These are construction documents for the VA Cincinnati Medical Center, specifically for a project to "Repair T5 Access Hatch" (Project Number 539-25-503). The project involves replacing an existing transformer (T5) located at 3200 Vine Street, Cincinnati, OH, with a new Square D Schneider Electric three-phase 150 KVA pad-mounted transformer. The project scope includes demolishing the existing transformer and primary cabling, then installing new primary cabling from the PPSU to the new T5 transformer, while retaining and reconnecting existing secondary feeders.

Key project details include a 550-day period of performance, with work to be completed on a weekend to minimize PPSU shutdown duration. The new transformer will be centered on the existing 67"x67" concrete pad, and the contractor must match conductor sizes, make all necessary terminations, and ensure the transformer is fully operational. Additional requirements include updating the arc flash study and performing tasks such as swabbing out raceway and conducting a mandrel test prior to running new cabling. The project is fully documented across six sheets, including site plans, demolition plans, new work plans, and single-line electrical diagrams.

View the file

Other files

File Type Posted
Bid RFIs.docx DOCX document
Arc Flash Study - T5.pdf PDF
signin 2.jpg JPG image
Transformer Measurements.docx DOCX document
Siemens Panel TR MAIN FDS.pdf PDF
36C25025B0043 0002.pdf PDF
signin 1.jpg JPG image
36C25025B0043 0001.pdf PDF
36C25025B0043_1posted.pdf PDF
Attachment VII VHA Directive 1192.01, Flu.pdf PDF
Attachment II 539-25-503 Repair Transformer Specs.pdf PDF
Attachment V EMR Form.pdf PDF
Attachment VI 852.219-75 LOS.pdf PDF
Attachment IV RFI Form.pdf PDF
Attachment I WD 10.21.2025.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

G100

COVER SHEET

A

Fi le

P at h

/1 5/

1:

:0

AM

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

321 4 5 6 7 8 9 10

REPAIR T5 ACCESS HATCH

3200 Vine Street, Cincinnati OH

539-25-503

Project Director

Issue date Chkd By Drwn By

G100 COVER SHEET

E1 SITE PLAN

E2 DEMO PLAN

E3 NEW WORK PLAN

E4 BASIS OF DESIGN

E5 SINGLE LINE - DEMO

E6 SINGLE LINE - NEW

SHEET

NUMBER SHEET NAME

SHEET INDEX

PHASING NARRATIVE

1. POP: 550 DAYS FROM NTP

2. SHUTDOWN TO BE COMPLETED ON A WEEKEND. WORK SHALL BE

COMPLETED SUCH THAT PPSU SHUTDOWN DURATION IS MINIMIZED.

REPAIR T5 ACCESS HATCH

539-25-503

VA Cincinnati 3200 Vine Street, Cincinnati, OH

Construction Documents

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

E1

SITE PLAN REFERENCE

A

Fi le

P at h

/1 5/

1:

:0

AM

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

321 4 5 6 7 8 9 10

REPAIR T5 ACCESS HATCH

3200 Vine Street, Cincinnati OH

539-25-503

Project Director

Issue date Chkd By Drwn By

DRAWINGS NOT TO SCALE.

GENERATOR

T5

PPSU

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

E2

DEMO PLAN

A

Fi le

P at h

/1 5/

1:

:0

AM

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

321 4 5 6 7 8 9 10

REPAIR T5 ACCESS HATCH

3200 Vine Street, Cincinnati OH

539-25-503

Project Director

Issue date Chkd By Drwn By

PLAN NOTES

1. DEMO EXISTING T5 TRANSFORMER. DEMOLISH PRIMARY CABLING FROM

T5 TO PPSU. RETAIN SECONDARY CONDUCTORS TO SIEMENS PANEL

FOR RECONNECTION.

2. SIEMENS PANEL FED BY T5 (LOCATION REFERENCE)

3. ONCE PRIMARY FEEDERS ARE REMOVED, CONTRACTOR TO SWAB OUT

RACEWAY AND PERFORM MANDREL TEST PRIOR TO RUNNING NEW

CABLING.

PPSU

T5 DEMOLISH

DRAWINGS NOT TO SCALE.

EXISTING TRANSFORMER PLATE

CURRENT PPSU ARC FLASH LABEL

GENERATOR

T5

PPSU

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

E3

NEW WORK

A

Fi le

P at h

/1 5/

1:

:0

AM

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

321 4 5 6 7 8 9 10

REPAIR T5 ACCESS HATCH

3200 Vine Street, Cincinnati OH

539-25-503

Project Director

Issue date Chkd By Drwn By

PLAN NOTES

1. CENTER NEW TRANSFORMER ON EXISTING CONCRETE PAD (67"X67").

RUN NEW PRIMARY CABLING TO PPSU. MAKE ALL REQUIRED

TERMINATIONS AND RECONDUCTOR AS NEEDED TO ENSURE

TRANSFORMER IS FULLY OPERATIONAL AND MAINTAINS EXISTING

FEEDS. MATCH SIZE OF CONDUCTORS TO EXISTING.

2. SIEMENS PANEL FED BY T5 (LOCATION REFERENCE)

3. TRANSFORMER BASIS OF DESIGN:

SQUARE D SCHNEIDER ELECTRIC

THREE PHASE PAD MOUNT 150 KVA

REFER TO SHEET E4.

4. RECONNECT EXISTING SECONDARY FEEDERS TO NEW T5. MAKE ALL

REQUIRED TERMINATIONS AND RECONDUCTOR AS NEEDED TO ENSURE

TRANSFORMER IS FULLY OPERATIONAL AND MAINTAINS EXISTING

FEEDS.

5. UPDATE ARC FLASH STUDY, AS NEEDED, FROM PPSU TO DOWNSTREAM

EQUIPMENT OF T5.

SQUARE D

SCHNEIDER

ELECTRIC

DRAWINGS NOT TO SCALE.

EXISTING

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

E4

BASIS OF DESIGN

A

Fi le

P at h

/1 5/

1:

:0

AM

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

321 4 5 6 7 8 9 10

REPAIR T5 ACCESS HATCH

3200 Vine Street, Cincinnati OH

539-25-503

Project Director

Issue date Chkd By Drwn By

GENERAL NOTES

A. CONTRACTOR SHALL FIELD VERIFY

EXISTING MEASUREMENTS OF T5

PRIOR TO SUBMITTING NEW

TRANSFORMER FOR REVIEW.

B. BASIS OF DESIGN HAS MEASUREMENTS

AND SPECS CLOSE ENOUGH TO BE

CONSIDERED A ONE FOR ONE

REPLACEMENT. REPLACEMENT FOR

BOD SHALL INCLUDE PRIMARY CABLING

REPLACEMENT, RIGGING, AND SPADE

EXTENSIONS FOR SECONDARY

BUSHINGS.

DRAWINGS NOT TO SCALE.

BUILDING 8

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

E5

SINGLE LINE - DEMOLITION

A

Fi le

P at h

/1 5/

1:

:0

AM

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

321 4 5 6 7 8 9 10

REPAIR T5 ACCESS HATCH

3200 Vine Street, Cincinnati OH

539-25-503

Project Director

Issue date Chkd By Drwn By

GENERAL NOTES

A. CONTRACTOR SHALL FIELD VERIFY EXISTING MEASUREMENTS OF T5

PRIOR TO SUBMITTING NEW TRANSFORMER FOR REVIEW.

B. BASIS OF DESIGN HAS MEASUREMENTS AND SPECS CLOSE ENOUGH TO

BE CONSIDERED A ONE FOR ONE REPLACEMENT. REPLACEMENT FOR

BOD SHALL INCLUDE PRIMARY CABLING REPLACEMENT, RIGGING, AND

SPADE EXTENSIONS FOR SECONDARY BUSHINGS.

DRAWINGS NOT TO SCALE.

PLAN NOTES

1. DEMOLISH EXISTING TRANSFORMER T5.

2. DEMOLISH #2 AWG PRIMARY CABLING FROM PPSU TO T5. RETAIN

SECONDARY CABLING FOR RECONNECTION.

LINE DIAGRAM 1 TR MAIN FDS FU (Siemens Panel) Frame/Model TRS Sensor/Trip 400A Setting LTPU Interrupting Rating 200kA Series Rating 0.0kA

BUILDING 8

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

E6

SINGLE LINE - NEW WORK

A

Fi le

P at h

/1 5/

1:

:0

AM

CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

321 4 5 6 7 8 9 10

REPAIR T5 ACCESS HATCH

3200 Vine Street, Cincinnati OH

539-25-503

Project Director

Issue date Chkd By Drwn ByDRAWINGS NOT TO SCALE.

GENERAL NOTES

A. CONTRACTOR SHALL FIELD VERIFY EXISTING MEASUREMENTS OF T5

PRIOR TO SUBMITTING NEW TRANSFORMER FOR REVIEW.

B. BASIS OF DESIGN HAS MEASUREMENTS AND SPECS CLOSE ENOUGH TO

BE CONSIDERED A ONE FOR ONE REPLACEMENT. REPLACEMENT FOR

BOD SHALL INCLUDE PRIMARY CABLING REPLACEMENT, RIGGING, AND

SPADE EXTENSIONS FOR SECONDARY BUSHINGS.

PLAN NOTES

1. RUN NEW #2 AWG PRIMARY CABLING FROM PPSU TO NEW T5.

2. CONNECT EXISTING SECONDARY FEEDERS TO NEW T5.

LINE DIAGRAM 2