PERFORMANCE WORK STATEMENT (PWS)

SECONDARY CRASH NETWORK (SCN)

AT

RAF MILDENHALL UK

NAME: HEADQUARTERS UNITED STATES AIR FORCES IN

EUROPE/ AIR FORCES AFRICA (HQ USAFE-AFAFRICA)

ORGANIZATION: DIRECTORATE OF COMMUNICATIONS (A6)

29 July 2020

1.0. DESCRIPTION OF SERVICES.

This PWS defines the requirement to Engineer, Furnish, Install and Test (EFI&T) a Secondary

Crash Network (SCN) notification system in 100 ARW/OSS Base Operations, Building (B) 669 at Royal Air Force (RAF) Mildenhall, United Kingdom (UK). Work shall be accomplished in B

669, Base Operations area, the drop locations reflected in Table 1, and coordination with 100 CS at RAF Mildenhall, UK.

2.0. MINIMUM QUALIFICATIONS:

The Project Manager, Site Point of Contact (POC), and respective alternate(s) shall be able to read, write, speak, and understand English. All reporting and documentation shall be in English.

The Contractor’s technical team shall be 8570 certified. For the SCN System proposed, the

Contractor’s technical team shall have the appropriate certifications. In their proposal, the

Contractor shall confirm their personnel have the required certifications.

3.0. ENGINEERING AND PROJECT IMPLEMENTATION:

3.1. Project Requirement: For the areas and circuits identified, the Contractor shall provide all management, personnel, equipment, tools, transportation, supplies, materials, supervision, and other incidentals necessary to install a SCN. The SCN shall have an Initiator Console that, when initiated, automatically rings the subscriber phones at the other end. On the Initiator Console, each subscriber’s line shall have an individual indicator, providing the following states: Idle, Ringing, Answered Active, and On Hold. The drop line status can be indicated by changing the

Icon or Color of the Icon.

3.1.1. B 669, Base Ops: The SCN Initiator Console shall be installed in B 669, Base Ops station. The Core Equipment supporting the SCN shall be installed in the Communications room in Room WX2 approximately 200’ down the hall from Base Ops. The Contractor shall EFI&T a new 42U cabinet to house the SCN equipment and terminate fiber optic and CAT 6 cables. The

Government shall provide a duplex 220 VAC, 50 Hz power Type G outlet and ground point for the SCN cabinet. The Contractor is responsible for providing the power cables between their equipment and the Government provided power outlet. The Contractor shall EFI&T all Core equipment, patching, and fiber cabling. All Contractor installed cables shall be supported at a minimum of every 18” to Contractor EFI&T cable tray work and/or Panduit, and/or Government furniture. The Government shall provide all outside plant and premise wiring to/at the Subscriber locations.

3.1.1.1. All SCN drops (except for Weather and the Fire department which are in B 669 also) will be ran on Single Mode (SM) Fiber Optic cable. The Contractor shall EFI&T 48 SM fibers within the Contractor’s cabinet to the Governments Core Node Room on the roof of B 669. The approximate distance is 250 feet. The Contractor shall terminate these 48 SM fibers to Contractor

EFI&T 48 port SC connector Fiber Optic Patch Panels (FOPP). The Contractor shall EFI&T the

FOPPs to be installed in their 42U cabinet and the matching one in the Core Node room in

Cabinet 2. The Contractor EFI&T Core Node Cabinet 2, 48 port FOPP’s shall be the demarcation point for all (external to B 669) SCN drops. The Government shall provide all fiber cross connects to the SCN drop building’s FOPP. The exception is the two B 669 drops: Fire

Department and Weather. The Contractor shall EFI&T these drops with new CAT 6 premise wiring from their 42U cabinet to Contractor EFI&T CAT 5e outlets at the Weather Counter and the Fire Department Dispatch desk. The Contractor EFI&T CAT 5e cables shall terminate to a

Contractor EFI&T CAT 5e Patch Panel that is installed in their 42U provided cabinet.

3.1.1.2 The Contractor shall EFI&T the SCN Initiator Console as directed by Base Operations

Personnel. The Initiator Console shall set on the existing Base Ops counter/work station. The

SCN Core shall be sized for one Initiator Console and up to Eighteen Subscriber users. The

Contractor shall EFI&T 10 Push to Talk (PTT) head sets and two PTT handsets for the Initiator

Console. The Contractor shall EFI&T all communication’s cabling back to their 42U cabinet in

WX2.

3.1.2. The below table provides the Subscriber users and their locations.

Secondary CCS

100 ARW Command Post BLDG 591

Weather (WX), BLDG 669 (Premise Wiring)

Fire House, BLDG 669 (Premise Wiring)

SFS BDOC, BLDG 645

Wing Safety, Bldg 568

Lakenheath ER, Hospital B 932

352 MOCC, B 802

100 ARW MOC, B 814

Emergency Management, B 680 (Two Drops)

ATOC, B 599

Alternate Command Post, B 809

Table 1. Drop Locations.

3.1.3. All cables shall be labeled appropriately in accordance with (IAW) typical commercial standards. Naming scheme shall also be coordinated with the Government Representative (GR).

3.1.4. Restore working area to original conditions, which existed prior to the installation, unless otherwise directed.

3.1.5. The Contractor shall coordinate planned outages with the 100 ARW Airfield Manager and

GR at least five workdays in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

3.1.6. Grounding and Bonding: All grounding and bonding shall follow J-STD-607-A.

3.1.7 For each customer reflected in Table 1, the Contractor shall EFI&T a separate user SCN phone. These shall be Single Line instruments that are only connected to the SCN and have PTT handsets. The Contractor shall coordinate the installation and testing of these phones/cross connections with the GR. The Contractor shall EFI&T all cross connects except for the inter-building Government provided fiber links.

3.1.8. The Contractor shall EFI&T an Uninterruptable Power Supply (UPS) for the SCN Core

Equipment. This UPS shall be installed in the bottom of the Contractor EFI&T 42 U Cabinet.

All SCN power modules shall terminate to this UPS. The Contractor shall EFI&T a “Computer

UPS” for the Base Ops Initiator Console and ensure it is powered via this UPS.

3.1.9. The Contractor shall EFI&T a Voice Recorder to provide recording capability for the

SCN, capable of recording up to 24 hours of conversation. The Voice Recorder shall record all

SCN conversations. It is suggested the Voice Recorder be installed in the Contractor’s 42U

EFI&T cabinet. The Contractor shall EFI&T a Voice Recorder control position within the B

669, Base Ops area. This shall be computer based and directly cabled to the Voice Recorder. It shall provide Recorder Administration and voice recording retrieval and playback. There will be

Government provided 220 VAC, 50 Hz Type G outlets available for the Voice Recorder

Administration Position and desk space. If the SCN Initiator Console can accomplish this function, then the Contractor shall state this in their proposal and no Recorder Administration position shall be required.

3.1.10. The Contractor shall EFI&T a modem nest in their B 669 42U cabinet for each non-CAT

6 SCN drop. For the drop location building comm rooms, the Contractor shall EFI&T fiber modems. At each Table 1 location, the Government shall provide 220 VAC, 50 Hz outlet in the site’s Communication Room for the Contractor’s EFI&T fiber modem. The fiber modem’s installation location shall be coordinated with the GR. The Contractor shall EFI&T the CAT 5e patch cord from their fiber modem to the Government’s Communication Room’s CAT 5e patch

Panel. The Contractor shall EFI&T the CAT 5e patch cord from their SCN PTT phone to the

Government’s CAT 5e outlet, in the room the Government designates for the drop phone. The

Contractor shall coordinate the installation and testing of these phones/cross connections with the

GR.

3.1.11. For the two drops for Emergency Management in B 680, the Contractor shall provide two

PTT phones. The Contractor shall EFI&T these to work over one Fiber Modem. The Contractor shall patch into the current two Government provided CAT 5e Patch Panel ports. If required, the

Contractor shall EFI&T a “Half-Tap” connection to accomplish this.

3.1.12. To allow for future expansion, the Contractor shall EFI&T all required hardware and software for the SCN system to add Four each future additional drops. This shall include Core

Equipment, Recorder, and Initiator Console capacity; PTT Phones, fiber modems (B 669 Core

Modems and customer end modems), cables, etc.. Paragraph 5.5. Training, shall include all SCN system provisioning for adding these additional drops. This shall include training for all Core

Equipment, Recorder, Initiator Console, and modem configurations. The Core Equipment UPS shall be EFI&T to provision power support for this additional capacity. This additional hardware and software shall be tested IAW paragraph 3.2.5. testing requirements and shall be part of paragraph 5.7. System Acceptance.

3.1.13. Fire Suppression. Any wall penetrations shall use adequate fire blocking to meet or exceed the current standard in place.

3.1.14. Excavation/Building Penetrations: All wall penetrations, including inside buildings, shall be restored to meet the required base fire and Host Nation ratings.

3.1.15. The Contractor shall coordinate the installation, cross connections, and testing of circuits with the GRs. The Contractor shall EFI&T all cross connects except the inter-building

Government fiber links..

3.2. Project Implementation:

3.2.1. Contractor Furnished (CF) Materials and Network Specific Warranty: The

Contractor shall furnish all materials for this project except as identified. The Contractor shall supply Commercial-Off-the-Shelf (COTS) end-item system components required for contract performance wherever possible. The Contractor’s proposal in response to the Government solicitation, shall identify all project materials and equipment to include the proposed manufacturer and part number. The Contractor furnished equipment shall be included on the

Defense Information Systems Agency’s (DISA) Approved Products List (APL). Note: The APL is the single list of products that have completed Cybersecurity and interoperability DISA certification. Unless otherwise specified, the Contractor shall provide copies of existing COTS technical or equipment manuals and warranty documentation and procedures for Contractor-furnished end-item system equipment maintenance. The Contractor shall identify and conduct system familiarization for Government personnel to ensure proper operation and maintenance of the system(s).

3.2.2. Network Test Plan: The Contractor shall derive a test plan and perform all applicable tests.

3.2.3. Physical Inspection: The physical inspection consists of the Contractor doing a physical inspection of each location where installation is required. At each location, the Contractor shall verify the specified placement of the equipment to ensure the installation shall meet required

Operational Safety and Health Administration (OSHA) and host nation safety standards. The

Contractor shall verify that each location shall have proper rack space, proper mounting of equipment, Grounding, and proper primary power. An installation Test Report shall be provided after physical inspection is completed. Results shall be in compliance before the component validation and operational tests are run.

3.2.4. Component Validation: The Contractor shall perform component validation by testing all of the individual SCN Equipment, Initiator Console, Cables, UPS, Voice Recorders, outlets, phones, and other related equipment, to ensure they are working correctly. The Contractor shall test components prior to assembly and installation before continuing on to Operational Testing.

An installation test report shall be provided after component validation is completed.

3.2.5. Operations Test: The Operations Test shall consist of testing the newly installed SCN

System. An Installation Test Report shall be provided after Operational Test is completed.

3.2.6. Project Completion and Government Representative (GR): The project shall not be considered complete until all parties sign an AFTO Form 747. This insures the Government is satisfied that the requirements of this document have been met. The AFTO Form 747 shall not be signed by the Government until all installations, testing, and reports are accepted. The

Contracting Officer shall designate an on-site GR whom shall act, in their stead, as a liaison between the Contracting Officer/RAF Mildenhall personnel and the Contractor personnel. The

GR shall assist the Contractor with arranging all testing with all Government personnel and any

Government inspections. The GR shall also assist the Contractor with the completion of the

AFTO 747. If the Contractor has any concerns, questions, etc. they shall address them through the GR.

4.0 MANAGEMENT:

4.1. Schedule. The Contractor shall provide a complete milestone schedule that denotes major activities to include time-phased start and completion dates for this project and sub-projects associated with the installation of the components and systems.

4.2. Post Award Teleconference and In-Brief. Two weeks after Contract Award, the 48 CONS shall coordinate a teleconference with the Contractor’s and all required Government personnel.

The Teleconference scope will be to ensure all requirements are understood and to answer any

Contractor site specific questions. The first day on-site, the Contractor shall conduct an in-brief with the GR or designated representative and other site personnel before the start of site survey or implementation. The in-brief shall familiarize the customer with the purpose of the Contractor's visit and coordinate the project schedule (e.g. arrange for required escorts; Quality Assurance personnel schedule; etc.). The Government shall coordinate with the Contractor the In-Brief’s time/date and location.

4.3.. Site Point of Contact: The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for this project in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours until project completion and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.

4.3.1. Site Access: The Contractor shall process and provide a site visit request letter, to the GR, within 5 calendar days after contract award. The visit request letter shall identify the names (as shown on the driver’s license), driver’s license numbers, the place of issue, and birth date of the personnel who will be performing work under this PWS. It shall also include the company name, address, phone number, contract number, project start date and end date. If required by GRs, the

Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be IAW base regulations. The Contractor shall coordinate with the site GRs to obtain and return temporary badges and vehicle registrations. Note the place of performance is the United Kingdom. The

Contractor shall be responsible for their employee’s Passport and Visa requirements for United

Kingdom entry and work performance.

4.3.2. Restricted Area Access: Stated work and associated products shall be performed at the

UNCLASSIFIED level. However, some of this work may take place in secure areas where

Contractor employees must be escorted at all times. The Contractor shall coordinate access to secure areas at least 5 calendar days ahead of time. It is the Government’s responsibility to provide escorts. Due to specific mission requirements inherent in the nature of controlled or restricted areas, the Government may direct the Contractor to leave a controlled or restricted area at any time.

4.4. Quality Assurance. The Contractor shall provide quality assurance support throughout the installation. This support shall include, the assistance of the GRs in performing random spot checks and system acceptance tests. Contractor Quality Assurance Evaluator (QAE) and GRs shall be responsible for identifying deficiencies and/or discrepancies throughout the life of the project.

4.5. Compliance. The Contractor shall remain in compliance with all United Kingdom, US

Federal, and base security and safety laws, regulations, policies, and requirements.

4.6. Clean up. Prior to all Contractor personnel leaving the site each day, the Contractor shall remove all debris and surplus materials from the work place. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard.

4.7. Restoration. The Contractor shall restore all disturbed property to the “as found” condition or better after installation. The Contractor shall comply with Base grounds restoration requirements.

4.8. Project Residue. The Contractor shall dispose all residues from this project off base and

IAW Federal, Host Nation, local, and base environmental laws and regulations

4.9. Service Outages. The Contractor shall coordinate planned disruption of service outages, (e.g., communications, electrical, or other utilities) with the GR at least five workdays in advance.

4.10. Environmental Management. The Contractor shall comply with the most stringent environmental United Kingdom, Federal, and local laws and regulations; and Air Force policies, instructions, and plans. The installer shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on RAF Mildenhall.

The Prime Contractor shall ensure their sub-Contractors (if any) comply with these specifications.

4.11. Walk-Through. The Contractor shall schedule a final project walk-through of all work completed prior to close out with the GR. This should be scheduled at least 72 hours prior to the event.

5.0 DELIVERABLES.

5.1. List of Deliverables. All deliverables are subject to Government acceptance and approval.

They shall meet professional standards and the requirements set forth in this Task Order. All deliverables shall be produced using recommended software tools/versions as accepted by the

Government. The Contractor shall submit the following deliverables:

Deliverables PWS Reference

Network Test Plan 3.2.2.

5.3.

Installation Test Report

3.2.3.

3.2.4.

3.2.5.

AFTO Form 747 3.2.6.

Project Schedule 4.1.

As Built 5.4.

Training Materials 5.5.

Test Report 5.3.

Cut Over Plan 5.2.

5.2. Cutover Plan: The Contractor shall provide a detailed Cutover Plan to delineate how the transition shall be implemented. This plan should outline how the system shall be placed into service and clearly specify how the newly installed systems shall connect to the existing base systems.

5.3. Acceptance Test Plan: The Contractor shall provide a detailed Acceptance Test Plan of the installation covering all aspects of the installation and demonstrate the acceptability of the work on meeting the Government requirement. The Contractor shall perform all tests and document results of tests with Government witnesses overseeing the Acceptance Testing.

5..4. As-Built Drawings: The Contractor shall provide as-built drawings for the installed equipment to include where and how equipment connects/interfaces with each other and existing base systems (Outside Plant cables, Premise Wiring, Voice, patch panels, etc.) . Rack Elevation and Floor Plan drawings shall be Contractor EFI&T reflecting SCN Core Equipment, Initiator

Console, Voice Recorder, UPSes, Fiber Modems, and PTT Phones.

5..5. Training: The Contractor shall provide operational hands on training for 10 Government

Personnel. The Contractor shall provide all training materials (slides, Technical Documents, Manuals, etc.). The training shall cover complete capabilities of the SCN, Initiator Consoles, UPSes, and Voice Recorders. The training shall also provide Operations and Maintenance for the complete SCN system so Government personnel shall be capable of adequately maintaining and providing future additional drops for the SCN system. This training shall cover the SCN

Equipment, the Recorder, Initiator Console, Drop Phones, Fiber Modems, paragraph 3.1.12.

Expansion Hardware/Software, and UPSes.

5.6. Contract Provision.

5.6.1. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment shall be withheld until such time as the cause of the failure is corrected to the Government satisfaction.

5.6.1.1. If necessary due to a failed test, after appropriate corrective action has been taken, all tests including those previously completed related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance. Pre-cutover audits shall consist of verification of all testing completed by the Contractor such that the system is deemed ready for functional cutover. As part of this audit, any engineered changes or approved waivers applicable to the installation shall be reviewed and agreed upon between the Contractor and the

Government. Post-cutover audits shall verify that all post-cutover acceptance testing has been performed satisfactorily in accordance with the standard practices and identify those tests, if any which have not been successfully completed and shall be re-tested prior to acceptance. The

Contractor shall do all testing in accordance with the acceptance test plan as mentioned above.

The Contractor shall provide a logical test process that minimizes interruptions and avoids sustained downtime and presents a contingency procedure to be implemented in the event of systems failure during testing.

5.6.2. Testing. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During the testing phase, the Government reserves the right to perform any of the Contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing. The

Test Report(s) shall be provided to the Government no later than 10 days after test(s) have been completed.

5.7. System Acceptance: Acceptance of the SCN installation shall be dependent upon successful completion and documentation of tests in the Contractor submitted/Government approved Test

Report. Screen shots (if applicable) shall serve to document successful test results.

6.0. WARRANTY

The Contactor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. The Contactor shall also provide a one year workmanship warranty to include all materials, software, software programming, and circuit terminations. The warranty period shall start from the date of system and or project acceptance, signing of AFTO

Form 747 by all parties. The Contactor shall provide hardware replacement/upgrades for one year for all equipment. The Contactor shall transfer warranties to the Government. The

Contactor shall provide their Maintenance and Technical representatives’ Web, Email, and Phone

Numbers for Government personnel to request support, as required.

7.0. PERFORMANCE.

7.1. Period of Performance. The period of performance for this requirement shall not exceed

120 days to complete all facets of the project including final walk thru with the GR, beginning after contract award.

7.2. Place of Performance. The place of performance is RAF Mildenhall UK.

7.3. Hours of Work. The Contractor shall routinely work during normal operating hours of the site. Monday through Friday (0730-1630 hrs), excluding Federal and UK Bank Holidays. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the GR at least 10 working days in advance.

8.0. STORAGE.

8.1. Temporary Storage: The Government shall provide secure and dry storage space for

Contractor materials. The Contractor shall be responsible for loading, unloading, un packing and transportation of all Contractor provided materials, test equipment, training documentation, etc..

The Contractor shall be responsible for disposal of all packing materials and unused installation materials. If the GR concurs, the Contractor may turn these items over to the Government for use/disposal at no compensation to the Contractor. If the GR does not agree, the Contractor shall properly dispose of these items IAW the local Governments’ environmental practices.

8.2. Temporary Storage address:

Shipping Address for project material storage is: Project shipping POC is:

100 CS/SCOI-TCF TSgt. Brandon S. Azevedo

C/O TSgt. Brandon S. Azevedo Bldg. 591/Rm 30A

Bldg. 591/Rm 30A RAF Mildenhall

RAF Mildenhall IP28 8NF

IP28 8NF United Kingdom

United Kingdom

9.0. Reference Standards:

NUMBER TITLE WEBSITE OR LOCATION

AFI AFI 13-213, Airfield Management Air Force Publications

FIPS Federal Information Processing

Standards Publications https://csrc.nist.gov/publications/fips

BICSI Building Industry Consulting Service

International, Inc. (BICSI) http://www.bicsi.org/

British Standards

Institute

BS 7671.2018, 18th Edition of The IET

Wiring Regulations https://www.cityandguilds.com/qualificatio ns-and-apprenticeships/building-services-industry/18th-edition

NFPA 70 (2020) National Fire Protection Association

(NFPA), National Electric Code (NEC) http://www.nfpa.org/

ANSI American National Standards Institute

(ANSI) and Internet Standards Resources http://www.ansi.org/

TIA Engineering: TIA Standards See

Commodity Specific Appendices and

Individual Task Orders http://www.tiaonline.org/

ANSI/TIA-569-E

(2019)

Commercial Building Standards for

Telecommunications Pathways and

Spaces http://www.tiaonline.org/ https://csrc.nist.gov/publications/fips http://www.bicsi.org/ https://www.cityandguilds.com/qualifications-and-apprenticeships/building-services-industry/18th-edition https://www.cityandguilds.com/qualifications-and-apprenticeships/building-services-industry/18th-edition https://www.cityandguilds.com/qualifications-and-apprenticeships/building-services-industry/18th-edition http://www.nfpa.org/ http://www.ansi.org/ http://www.tiaonline.org/

ANSI/TIA-570

(2008)

Residential Telecommunications Cabling

Standard http://www.tiaonline.org/

EIA/CIA-310-E

(2005)

Racks, Panels and Associated Equipment http:/global.ihs.com/

ANSI/NEMA-FB

1 (2012)

Fittings, Cast Metal Boxes and Conduit

Bodies for Conduit, Electrical Metallic

Tubing (EMT) and Cable http://www.nema.org

ANSI/EIA-310-D Cabinets, Racks, Panels, and Associated

Equipment http://www.server-racks.com/eia-310.html

ANSI/TIA/EIA-

606-C – (2017)

Administration Standard for the

Telecommunications Infrastructure of

Commercial Buildings www.flexcomm.com/library/606aguide.pdf

ANSI-J-STD-607

– D (2019)

Commercial Building Grounding

(Earthing) and Bonding Requirements for Telecommunications http://www.ansi.org/

BICSI TDMM

Manual - (2006, 11th Edition)

Building Industries Consulting Services

International Telecommunications

Distribution Methods (TDM) Manual https://www.bicsi.org/default.aspx

NEMA TC 2-

(2013)

Electrical Polyvinyl Chloride (PVC)

Tubing and Conduit http://www.nema.org/Standards/Complime ntaryDocuments/Contents%20and%20Sco pe%20NEMA%20TC%202-2013.pdf

OSHA CFR 29

Part 1910-268 -

Telecommunications https://www.osha.gov/pls/oshaweb/owasrc h.search_form?p_doc_type=STANDARDS

&p_toc_level=1&p_keyvalue=1910

TIA 526-14-B

(2010)

Optical Power Loss Measurement of

Installed Multimode Fiber Cable Plant http://www.tiaonline.org/

REA TE&CM 643

Form 515C

Rural Electrification Administration

(REA)

http://www.rurdev.usda.gov/supportdocum ents/utp_bulletins_1753f-152.pdf

ANSI/TIA-568-

.1.E (2020)

Commercial Building

Telecommunications Cabling Standard http://www.tiaonline.org/

ANSI/TIA-568-

.2.D (2018)

Balanced Twisted-Pair

Telecommunication Cabling and

Components Standard http://www.tiaonline.org/ http://www.tiaonline.org/ http://www.nema.org/ http://www.server-racks.com/eia-310.html http://www.flexcomm.com/library/606aguide.pdf http://www.ansi.org/ https://www.bicsi.org/default.aspx http://www.nema.org/Standards/ComplimentaryDocuments/Contents%20and%20Scope%20NEMA%20TC%202-2013.pdf http://www.nema.org/Standards/ComplimentaryDocuments/Contents%20and%20Scope%20NEMA%20TC%202-2013.pdf http://www.nema.org/Standards/ComplimentaryDocuments/Contents%20and%20Scope%20NEMA%20TC%202-2013.pdf https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=1910 https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=1910 https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=1910 http://www.tiaonline.org/ http://www.rurdev.usda.gov/supportdocuments/utp_bulletins_1753f-152.pdf http://www.rurdev.usda.gov/supportdocuments/utp_bulletins_1753f-152.pdf

ANSI/TIA-568-

.3.D (2016)

Optical Fiber Cabling Components

Standard http://www.tiaonline.org/

ANSI/TIA-570

(2008)

Residential Telecommunications Cabling

Standard http://www.tiaonline.org/

ANSI/TIA-598-C

(2005)

Optical Fiber Cable Color Coding http://www.tiaonline.org/

10.0. LABELING:

The Contractor shall provide an effective labeling and numbering scheme to ensure administration tasks are simplified, to include, moves, adds and changes can be carried out with little guesswork, unused capacity can be easily identified and failed components can easily and quickly be identified during troubleshooting and repair activities. This will include all Contractor

EFI&T Premise Wiring. Naming scheme shall be coordinated with the GR.

11.0. ATTACHMENT:

Sketch #1. SCN Requirements.