized Basis of Design

(a) Finalized Specifications

(b) Commissioning Requirements (if applicable)

(c) Itemized Cost Estimate

(d) Drawing Set (Overall)

(i) Finalized Drawings and details

(ii) Codes, standards, and AHJ standards finalized and compliance confirmed.

(iii)Approved Machine Requirements

(iv) Consistency with Specifications

(v) All comments addressed.

(e) Architectural Drawings

(i) Fully dimensioned floor plans

(ii) Architectural assemblies finalized

(iii)Sections and Details complete

(iv) Hardware finalized with schedules

(f) MEP Drawings

(i) All equipment schedules finalized

(ii) Complete One-line Diagrams

(iii)Fully dimensioned systems

(g) Structural Drawings

(i) All penetrations coordinated and approved

(ii) Finalized Structure with loads fully incorporated

(iii)Finalized calculations

(h) Rigging and hoisting plan for chiller placement.

(i) Submittal Register

(iv) 100% - Complete Construction Documents

(a) Drawings stamped and sealed by professional engineers licensed in the project jurisdiction.

5. The Contractor must provide design period services to include drawings, and specifications reflecting specific tasks identified herein, in addition to on-site meetings with professional and administrative staff, site investigative work, and review of supplementary documents.

6. The Contractor is responsible for professional quality and technical accuracy in providing GPO with documents. All designs shall comply with GPO Design Standards, NEC, NFPA, IBC, IMC, ASHRAE standards, and OSHA requirements.

7. The Contractor must provide competent design period services with staff and consultants adequately knowledgeable in:

(i) manufacturing space design and construction

(ii) the various subordinate design disciplines including but not limited to mechanical, electrical, plumbing, structural, fire protection, life safety

(iii) other building/utility systems as required.

8. The DB Team must verify necessary building architectural and utility system components to ensure environmental conditions remain within manufacturer tolerances. This includes, but is not limited to items such as:

(i) Existing conditions verification – upgrades to meet current codes.

(ii) Equipment Compatibility – Floor Levelness, MEP requirements, proper clearances, etc.

(iii) Adjacent Machinery – Static and dynamic load impact. Air Flow competition.

(iv) Electrical- Capacity on existing panels and substations to provide power

(v) Structural conflicts – Floor/wall penetrations, etc.

9. GPO design period services to include Design Development, Construction Documents, and Quality

Assurance/Quality Control (QA/QC). All submissions and related work for each design phase must conform to the requirements in this document.

10. The Contractor must resolve conflicting criteria with the COR.

B. Submission Requirements

1. Design Development

Design Development includes the work required to represent the project as a set of drawings, including.

site surveys or requests for information. The contractor should have as much physical presence as needed to verify all conditions to accurately depict the existing space for any new work.

2. Construction Documents

The Contractor must provide a checklist of all submittals, certifications, tests, and inspections required per drawing and specification section. This checklist will show all products requiring submittals in the form of shop drawings, data sheets, manufacturer cut sheets, etc. as well as all other items shown as required submittal items including, but not limited to, reports, system evaluations, testing, operating and maintenance manuals, etc.

The Contractor must provide 100% drawings in AutoCAD/Revit and pdf. Specifications are provided separately in text-format for construction period use by GPO. A share-point site or email with hyperlink click and download such as Procore is encouraged for ease of transfer.

The DB team is responsible for professional quality and technical accuracy in providing GPO with documents. Services include but are not necessarily limited to:

• Contract Administration

• Architectural design documents and calculations in detail of construction documents including all plans, elevations, sections, details, and schedules.

• Mechanical design documents and calculations in detail of construction documents including all plans, elevations, sections, details, schedules, calculations to size all HVAC and plumbing components.

• Electrical design documents in detail of construction documents including all plans, elevations, sections, details, diagrams, schedules, showing power distribution systems, lighting, and signal systems.

• Fire Protection design documents in detail of construction documents including all plans, elevations, sections, details, diagrams, and schedules.

• Presentation and review submissions. Meetings with GPO representatives, and field technical personnel.

3. Drawings

• Drawings must be presented at a scale where work required is clear, legible, and easy to interpret.

• Drawings must be independent for demolition, architectural, mechanical, structural, civil, etc., and must show, on separate views, required demolition and reconstruction details for each function.

• Drawings must be prepared using AutoCAD/Revit 2020 or newer (or equivalent) and plotted on

30" x 42” sheets.

• Final drawings must bear GPO title block and nomenclature. Drawings must be on the same type and size sheets. All views, elevations, sections, etc., must be complete to ensure total contractor compliance without any ambiguities, or subject to various interpretations.

• All drawings are required to show existing conditions as of the date of the design submission.

• All sheets of drawings must contain A/E official stamp with professional seal and signature along with the name and address of the firm.

4. Specifications

• Specifications must be prepared and submitted individually in latest version of Microsoft Word.

• The Contractor must review and edit applicable sections of the specifications for completeness, relevance, and correctness. The intent is to provide specifications suitable for the project intention and detailed enough to enable the contractor to perform the work in the simplest and practical manner.

• Where a particular item is referenced in the specifications, consult with COR for directions on which item to select. The contractor must not be provided with options or choices to make selections but must be provided the specific selection.

• The Contractor must obtain the name and type of specialty materials and equipment required for use on the project. All items shown in the specifications must, if named specifically by brand or trade name, carry the statement "or approved equal" with salient characteristics listed.

(a) Exceptions may occur due to previously purchased or installed items interacting with new construction. In this situation, items used should be the same as existing or matched accordingly.

Information on such items must be obtained by the contractor from GPO.

• Construction tolerances must be specified in detail in all specification sections or identified on plans.

• Legal precedence of "specifications over drawings" must not be used to resolve design ambiguities between drawings and specifications, or to justify omission of drawings or notes required for clarity.

• Contradiction, ambiguity, or statements subject to various interpretations, must be corrected to reflect a single clear intention.

C. Quality Assurance/ Quality Control (QA/QC)

To reduce design errors and omissions, the Contractor must submit and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort. All systems shall be inspected, tested, and commissioned prior to final acceptance.

These plans must include, but are not limited to, methods to verify the operating tolerances of the machine.

The Contractor will work with the machine manufacturer to validate the acceptance of the Canon ProStream

Press.

The COR, GPO, AHJ, or other Safety Personnel may conduct inspections of work or working environment at any time; full cooperation with reviewing personnel is mandatory. The Contractor shall accomplish corrective work required prior to performing further construction.

D. Performance Standards

The completed installation shall:

• Maintain structural integrity within allowable limits.

• Provide electrical power within manufacturer tolerances.

• Maintain environmental conditions within specified temperature and humidity range.

• Provide process cooling and compressed air meeting OEM specifications.

• Achieve successful OEM startup without infrastructure-related deficiencies.

Corrective action required to meet performance standards shall be performed at no additional cost to the

Government.

E. Code Compliance

1. Any deviations or work that is non-conformant to standards, regulations, or specifications shall be removed and corrected at no cost to the Government.

2. Installation of electrical systems shall be performed by licensed or journeymen electrician; provide documentation via submittal.

3. In the development of submissions, must utilize certain GPO and other design and construction criteria. The design is not limited to these items and must be the result of compliance with applicable codes and standards, the user requests, and the Contractor’s expertise and creativity.

4. Compliance to all known applicable codes must be reflected in the completed design and construction contract documents.

V. Construction Period

A. General Requirements

1. The Contractor will make any required modifications to the space as indicated by the construction documents.

2. The Contractor shall follow the designer’s recommendations for any work entailed by their design, such as materials or methods to be used. Any disagreements shall be resolved by the COR.

3. The Contractor shall give the COR advance notice of any demolition in the work schedule, whether it be for investigation or construction.

4. Contractor shall ensure all nearby adjacent surfaces and areas are protected from damage during the period of construction and should any damage occur, it will be the responsibility of the

Contractor to repair before the end of the contract period.

5. In the event of accidents of any kind, the Contractor shall furnish GPO with copies of all accident reports at the same time they are forwarded to any other parties, without delay, for review.

6. The Contractor must maintain all construction permits visible and updated as required.

7. Utility outages shall require advance written approval.

8. The Contractor shall prohibit smoking in and adjacent to construction areas.

9. The Contractor will prevent accidental smoke detector operation.

B. Fire and Safety

1. Develop a plan detailing project specific, fire-safety measures. Conduct meetings with the building’s facilities management to determine the type and capabilities of the fire-suppression systems on site.

2. Maintain site and building access free and unobstructed to facility emergency services.

3. All temporary construction partitions must meet fire-safety requirements.

4. Temporary heating and electrical installations must comply with OSHA 1926, NFPA 241 and

NFPA 70.

5. Contractor furnished fire extinguishers must be provided and maintained in construction areas and in temporary storage areas. Extinguishers must be raised two feet off the floor.

6. Flammable and combustible liquids must be stored, disposed and used in accordance with OSHA

1926, NFPA 241 and NFPA 30.

7. Existing fire protection must not be impaired, and a fire watch must be provided should protection become impaired. Notify the COR and Fire Inspector if these conditions are expected or occur.

8. Perform hot work in accordance with NFPA 241 and NFPA 51B. The Contractor must obtain and fill out a GPO hot work permit from the COR prior to the start of hot work

C. Site Protection

1. No dust and debris should get into the production area on the same floor.

2. The Contractor shall provide, erect, and maintain catch platforms, lights, barriers/walls, weather protection, warning signs and other items as required for proper protection of the public, occupants of the building, and workmen engaged in work and adjacent construction.

3. The Contractor shall not close or obstruct walkways, passageways or stairways. The Contractor shall not store or place materials in passageways, stairs or other means of egress and shall conduct operations with minimum traffic interference.

D. Cleanup and Restoration

1. The Contractor shall remove waste generated from the worksite on a scheduled basis. Waste shall be deposited in an appropriate dumpster provided by the Contractor, located in an area approved by the COR and removed from the grounds weekly or when full. The Contractor is responsible for the procurement of waste services. No government -leased or owned dumpster shall be used to dispose of construction waste.

2. Damage of interior and exterior items such as walls, ceiling tile, and any other Government owned equipment shall be repaired/replaced at no cost to the Government.

3. Upon completion of work, the Contractor is responsible for any punch list items accrued during the final walkthrough by the COR. This contract will not be fulfilled until all items are addressed in a timely manner, inspected by the COR, and have written approval.

E. Government Furnishings

1. Services

• GPO will provide house services, such as 120V house Electrical, water, etc.

• GPO will oversee all matters relating to facilities equipment and systems such as HVAC, electricity, plumbing, etc. Any adjustments to these utilities will be handled internally by the

Facilities Management or by others.

2. Loading Dock

• Loading dock hours of operations are from 7:00 AM to 2:30 PM, Monday through Friday.

Coordinate with the COR for usage.

• The address of loading dock is 44 H Street, NW, Washington, DC 20401.

• Equipment or materials shall not exceed what can be handled by GPO’s elevators as listed below.

• Oversized payloads will require special handling by the Contractor. If any part or equipment exceeds 20,000 lbs., it shall be delivered through the wall or windows. If the wall or window is demolished for work, the Contractor must restore the wall and window to the original condition.

3. Elevators

• Use of freight elevators for transporting materials and equipment is provided. The max specifications of the freight elevators are as follows:

(a) Height - 7' 6"

(b) Width - 7' 0"

(c) Length - 10' 0"

(d) Weight - 20,000 lbs.

4. Material Storage

• The Contractor shall confine storage of materials on the job site to areas approved by the COR and shall not unnecessarily encumber the premises or overload any portion with materials to a greater extent than the structure design load.

• The Contractor shall verify available storage space at the job site with the COR. Any additional off-site space is the responsibility of the Contractor. The Contractor shall allocate the available storage areas and coordinate their use with the other trades on the job.

5. Parking

• Parking is available in Lot 50 at GPO headquarters at a daily rate of $9. Space is limited due to multiple, ongoing construction projects. The Contractor shall limit the number of Contractor vehicles onsite to an appropriate level. Coordinate with the COR for proper parking if standard lot spaces are not being used.

F. GPO Regulations

1. Crane Work

• Any crane work will be scheduled on weekends (Saturdays and Sundays) or Federal Holidays, and subject to the COR’s approval.

2. Gas-Powered Vehicles

• Propane-powered forklifts may be used during weekend work, Federal holidays, or off hours

(4pm-10:30pm) with GPO’s approval and permission.

3. Security

• Contractor’s vehicles, work bags, toolboxes, material, etc. will be inspected upon arrival and checked when leaving the premises of the building. The Contracting Officer’s Representative

(Luis Gallegos work cell: 202-285-8480) will be the main point of contact for escorting purposes.

• The Contractor shall safeguard all Government property in the work area. At the close of each work period, equipment shall be secured and/or taken away from the work site daily.

• The Contractor shall cooperate with those in authority on the premises to prevent the entrance and exit of all workers and/or others whose presence is forbidden or undesirable.

• Follow the most up to date Contractor Security Requirements.

4. Escorting Requirements

• Terminology

(a) Visitor – A person who has been authorized entry to GPO facilities via a visitor’s pass.

Visitors are a type of non-badged personnel.

(b) Visitors Pass – An ID distributed by GPO security in exchange for the visitor’s valid government-issued ID. IDs are returned once the visitor returns the visitor’s pass at their original point of entry

(c) Affiliate – A person who requires prolonged or special access to GPO and as such, undergoes a screening process by GPO Security. Any visitors who intend to make modifications to the building must become affiliates prior to the start of work. Affiliates can be badged or non-badged.

(d) Affiliate Badge – A form of GPO ID issued to select affiliates at the sponsorship of a GPO

Employee. Typically reserved for affiliates of higher standing such as supervisors or specialists.

An affiliate badge grants a person the authority to access GPO facilities without supervision so long as they comply with GPO entry protocols. These access privileges are maintained while the Affiliate badge is in good standing (not expired or terminated). Affiliate badges are to be returned to GPO security once terminated.

(e) Badged Individual – Anyone issued a unique GPO ID as part of their duties. This classification includes not just GPO employees but also affiliates or authorized GPO tenants. Badged individuals are granted an expedited entry into GPO facilities and the ability to escort non-badged personnel, such as visitors.

• GPO Security Requirements

(a) Non-Badged Personnel (Visitors, Non-badged affiliates, etc) must always be escorted by

Badged Individuals.

(b) Badged individuals can escort up to five (5) non-badged personnel.

(c) In larger groups, the ratio of 1:5 (1 badged: 5 non-badged) is not to be exceeded. This ratio must be monitored and maintained at all times.

• Contract Requirements

(a) The general Contractor bears full responsibility for upholding GPO Security requirements, including:

(i) Submitting paperwork for their staff to become affiliates in a timely manner.

(ii) Submitting paperwork for select members of their staff to receive affiliate badges in a timely manner.

(iii)Not depending on GPO or other independent parties to fulfill their escorting requirements under any circumstances.

(b) The general contractor must demonstrate the ability to meet GPO security requirements through the following:

(i) Acquiring a sufficient roster of affiliates to properly staff the project.

(ii) Maintaining a consistent, daily site presence of badged-to-non-badged affiliates according to the 5:1 ratio.

(iii) Providing GPO with regular escorting metrics such as daily head counts and advanced work schedules for badged personnel.

VI. Period Of Performance

A. A timeline based on design-build contract award of approximately May 2026 is offered below.

B. The CO and COR will conduct periodic reviews with the contractor. The Contractor must perform the work required within the limits of the following schedule:

Predesign Meeting with GPO staff Day 0

Technical Kickoff Meeting +3 days, Day 3

20% Conceptual Design Development (DD) & Submit +18 days, Day 21

GPO Review +10 days, Day 31

65% DD & Submit +30 days, Day 61

GPO Review +21 days, Day 82

95% DD & Submit +21 days, Day 103

GPO Review +15 days, Day 118

100% Construction Document (CD) Review Package +14 days, Day 132

Schedule Contingency +10 days, Day 142

Construction NTP and Multi-Phased Construction +21 days, Day 163

QA/QC of Construction, Substantial Completion, and Punchlist

Review.

+17 Days, Day 180

C. All work shall be completed within 26 weeks (180 days) of the Notice to Proceed (NTP). The

Contractor shall submit the design timeline, safety plans, quality control plan, schedules, pre‐construction submittals, etc. shall be submitted within 14 days of the Construction NTP.

D. The Contractor must submit a baseline Critical Path Method (CPM) schedule within 10 calendar days of the NTP. The schedule shall include site survey, design milestones, procurement, construction, rigging, commissioning, and OEM startup coordination. An updated CPM schedule shall be part of the

95% Design submittal to better reflect construction.

E. Work Schedule

Work will be performed during normal business hours from 7:00 AM until 3:00 PM. The Contractor must coordinate working schedule with the COR prior to beginning construction. Any work to be performed outside normal business hours and on weekends or holidays will need to be coordinated with the COR three (3) days prior.

F. Federal Legal Holidays

New Year’s Day January 1

Martin Luther King’s Birthday Third Monday in January

President’s Day Third Monday in February

Memorial Day Last Monday in May

Juneteenth June 19

Independence Day July 4

Labor Day First Monday in September

Columbus Day Second Monday in November

Veteran’s Day November 11

Thanksgiving Day Fourth Thursday in November

Christmas Day December 25

VII. Privacy Statement

Information Security: The C&A requirements do not apply; a Security Accreditation Package is not required. Incidental exposure to protected health information may occur from accessing the work site.

Staff will follow all Privacy & Security policies and procedures.

VIII. Post Construction Quality Validation and Contract Close-out

A. FAR 52.246‐21 Warranty of Construction, The Contractor shall provide a minimum one-year warranty on workmanship and installed systems commencing upon final acceptance.

B. Closeout – Final acceptance shall occur only after successful OEM startup, completion of commissioning activities, submission of required documentation, and correction of punch list items.

C. The Contractor must submit the record drawings showing any changes or modifications to the bid documents reflected on the hard-copy set of “as-builts”; Drawings must be individually marked

“Record Drawing” and submitted in a single package as follows;

1. Drawings in AutoCAD (DWG) or Revit (RVT) format of the entire project shall be delivered electronically.

2. Drawings must represent final project with all demolished and/or removed items deleted from the .dwg/.rvt files.

3. Drawings in (PDF) format of the entire project in addition to 1 set of full size 30 x 42" drawings.

[END OF SECTION C]

Section D - Packaging and Marking: None

Section E - Inspection and Acceptance Terms:

E.1 MATERIALS MANAGEMENT ACQUISITION REGULATION (MMAR) 46.503

PLACE OF ACCEPTANCE (APR 2010)

The Contracting Officer or the duly authorized representative will accept supplies and services provided under this contract. The place of acceptance will be: United States Government Publishing Office 732

North Capital Street NW Washington DC 20002.

E.2 RESPONSIBILITY FOR INSPECTION AND ACCEPTANCE

The Contracting Officer’s Representative (COR), as appointed/designated by letter as per the information listed in Section G of this document, is the Government's official responsible for inspection and acceptance of required services under the terms and conditions of this contract. The Government may designate additional representative(s)to provide periodic inspections or observations during the performance of this contract. However, Government inspections are for the sole benefit of the

Government and do not relieve the Contractor of its responsibilities to provide adequate quality control for the works described in Section J Attachments: Plans and Specifications. The Contractor is responsible for inspection of its own work to ensure that all work performed conforms to the terms and conditions of the contract.

E.3 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE

The U.S. GPO is a legislative branch of the United States Government. Accordingly, the Federal

Acquisition Regulations (FAR) in not applicable to this and all GPO procurements. The Contractor should note that only those provisions of the Materials Management Acquisition Regulations (MMAR) which are specifically incorporated by reference into this solicitation are applicable.

The following Contract clauses pertinent to this section are hereby incorporated by reference (by

Citation, Number, Title, and Date) in accordance with the clause at MMAR 52.252 2 CLAUSES

INCORPORATED BY REFERENCE in Section I of this Contract. Full text of the clauses is available at: P805.33 Materials Management Acquisition Regulation (MMAR)

52.232-4 52.232 34 Payment by Electronic Funds Transfer Central Contractor

Registration (May 1999)

52.236-2 52.236-2 Differing Site Conditions (APR 1984)

52.236-3 52.236-3 Site Investigation and Conditions Affecting the Work (APR

1984)

52.236-5 52.236-5 Material and Workmanship (APR 1984)

52.236-6 52.236-6 Superintendence by the Contractor (APR 1984)

52.236-7 52.236-7 Permits and Responsibilities (NOV 1991)

52.236-8 52.236-8 Other Contracts (APR 1984)

52.236-9 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements (APR 1984)

52.236-10 52.236-10 Operations and Storage Areas (APR 1984)

52.236-12 52.236-12 Cleaning Up (APR 1984)

52.236-13 52.236-13 Accident Prevention (NOV 1991)

52.236-15 52.236-15 Schedules for Construction Contracts (APR 1984)

52.236-17 52.236-17 Layout of Work (APR 1984)

52.236-21 52.236-21 Specifications and Drawings for Construction (FEB 1997)

52.236-27 52.236-27 Site Visit (Construction) (FEB 1995)

CONTRACT CLAUSES INCORPORATED BY FULL TEXT:

52.246-12 Inspection of Construction.

INSPECTION OF CONSTRUCTION (AUG 1996)

(a) Definition. “Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The

Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to

Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not-

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this- section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may-

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of clause)

52.246-21 Warranty of Construction.

WARRANTY OF CONSTRUCTION (MAR 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work.

If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect.

In addition, the Contractor shall remedy at the Contractor’s expense any damage to Government-owned or controlled real or personal property, when that damage is the result of—

(1) The Contractor’s failure to conform to contract requirements; or

(1) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the…

This is the start of the file's text. The full file is on GovTribe.