Attachment J-2 - 030ADV26R0048 - Deliverables Price Schedule 7-16-26 (2 Pages) - Theater Rigging.docx

DOCX document 21 KB Posted

Attached to
Theater Rigging Control System Modernization
Solicitation number
030ADV26R0048
Issued by

About this file

Summary

This is a Deliverables Price Schedule for solicitation 030ADV26R0048, issued by the Library of Congress for the Theater Rigging Control System Modernization project at the Coolidge Auditorium. Offerors must provide firm fixed prices for each deliverable listed, with the exception of those marked "Not Separately Priced" (NSP). Proposals lacking pricing for all required deliverables will be rejected. The schedule spans from September 2026 through September 2027, with key milestones including a kick-off meeting by September 30, 2026; site survey and system design by November 15, 2026, and February 5, 2027, respectively; and infrastructure removal, control system architecture, motion control functionality, curtain motor, installation, testing, and commissioning all due by September 28, 2027. Documentation is also required by September 28, 2027, followed by a one-year maintenance and warranty support period extending from September 28, 2027, through September 27, 2028.

The deliverables encompass the complete replacement of the Coolidge Auditorium's legacy theatrical rigging control system, which has been inoperable for over a year. The work involves removing the existing distributed control infrastructure installed in the 1990s, designing a unified control environment, and installing new motorized rigging systems while adhering to historic preservation constraints and structural limitations specific to the protected performance venue.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-2 – 030ADV26R0048 – Deliverables Price Schedule 07-16-26 (1 Page)

Offeror shall provide a firm fixed price for each deliverable in the below price schedule. Proposals that do not provide prices for each deliverable (excluding the deliverable marked as Not Separately Priced (NSP) will not be accepted.

Paragraph reference
Deliverable
Due date
Payment Amount
C.4.1
Kick-Off Meeting

No later than 9/30/2026

Not Separately Priced (NSP)

C.3.1A
Site Survey

No later than 11/15/2026

NSP

C.3.1B
System Design

NLT 02/05/2027

C.3.2
Infrastructure Removal Services

NLT 09/28/2027

C.3.3.1
Existing Infrastructure/Included Systems

NLT 09/28/2027

C.3.3
Control System Architecture

NLT 09/28/2027

C.3.3.2
Motion Control Functionality

NLT 09/28/2027

C.3.5
Curtain Motor

NLT 09/28/2027

C.3.6
Installation, Testing and Commissioning

NLT 09/28/2027

C.3.7
Maintenance and Warranty Support

09/28/2027 – 09/27/2028

C.3.8
Documentation

NLT 09/28/2027