Attachment J-1 - HSC-L_Draft_SOW-20260317.pdf
PDF 1 MB Posted
- Solicitation number
- 70Z02326IHSCL1GHT
About this file
Summary
This is a Draft Statement of Work (SOW) for the USCG Homeland Security Cutter – Light Icebreaker (HSC-L) program, issued on March 18, 2026. The document establishes requirements for designing, fabricating, constructing, testing, delivering, and supporting seven light icebreaker vessels for the United States Coast Guard. The primary operational capability is icebreaking to promote safety and facilitate commerce in U.S. waters, with secondary capabilities including aids-to-navigation maintenance, vessel escort, and search-and-rescue support. The contract encompasses design and engineering through Critical Design Review and Production Readiness Review, production of a lead boat (HSC-L-1) and follow boats, technical data submissions, crew training, logistics support, warranty provision, and operational test support. The Contractor must develop a production-ready design from the Government-provided contract design and produce vessels sustainable over a 30-year lifecycle, utilizing standardized equipment including Scalable Integrated Navigation System-2 (SINS-2) and Automatic Identification System-2 (AIS-2) supplied by Teledyne FLIR Maritime US Inc.
The SOW details extensive requirements across multiple work breakdown structure categories, including program management with quarterly Program Management Reviews, configuration management with formal baselines (Functional, Allocated, Developmental, and Product Configuration Baselines), design reviews progressing through Preliminary Design Review to Critical Design Review, integration and engineering across four phases, and comprehensive testing including watertight integrity, propulsion systems, steering, electrical systems, HVAC, fire suppression, full power and endurance trials, speed tests, maneuvering demonstrations, weight control, and one-time tests such as inclining experiments and bollard pull tests. Additional requirements encompass technical data delivery per MIL-STD-31000 standards, provision of 3D product models in native and STEP formats, drawings in AutoCAD format, system diagrams, technical manuals per MIL-DTL-24784, crew familiarization and OEM training, Integrated Logistics Support including maintenance planning and supply support, mockups of pilothouse and aft deck spaces, and facilities providing dedicated office space for ten Government personnel at the construction facility. The Contractor bears responsibility for all long-lead material procurement, Government-furnished equipment integration, testing and trials, safety and accident prevention, human systems integration, weight control, and delivery of each vessel in complete operational condition to USCG Yard, Baltimore, MD, where a Post-Delivery Availability period is conducted by the Government.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
USCG Homeland Security Cutter – Light Icebreaker (HSC-L) Statement of Work
Department of Homeland Security (DHS)
United States Coast Guard (USCG)
Homeland Security Cutter – Light Icebreaker
(HSC-L)
Request for Proposal
(RFP)
STATEMENT OF WORK
(SOW)
18 MAR 2026
Revision DRAFT ii
Table of Contents
RECORD OF CONTRACT CHANGES
C.1 [Orig] Background
C.2 [Orig] General Statement of Work
C.2.1 [Orig] American Bureau of Shipping (ABS) Communications
C.2.2 [Orig] Contract Award and Communications
C.2.3 [Orig] Design and Engineering (CLIN -001)
C.2.4 [Orig] Design and Engineering Changes (CLIN -001)
C.2.5 [Orig] Long Lead Time Materials (SLIN -002AA)
C.2.6 [Orig] Production of Lead Boat; HSC-L-1 (SLIN -002AB)
C.2.7 [Orig] Follow Boat Production (SLIN -002AB)
C.2.8 [Orig] Technical Data Submissions (CLIN -003)
C.2.9 [Orig] Optional Technical Data Rights (SLINs -003AA, -003AB, -003AC)
C.2.10 [Orig] Training (CLIN -004)
C.2.11 [Orig] Deep Insurance Spares (CLIN -005)
C.2.12 [Orig] Operational Test Support (CLIN -006)
C.2.13 [Orig] Boat Transport to Delivery (CLIN -007)
C.2.14 [Orig] Special Studies (CLIN -008)
C.2.15 [Orig] Capital Expenditures (CAPEX) (CLIN -009)
C.2.16 [Orig] Display Model (CLIN -010)
C.2.17 [Orig] Ceremonies and Events (CLIN -011)
C.3 [Orig] Specific Statements of Work
C.3.040 [Orig] Program Management
C.3.041 [Orig] Configuration Management
C.3.045 [Orig] Care of Boat During Construction
C.3.068 [Orig] Integration and Engineering
C.3.073 [Orig] Noise and Vibration
C.3.076 [Orig] Material Certifications
C.3.077 [Orig] Production Safety and Accident Prevention
C.3.080 [Orig] Integrated Logistics Support (ILS)
C.3.081 [Orig] Maintenance Planning
C.3.083 [Orig] Supply Support
C.3.084 [Orig] Preservation, Packing and Marking
C.3.085 [Orig] Drawings
C.3.086 [Orig] Technical Manuals and Other Data
C.3.087 [Orig] Facilities iii
C.3.088 [Orig] Human Systems Integration (HSI)
C.3.092 [Orig] Test Administration and Testing
C.3.096 [Orig] Weight Control and Weight Reports
C.3.097 [Orig] One-Time Tests (OTTS)
C.3.098 [Orig] Mockups
C.3.099 [Orig] Photographs and Videos
APPENDIX A: [ORIG] CDRL MILESTONE CHART ...................................................................................... TBD
APPENDIX B: [ORIG] LIST OF REFERENCES .............................................................................................. TBD
APPENDIX C: [ORIG] LIST OF GOVERNMENT FURNISHED INFORMATION ....................................... TBD iv
RECORD OF CONTRACT CHANGES
Version Date Purpose
Orig 05/XX/2026 Initial Release
C.1 [Orig] Background
(a) The U.S. Coast Guard maintains and operates icebreaking vessels to promote safe navigation and facilitate commerce in U.S. waters. These missions originate in Executive Order 7521 (21 Dec
1936), which directs the U.S. Coast Guard (USCG) to provide domestic icebreaking in ice-covered waterways to facilitate safe commercial navigation and prevent ice-related flooding. These missions prove critical to the Northeast region, where the economy depends on key shipping channels to maintain the transit of over 100 million tons of vital commodities annually.
The Homeland Security Cutter (HSC) program intends to develop a materiel solution to recapitalize the Coast Guard’s light icebreaking capability in Northeast region. The current 65-ft WYTL class of light domestic icebreakers has exceeded 50 years of service. The fleet can no longer meet mission or regulatory demands. The HSC-Light Icebreaker (HSC-L) program plans to acquire seven new vessels to carry on the light icebreaker mission.
C.2 [Orig] General Statement of Work
(a) [Orig] The HSC-L Program intends to acquire seven HSC-L boats collectively called HSC-L under this contract, which are to be fully operational and sustainable over a projected 30-year life cycle. This solicitation seeks a Shipbuilder to produce HSC-Ls that provide long term supportability and affordability while complying with USCG technical and management requirements.
(b) [Orig] The HSC-L contract design is provided. The Contractor shall further develop this design product to be production-ready. The production-ready design shall have the following primary operational capability: icebreaking to promote safety and facilitate commerce in U.S. waters.
Secondary capabilities shall include; establish, maintain, and operate aids to navigation; position and perform maintenance on Federal floating aids to navigation on inland waterways; position and perform maintenance on river buoys; position and construct beacons; perform maintenance on fixed aids to navigation; transmit/receive marine safety information; provide lift capability; escort vessels;
provide command and control; conduct communications; employ sensors; conduct search & rescue.
(c) [Orig] This Contract encompasses the technical, procurement, and other tasks necessary to develop a production-ready design from the USCG contract design and produce HSC-Ls.
(d) [Orig] The term “lead boat” within the context of this contract refers to the first HSC-L produced under this contract. The lead boat is also referred to as HSC-L-1.
(e) [Orig] Reference document effectivity shall be in accordance with the Section J Attachment J-
1, “Technical Specification” Section 042.4.
(f) [Orig] Equipment and Design Standardization. The following systems and equipment on HSC-
Ls are standardized in support of operability and sustainability.
1. [Orig] The Scalable Integrated Navigation System - 2 (SINS-2).
2. [Orig] The Automatic Identification System - 2 (AIS-2).
3. [Orig] The supplier of the equipment and sensors with comprise SINS-2 and AIS is:
Teledyne FLIR Maritime US Inc.
110 Lowell Road, Hudson, NH 03051, USA
603.324.7900
(g) [Orig] Supply Chain Risk Management. The Contractor shall implement supply chain assurance to reduce risk of counterfeit and non-conforming supplies and ensure resilience of the supply chain. The Contractor shall source critical components only from original manufacturers or authorized suppliers and maintain documentation of authenticity for such.
(h) [Orig] Delivery and Acceptance. Delivery of each HSC-L by the Contractor, and Acceptance of each HSC-L by the USCG comprise a single contract execution event which will occur at USCG
Yard as specified in Section F clause titled “Lead and Follow Boats”. The words Delivery and
Acceptance in this contract are used interchangeably and refer to the same event.
(i) [Orig] USCG will conduct a Post-Delivery Availability at the USCG Yard, Baltimore, MD.
Off-hour time will be made available for Shipbuilder employees or representatives to correct trial cards and provide warranty repairs.
(j) [Orig] The Contractor shall incorporate into their production, the selected equipment identified in the proposal and incorporated into the contract as Section J, Attachment J-14, Major Equipment
List. Changes to the Major Equipment List must be requested by the contractor and approved by the
Government prior to implementation. Government approval of changes to the Major Equipment List does not alleviate the contractor’s responsibility to meet all other requirements of this contract.
C.2.1 [Orig] American Bureau of Shipping (ABS) Communications
(a) [Orig] If required, the Contractor shall authorize direct communication between the Coast
Guard and ABS for compliance, progress and reporting issues. Any communication with ABS by either the shipbuilder or the Coast Guard shall be shared by all parties.
C.2.2 [Orig] Contract Award and Communications
(a) [Orig] The Coast Guard will provide an Integrated Data Environment (IDE).
(b) [Orig] All official contract execution correspondence shall be accomplished via the IDE. The
Contractor shall obtain an appropriate number of Common Access Cards (CAC) or public key infrastructure (PKI) tokens as per the procedures in Section I clauses titled “Facility and Computer
Access” to execute official contract correspondence in the IDE.
(c) [Orig] Contract data deliverables shall be submitted via the IDE unless otherwise annotated in the Data Item.
(d) [Orig] The Effective Date of Contract Award (EDCA) is established in the SF33.
(e) [Orig] If the IDE is inaccessible, deliverables shall be submitted by email on or before their contractual due dates to the USCG Contracting Officer at the address specified in Section F clause titled “Data Deliverables”.
C.2.3 [Orig] Design and Engineering (CLIN -001)
(a) [Orig] The Contractor shall develop the production-ready design of HSC-L-1 from the USCG
Contract Design through Preliminary Design Review (PDR), Critical Design Review (CDR), and
Production Readiness Review (PRR). Design and Engineering also includes:
• Systems interface and integration;
• Requirements testing and verification;
• Production design and preparations through completion of final transitional designs;
• Human systems integration; and
• Mockups.
(b) [Orig] The Contractor shall execute technical reviews in accordance with Attachment J-2, “Design and Readiness Review Requirements and Criteria”.
(c) [Orig] The Contractor shall prepare and deliver design data in accordance with Attachment J-
4, “Contract Data Requirements List”.
(d) [Orig] All data deliveries and milestones during design will align with the Section F clause titled “Period of Performance (POP) / Delivery Schedule” and Attachment J-4, “Contract Data
Requirements List”. The Date of Contract Award shall be the baseline start date for contract execution unless otherwise specified by the Contracting Officer.
(e) [Orig] Technical data associated with preliminary, functional, and transitional design shall be delivered.
C.2.4 [Orig] Design and Engineering Changes (CLIN -001)
(a) [Orig] The Contractor shall implement Government-initiated and Contractor-proposed change orders to the design under CLIN -001.
(b) [Orig] Change orders can only be implemented after the change order has been authorized by the
Contracting Officer via a contract modification.
(c) [Orig] Design and Engineering Changes are applicable only to CLIN -001 Design and
Engineering. The pricing impact associated with other CLINs under this Contract shall be incorporated into the Pricing Table at the time of the bi-lateral contract modification, which each
Pricing Table being labeled to correspond with the modification number. The Pricing Table shall reflect submitted and approved Design and Engineering Change costs for CLIN -001 in addition to costs of production CLINs affected by changes on both an individual and cumulative scale.
(d) [Orig] Costs other than those allocated under CLIN -001 will be incorporated into Attachment
J-XXX of the Contract prior to commencement of production.
(e) [Orig] The steps below outline the general procedures for the Engineering Change Proposal (ECP) approval process for each change order.
1. [Orig] Both the Contractor and Government can propose change orders.
a. [Orig] For the Government proposed change orders, the Government will provide an
Engineering Change Request (ECR) to the Contractor. The ECR is a request for change that is reviewed and approved by the Government led Configuration Control Board to proceed to the ECP process.
b. [Orig] For Contractor proposed change orders, an ECP can be generated by the
Contractor without a preceding ECR.
2. [Orig] The Contractor shall submit an ECP to the Government, which will be reviewed internally by the Government.
3. [Orig] The Contractor and Government will enter negotiations to align on scope and cost of the ECP.
4. [Orig] After an ECP has been accepted by the Government, the Government will issue a bi-lateral modification to update language within the contract and attachments, as necessary.
5. [Orig] Once modification is issued, the Contractor shall proceed immediately in accordance with the scope of the modification.
6. [Orig] Invoicing shall adhere to requirements set forth in G.16 CONTRACT
ADMINISTRATION FOR DESIGN AND ENGINEERING CHANGES.
(f) [Orig] All implemented Design and Engineering Changes shall adhere to the same procedures and scope outlined in CLIN -001 Design and Engineering.
C.2.5 [Orig] Long Lead Time Materials (SLIN -002AA)
(a) [Orig] The Contractor shall procure long lead time materials (LLTM) identified in the Section J
Attachment J-7, “Long Lead Time Material (LLTM) and Insurance Spares List.” LLTM is Contractor
Furnished Equipment. USCG acceptance of LLTM is concurrent with boat delivery. Warranty for all
LLTM shall begin at boat delivery.
(b) [Orig] A Delivery Order for LLTM SLINs for HSC-L-1 in Ordering Period 1 shall not be issued until after successful completion of Preliminary Design Review or when authorized by the Contracting
Officer.
(c) [Orig] All responsibility for performance, timeliness, and quality of LLTM other than directed standardized equipment remains with the Contractor. The Contractor shall maintain the condition of
LLTM through proper storage and care.
(d) [Orig] LLTM for each follow boat is subject to Economic Price Adjustment for materiel costs as itemized per the procedure in Section H clause titled “Economic Price Adjustment”.
C.2.6 [Orig] Production of Lead Boat; HSC-L-1 (SLIN -002AB)
(a) [Orig] Placement of these production orders is predicated upon successful completion of the
Critical Design Review, a Production Readiness Review, and Contracting Officer direction.
(b) [Orig] The Contractor shall construct the lead HSC-L in accordance with the production design developed by the Contractor.
(c) [Orig] The lead boat shall be built, tested and verified to meet the requirements of the Section J attachment, Section J-1, “Technical Specification”. Any requirement not in compliance shall nonetheless be satisfied by the Contractor unless specifically stated in the contract to be the responsibility of the
Government.
(d) [Orig] The Contractor shall be responsible for procurement, installation, integration and testing of all Contractor Furnished Equipment (CFE) including software.
(e) [Orig] The lists of Government Furnished Information, which the USCG will furnish, are included in Section J.
(f) [Orig] The Contractor shall be responsible for the procurement and outfit of onboard spares, repair parts, equipage, tools and support equipment/documentation for all Contractor Furnished Equipment.
(g) [Orig] The Contractor shall provide system stock initial logistics spares, including depot level maintenance special tools, for each HSC-L and deliver them as specified in Section F clause titled
“System Stock, Consumables, Training Material, and Other Associated Items”.
(h) [Orig] The Contractor shall provide spare and consumable parts for urgent/emergent preventive and/or corrective maintenance. These orders may require expedited handling. Spare and consumable parts will be delivered directly to a boat as specified in the order placed in accordance with the Section
H clause titled “Orders”.
(i) [Orig] The Contractor shall provide outfitting, comprised of Storeroom Items (SRI), Operating
Space Items (OSI), General Use Consumables (GUC), and Allowance Equipage List (AEL) items, and install these items in each boat prior to delivery. The Contractor shall outfit each boat before delivery in accordance with industry standards.
(j) [Orig] The Contractor shall prepare and integrate all plans and schedules required for construction of the lead HSC-L.
(k) [Orig] The Contractor shall be responsible for overall project management, subcontractor management, technical direction, coordination and administrative work to ensure that all contractual requirements are properly accomplished.
(l) [Orig] The Contractor shall conduct required verification, testing and trials (including but not limited to Acceptance Trials).
(m) [Orig] The Contractor shall provide access during production as per the procedures in Section H clauses titled “Access to Contractor’s Facility” and “Access to the Boats” and in accordance with
Section C.3.087, and Section C.3.097.
(n) [Orig] The Contractor shall deliver each HSC-L complete in all respects, including documentation and certifications, with discrepancies corrected.
(o) [Orig] The Contractor shall prepare and deliver data in accordance with Attachment, J-4, “Contract
Data Requirements List.”
(p) [Orig] Technical data as described in paragraph C.2.8 below for each lead HSC-L shall be delivered (CLIN -003).
(q) [Orig] The Contractor shall provide a Warranty in accordance with the period of performance established in Section F clause titled “Warranty SLINs (XX)” and Section H clause titled “Warranty”.
(r) [Orig] Training Courses for crew members of each HSC-L shall be provided (CLIN -004) as described in paragraph C.2.10 below.
(s) [Orig] The Contractor shall provide 200 hours of subject matter expert (SME) time to educate and inform Government and Government-contracted personnel related to then analysis, design, development and implementation of Familiarization Training (to include underway training) and review related materials. SME access will be utilized by Government and contracted training personnel to conduct training analysis on shipboard systems. Further shipbuilder SMEs may be asked to verify the design and development of training materials for validation of content.
C.2.7 [Orig] Follow Boat Production (SLIN -002AB)
(a) [Orig] The Coast Guard plans to order for production each follow-boat listed in Section B, and to authorize production of at least the number of HSC-L listed in each ordering period. Design Reviews at noted in paragraph C.3.068 may be consolidated or waived based upon agreement between the
Contractor, Contracting Officer and/or COR.
(b) [Orig] Each follow HSC-L is subject to Economic Price Adjustment for material costs as itemized per the procedure in Section H clause titled “Economic Price Adjustment”.
(c) [Orig] Each requirement stated for the HSC-L lead boat in paragraphs C.2.6(c) through C.2.6(s) shall also apply to each follow-HSC-L.
(d) [Orig] Technical data as described in paragraph C.2.8 below for each follow HSC-L shall be delivered (CLIN -003 SLINS).
(e) [Orig] The Contractor shall provide a Warranty in accordance with the period of performance established in Section F clause titled “Warranty SLINs (XX)” and Section H clause titled “Warranty”.
(f) [Orig] Training Courses for crew members of each follow HSC-L shall be provided as described in paragraph C.2.10 below (CLIN -004 SLINs).
C.2.8 [Orig] Technical Data Submissions (CLIN -003)
(a) [Orig] The Contractor shall deliver Data Rights as listed in Section J, Attachment J-9A, “Technical
Data Rights Tables”.
C.2.9 [Orig] Optional Technical Data Rights (SLINs -003AA, -003AB, -003AC)
(a) [Orig] The Contractor shall deliver Optional Technical Data Rights as listed in Section J, Attachment J-9B, “Restricted Data Technical Data and Software Matrices” as ordered by the
Government.
(b) [Orig] Orders will be placed in accordance with the clause in Section H clause titled “Orders
(Fixed Price)” and at the prices provided by the Contractor in Section J, Attachment J-9B, “Restricted
Data Technical Data and Computer Software Matrices.”
C.2.10 [Orig] Training (CLIN -004)
(a) [Orig] The Contractor shall provide crew familiarization (FAM) and original equipment manufacturer training to USCG personnel for each HSC-L delivered.
C.2.10.1 [Orig] Crew Familiarization Training (SLIN -004AA)
(b) [Orig] The Contractor shall provide five days of crew familiarization (FAM) within two days of the boat being delivered unless otherwise arranged between the Contractor and USCG.
1. [Orig] The FAM shall be designed so that the crew will be able to operate all controls, navigation, and communication equipment to safely pilot the boat.
2. [Orig] The FAM shall concentrate on the safe use of the boat, basic operation of all boat controls and equipment, and maintenance.
3. [Orig] The FAM shall be provided at the acceptance location.
4. [Orig] The prescribed time for FAM shall cover both operator and maintainer FAM requirements. Up to 10 operators and up to 10 maintainers shall receive FAM during each session.
Operator and maintainer FAM sessions may be run concurrently for time efficiency. The FAM may include classroom sessions in addition to actual operation of the boat.
5. [Orig] FAM shall be performance-based and shall be conducted using operational equipment installed onboard the delivered boat.
6. [Orig] FAM training instructors shall provide step-by-step demonstrations of system/equipment operation and maintenance that shall be immediately followed by a time during which students reenact and perform the identical sequence of tasks.
7. [Orig] Operator and Maintainer FAM shall address all topics included in the BIB and OEM manuals (as applicable). The BIB and OEM manuals shall be used as a FAM aid.
(c) [Orig] At a minimum, operator FAM shall include, but not be limited to:
1. [Orig] Basic operation of all boat systems, sub-systems, equipment, operational characteristics, and parameters such as basic construction features, draft, turn radius, stopping distance, maximum sea states, and maximum safe speeds.
2. [Orig] Controls for boat handling, deck equipment, engines, electronics, fuel, bilge, fendering, and propulsion.
3. [Orig] Start-up and shut-down procedures.
4. [Orig] Warnings.
5. [Orig] Casualty control and emergency procedure for each action in the BIB and OEM manuals.
6. [Orig] Safe piloting, to include navigating at speed, holding station, and slow speed maneuvering alongside a pier or ship.
7. [Orig] Eight hours underway with the USCG operating the boat under Contractor supervision.
(d) [Orig] At a minimum, maintainer FAM shall cover, but not be limited to, organizational preventative and corrective maintenance for the following systems: propulsion, engines, electrical, electronics, steering, and hotel systems. The Contractor shall demonstrate the use of all special tools provided.
(e) [Orig] The Contractor shall provide a syllabus that includes, at a minimum, an agenda listing the topics and approximate time devoted to each [CDRL].
(f) [Orig] A copy of all materials used for the FAM shall be provided to the USCG upon completion of FAM.
C.2.10.2 [Orig] Original Equipment Manufacturer (OEM) Training (SLIN -004AB)
(g) [Orig] The Contractor shall procure and coordinate delivery of available OEM training courses related to the equipment on each HSC-L for the HSC-L crews for each HSC-L delivered. Training shall cover Organizational level (O-level) equipment maintenance, troubleshooting and operation.
1. Minimum equipment/system training requirements are provided below.
• Propulsion Engine.
• Reduction Gear.
• Generator Engine(s).
• Electrical Distribution Panels.
• Steering System.
• Integrated Bridge System.
• Machinery Plant Control and Management System.
• Propulsion Control
• Integrated Bridge System
• Deck Equipment and Crane.
2. [Orig] The Government will select the required courses from this list. The Contracting Officer will direct the Contractor to provide the courses required per each HSC-L delivered.
3. [Orig] This will include services and courses from Original Equipment Manufacturer authorized trainers for major equipment in accordance with CDRL. Training shall be conducted at the Contractor’s or Subcontractor’s facility as appropriate. The Contractor shall obtain prior USCG approval before arranging any COTS training in a foreign country.
C.2.11 [Orig] Deep Insurance Spares (CLIN -005)
(a) [Orig] The Contractor shall provide Deep Insurance Spares to replace major equipment that becomes damaged beyond repair and shall be comprised of selected Long Lead Time Material components. The government anticipated insurance spare list is provided in Attachment J-7, “Long Lead
Time Material (LLTM) and Insurance Spares List.”
(b) [Orig] The Government may order Deep Insurance Spares in Attachment J-7, “Long Lead Time
Material (LLTM) and Deep Insurance Spares List” at the unit prices. Deep Insurance Spares shall be delivered as required by Section F clause titled “Insurance Spares”.
C.2.12 [Orig] Operational Test Support (CLIN -006)
(a) [Orig] Operational Test Support as described in paragraph C.3.080 and C.3.092 below shall be provided for each boat (CLIN -006).
C.2.13 [Orig] Boat Transport to Delivery (CLIN -007)
(a) [Orig] Each HSC-L ordered shall be prepared for sea and delivered by a qualified master and crew to USCG Yard, Baltimore, MD. A limited number of USCG crew will accompany the HSC-L during the delivery.
C.2.14 [Orig] Special Studies (CLIN -008)
(a) [Orig] If ordered, the Contractor shall conduct special studies and analyses in support of this contract for non-warranty and/or Government-required changes.
(b) [Orig] The Contractor shall provide engineering services in support of the boat(s) to accomplish, in a timely manner, activities including but not limited to design activities in support of fielding the HSC-
Ls as well as corrections for minor repairs and deficiencies that are deemed to be the Government's responsibility. Requirements under this CLIN might include, but are not limited to, the correction of problems with Government Furnished Equipment (GFE), Government requirements identified by
Acceptance Trial cards, design of homeport specific brows, and the development of various engineering products/drawings. The requirements associated with this CLIN are over and above those specified in other contract CLINs.
(c) [Orig] Orders under this CLIN will be placed by a Coast Guard approved Technical Instruction
(TI) in accordance with the Section H clause titled “Orders (Fixed Price)”. Prior to the placement of an order, the contractor shall submit, as requested, a draft TI for approval by the Coast Guard detailing the specific effort to be accomplished, the period of performance covered by the TI, the FFP cost proposal for the work and the list of deliverables that will be submitted.
(d) [Orig] Travel billed in association with these activities will be billed in accordance with Joint
Federal Travel Regulations and be approved at least two weeks in advance by the COR.
C.2.15 [Orig] Capital Expenditures (CAPEX) (CLIN -009)
(a) [Orig] The Contractor shall implement facility improvements or process improvement projects to provide cost savings, quality improvements, or schedule efficiencies to the Government for HSC-L construction or other Coast Guard programs.
(b) [Orig] Orders under this CLIN will be placed by a Coast Guard approved Technical Instruction
(TI) in accordance with the Section H clause titled “Orders (Fixed Price)” and Section H clause titled
“Capital Expenditures (CAPEX).”
C.2.16 [Orig] Display Model (CLIN -010)
(a) [Orig] Display Models. The Contractor shall produce a 1:20 scale display model. The hull, deck arrangement, pilothouse, and all components of the models shall conform accurately to the scaled dimensions of the HSC-L. The model shall be constructed and finished using durable materials that are resistant to humid conditions.
1. [Orig] The model shall be of sufficient detail to accurately reflect the HSC-L including:
• [Orig] Realistic colors and finishes.
• [Orig] A hull which is outfitted to accurately reflect the HSC-L including: fendering;
propeller; shafting; skegs; and other components of the HSC-L.
• [Orig] Deckhouse, exterior equipment, and furnishings including: operator’s console, seating, deck lockers, cranes, masts, hatches, vents, mooring fittings, tow bitt(s), handrails, non-skid, antennas, lights, outfit including life rings, distress marker lights, lift fittings and boat hooks, and anchor if stored in a visible location.
• [Orig] Transparent pilothouse windows, allowing visibility to a fully outfitted pilothouse.
• [Orig] The model shall include USCG markings, including the “U.S. Coast Guard”, and hull number. The hull number shall be identical to HSC-L-1.
2. [Orig] The model shall be set on an oak base with a “honey” finish.
3. [Orig] A base shall be provided with port and starboard brass plaques that identify the models and the “US Coast Guard Homeland Security Cutter-Light Icebreaker (HSC-L)” and give the basic dimensions of the HSC-L and the manufacturer’s name.
4. [Orig] The model shall be enclosed in a safety plate glass case on a display table with wheels.
5. [Orig] The model shall be provided with an oak display table that is 30 inches (0.76m) high with a width and depth appropriate to contain the model.
6. [Orig] The model, case, and table shall be provided with a crate suitable for shipping.
Delivery location is specified in Section F clause titled “Display Models”.
C.2.17 [Orig] Ceremonies and Events (CLIN -011)
(a) [Orig] The Contractor shall coordinate and host a keel laying ceremony to mark the formal recognition of the start of HSC-L construction. The Contractor shall provide all necessary logistical support, including but not limited to shipyard venue preparation, event staffing, security, audio/visual equipment, seating, signage, and refreshments. The Contractor shall also support the participation of 200 designated government representatives and guests.
(b) [Orig] The Contractor shall coordinate and host a christening ceremony upon completion of boat construction and prior to delivery. The Contractor shall provide all necessary logistical support, including but not limited to venue preparation, event staffing, security, audio/visual equipment, seating, signage, and refreshments. The Contractor shall also support the participation of 200 designated government representatives and guests.
C.3 [Orig] Specific Statements of Work
(a) [Orig] The following subparagraph numbering corresponds to the Ship Work Breakdown Structure established by the National Shipbuilding Research Program.
C.3.040 [Orig] Program Management
C.3.040.1 [Orig] General
C.3.040.1.1 [Orig] This Statement of Work (SOW) and the associated Specification establish requirements for the design, fabrication, construction, testing, delivery, logistical support, and technical documentation for the HSC-L.
C.3.040.1.2 [Orig] The Contractor shall manage the entire work effort to develop the contract design into a production ready design, fabricate, construct, test, deliver, and support the HSC-L. This shall include ensuring that each HSC-L, logistics, and technical documentation meet the requirements of the
SOW and the Specification. The requirements of the SOW and Specification apply to each HSC-L, unless otherwise indicated.
C.3.040.1.3 [Orig] In case of inconsistency between the requirements within documents cited or referenced within the contract, the following order of precedence applies. Note: silence of one document with respect to details shown in another shall not be considered an inconsistency. Additional order of precedence requirements are in Section J Attachment J-1, “Technical Specification”, Section 042.5.
C.3.040.1.3.1 [Orig] The contract requirements.
C.3.040.1.3.2 [Orig] This Statement of Work.
C.3.040.1.3.3 [Orig] The HSC-L System Specification.
C.3.040.2 [Orig] Meetings
C.3.040.2.1 [Orig] General: The Contractor shall host meetings or be present at USCG meetings as required throughout the contract. For all meetings, the Contractor shall provide agendas and minutes unless stated otherwise in the SOW. The Contractor shall prepare and finalize the minutes for all meetings with input from the Contracting Officer’s Representative (COR). Minutes shall include action items, action items’ assignment (i.e., Contractor, USCG), and status. [CDRL]
C.3.040.2.2 [Orig] Meetings: The Contractor, Contracting Officer, or COR may request in-person and/or remote meetings to be hosted at the Contractor’s facility or at an alternate location as agreed to by both parties and shall have a video conference for additional off-site USCG representation unless otherwise agreed to by both parties. Meetings shall be requested by providing the Contractor or
Contracting Officer/COR notice 30 calendar days in advance or as agreed to by the Contracting Officer.
C.3.040.2.3 [Orig] Identified Formal Meetings, Conferences, and Reviews:
C.3.040.2.3.1 [Orig] Post Award Conference
C.3.040.2.3.1.1 [Orig] The Post Award Conference serves as a kick-off meeting for the contract.
C.3.040.2.3.1.2 [Orig] The Post Award Conference shall be led by the Contractor and include a review of deliverables, warranty terms and conditions, human systems integration, logistics and supply support, the Design and Development Plan, production planning, and any questions, concerns, or clarifications the Contractor requests with the Design Artifacts, the Specification or Statement of Work.
C.3.040.2.3.1.3 [Orig] The conference shall be no more than 5 days in duration, hosted by the
Contractor, include sufficient space for 45 Government personnel, and be scheduled to occur within 30 days after contract award at a location agreed upon by both parties.
C.3.040.2.3.2 [Orig] Program Management Reviews (PMR)
C.3.040.2.3.2.1 [Orig] The Contractor shall conduct PMRs at its facility, quarterly, beginning no later than three months after award. The Contractor shall attend each PMR with the appropriate personnel to address issues raised from the agenda items.
C.3.040.2.3.2.2 [Orig] Each PMR shall address the planned efforts for boat design, boat construction, testing, logistics support, human systems integration, management processes, life cycle support, risk management, Long Lead Time Material (LLTM), subcontractor management, procurement schedules, critical material schedules, and shall include identification and resolution of technical and management issues affecting schedules, cost, and performance and program risk. Each PMR shall also provide an update regarding the exact count of active employees by trade within the shipyard, planned hiring activities to maintain staffing, and other risks, opportunities, and concerns. [CDRL]
C.3.040.2.3.2.3 [Orig] Each PMR shall include splinter sessions to address issues on the agenda. The
Contractor shall coordinate schedules with the Government to run sessions using multiple rooms at the same facility in parallel to address every applicable splinter session topic in a timely fashion.
C.3.040.2.3.3 [Orig] Design Reviews
C.3.040.2.3.4 [Orig] Mockup Reviews
C.3.040.2.3.5 [Orig] Production Readiness Reviews
C.3.040.2.3.6 [Orig] Test Readiness Reviews
C.3.040.2.3.7 [Orig] Post-OT&E Design Reviews
C.3.040.2.3.8 [Orig] Integrated Baseline Reviews
C.3.040.3 [Orig] Data Exchange
C.3.040.3.1 [Orig] All data, drawings, and/or information submitted by the Contractor to the USCG shall be in accordance with section C.2.2, unless otherwise stated in the SOW, Specification, or CDRL to require hard copies to the USCG.
C.3.040.4 [Orig] Integrated Master Schedule (IMS) [CDRL]
C.3.040.4.1 [Orig] The Contractor shall develop and maintain an event-driven, Integrated Master
Schedule (IMS). The IMS shall show critical development milestone events and accomplishments for the prime and major subcontractors through the end of the contract performance period.
C.3.040.4.2 [Orig] The IMS shall also show all of the following events and milestones:
C.3.040.4.2.1 [Orig] Boat Deliveries
C.3.040.4.2.2 [Orig] Deliverables (e.g., CDRL, data) submission schedule
C.3.040.4.2.3 [Orig] Meetings (e.g., design reviews) and program reviews
C.3.040.4.2.4 [Orig] Schedule of required dates for materials
C.3.040.4.2.5 [Orig] Major milestones
C.3.040.4.2.6 [Orig] Configuration Baselines
C.3.040.4.2.7 [Orig] Contractor’s program phases
C.3.040.4.2.8 [Orig] Long-Lead Time Materials (LLTM) order date, as required
C.3.040.4.2.9 [Orig] The IMS shall reflect the baseline start/finish dates as well as the actual start/finish dates of all phases and intervals.
C.3.040.5 [Orig] Integrated Baseline Reviews (IBR): The Contractor shall host an IBR periodically to review the current delivery order and deliverables. IBRs shall be hosted by the Contractor at the
Contractor’s facility.
C.3.040.5.1 [Orig] IBRs shall be hosted in response to events, or at least annually, and may be held in conjunction with other meetings. Events that require IBRs include: a request by the Contractor, orders that include a new production of HSC-Ls, or an order or contract change that significantly alters the rate or schedule of production.
C.3.041 [Orig] Configuration Management
C.3.041.1 [Orig] General
C.3.041.1.1 [Orig] The Contractor shall be responsible for developing, documenting, and managing configuration of all boats.
C.3.041.1.2 [Orig] The Contractor shall establish unique identifiers for each developed and furnished document, physical hardware/equipment, and software. The unique identifier shall be used consistently between CDRLs.
C.3.041.2 [Orig] Configuration Status Accounting (CSA)
C.3.041.2.1 [Orig] The Contractor shall provide Configuration Status Accounting (CSA) as a means of creating a process to maintain and organize the knowledge base necessary to perform Configuration
Management (CM).
C.3.041.2.2 [Orig] The Contractor is responsible for CSA through the establishment of the Product
Configuration Baseline (PCB). After the establishment of the PCB, the responsibility for CSA and management of the PCB will be transferred to the USCG.
C.3.041.2.3 [Orig] CSA activities shall meet Section 7 of MIL-HDBK-61B and the CSA program shall address the tasks identified in Figure 8 of MIL-HDBK- 61B. The CSA system shall be accessible, viewable, and maintainable by the USCG through a standard USCG workstation.
C.3.041.3 [Orig] Configuration Baseline Definitions
C.3.041.3.1 [Orig] General: A configuration baseline is a fixed reference configuration established by defining and recording the approved configuration documentation for a system or CI at a milestone event or specified time.
C.3.041.3.2 [Orig] Functional Configuration Baseline (FCB)
C.3.041.3.2.1 [Orig] The Functional Configuration Baseline (FCB) consists of the boat’s technical, mission, operational and functional requirements, interoperability and interface characteristics, and design constraints as contained in the Contract Design Artifacts and Specification at contract award, including those items or capabilities that the Contractor offered and were incorporated into the contract.
C.3.041.3.2.2 [Orig] USCG will provide the Contractor with the FCB in the form of the Specification and HSC-L Contract Design artifacts.
C.3.041.3.3 [Orig] The Allocated Configuration Baseline (ACB)
C.3.041.3.3.1 [Orig] The Allocated Configuration Baseline (ACB) is the contractor’s design at PMR #1 that formally breaks down the functional requirements identified in the FCB into more detailed functional requirements and interface characteristics.
C.3.041.3.4 [Orig] The Developmental Configuration Baseline (DCB)
C.3.041.3.4.1 [Orig] The Developmental Configuration Baseline (DCB) represents the USCG-accepted
“build to” configuration of the first boat. The DCB is the Contractor’s responsibility and may be established in phases as a result of a series of detailed design reviews (DDRs) leading up to the Critical
Design Review (CDR). When the USCG accepts a deliverable, its contents become part of the DCB.
The DCB is established when deliverables associated with the DDRs up to the CDR have been accepted.
C.3.041.3.5 [Orig] Preliminary Product Configuration Baseline (p-PCB)
C.3.041.3.5.1 [Orig] The preliminary Product Configuration Baseline (p-PCB) is established by the
Contractor upon USCG acceptance of the technical data that represents the configuration of the first boat. The technical data shall include Contractor-formatted preliminary 3D model (in both native and
STEP format), and Contractor-formatted 2D drawing set (PDFs, native, and AutoCAD format) that reflects the as-built configuration.
C.3.041.3.6 [Orig] Product Configuration Baseline (PCB)
C.3.041.3.6.1 [Orig] The Product Configuration Baseline (PCB) is established upon adjudication of the
Physical Configuration Audit (PCA). The PCB consists of the complete technical data package as required in SOW Section C.3.085. The USCG will notify the Contractor once the PCB has been established.
C.3.041.3.6.2 [Orig] Once the PCB is established, configuration is under USCG control. The
Contractor shall not change or modify the configuration on any boat in production or any boat already in service without approval from the USCG. This includes change or modification during the completion of warranty work.
C.3.041.4 [Orig] Physical Configuration Audit (PCA)
C.3.041.4.1 [Orig] The USCG will conduct a Physical Configuration Audit (PCA) on a production-representative boat to verify conformance with the product drawings.
C.3.041.4.2 [Orig] The boat for the PCA will be designated by the USCG and will incorporate all approved changes identified during operational test and evaluation (OT&E).
C.3.041.4.3 [Orig] SOW Section 085’s product drawings will be used for the PCA. The product drawings shall reflect any changes incorporated into production as a result of OT&E. The Contractor shall provide one hard copy set at PCA.
C.3.041.4.4 [Orig] The USCG will conduct an audit at the Contractor’s facility, or an alternate facility agreed to by both parties, for the designated HSC-L. The physical boat will be compared to each product drawing and each product drawing will be compared to the physical boat to validate that documented details match. Any discrepancies between the physical boat and the product drawings will be documented in a USCG-generated PCA report.
C.3.041.4.5 [Orig] The PCA is scheduled to take no more than two weeks to complete. A Contractor representative is invited but not required to attend. The boat shall be prepared by the Contractor and accessible to USCG. The Contractor shall provide services to the boat to allow powering up of systems.
C.3.041.4.6 [Orig] The Contractor shall review the report and shall propose a resolution for each discrepancy. Resolution may be in the form of:
C.3.041.4.6.1 [Orig] The drawings are correct and the boats, including those already accepted, those in production, and the PCA boat, shall be corrected.
C.3.041.4.6.2 [Orig] The boat is correct, and the product drawings shall be revised.
C.3.041.4.7 [Orig] The Contractor shall prepare a PCA Resolution Report that shall identify a corrective action for each discrepancy to include anticipated dates when the actions will be completed.
C.3.041.5 [Orig] Configuration Control
C.3.041.5.1 [Orig] Engineering Change Proposal (ECP) - The Contractor can propose changes to the contract requirements, address DMSMS/obsolete, or to the design by submitting a DD Form 1692 supplied as Government Furnished Information (GFI). Engineering Change Proposals (ECPs) shall be in accordance with C.2.4(e).
C.3.041.5.2 [Orig] Request for Variance (RFV) - The Contractor may propose variance from a particular requirement of an item’s configuration baseline documentation for a specific hull or number of hulls, or for a specific period, by submitting a Request for Variance (RFV). An RFV differs from an engineering change because it does not require a change to the configuration baseline document but merely documents the authority for the specified hulls and their configuration documentation to differ from the baseline document. A DD Form 1694 supplied as Government Furnished Information (GFI) may be used. The
USCG will review RFVs. Upon acceptance in the form of a contract change, the Contracting Officer will authorize the Contractor to implement the RFV.
C.3.041.6 [Orig] Diminishing Manufacturing Sources/Material Shortages (DMSMS) and Obsolescence
C.3.041.6.1 [Orig] The Contractor shall be responsible for addressing Diminishing Manufacturing
Sources/Material Shortages (DMSMS) and obsolescence throughout the life of the contract. If
DMSMS/obsolescence concerns appear to affect the boat, the Contractor shall inform the USCG as soon as the Contractor becomes aware of the issue.
C.3.041.6.2 [Orig] The Contractor shall be responsible for providing recommended solutions to the
USCG, which may include alternate vendors, new sources of supply, or substitute parts.
C.3.041.6.3 [Orig] The Contractor shall bear all costs associated with revising technical documentation and substituting any Configuration Item (CI) when the reason for substitution is that the component is
DMSMS/obsolete. This does not apply to USCG specified parts.
C.3.041.6.4 [Orig] Software Development
C.3.041.6.4.1 [Orig] The Contractor shall provide the following for custom software developed for the
HSC-L program.
C.3.041.6.4.1.1 [Orig] Interface Design Description (IDD). [CDRL]
C.3.041.6.4.1.2 [Orig] System/Subsystem Design Description (SSDD). [CDRL]
C.3.041.6.4.1.3 [Orig] Firmware Support Manual (FSM). [CDRL]
C.3.041.6.4.1.4 [Orig] Vulnerability and Resolution Report (VRR). [CDRL]
C.3.045 [Orig] Care of Boat During Construction
C.3.045.1 [Orig] General
C.3.045.1.1 [Orig] The boat shall be maintained in a clean condition to prevent deterioration or contamination of equipment, machinery, and materials. This shall include routine cleaning and prevention of buildup of condensation that may subject the boat to damage.
C.3.045.1.2 [Orig] Equipment, prefabricated parts, Government-furnished equipment (GFE), and all other items stored by the Contractor for the boat shall be kept clean and protected from the environment and vermin.
C.3.045.1.3 [Orig] Preservatives or protective covers applied by OEM shall be left intact (or replaced if deteriorated, damaged, or removed) until installation of the machinery or equipment on the boat. If removal of the preservative or protective cover is necessary for testing the machinery or equipment prior to installation, the Contractor shall preserve and protect the machinery or equipment, in accordance with the OEM’s instructions, until installed.
C.3.045.1.4 [Orig] Preservatives or protective covers on working parts shall be thoroughly removed prior to operation of machinery or equipment.
C.3.045.2 [Orig] Physical Protection
C.3.045.2.1 [Orig] The Contractor shall provide physical protection and access control for the boat and its associated components until acceptance by the USCG.
C.3.045.3 [Orig] Protection of Machinery, Equipment, and Material
C.3.045.3.1 [Orig] The Contractor shall be responsible for the care of all machinery and equipment, whether furnished by the Contractor or by the USCG. A thorough cleaning shall be performed on any equipment, prior to energizing, which may have been subjected to foreign-matter intrusion.
C.3.045.3.2 [Orig] The Contractor shall ensure that all machinery, equipment, and materials are protected during hull blasting evolutions to prevent contamination or unintended damage.
C.3.045.4 [Orig] Protection of the HSC-L During Construction and Trials
C.3.045.4.1 [Orig] All parts of the boat shall be maintained in an undamaged condition during the entire period the boat is in the Contractor's possession. The Contractor shall act as necessary to prevent abnormal wear and damage to the boat and to prevent corrosion or other environmental deterioration during construction, testing, trials, and delivery.
C.3.045.4.2 [Orig] While the boat is in the Contractor's possession, the Contractor is responsible for safeguarding the boat and equipment from damage due to wind, fire, freezing, high temperature, water, and UV exposure.
C.3.045.4.3 [Orig] Temporary covers shall be provided and used during construction to:
C.3.045.4.3.1 [Orig] Protect flooring, machinery, and other equipment requiring protection that is installed aboard the boat.
C.3.045.4.3.2 [Orig] Protect equipment requiring protection from the weather as recommended by the manufacturer.
C.3.045.4.3.3 [Orig] Cover over openings in the boat to protect the interior against damage due to weather.
C.3.045.4.4 [Orig] The Contractor shall use fireproof or fire-resistant covers to prevent damage or possible ignition of equipment or materials due to falling sparks or other potential sources of fire.
C.3.045.4.5 [Orig] During the construction process the Contractor shall protect the boat from damage due to components containing mercury (e.g., fluorescent lights, thermostats, electrical test equipment, etc.).
C.3.045.4.6 [Orig] Inspect and clean the hull and propellers of marine growth and renew all cathodic protection no more than 30 days prior to delivery or acceptance by the USCG.
C.3.045.4.7 [Orig] If the boat is grounded or involved in a collision , the Contractor shall:
C.3.045.4.7.1 [Orig] Immediately notify the Contracting Officer of the incident;
C.3.045.4.7.2 [Orig] Haul the HSC-L from the water and block on shore for inspection, unless otherwise agreed to by the Contracting Officer; and
C.3.045.4.7.3 [Orig] After an inspection, submit an incident report, detailing the incident and any damage found (including pictures).
C.3.045.5 [Orig] Launching, Docking, and Undocking
C.3.045.5.1 [Orig] The Contractor shall properly launch the boat. The Contractor shall be responsible for the safe launching of the boat and its condition of stability when waterborne.
C.3.045.5.2 [Orig] Should there be any evidence that the boat has been damaged during launching, the Contractor shall immediately have the boat hauled from the water and blocked on shore for inspection, unless otherwise agreed to by the Contracting Officer and/or COR.
C.3.045.6 [Orig] The Contractor shall provide continuous cathodic protection while the boat is waterborne.
C.3.068 [Orig] Integration and Engineering
C.3.068.1 [Orig] General
C.3.068.1.1 [Orig] The Contractor shall provide Integration and Engineering to design and produce boats that meet all requirements identified in the Contract.
C.3.068.1.2 [Orig] Integration and Engineering consists of four phases:
C.3.068.1.2.1 [Orig] Phase 1: Design – begins at contract award and concludes at completion of the
Critical Design Review (CDR).
C.3.068.1.2.2 [Orig] Phase 2: Development – begins at completion of CDR and concludes at
USCG acceptance of the first boat.
C.3.068.1.2.3 [Orig] Phase 3: Operational Test & Evaluation (OT&E) – conducted by the USCG and begins at USCG acceptance of the first boat and concludes after completion of OT&E and initiation of Phase 4: Production
C.3.068.1.2.4 [Orig] Phase 4: Production – begins after USCG completion of OT&E and includes production of all follow-on boats incorporating any changes resulting from OT&E as reviewed and agreed upon in the Post-OT Design Review (Post-OTDR).
C.3.068.1.3 [Orig] The Contractor…